EE97 Lectures
Senior Project DesignFall 2006
Lecture 5Concept: Risk & Risk Management
10-06-06
2
Quote for the Day
“Knowledge to inform…guts to lead”
—Ron Lasser
3
First Thoughts on Risk
What does this tell us about risk?
4
Risk Management ala’ Dilbert
5
And another view
6
“The biggest risk may be not taking any”
Risk as a Paradox
7
“Nothing ventured,nothing gained”
Or…Maybe Other Terms
8
“Footprints in the sands of time were not made by those sitting down”
Or...in as Action
9
“You miss 100% of theshots you don’t take”
Or…by Wayne Gretzky
10
“You can’t steal 2nd base with one foot on 1st base”
—Unknown
Or…by way of The National Pastime
11
The ObjectivesUnderstand risk Apply project risk management to your project for your project proposalIdentify the elements of a risk management planList common sources of risks in technology projectsIdentify the qualitative risk analysis process and explain how to calculate risk factors and use expert judgment to rank risksExplain the quantitative risk analysis process and how to apply decision trees, simulation, and sensitivity analysis to quantify risksProvide examples of negative and positive risksDiscuss what is involved in risk management
12
Risk and Regret
Risk is the chance or possibility of lossRegret is the amount of loss a person can tolerate
13
What is risk?risk (r ih sk) n.
The possibility of suffering harm or loss; danger. A factor, thing, element, or course involving uncertain danger; a hazard: “the usual risks of the desert: rattlesnakes, the heat, and lack of water”(Frank Clancy)
The danger or probability of loss to an insurer. The amount that an insurance company stands to lose.
The variability of returns from an investment. The chance of nonpayment of a debt.
One considered with respect to the possibility of loss: a poor risk.
14
Or is Risk…The potential future harm that may arise from some present action
Often combined or confused with the probability of an event which is seen as undesirable
A believable scenario combining regret and rewardprobabilities into an expected value
The assessment of some probability of expected harms
The value at riskAssessment (or "measure" although it is not usually possible to directly measure) of risk, and (for some applications) the formal methods used to determine this value
15
What is regret?re·gret (r -gr t )
v. tr.To feel sorry, disappointed, or distressed about. To remember with a feeling of loss or sorrow; mourn.
v. intr.To feel regret.
n.A sense of loss and longing for someone or something gone. A feeling of disappointment or distress about something that one wishes could be different.
regretsA courteous expression of regret, especially at having to decline an invitation.
16
Anunexpected
eventor change
Aprobability
of thatevent
Theimpactof thatevent
R I S K
“Cause” “Consequence”“Chance”
Maybe we should talk about chance...
The Three Components of
17
What is Uncertainty?
un·cer·tain·ty n-sûr tn-tn. pl. un·cer·tain·tiesThe condition of being uncertain; doubt. Something uncertain: the uncertainties of modern life.Statistics. The estimated amount or percentage by which an observed or calculated value may differ from the true value
Great! So now we need to know the definition of uncertain
18
What does Uncertain mean?
un·cer·tain n-sûr tnadj.
Not known or established; questionable: domestic changes of great if uncertain consequences.Not determined; undecided: uncertain plans.Not having sure knowledge: an uncertain recollection of the sequence of events.
Subject to change; variable: uncertain weather.Unsteady; fitful: uncertain light.
19
Frank H. Knight established the economic definition of the terms in his landmark book, Risk, Uncertainty, and Profit (1921): risk is present when future events occur with measurable probabilityuncertainty is present when the likelihood of future events is indefinite or incalculable
Uncertainty vs. RiskUncertainty:
Some parameters are not knownRisk assessments may be right or wrong
Risk:Fully quantified (for example, a die)
Decision-maker knows all of the odds
20
Certainty:
•Each decision has a known outcome•Problem can be solved deterministically
Risk
•The nature of the problem is random•But the probabilities of the different states are known
Uncertainty:
•The nature of the problem is random•The probabilities of the different states are unknown
Conflict:
•The nature of theproblem is random•The probabilitiesof the different statesare somewhatdetermined by anopponent
You are here (probably)
Chaos:
•Uncertainty even in the fundamentals
Spectrum of the… Unknown
21Source: De Meyer, Loch, Pich, INSEAD Singapore 2000 IEEE Conference on Management of Innovation and Technology
Types of Uncertainty
Variation in durations, costs, performance levels of resourcesForeseen risks (identified upfront)Unforeseen risks (encountered
mid-project)Chaos – fundamental uncertainty about the basic structure of the project
22
What is Consequence?con·se·quencen.
Something that logically or naturally follows from an action or condition. The relation of a result to its cause. A logical conclusion or inference. Importance in rank or position: scientists of consequence.Significance; importance: an issue of consequence.
23
What is Mitigation?
mit·i·gatev.v. tr.
To moderate (a quality or condition) in force or intensity; alleviate. v. intr.To become milder.
24
Concept Planning Implementation Close-out
Risk
Total (cumulative) Cost
Risk impact is the highestduring this period
Risk and Cost over a Project Lifecycle
25
Frank and Ernest -- “Classifying Risk”
26Also: social implications of teambuilding, the need to be positiveand uplifting. Negative thoughts are socially suppressed.
What causes projects to overlook risk?
Quantifying risks could lead to the project not being funded
“conflict of interisk” – shows need for independent analysis
The stakeholder doesn’t want to spend the time/energy
“the Nike stakeholder – just do it”The stakeholder doesn’t believe that the risks are real
“The ostrich effect”The stakeholder wants to “keep it simple”
“The ignorant stakeholder”
27
Risk Management ProcessIdentification and assessmentPossible actions available:
Avoidance Reduction Retention Transfer
Create the planImplementationReview and evaluation of the plan
28
Categories of Project Risk
Known, controllable (subjective)Known, uncontrollable (objective)Unknown
29
Strengths
Weaknesses
ThreatsOpportunities
Major possibilitiesfor project success
Leave these opportunitiesfor others to explore HIGH RISK AREA !
Determine how to usestrengths to defend
SWOT Analysis
Helps identify the broad negative and positive risks that apply to a project
30
Aware of Aware of
Manage
Track only
ManageWorkReduction
Risk Avoidance Risk Management
• identify risks up front• assess impact to project• focus management on critical risks• track the broader scope of risks
• identify risks up front• assess impact to project• manage all risks
Source: US Navy, Acquisition Reform – Performance-Based Business Environment Initiative SECNAVINST 5000.2
Moving from Risk Avoidance to Risk Management
31
assumption risk
Low probability and/or low severity
riskscan be managed as assumptions and
tracked accordingly
…but carefully consider your
assumptions and monitor them – they easily become risks
..see p38-40 of Royer
Unmanaged assumptions are not as apparentas risks – but can be most dangerous to your project.Consider them a “source” of risk even though not yeta risk themselves.
Assumptions and Risks
32
Manageable Risks?
Only some factors are truly manageable risks.Make sure you spend your time managing those risks.
33
Risk Conditions (Sampling)
IntegrationInadequate planning, insufficient resources, lack of training ramp up time, insufficient project definition
ScopePoor project and mission objectives, incomplete quality definition, inadequate plans for control of scope (added requirements as project progresses)
TimeErrors in schedule, task, and activity durations, poor allocation of resources, changes in scope, resource availability or lack of it when needed
CostError in cost estimates, productivity or performance failures, changes in contingencies, purchasing, planning, or equipment maintenance
QualityPoor attitude toward robust deliverables, substandard workmanship, materials, or design, inadequate quality assurance reviews or practice
CommunicationsCarelessness in planning, lack of documentation, lack of weekly status review or other design reviews
EthicsLack of authenticity or honesty in transactions, lack of meeting commitments, illegal or immoral behavior or actions
34
The Risk “Filter”
Know when you’re really dealing with manageable risk!
35
Best Risk Statement"If we fail to communicate clearly then effort will be wasted resolving misunderstandings"•Has a probability
•we can ask how likely this is to happen•Has a consequence
•additional cost and possible schedule delay
Poor Risk Statement"Communication is a problem"
•What is the probability? •What are the consequences? Better Risk Statement
"We may fail to communicate adequately"
•Expresses a probability •"may"
•Contains a condition •"fail to communicate…."
•Doesn't have a consequence
Generating Risk Statements
36
Closing Processes
Initiating Processes
Planning Processes
Controlling Processes
Executing Processes
Risk Management PlanningRisk IdentificationQuantitative Risk AnalysisQualitative Risk AnalysisRisk Response Planning
Risk Monitoring and Control
PMBOK® Process Groupings
Source: Project Management Book of Knowledge
37
What is Risk ManagementProcess of measuring, or assessing risk and then developing strategies to manage the risk
The ideal: a prioritization process whereby the risks with the greatest loss and the greatest probability of occurring are handled first, and risks with lower probability of occurrence and lower loss are handled laterTypicalaly, very difficult process to balance between risks with a high probability of occurrence but lower loss vs. a risk with high loss but lower probability of occurrence
An assessement of the opportunity cost: Resources spent on one task instead could be spent on other more profitable activities
Ideal: expend least amount of resources while reducing the effects of risk as much as possible
38
Why is Project Risk Management Important?
Art and science of identifying, analyzing, and responding to risk throughout project life cycleRisk management helps improve project success
Project definitionProject scopeEstimating realistic outcomes and durations
KPMG study found that 55 percent of runaway projects—projects that have significant cost or schedule overruns—did no risk management at all.*
*Source: Cole, Andy, “Runaway Projects—Cause and Effects,” Software World, Vol. 26, no. 3, pp. 3–5 (1995).
39
Benefits from Risk Management
80%
60%47% 47% 43%
35%
6%0%
20%
40%
60%
80%
100%
Anticip
ate/avo
id pro
blems
Preven
t surp
rises
Impro
ve ab
ility t
o neg
otiate
Meet c
ustom
er co
mmitmen
ts
Reduce
sche
dule sl
ipsRedu
ce co
st ov
erruns
None
Source: Kulik, Peter and Catherine Weber, “Software Risk Management Practices – 2001,” KLCI Research Group (August 2001).
40
“The essence of Risk Management lies in maximizing the areas where we have some control over the outcome while minimizing the areas where we have absolutely no control over the outcome and the linkage between cause and effect is hidden from us.”
The Essence
Source: Against The Gods by P. Bernstein, Ch 12, p197
41
PMBOK® Risk Management Overview
Risk ManagementPlanningIdentificationQualitative risk analysisQuantitative risk analysisRisk response planningRisk monitoring and control
42Source; Carnegie Mellon Software Engineering Institute
Communicatethroughout!
Contro
l
Analyze
Plan
Trac
k
Identify
Provide info and feedback inside/outside the project on risk activities, current risks, and emerging risks. Do this throughout all functions!
Communicate
Correct for deviations from plansControl
Monitor risk indicators and mitigations
Track
Translate risk info into decisions and mitigating actions (immediate and future) and implement those actions
Plan
Transform risk data into decision-making info. Evaluate impact, probability and timeframe, classify and prioritize risks
Analyze
Search for and locate risks before they become a problem
Identify
DescriptionFunction
CMU Risk ManagementIdentify, Analyze, Plan, Track, Control, Communicate
43
Risk Management PlanningA risk management plan is key deliverableProject team reviews multiple items to formulate plan:
Project definition documents Sponsor’s approaches to riskScheduleCustomer valueTrade-offsUnique items, agreements, suppliers, partners which are critical for success
Scope will vary with project requirements
44
Identification and assessment
Identify potential risksAssess potential severity of loss and to the probability of occurrence.
45
Risk Identification
Understanding what events are probable and might hurt or enhance a particular project.
Tools and techniques:
Brainstorming
The Delphi Technique
Interviewing
SWOT analysis
Categories of Risk• Market risk• Financial risk• Technology risk• People risk• Structure/process risk• ?
46
Brainstorming
A group technique to:Generate ideas or solutionMay be for a generic or a specific problemUsually by listing ideas spontaneously and without judgment
Recommended: an experienced facilitator needs to lead the work sessionMany different techniquesDon’t overuse or over abuse
Psychology literature shows that individuals produce a greater number of ideas working alone than they do through brainstorming in small, face-to-face groupsGroup effects often inhibit idea generation
47
Delphi TechniqueUsed to derive a consensus among a set of experts who make predictions about future developments.Performed with an independent and anonymous input regarding future eventsRepeated rounds of questioning with written responsesAvoids the biasing effects possible in oral methods—e.g., brainstorming
• Project risk experts participate –but anonymously.• Facilitator uses a questionnaire to gather ideas about key project risks.• Responses submitted and circulated to the experts for further comment.• Several rounds are used to reach consensus
48
InterviewingA method of fact-finding for collecting information in face-to-face, phone, e-mail, or instant-messaging discussionsSpeaking to people with knowledge in the application area or with applicable experience helps to identify potential risksPrepare a set of questions in advance to use as a guideline during an interviewUse open ended questionsLet the interviewee guide and lead you to where they want to take youSuccess, when the interview is over, is like having taken a walk in their shoes!
49
Course of Action for RiskContingency plans
Predefined actions project team will take if an identified risk event occursDefined for catastrophic events
Fallback plansDefined for high impact risks impacting objectives, budget, time, or peopleImplemented when attempts to reduce the risk are not effective
Contingency reservesMaintained by the project sponsor to reduce the cost or schedule overruns to a manageable level of riskProject team may or may not obtain these strategic reserves
50
Possible actionsRisk avoidance
Includes not performing an activity that could carry riskExample: not buying a property or business in order to not take on the liability that comes with it
Losing out on the potential gain that accepting (retaining) the risk may have allowed
Example: not entering a business to avoid the risk of loss, butavoids the possibility of earning the profits.
Risk reductionMethods that reduce the severity of the loss
Example: sprinklers designed to put out a fire to reduce the risk of loss by fireMethod may cause a greater loss by water damage and therefore may not be suitableHalon fire suppression systems may mitigate that risk, but the cost may be prohibitive as a strategy
Risk retentionAccepting the loss when it occurs
Example: self insuranceRisk transfer
Causing another party to accept the risk, typically by contractExample: Insurance; another involves contract language that transfers a risk to another party without the payment of an insurance premium
51
Create the Plan
Combine methods to be used Define contingency plans if risks do occur
Assess risk of contingency planDecide on escalation plan
Allocate resources to match methods
52
Implementation
Execute plan to mitigate risks
53
Review and Evaluation of the Plan
Establish checkpoints to evaluate risks on periodic intervalsChange execution as required
54
Risk Monitoring and ControlExecuting a risk management process to respond to unexpected or foreseen but undesired eventWorkarounds are responses to unplanned risk events when no contingency plans are availableRisk monitoring and control deliverables:
Requested changesRecommended corrective and preventive actionsUpdates to the risk matrix, project management plan, weekly status reports or other important documentation that communicates to all impacted individuals, project areas, and external project resources
55
LimitationsImproper assessment and prioritization is time wasted Too much time for assessment and managing diverts resources that may be otherwise profitably engage on higher return tasksFor unlikely events, better course is to simply retain the risk, and deal with the result if the loss does occurRisk management processes is a process, but should not be a project which prevents the organization from starting and completing real projects Value at risk is a measure used to estimate how the value of an asset decreases over a certain time period under usual conditions; risk management looks at a moment in time
56
Schedule
ScopeProduct, Deliverable, Output
Resources
$$$Quality&
what the customer wants
Risk Management Framework
57
Risk Breakdown Structure Example 1
HomeEntertainment
Business Technical OrganizationalProject
Management
Competitors
Suppliers
Cash flow
Hardware
Software
Mechanical
Sponsorsupport
Customersupport
Expertsupport
Schedule
Budget
Time
58Source: M. Ingbretson, PM Network, December 2002
Risk Breakdown Structure Example 2
59
Risk Breakdown Structure
A toolDetermines the hierarchy of potential risksOrganizes into categories for a projectIdentifies contingencies to mitigate multiple risks across several categories
Also called a risk assessment tree
60
Source: Hillson, David, “The Risk Breakdown Structure as an Aid to Effective Risk Management”, 2002This paper has templates of RBSs for SW development, construction, pharmaceutical, etc., projects
How to use the RBSRisk identification aid
Upper levels used as a prompt for complete coverageUsed as a basis for a risk checklist
Risk assessmentCompare identified risks using ‘risk score’ for each
Comparison of projects or tendersCommon framework allows direct comparison
Risk reporting and communicationEasy to roll-up risk information to external project team resources
Lessons LearnedAccessible, common format facilitates post-project reviews
61
Risk RegisterA document that contains the results of various risk management processes
Presented as a table or spreadsheet format
A tool for documenting potential risk events and related informationContains a list of identified risks and other information neededRisks refer to specific, uncertain events that may occur to the detriment or enhancement of the project
Source: Kendrick
62
Risk Register Contents (1)
An identification number for each risk eventA rank for each risk eventThe name of each risk eventA description of each risk eventThe category under which each risk event fallsThe root cause of each risk
Source: Kendrick
63
Risk Register Contents (2)
Triggers for each risk; triggers are indicators or symptoms of actual risk eventsPotential responses to each riskThe risk owner or person who will own or take responsibility for each riskThe probability and impact of each risk occurringThe status of each risk
Source: Kendrick
64
Possible fields for a “Risk Register”
Risk identification number Risk type (where indication helps in planning responses)Risk Owner Raised by (person)Date identifiedDate last updatedDescriptionCost if it materializesProbabilityImpact
ProximityPossible response actionsChosen actionTarget dateAction owner/custodian (if differs from risk owner)Closure dateCross references to plans and associated risks and may also includeRisk status and Risk Action Status
65
Risk Register—Example
66
Real Projects: The Truth Is Out ThereProjects FAIL for Three Reasons:
The Objective (Scope) Is Actually ImpossibleIt cannot be accomplished with the allocated amount of time
The Project Is Over ConstrainedThe Project Is Poorly Planned and Executed
Check Project Scope—make it realistic
Identify All Constraints—understand the restrictions
Construct A Project Plan—think through all tasks the team must accomplish for success
67
Risk Utility
Risk utility is the amount of satisfaction received from a potential payoff
Risk aversion have a low tolerance for taking chances
Utility rises at a decreasing rate for peopleRisk-seekers have a higher tolerance for risk
Satisfaction increases when more payoff is at stake
Risk neutrals seek a balance between risk and payoff
More likely to desire contingencies
68
Risk Utility as a function of Risk Preference
PotentialPayoff
Risk Averse
PotentialPayoff
Risk Neutral
PotentialPayoff
Risk Seeking
69
Assessing Risk
Probability theoryA branch of mathematics concerned with the analysis of random phenomenaIf the outcome of a random event cannot be determined before it occurs, but it may be any one of several possible outcomes, then the actual outcome is considered to be determined by chance
70
Impact of event*
Probability of event
Event
*Could be in dollars, time, morale, usually convertible to $$$$
Risk—Expressed as Impact and Probability!
LowRisk Moderate
Risk
HighRisk
Below Risk Threshold
71
0
1
2
3
4
5
6
1 2 3 4 5 6 7 8 9 10 11 12
Frequency
Risk Depends on Probability
If you throw a six-sided die:
72
Key Project Risk TerminologyRisk Event
Specific event that may affect the project for better or worse
Risk Event ProbabilityAn estimate of the chance that a given risk event will occur
Risk Event ValueAn estimate of the gain/loss that will be incurred to the project if that
Risk Event does occurExpected Monetary Value (EMV)Risk Event Value x Risk Event ProbabilityExpected Value (EV)
The value (similar to EMV) when the item being assessed is not $$$
73
Qualitative Risk Analysis
Assess the likelihood and impact of identified risks to determine their magnitude and priority.Risk quantification tools and techniques include:
Probability/impact matrixesThe Top Ten Risk Item TrackingExpert judgment
Source: Kendrick
74
Quantitative Risk Analysis
Often follows qualitative risk analysis, but both can be done together.Large, complex projects involving leading edge technologies often require extensive quantitative risk analysis.Main techniques include:
Decision tree analysisSimulationSensitivity analysis
Source: Kendrick
75
Macro RiskWhen loss and likelihood are considered in a large number of cases (a population), uncertainty becomes visible and distributions and histograms may be developed:
Frequency
LossesMean
76
Which project would yourather manage? Why?
Risk in Projects, Micro Risk
In project management, there is no population There is only one projectto be managed, so managing risk requires attention to the spread of the distribution as well as the meanTo compare two projects, where the loss is measured in time:
Consider that Project A has a decent chance of finishing BEFORE project B!
Expected Duration of Project A
Expected Duration of Project B
Frequency
Frequency
77
Probability/Impact MatrixLists the relative probability of a risk occurring on one side of a matrix or axis on a chart and the relative impact of the risk occurring on the otherConstruct:
List the risks and then label each one as high, medium, or low in terms of its probability of occurrence and its impact if it did occur
Also calculate risk factors:Numbers that represent the overall risk of specific events based on their probability of occurring and the consequences to the project if they do occur
Source: Kendrick
78
Probability/Impact Matrix—Example
Risk 6 Risk 9 Risk 1Risk 4
Risk 3Risk 7
Risk 2Risk5
Risk 11
Risk 8Risk 10 Risk 12
Probability
Impact
High
High
Low
Medium
LowMedium
79
SimulationUses a representation or model of a systemAnalyzes the expected behavior or performance of the systemMonte Carlo analysis simulates a model’s outcome many times to provide a statistical distribution of the calculated resultsTo use a Monte Carlo simulation:
Three estimates required (usually most likely, pessimistic, and optimistic) In addition, an estimate of the likelihood of the estimate being between the most likely and optimistic values
Source: Kendrick
80
Steps of a Monte Carlo Analysis
1. Assess the range for the variables being considered
2. Determine the probability distribution of each variable
3. For each variable, select a random value based on the probability distribution
4. Run a deterministic analysis or one pass through the model
5. Repeat steps 3 and 4 many times to obtain the probability distribution of the model’s results
Source: Kendrick
81
Monte Carlo Simulation Results for Project Schedule--Example
s1
Slide 81
s1 I can't seem to read the final art files for this chapter. This figure is the same as what should be here except for the dates. OK as is, or can someone put in the proper art file?schwalbe, 1/21/2005
82
Monte Carlo Simulation Results for Project Schedule--Validation
0
5
10
15
20
25
30
35
40
45
50
10/14/05 10/21/05 10/28/05 11/4/05 11/11/05 11/18/05 11/25/05 12/2/05 12/9/05 12/16/05 12/23/05 12/30/05 1/6/06 1/13/06 1/20/060
50
100
150
200
250
300
s2
Slide 82
s2 I can't seem to read the final art files for this chapter. This figure is the same as what should be here except for the dates. OK as is, or can someone put in the proper art file?schwalbe, 1/21/2005
83
Success Potential Scoring Sheet
100Total
3Hard-Working, Focused Staff
3Clear Visions and Objectives
6Ownership
8Competent Staff
9Smaller Project Milestones
10Realistic Expectations
11Proper Planning
15Clear Statement of Requirements
16Executive Management support
19User Involvement
Relative ImportanceSuccess Criterion
84
Decision Trees and Expected Monetary Value (EMV)
A decision tree is a diagramming analysis technique
Useful to select the best course of action in situations in which future outcomes are uncertain
Estimated monetary value (EMV) is the product of a risk event probability and the risk event’s monetary value.A decision tree to help find the EMV
Source: Kendrick
85
Expected Monetary Value (EMV)—Example
Source: Kendrick
86
Sensitivity Analysis
A technique used to show the effects of changing one or more variables on an outcomeFor example:
Determines what the monthly payments for a loan will be given different interest rates or periods of the loanCalculates break-even points based on different assumptions.
Spreadsheet software, such as Excel, is a common tool for performing sensitivity analysis
Source: Kendrick
87
Sensitivity Analysis for Determining Break-Even Point—Example
Source: Kendrick
88
Risk Response Planning
After identifying and quantifying risks, you must decide how to respond to themFour main response strategies for negative risks:
Risk avoidanceRisk acceptanceRisk transferenceRisk mitigation
89
Risk Management Plan—Example
MethodologyRoles and responsibilitiesBudget and scheduleCategories of riskProbability and impact of identified risksDocumentation of risk with associated courses of action
90
26% Successful (on time/on budget)46% “Challenged” (late, over budget, etc.)28% Cancelled
Behind the numbers:Software Development Projects, averaging $2MReported by CIOs, IT Managers
How Many Projects Fail?
Source: The Standish Group International: West Yarmouth, MA
“75% of All Projects Fail”
91
A Big Project of the 80’s:Apart from wars, this was the most expensive undertaking in the world. It was a huge engineering project that employed thousands, cost millions of dollars, and took years to complete.
What was it?
Name this Project
Source: Kendrick
92Source: Kendrick
Project SponsorFerdinand de Lesseps"The Great Engineer", Completed Suez Canal, – 1869Great financial and engineering successBelieved that a Central American Canal would save $48 million per year, and would cost less than $100 millionVery persuasive and influential, but he was:
Not an engineer.Not a good administrator.Blind to his own shortcomings.Convinced he was infallible.
93Source: Kendrick
Planning for the Canal$60 million was raised from private investors, knowing that this was one third the estimated costNo planning for problems was done, believed that technology would appear to finish the jobInsufficient effort put into proving feasibility of the project; Issues included:
A nine mile length of 400' deep trench Only one third of the money was for diggingDiseasesRiver floods
94
Managing the ProjectThe first year: 1881, engineering estimates for digging more than doubled, costs and schedule were not changedConstant problems with disease, flooding, rain, and equipmentIn 1885, cost estimates quadrupled. More money was raised from investors, canal opening delayed "somewhat"In 1887 costs were raised again (to $330 million); canal was changed to a lock style designIn 1889, still more money was needed, but raising more money was impossible - effort collapsed; Soon after was bankruptcy and liquidation of de Lessep'sCompany1891, more scandal, blame; French government fell
Source: Kendrick
95
CONSTRAINLeast Flexible
SCHEDULE SCOPE RESOURCES
OPTIMIZESomewhat Flexible
ACCEPTMost Flexible
Anatomy of a Failed ProjectThe First Panama Canal Project: Background and Scope DefinitionProject Objective:
Construct a sea-level canal across the fifty mile wide Isthmus ofPanamaCost: $60 MillionTime: 12 yearsCompletion: 1892
Source: Kendrick
96
Lessons LearnedOver ten years of workCost of $300 millionMore than 20,000 lives lostLots of dirt moved, but no canalSea level canal seen as probably impossibleFerdinand de Lesseps:
Consistently misjudged progress.Had a misplaced faith that needed medicines and machines would materialize.Died broken and in poverty.
Source: Kendrick
97
Project Risk Management
Two Sides of the Same Coin:You Cannot Manage What Might Go Wrong Until You Know What “Going Right” Looks Like
Depends on Project Planning to:Identify (and Avoid) Truly Impossible ProjectsDevelop Negotiation Data for Over ConstrainedProjectsEliminate Poorly Planned and Executed Projects
Source: Kendrick
98
Characteristic High Risk Low RiskTotal effort hours Large project > 5000 hours Small project < 1000 hoursDuration Longer than 12 months Less than 4 monthsTeam size Over 8 members Fewer than 4Number of clients or client organizations
More than three One
Project scope / deliverables Poorly defined Well definedBusiness benefit Not clear Well definedProject team and client business knowledge
Neither the project team nor the client have solid business knowledge
Both the project team and the client have solid business knowledge
Requirements Very complex, hard for client to define Easy for client to defineDependency on other projects or outside teams
Dependent on three or more outside projects or teams
No more than one dependency on an outside project or team
Project Sponsorship Unknown (should not start the project) Identified and enthusiasticClient commitment Unknown, passive PassionateChanges required for existing procedures, processes and policies
Large amount of change Little change
Organization structures Large amount of change Little or no changeProject manager experience Little experience on similar projects Similar experience on multiple projectsPhysical location of team Team is dispersed at several sites Team is located togetherUse of formal methodology Large project / no formal methods or
processesSmall project / standard methods in use
Technology New technology is being used for critical components
No new technology required
Response time Very short response times are critical Normal response time is acceptableData quality Data is of poor quality Data is of good qualityVendor partnership Have not worked with the vendor before Have a good relationship with the vendor
Risk Checklist - Sample
Source: Matlzman
99
How does this all apply to you?You need to assess the risks for your project in your project proposalThe risk assessment consists of four parts:
Identifying the risk – defining the harmful event (or outcome)Determining the likelihood of the risk occurring –its probability and a justification of how the probability is reachedThe mitigation – how you plan to prevent the harmful event occurringThe contingency – what you will do if the risk (harmful event) actually occurs
100
The Final Remark
“It might get really worse before it
gets worse”— Lilly Tomlin