clarifiers getting old? the city of warren’s experience in
TRANSCRIPT
Clarifiers Getting Old? The City of Warren’s Experience in Replacing Final
Clarifiers
Trevor Wagenmaker, P.E., Hubbell, Roth & Clark Todd Schaedig, P.E., City of Warren.
January, 2017
Background
City of Warren is the 3rd largest City in Michigan with a population of 135,000
Home to the General Motors Tech Center
Background
City of Warren WWTP is a 54 MGD Tertiary Plant with a peak wet weather flow of 180 MGD
Secondary Treatment System includes eight (8) 100 foot diameter secondary clarifiers.
There are two banks of four clarifiers each, with a splitting box for each back of clarifiers
Background
Four (4) of the eight clarifiers were constructed in the 1950’s and had not been rehabilitated since
Background
There were in extremely poor condition
Flow Split Structure
The flow split structure was also failing
Summary of Problems
Clarifiers only had 10 feet of sidewater depth which limited performance (10 State Standards recommended depth is 12 feet)
Generally poor settling performance due to configuration of effluent weirs and lack of baffling
Constant breakdowns in clarifier mechanisms and steel degradation to the point of yearly failures
Summary of Problems (cont.)
No SCADA control or monitoring of any electrical components
Ice problems in the winter with the scum beach/scum arm freezing
Concrete degradation of the tanks increasingly bad Flow split structure was very difficult to operate with
no gate operators and limited access
Study Phase
Option of Total Replacement versus Partial replacement Costs were much higher for total replacement Base slab was in good condition Pipes were in good condition
How increase sidewater depth of tanks to 12 feet? This would require either raising flow split structure
approximately two feet or lowering clarifier base slab Backwater affects to aeration tanks were a concern
Study Phase (cont.)
How maintain treatment during construction? Reconstructing flow split structure would eliminate
existing piping connections to all four clarifiers Performance Enhancements Influent flow dissipation. Numerous options by different
manufacturers, LA-EDI Effluent flow baffling Effluent In-board Launders Stamford Baffles
Study Phase
Performance enhancement options Resolve ice issues for scum arm Torque monitoring for clarifier drive (SCADA) Algae control on effluent weirs/launders Brushes Effluent trough covers
Automatic control for flow split structure gates Roadway thru the area
Demolition
Walls and mechanism were removed
Construction Process
Base slab was extended/thickened.
Construction Process
New taller walls, reconnection of pipes.
Construction Process
Grout floor topping removed and replaced, new concrete effluent launders.
Temporary Flow Bypass System
Maintain flow to two clarifiers while flow split structure was being reconstructed
Temporary Flow Bypass System
Routed temporary pipe to influent of clarifiers
Galvanizing Operation of Steel Clarifier Mechanism
Galvanizing of new clarifier mechanism steel components eliminates need to field paint
Construction Process
Clarifier mechanism installed.
Flow Split Structure
• Resealed floor opening to effluent chamber below
Flow Split Structure
• Rebuilt walls, new automated gates to each clarifier
Site Improvements
New roadway thru site
Algae Brushes
Effluent Stamford Baffles
Dual Suction Header Sludge Withdrawal
Influent Flow Dissipation
Torque Monitoring
SCADA Improvements
Costs
Total Project Cost $5,460,393.94 Study of Alternatives $32,000.00 Project Design $247,400.00 Geotechnical Investigation $5,954.18 Construction Cost $4,989,170.76 Materials Testing $13,801.96 Construction Administration $98,960.00 Controls Manufacturing and Programming $59,427.04 Project Inspection - Performed by Plant Staff - Estimated
Savings $150,000
Questions