R.A. No. 6831, Article XLIV
1990 Countrywide Development Fund
Special Provision No. 1 Use and Release
of Funds for Capital OutlaysThe amount herein appropriated for capitaloutlays shall be used for infrastructure and other
priority projects upon approval of thePresident of the Philippines and shall bereleased directly to the appropriateimplementing agency.
-
8/13/2019 Cjmlpas Pdaf Notes
2/55
R.A. No. 7078, Article No. XLIV
1991 Countrywide Development Fund
Special Provision No. 1 Use and Release of
FundsThe amount herein appropriated shall be used forinfrastructure and other priority projects andactivities upon approval of the President ofthe Philippines and shall be released directly tothe appropriate implementing agency not later thanthe third quarter of the current year, subject to thesubmission of the required list of projects andactivities.
-
8/13/2019 Cjmlpas Pdaf Notes
3/55
R.A. No. 7180, Article XLII
1992 Countrywide Development Fund
Special Provision No. 1 Use and Release of
FundsThe amount herein appropriated shall be used forinfrastructure and other priority projects andactivities upon approval of the President of
the Philippines and shall be released directly tothe appropriate implementing agency subject to thesubmission of the required list of projects andactivities.
-
8/13/2019 Cjmlpas Pdaf Notes
4/55
R.A. No. 7645, Article XXXVIII
1993 Countrywide Development FundSpecial Provision No. 1 Use and Release of
Funds
The amount herein appropriated shall be used forinfrastructure and other priority projects and activitiesas proposed and identified by officials concernedaccording to the following allocations:Representatives, P12.5M each; Senators, P18Meach; Vice-President, P20M.
The fund shall be automatically released quarterlyby way of Advice of Allotment and Notice of Cash
Allocation directly to the assigned implementing agencynot later than 5 days after the beginning of eachquarter upon submission of the list of projectsand activities by the officials concerned.
-
8/13/2019 Cjmlpas Pdaf Notes
5/55
-
8/13/2019 Cjmlpas Pdaf Notes
6/55
1994 Countrywide Development FundSpecial Provision No. 2 Submission of
Quarterly Reports
The DBM shall submit within 30 days after theend of each quarter a report to the SenateCommittee on Finance and the House
Committee on Appropriations on the releasesmade from this Fund. The report shall includethe listing of the projects, locations,
implementing agencies and the endorsingofficials.
-
8/13/2019 Cjmlpas Pdaf Notes
7/55
R.A. No. 7845, Article XLII
1995 Countrywide Development FundSpecial Provision No. 1 Use and Release of Funds.
The amount herein appropriated shall be used for
infrastructure, purchase of equipment and other priorityprojects and activities, as proposed and identified byofficials concerned according to the followingallocations: Representatives, P12.5M each; Senators,P18M each; Vice-President, P20M.
The fund shall be automatically released semi-annually byway of Advice of Allotment and Notice of Cash Allocationdirectly to the designated implementing agency not later than5 days after the beginning of each semester upon submission
of the list of projects and activities by the officials concerned.
-
8/13/2019 Cjmlpas Pdaf Notes
8/55
R.A. No. 7845, Article XLII
1995 Countrywide Development Fund
Special Provision No. 2 Submission of Semi-
Annual Reports
The DBM shall submit within 30 days after the endof each semester a report to the Senate Committee
on Finance and the House Committee onAppropriations on the releases made from thisFund. The report shall include the listing of the
projects, locations, implementing agencies and theendorsing officials.
-
8/13/2019 Cjmlpas Pdaf Notes
9/55
R.A. No. 8174, Article XLII
1996 Countrywide Development FundSpecial Provision No. 1 Use and Release of Funds.
The amount herein appropriated shall be used forinfrastructure, purchase of equipment and other priorityprojects and activities, including current operatingexpenditures, except creation of new plantilla positions asproposed and identified by officials concernedaccording to the following allocations:Representatives, P12.5M each; Senators, P18M each;Vice-President, P20M.
The fund shall be automatically released semi-annually byway of Advice of Allotment and Notice of Cash Allocationdirectly to the designated implementing agency not later than30 days after the beginning of each semester upon submissionof the list of projects and activities by the officials concerned.
-
8/13/2019 Cjmlpas Pdaf Notes
10/55
R.A. No. 8174, Article XLII
1996 Countrywide Development Fund
Special Provision No. 2 Submission of Semi-
Annual Reports
The DBM shall submit within 30 days after the endof each semester a report to the Senate Committee
on Finance and the House Committee onAppropriations on the releases made from thisFund. The report shall include the listing of the
projects, locations, implementing agencies and theendorsing officials.
-
8/13/2019 Cjmlpas Pdaf Notes
11/55
R.A. No. 8250, Article XLII
1997 Countrywide Development FundSpecial Provision No. 1 Use of Funds.
The amount herein appropriated shall be used forinfrastructure, purchase of equipment and other priorityprojects and activities, including current operatingexpenditures, except creation of new plantilla positions asproposed and identified by officials concernedaccording to the following allocations:Representatives, P11.25M each; Senators, P10.8M
each; Vice-President, P18M.
-
8/13/2019 Cjmlpas Pdaf Notes
12/55
R.A. No. 8250, Article XLII
1997 Countrywide Development FundSpecial Provision No. 2 Publication ofCountrywide Development Fund Projects
Within 30 days after the signing of this Act into law, theMembers of Congress and the Vice-President shall, in consultation
with the implementing agency concerned, submit to the DBM the listof 50% of projects to be funded from the allocation from the CDF
which shall be duly endorsed by the Senate President and theChairman of the Committee on Finance in the case of Senate andSpeaker of the House of Representatives and the Chairman of theCommittee on Appropriations in the case of the House of
Appropriations and the remaining 50% within six (6) months
thereafter.
Continued next page
-
8/13/2019 Cjmlpas Pdaf Notes
13/55
R.A. No. 8250, Article XLII
1997 Countrywide Development FundSpecial Provision No. 2 Publication ofCountrywide Development Fund Projects
The list shall identify the specific projects, locations,implementing agencies, and target beneficiaries and shall be the basisfor the release of funds. The said list shall be published in a
newspaper of general circulation by the Department of Budget andManagement. No funds appropriated herein shall be disbursed forprojects not included in the list herein required.
-
8/13/2019 Cjmlpas Pdaf Notes
14/55
R.A. No. 8250, Article XLII
1997 Countrywide Development FundSpecial Provision No. 3 Release of Fund
The fund shall be released by way of Special AllotmentRelease Order and Notice of Cash Allocation directly tothe designated implementing agency within 10 days afterthe publication of the list of projects as required in thepreceding section.
-
8/13/2019 Cjmlpas Pdaf Notes
15/55
R.A. No. 8522, Article XLII
1998 Countrywide Development Fund
Special Provision No. 1 Use of Fund
The amount herein appropriated shall be used forinfrastructure, purchase of equipment and otherpriority projects and activities, including currentoperating expenditures except creation of new
plantilla positions as proposed and identifiedby officials concerned according to thefollowing allocations: Representatives,P11.25M each; Vice-President, P18M.
-
8/13/2019 Cjmlpas Pdaf Notes
16/55
R.A. No. 8522, Article XLII
1998 Countrywide Development FundSpecial Provision No. 2 Publication of
Countrywide Development Fund Projects
Within 45 days after the signing of this Act into law, the Membersof the House of Representatives and the Vice-President shall,submit to the DBM the list of 50% of projects to be funded from theallocation from the Countrywide Development Fund which shall beduly endorsed by the Speaker of the House of Representatives andthe Chairman of the Committee on Appropriations in the case of theHouse of Representatives and the remaining 50% within six (6)months thereafter. The list shall identify the specific projects,location, implementing agencies, and target beneficiaries and shall
be the basis for the release of funds. The said list shall be published
for in a newspaper of general circulation by the Department ofBudget and Management: PPROVIDED, That said publication is nota requirement for the release of funds.
-
8/13/2019 Cjmlpas Pdaf Notes
17/55
R.A. No. 8522, Article XLII
1998 Countrywide Development FundSpecial Provision No. 3 Release of
Fund
The fund shall be released by way of Special
Allotment Release Order and Notice of CashAllocation directly to the designatedimplementing agency based on the list of
projects as required in the preceding section.
-
8/13/2019 Cjmlpas Pdaf Notes
18/55
R.A. No. 8745, Article XLII
1999 Food Security Program FundSpecial Provision No. 1 Use and Release of
Fund
The amount herein authorized shall be used tosupport the Food Security Program of the
government, which shall include farm-to-marketroads, post harvest facilities, and other agriculturalrelated infrastructures. Releases from this Fundshall be made directly to the implementing agency
subject to prior consultation with theMember of Congress concerned.
-
8/13/2019 Cjmlpas Pdaf Notes
19/55
1999 Lingap Para sa Mahihirap ProgramFundSpecial Provision No. 1 Use and Release of
Fund
The amount herein authorized for the Lingap Parasa Mahihirap Program Fund shall be used
exclusively to satisfy the minimum basic needs ofpoor communities and disadvantaged sectors:PROVIDED, That such amount shall be releaseddirectly to the implementing agency upon prior
consultation with the Member of Congressconcerned.
-
8/13/2019 Cjmlpas Pdaf Notes
20/55
-
8/13/2019 Cjmlpas Pdaf Notes
21/55
2001 Reenacted Budget
-
8/13/2019 Cjmlpas Pdaf Notes
22/55
R.A. No. 9162, Article XLIX
2002 Priority Development Assistance Fund
Special Provision No. 1 Use and Releaseof the Fund
The amount herein appropriated shall be usedto fund priority programs and projects or to fund
the required counterpart for foreign assistedprograms and projects: PROVIDED, That suchamount shall be released directly to theimplementing agency or Local Government Unitconcerned.
-
8/13/2019 Cjmlpas Pdaf Notes
23/55
R.A. No. 9206, Article XLVII
2003 Priority Development Assistance FundSpecial Provision No. 1 Use and Release of
the Fund
The amount herein appropriated shall be used to fundpriority programs and projects or to fund the requiredcounterpart for foreign assisted programs and projects:PROVIDED, That such amount shall be released directly to
the implementing agency or Local Government Unitconcerned concerned: PROVIDED, FURTHER, That theallocations authorized herein may be realigned to any expenseclass, if deemed necessary: PROVIDED, FURTHERMORE,That a maximum of 10% of the authorized allocations by
district may be used for the procurement of rice and otherbasic commodities which shall be purchased from theNational Food Authority.
-
8/13/2019 Cjmlpas Pdaf Notes
24/55
R.A. No. 9206
2003 DPWH BudgetSpecial Provision No. 1 Restriction on the
Delegation of Project Implementation
The implementation of the projects funded herein shall notbe delegated to other agencies, except those projects to beimplemented by the Engineering Brigades of the AFP and
inter-department projects undertaken by other offices andagencies including local government units with demonstratedcapability to actually implement the projects by themselvesupon consultation with the Members of Congress
concerned. In all cases the DPWH shall exercise technicalsupervision over projects.
-
8/13/2019 Cjmlpas Pdaf Notes
25/55
R.A. No. 9206
2003 DepED School Building ProgramSpecial Provision No. 2 Allocation of School
Building
The allocation herein provided for school buildings shall beapportioned as follows: (1) 50% to be allocated pro-rataaccording to each legislative districts student population inrelation to xxx; (2) 40% to be allocated only among those
legislative districts with classroom shortages, pro-rata toxxx;(3) 10% to be allocated in accordance with the policyconsiderations as may be determined by the DepEd:PROVIDED that calamity stricken areas shal lbe given priority
in the implementation of the DepEd School BuildingProgram.
-
8/13/2019 Cjmlpas Pdaf Notes
26/55
R.A. No. 9206
2003 DepED School Building Program
Special Provision No. 3 Submission of theList of School Buildings
Within 30 days after the signing of this Act intolas, DepEd after consultation with therepresentative of the legislative district
concerned, shall submit to DBM the list of 50%of school buildings to be constructed everymunicipality xxx. The list as submitted shall be
the basis for the release of funds xxxx.
-
8/13/2019 Cjmlpas Pdaf Notes
27/55
2004 Reenacted Budget
-
8/13/2019 Cjmlpas Pdaf Notes
28/55
R.A. No. 9336, Article L
2005 Priority Development Assistance Fund
Special Provision No. 1 Use and Release of the FundThe amount appropriated herein shall be used to fund
priority programs and projects under the 10-Point Agenda ofthe national government and shall be released directly to theimplementing agencies, as indicated hereunder, to wit:
(Note: Project Menu is presented with the list of priorityprograms and projects together with the identified
implementing agencies)
PROVIDED, That in the procurement of commonly useditems, the implementing agencies shall adhere to the price listand the rules and regulations to be issued by the government
procurement policy board.
-
8/13/2019 Cjmlpas Pdaf Notes
29/55
R.A. No. 9336
2005 DepED School Building Program
Special Provision No. 2 Allocation of
School BuildingsThe allocation herein provided for schoolbuildings shall be apportioned as follows: (1)
50% to be allocated pro-rata according toeach legislative districts studentpopulation xxxx; (2) 40% to be allocatedonly among those legislative districts withclassroom shortages xxxxx; (3) 10% to beallocated in accordancexxxx
-
8/13/2019 Cjmlpas Pdaf Notes
30/55
-
8/13/2019 Cjmlpas Pdaf Notes
31/55
2006 Reenacted BudgetR.A. 9358 Supplemental Budget for 2006
Sec. 2.A Use of Funds The amount of P1.0Bappropriated for school building under B.1 shall beapportioned as follows: xxxx
Provided, That the funds shall be directly released to andadministered by the DPWH: Provided, further, That toencourage the participation of nongovernmentalorganizations (NGOs) in the construction of school buildings,
the amount of at least P250M, of the P500M for theconstruction and completion of school buildings shall be madeavailable to NGOs, including the Federation of Filipino-Chinese Chambers of Commerce and Industry, Inc. for itsOperation Barrio School program with capability and
proven track record in the construction of public schoolbuildings: xxxxx
-
8/13/2019 Cjmlpas Pdaf Notes
32/55
R.A. No. 9401, Article XLVII
2007 Priority Development Assistance FundSpecial Provision No. 1 Use and Release of the Fund
The amount appropriated herein shall be used to fund priorityprograms and projects under the 10-Point Agenda of the national
government and shall be released directly to the implementing agencies, asindicated hereunder, to wit:
(Note: Project Menu is presented with the list of priority programsand projects together with the identified implementing agencies)
PROVIDED, That in the procurement of commonly used supplies,the implementing agencies shall adhere to the price list and the rules andregulations to be issued by the Government Procurement Policy Board:PROVIDED, FURTHER, That the amount of P300M shall be set aside asseed money for the Kalinga Pilipinas Congressional District Housing
Program at P5M per congressional district with counterpart funding in theequivalent amount from the allocation of each congressional district.
-
8/13/2019 Cjmlpas Pdaf Notes
33/55
-
8/13/2019 Cjmlpas Pdaf Notes
34/55
GPPB Resolution No. 12-2007 dated June 29, 2007
Amendment of Sec. 53 of the Implementing Rules andRegulations Part A of R.A. 9184 and PrescribingGuidelines on Participation of Non-Governmental
Organizations in Public ProcurementSec. 53 - Negotiated Procurement is a method xxxxx
When an appropriation law or ordinance earmarks anamount to be specifically contracted out to Non-Governmental Organizations (NGOs), the procuring entitymay enter into a Memorandum of Agreement with an NGO,subject to guidelines to be issued by the GPPB.
-
8/13/2019 Cjmlpas Pdaf Notes
35/55
2007 DPWH Regular Budget
Special Provision No. 1 Restriction on Delegation ofProject Implementation
The implementation of the project funded herein shall not be
delegated to other agencies, except those projects to beimplemented by the AFP Corps of Engineers, and inter-department projects to be undertaken by other offices andagencies, including local government units with demonstrated
capability to actually implement the projects by themselvesupon consultation with the representative of thelegislative district concerned xxx
-
8/13/2019 Cjmlpas Pdaf Notes
36/55
2007 DPWH Regular Budget
Special Provision No. 16 Realignment of Funds
The Secretary of Public Works and Highways is authorized to
realign funds released from appropriations under B.I.g fromone project/scope of work to another: PROVIDED, That xxxx(iii) the request is with the concurrence of thelegislator concerned; xxxx.
-
8/13/2019 Cjmlpas Pdaf Notes
37/55
R.A. No. 9498, Article XLVI
2008 Priority Development Assistance FundSpecial Provision No. 1 Use and Release of the Fund
The amount appropriated herein shall be used to fund priorityprograms and projects under the 10-Point Legacy Agenda of the
national government and shall be released directly to theimplementing agencies, as indicated hereunder, to wit:(Note: Project Menu is presented with the list of priority programsand projects together with the identified implementing agencies)
PROVIDED, That in the procurement of commonly used supplies,the implementing agencies shall adhere to the price list and therules and regulations to be issued by the Government ProcurementPolicy Board: PROVIDED, That the amount herein authorized cannot be impounded and shall be released within the budget year:PROVIDED, FURTHERMORE, That the appropriation herein
authorized shall have validity of 2 years as provided under Section66 of the General Provisions of this Act.
-
8/13/2019 Cjmlpas Pdaf Notes
38/55
R.A. No. 9498
2008 DPWH Budget
Special Provision No. 1 Restriction onDelegation of Project Implementation
Special Provision No. 17 Realignment ofFunds
The wordings are the same as in theprevious years
-
8/13/2019 Cjmlpas Pdaf Notes
39/55
2008 DepED School Building ProgramBudgetSpecial Provision No. 2 Allocation of
School Buildings
Special Provision No. 3 Submission of theList of School Buildings
The wordings are the same as in theprevious years
-
8/13/2019 Cjmlpas Pdaf Notes
40/55
R.A. No. 9524, Article XLIX
2009 Priority Development Assistance FundSpecial Provision No. 1 Use and Release of the Fund
The amount appropriated herein shall be used to fund priorityprograms and projects under the 10-Point Legacy Agenda of the national
government and shall be released directly to the implementing agencies,as indicated hereunder, to wit:
(Note: Project Menu is presented with the list of priorityprograms and projects together with the identified implementingagencies)
PROVIDED, That in the procurement of common-used supplies,the implementing agencies shall adhere to the price list and the rules andregulations to be issued by the Government Procurement Policy Board
-
8/13/2019 Cjmlpas Pdaf Notes
41/55
2009 DPWH BudgetSpecial Provision No. 1 Restriction on Delegation ofProject Implementation
Special Provision No. 19 Realignment of Funds
The wordings are the same as in the previous years
Special Provision No. 12 Notice of Project Implementation
To enhance transparency, the DPWH shall coordinate and notifyin writing the representative of the district concerned, theimplementation of all projects whether sourced from newappropriations under this Act or other authorized appropriations.
Note: Direct veto by the President
-
8/13/2019 Cjmlpas Pdaf Notes
42/55
2009 DepED BudgetSpecial Provision No. 15 Construction of School Buildingsin Areas Experiencing Acute Classrooms Shortage
School buildings for areas experiencing acute classroom shortagemay be funded out of the appropriation under B.I.e in accordancewith the guidelines to be formulated by the DepEd. For this purpose,Areas Experiencing Acute Classroom Shortage shall refer to xxxx;(PROVIDED, That upon concurrence of the Representative of the
district concerned, local government units with constructioncapability may be allowed to undertake the construction capabilitymay be allowed to undertake the construction of school building
within their locality): PROVIDED, FURTHER that the DepEd shall
allow the participation of non-government organizations in thebidding and construction of school buildings. (Direct veto,Presidents Veto Message, March 12, 2009, page 1251, RA9524)
-
8/13/2019 Cjmlpas Pdaf Notes
43/55
2009 DepED School Building Program
BudgetSpecial Provision No. 2 Allocation of
School Buildings (Direct veto by the
President)
Special Provision No. 3 Submission of the
List of School Buildings (The wordings arethe same as in the previous years)
-
8/13/2019 Cjmlpas Pdaf Notes
44/55
R.A. No. 9970, Article XLVII
2010 Priority Development Assistance FundSpecial Provision No. 1 Use and Release of the Fund
The amount appropriated herein shall be used to fundpriority programs and projects under the 10-Point Legacy
Agenda of the national government and shall be releaseddirectly to the implementing agencies, as indicated hereunder,to wit:
(Note: Project Menu is presented with the list of priorityprograms and projects together with the identifiedimplementing agencies)
PROVIDED, That in the procurement of common-usedsupplies, the implementing agencies shall adhere to the price
list and the rules and regulations to be issued by theGovernment Procurement Policy Board
R A N 9970
-
8/13/2019 Cjmlpas Pdaf Notes
45/55
R.A. No. 9970
2010 DPWH Budget Special Provision No. 1 Restriction on
Delegation of Project Implementation
Special Provision No. 17 Realignment ofFunds
The wordings are the same as in theprevious years
-
8/13/2019 Cjmlpas Pdaf Notes
46/55
2010 DepED School Building Program
BudgetSpecial Provision No. 2 Allocation of
School Buildings
Special Provision No. 3 Submission of theList of School Buildings
The wordings are the same as in theprevious years
R A N 10147
-
8/13/2019 Cjmlpas Pdaf Notes
47/55
R.A. No. 10147
2011 Priority Development Assistance FundSpecial Provision No. 1 Use and Release
of the Fund
The amount appropriated herein shall be usedto fund the following priority programs andprojects to be implemented by thecorresponding agencies:
(Note: Project Menu is presented with thelist of priority programs and projects togetherwith the identified implementing agencies and
the list of requirements)
R A N 10147
-
8/13/2019 Cjmlpas Pdaf Notes
48/55
R.A. No. 10147
2011 Priority Development Assistance FundSpecial Provision No. 2 Allocation of
Funds
Congressional District and Party ListRepresentatives: P70M (P40M for hard projectsand P30M for soft projects)
Senators: P200M (P100M for hard projects andP100 for soft projects)
R A No 10155
-
8/13/2019 Cjmlpas Pdaf Notes
49/55
R.A. No. 10155
2012 Priority Development Assistance FundSpecial Provision No. 1 Use and Release
of the Fund
The amount appropriated herein shall be used tofund the following priority programs andprojects to be implemented by thecorresponding agencies:
(Note: Project Menu is presented with thelist of priority programs and projects togetherwith the identified implementing agencies and
the list of requirements)
R A No 10155
-
8/13/2019 Cjmlpas Pdaf Notes
50/55
R.A. No. 10155
2012 Priority Development Assistance FundSpecial Provision No. 3 LegislatorsAllocation
Congressional District and Party ListRepresentatives: P70M (P40M for hard projectsand P30M for soft projects)
Senators: P200M (P100M for hard projects andP100 for soft projects)
R A No 10155
-
8/13/2019 Cjmlpas Pdaf Notes
51/55
R.A. No. 10155
2012 Priority Development Assistance FundSpecial Provision No. 2 Legislators
AllocationIdentification of projects and/or designation of
beneficiaries shall conform to the priority list,standard or design prepared by each implementingagency: PROVIDED, That preference shall be givento projects located in the 4th to 6th class
municipalities or indigents identified under theNHTS-PR by the DSWD. For this purpose, theimplementing agency shall submit to Congress saidpriority list, standard or design within 90 days from
effectivity of this Act.
R A No 10352
-
8/13/2019 Cjmlpas Pdaf Notes
52/55
R.A. No. 10352
2013 Priority Development Assistance FundSpecial Provision No. 1 Use and Release of
the Fund
The amount appropriated herein shall be used tofund the following priority programs and projects tobe implemented by the corresponding agencies:
(Note: Project Menu is presented with the list ofpriority programs and projects - categorized intohard and soft projects, together with the identifiedimplementing agencies and list of requirements)
R A No 10352
-
8/13/2019 Cjmlpas Pdaf Notes
53/55
R.A. No. 10352
2013 Priority Development Assistance FundSpecial Provision No. 1 Use and Release of
the FundPROVIDED, That this Fund shall not be used for thepayment of Personal Services expenditures:PROVIDED, FURTHER, That all procurement shallcomply with the provisions of R.A. No. 9184 and itsRevised Implementing Rules and Regulations:
PROVIDED, FINALLY, That for infrastructureprojects, LGUs may only be identified asimplementing agencies if they have the technicalcapability to implement the same
R A No 10352
-
8/13/2019 Cjmlpas Pdaf Notes
54/55
R.A. No. 10352
2013 Priority Development Assistance FundSpecial Provision No. 2 Project Identification
Identification of projects and/or designation of beneficiaries shallconform to the priority list, standard or design prepared by eachimplementing agency: PROVIDED, That preference shall be given toprojects located in the 4th to 6th class municipalities or indigentsidentified under the NHTS-PR by the DSWD. For this purpose, theimplementing agency shall submit to Congress said priority list,standard or design within 90 days from effectivity of this Act.
All programs/projects, except for assistance to indigents patientsand scholarships, identified by a member of the House ofRepresentatives outside of his/her legislative district shall have the
written concurrence of the member of the House of Representativesof the recipient or beneficiary legislative district, endorsed by the
Speaker of the House of Representatives
R A No 10352
-
8/13/2019 Cjmlpas Pdaf Notes
55/55
R.A. No. 10352
2013 Priority Development Assistance FundSpecial Provision No. 3 LegislatorsAllocation
The amount of projects to be identified bylegislators shall be as follows:a. For Congressional District and Party-listRepresentatives: P30M for the soft programsand projects and P40M for the infrastructureProjects
b. For Senators: P100M for soft projects and
P100 for hard projects