CLF&P Transmission Project Status Update The projects currently planned for the CLF&P transmission system are included on the following pages as shown in the WestConnect 2014 Annual Ten Year Transmission Plan. For updates on project status between Annual Ten Year Transmission Plans, refer to the quarterly stakeholder meeting presentations in the Transmission Planning -> TCPC folder on the CLPT OASIS site.

Upload: dangthien

Post on 28-Sep-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

CLF&P Transmission Project Status Update

The projects currently planned for the CLF&P transmission system are included on the following pages as shown in the WestConnect 2014 Annual Ten Year Transmission Plan. For updates on project status between Annual Ten Year Transmission Plans, refer to the quarterly stakeholder meeting presentations in the Transmission Planning -> TCPC folder on the CLPT OASIS site.

Project Sponsor: Cheyenne Light Fuel and Power

Additional Project Participants: WAPA‐RMR

Project Description: New 115 kV substation about 1.5 miles from the Warren substation 

on the Warren‐Corlett 115 kV line

Voltage Class: 115 kV

Facility Rating:

Point of Origin/Location: North Range 115 kV (North Range Business Park, Cheyenne, WY)

Point of Termination:

Intermediate Points:

Length of Line (in Miles): 0.0

Type of Project: Substation

Development Status: In‐Service

Routing:

Subregional Planning Group: CCPG

Purpose of Project: Increased load serving capability and improved reliability.

Estimated Cost (in 2013 Dollars): $400,000

Schedule:

Construction Date: 2011

Planned In‐Service Date: 2013

Regulatory Info: Approved ‐ Wyoming PSC

Regulatory Date: 2012

Permitting Info:

Permitting Date:

Contact Information: Wes Wingen

Email [email protected]

Phone 605‐721‐2268

Website Information

North Range 115 kV Substation

Cheyenne Light Fuel and Power2014‐2023 Transmission Plan

LegendHappy Jack 115 kV to North Range 115 kV (Proposed)

� SUBSTATION

115 kV

WAPA

0 0.50.25

Miles

North Range

CLFP North Range 115 kV to Happy Jack 115 kV.

Happy Jack

Map Printed12/09/11.Line Route shown is for informational purposes only.

Project Sponsor: Cheyenne Light Fuel and Power

Additional Project Participants: Black Hills Power

Project Description: New 115kV lines connecting Cheyenne Prairie Generating Station to 

existing lines between East Business Park and Archer 115kV

Voltage Class: 115 kV

Facility Rating: 222 MVA

Point of Origin/Location: Cheyenne Prairie Generating Station 115kV

Point of Termination: East Business Park ‐ Archer 115 kV Tap

Intermediate Points:

Length of Line (in Miles): 1.3

Type of Project: Transmission Line

Development Status: Planned

Routing:

Subregional Planning Group: CCPG

Purpose of Project: Increase load serving capability and improved reliability

Estimated Cost (in 2013 Dollars): $6,500,000

Schedule:

Construction Date: 2012

Planned In‐Service Date: 2014

Regulatory Info: Approved ‐ Wyoming PSC

Regulatory Date: 2012

Permitting Info:

Permitting Date:

Contact Information: Wes Wingen

Email [email protected]

Phone 605‐721‐2268

Website Information

Cheyenne Prairie Generating Station 115 kV Lines

Cheyenne Light Fuel and Power2014‐2023 Transmission Plan

_

Cheyenne Praire Generating StationSubstation

Source: Esri, i-cubed, USDA, USGS, AEX, GeoEye, Getmapping, Aerogrid, IGN, IGP, and the GIS User Community, Copyright:©2012 Esri, DeLorme, NAVTEQ, TomTom

Map Printed 12/12/12

_ SubstationWAPA Transmission CLFP Transmission Route

0 2,0001,000Feet

¹

Project Sponsor: Cheyenne Light Fuel and Power

Additional Project Participants:

Project Description: New 115 kV line between Corlett and the new South Cheyenne 115 

kV substations.

Voltage Class: 115 kV

Facility Rating: 219 MVA

Point of Origin/Location: Corlett 115 kV substation

Point of Termination: South Cheyenne 115 kV substation

Intermediate Points:

Length of Line (in Miles): 9.0

Type of Project: Transmission Line

Development Status: Under Construction

Routing:

Subregional Planning Group: CCPG

Purpose of Project: Increased load serving capability and improved reliability.

Estimated Cost (in 2013 Dollars): $4,300,000

Schedule:

Construction Date: 2011

Planned In‐Service Date: 2014

Regulatory Info: Approved ‐ Wyoming PSC

Regulatory Date: 2012

Permitting Info:

Permitting Date:

Contact Information: Wes Wingen

Email [email protected]

Phone 605‐721‐2268

Website Information

Corlett‐South Cheyenne 115 kV Line

Cheyenne Light Fuel and Power2014‐2023 Transmission Plan

Project Sponsor: Cheyenne Light Fuel and Power

Additional Project Participants: WAPA‐RMR

Project Description: New 115 kV line between the new North Range and Swan Ranch and 

Cheyenne South 115 kV substations.

Voltage Class: 115 kV

Facility Rating: 189 MVA

Point of Origin/Location: North Range 115 kV substation

Point of Termination: Cheyenne South 115 kV substation

Intermediate Points: Swan Ranch 115kV substation

Length of Line (in Miles): 13.0

Type of Project: Transmission Line

Development Status: Under Construction

Routing:

Subregional Planning Group: CCPG

Purpose of Project: Increased load serving capability and improved reliability.

Estimated Cost (in 2013 Dollars): $3,300,000

Schedule:

Construction Date: 2011

Planned In‐Service Date: 2014

Regulatory Info: Approved ‐ Wyoming PSC

Regulatory Date: 2013

Permitting Info:

Permitting Date:

Contact Information: Wes Wingen

Email [email protected]

Phone 605‐721‐2268

Website Information

North Range‐Swan Ranch‐Cheyenne South 115 kV Line

Cheyenne Light Fuel and Power2014‐2023 Transmission Plan

Project Sponsor: Cheyenne Light Fuel and Power

Additional Project Participants: WAPA‐RMR

Project Description: New 115 kV line between Happy Jack and the new North Range 115 

kV substations.

Voltage Class: 115 kV

Facility Rating: 222 MVA

Point of Origin/Location: Happy Jack 115 kV

Point of Termination: North Range 115 kV

Intermediate Points:

Length of Line (in Miles): 1.0

Type of Project: Transmission Line

Development Status: Under Construction

Routing:

Subregional Planning Group: CCPG

Purpose of Project: Increased reliability.

Estimated Cost (in 2013 Dollars): $900,000

Schedule:

Construction Date: 2012

Planned In‐Service Date: 2014

Regulatory Info: Approved ‐ Wyoming PSC

Regulatory Date: 2012

Permitting Info:

Permitting Date:

Contact Information: Wes Wingen

Email [email protected]

Phone 605‐721‐2268

Website Information

Happy Jack‐North Range 115 kV Line

Cheyenne Light Fuel and Power2014‐2023 Transmission Plan

Project Sponsor: Cheyenne Light Fuel and Power

Additional Project Participants:

Project Description: New 115 kV substation in Swan Ranch Business Park in Cheyenne, 

Wyoming.

Voltage Class: 115 kV

Facility Rating:

Point of Origin/Location: Swan Ranch 115 kV (Swan Ranch Business Park, Cheyenne, WY)

Point of Termination:

Intermediate Points:

Length of Line (in Miles): 0.0

Type of Project: Substation

Development Status: Planned

Routing:

Subregional Planning Group: CCPG

Purpose of Project: Increased load serving capability and improved reliability.

Estimated Cost (in 2013 Dollars): $2,500,000

Schedule:

Construction Date: 2014

Planned In‐Service Date: 2014

Regulatory Info:

Regulatory Date:

Permitting Info:

Permitting Date:

Contact Information: Wes Wingen

Email [email protected]

Phone 605‐721‐2268

Website Information

Swan Ranch 115 kV Substation

Cheyenne Light Fuel and Power2014‐2023 Transmission Plan

Project Sponsor: Cheyenne Light Fuel and Power

Additional Project Participants:

Project Description: Two new radial 115kV transmission lines from North Range to the 

new Microsoft Data Center substation

Voltage Class: 115 kV

Facility Rating:

Point of Origin/Location: Microsoft Substation (near Cheyenne, WY)

Point of Termination:

Intermediate Points:

Length of Line (in Miles):

Type of Project: Transmission Line and Substation

Development Status: Planned

Routing:

Subregional Planning Group: CCPG

Purpose of Project: To serve the Microsoft Data Center load

Estimated Cost (in 2013 Dollars): $9,500,000

Schedule:

Construction Date: 2014

Planned In‐Service Date: 2015

Regulatory Info: Submitted ‐ Wyoming PSC

Regulatory Date: 2013

Permitting Info:

Permitting Date:

Contact Information: Wes Wingen

Email [email protected]

Phone 1‐605‐721‐2268

Website Information

Microsoft Substation and Transmission

Cheyenne Light Fuel and Power2014‐2023 Transmission Plan

Project Sponsor: Cheyenne Light Fuel and Power

Additional Project Participants:

Project Description: Add a second 230/115kV Transformer at South Cheyenne

Voltage Class: 230 kV

Facility Rating: 200 MVA

Point of Origin/Location: South Cheyenne Substation (near Cheyenne, WY)

Point of Termination:

Intermediate Points:

Length of Line (in Miles):

Type of Project: Transformer

Development Status: Planned

Routing:

Subregional Planning Group: CCPG

Purpose of Project: Increase load serving capability and reliability

Estimated Cost (in 2013 Dollars): $4,200,000

Schedule:

Construction Date: 2014

Planned In‐Service Date: 2015

Regulatory Info: Submitted ‐ Wyoming PSC

Regulatory Date: 2013

Permitting Info:

Permitting Date:

Contact Information: Wes Wingen

Email [email protected]

Phone 1‐605‐721‐2268

Website Information

Second South Cheyenne 230/115kV Transformer

Cheyenne Light Fuel and Power2014‐2023 Transmission Plan

^

^

^

^

Copyright:© 2012 Esri, DeLorme, NAVTEQ, TomTom, Source: Esri,DigitalGlobe, GeoEye, i-cubed, USDA, USGS, AEX, Getmapping, Aerogrid,IGN, IGP, and the GIS User Community

^ SubstationsProposed North Range to Cheyenne South 115kVProposed Corlett to Cheyenne South 115 kV Existing 115kVWAPA

0 21Miles

¹North Range-South Cheyenne 115 kV Project.

Corlett

Swan Ranch (Proposed)

Map Printed 11/18/2013.Line Route shown is for informational purposes only.

North Range

Cheyenne South

Happy JackMicrosoft Data

Center (Proposed)