PRODUCT COST CONTROLLING END USER TRAINING DOCUMENTS COST CENTER ACCOUNTING Functionality The Material cost estimate is calculated for all the in-house manufactured products (finished goods and semi finished goods). The system accesses the Bill of Material and Routing or Master Recipe maintained by PP for the finished goods. It is used to calculate the cost of good manufactured and cost of good sold for each product unit. Business Scenario You want to calculate & save cost estimate for a new product to be produced in plant 1200 since the beginning of May 2004. Requirements Reqd from Production Planning Quantity structure for the material was prepared by PP: Bill Of Material and rate routing for repetitive manufacturing Master Recipe for process manufacturing Reqd from Controlling The following done by the CO: Procurement alternative were created if more than one version exist Mixing Ratios were maintained if more than one more procurement alternative exist Menu Path Accounting Controlling Product Cost Controlling Material Costing Cost Estimate with Quantity Structure CK11N - Create Transaction Code CK11N SAPTOPJOBS Page 1 of 19

Upload: zakir-chowdhury

Post on 01-Nov-2014

95 views

Category:

Documents


3 download

DESCRIPTION

CK11N Create Material Cost Estimate

TRANSCRIPT

Page 1: CK11N Create Material Cost Estimate

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Functionality

The Material cost estimate is calculated for all the in-house manufactured products (finished goods and semi finished goods). The system accesses the Bill of Material and Routing or Master Recipe maintained by PP for the finished goods. It is used to calculate the cost of good manufactured and cost of good sold for each product unit.

Business Scenario

You want to calculate & save cost estimate for a new product to be produced in plant 1200 since the beginning of May 2004.

Requirements

Reqd from Production PlanningQuantity structure for the material was prepared by PP:

Bill Of Material and rate routing for repetitive manufacturing Master Recipe for process manufacturing

Reqd from Controlling

The following done by the CO: Procurement alternative were created if more than one version exist Mixing Ratios were maintained if more than one more procurement alternative exist

Menu Path Accounting Controlling Product Cost Controlling Material Costing Cost Estimate with Quantity Structure CK11N - Create

Transaction Code CK11N

1. Double click on CK11N - Create.

SAPTOPJOBS Page 1 of 12

Page 2: CK11N Create Material Cost Estimate

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

2. Update the following fields:

Field Name Field Description Values

Material Code identifying a product or component

22000051

Plant Code identifying the operational unit of the company where the material is manufactured and stored

1200

Costing variant Costing variant, i.e. for Legal valuation.

SPC1

Costing version Costing version, i.e. for mix costing considering different production versions.

1

3. Click the Dates tab button.

SAPTOPJOBS Page 2 of 12

Page 3: CK11N Create Material Cost Estimate

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Note: Alternatively you can click the Enter button or click the Default values button to copy the dates, as you prepare costing for the next period. If you would like to create cost estimate to be used since the current date you have to specify this current date in the ‘Costing date from’ field.

4. Update the following fields:

Field Name Field Description Values

Costing date from Description of the Costing date from.

01.05.2004

Costing date to Description of the Costing date to.

31.12.9999

Qty structure date Description of the Qty structure date.

01.05.2004

Valuation date Description of the Valuation date.

01.05.2004

5. Click the Enter button.

SAPTOPJOBS Page 3 of 12

Page 4: CK11N Create Material Cost Estimate

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

6. Click the Only materials / All items button.

SAPTOPJOBS Page 4 of 12

Page 5: CK11N Create Material Cost Estimate

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

7. Click the Dates tab button.

SAPTOPJOBS Page 5 of 12

Page 6: CK11N Create Material Cost Estimate

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

8. Click the Qty struct. tab button.

SAPTOPJOBS Page 6 of 12

Page 7: CK11N Create Material Cost Estimate

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

9. Click the Valuation tab button.

SAPTOPJOBS Page 7 of 12

Page 8: CK11N Create Material Cost Estimate

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

10. Click the History tab button.

11. Click the Costs tab button.

SAPTOPJOBS Page 8 of 12

Page 9: CK11N Create Material Cost Estimate

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

12. Click the List button.

SAPTOPJOBS Page 9 of 12

Page 10: CK11N Create Material Cost Estimate

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Display Material Cost Estimate with Quantity Structure 

13. Click the Type of Cost Component Split  button.

SAPTOPJOBS Page 10 of 12

Page 11: CK11N Create Material Cost Estimate

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Type of cost component split

14. Click the Auxiliary cost component split radio button.

15. Click the Continue button.

Display Material Cost Estimate with Quantity Structure

16. Click the Save button.

SAPTOPJOBS Page 11 of 12

Page 12: CK11N Create Material Cost Estimate

PRODUCT COST CONTROLLINGEND USER TRAINING DOCUMENTS

COST CENTER ACCOUNTING

Display Material Cost Estimate with Quantity Structure

SAPTOPJOBS Page 12 of 12