clic tbm prototype t0@clex integration. inventory. planning report #2 - march 2014

28
1 [19-Mar-2014] «BE/RF» CLIC TBM Prototype T0@CLEX Integration. Inventory. Planning Report #2 - March 2014 Dmitry Gudkov 1

Upload: jud

Post on 23-Feb-2016

38 views

Category:

Documents


0 download

DESCRIPTION

CLIC TBM Prototype T0@CLEX Integration. Inventory. Planning Report #2 - March 2014. Dmitry Gudkov. CONTENTS. 2D layout Inputs Supporting elements for CLEX components in the working area Integration Inventory Integration of TBM and modification of CLEX components. Drive beam - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report #2 - March 2014

1[19-Mar-2014] «BE/RF»

CLIC TBM Prototype T0@CLEX

Integration. Inventory. Planning

Report #2 - March 2014

Dmitry Gudkov

1

Page 2: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report #2 - March 2014

2[19-Mar-2014] [CMWG Meeting] «BE/RF» 2

CONTENTS

2D layout

Inputs

Supporting elements for CLEX components in the working area• Integration• Inventory

Integration of TBM and modification of CLEX components. Drive beam

Integration of TBM and modification of CLEX components. Probe beam

Inventory of the CLEX components - Under way, will be shown next time.

Status of components production for TBM

Planning for the TBM installation in CLEX

Documentation

Page 3: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report #2 - March 2014

3[19-Mar-2014] [CMWG Meeting] «BE/RF» 3

TBM Prototype T0@CLEX. Integration. Phase 1.

Igor Syratchev

Page 4: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report #2 - March 2014

4[19-Mar-2014] [CMWG Meeting] «BE/RF» 4

TBM Prototype T0@CLEX. Integration. Phase 1.

Igor Syratchev

Page 5: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report #2 - March 2014

5[19-Mar-2014] [CMWG Meeting] «BE/RF» 5

TBM Prototype T0@CLEX. Integration. Phase 1.

Igor Syratchev

Page 6: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report #2 - March 2014

6[19-Mar-2014] [CMWG Meeting] «BE/RF» 6

TBM Prototype T0@CLEX. Integration. Phase 1.

Mod

ule

bord

er Module border

• 1 PETS and 1 SAS will be powered;• VGVs are installed on each extremity to

detach the test stand;

2D layout is based on one phase 3.1 (see above)Phase 3.3 requires another modification of the primary RF network (2..3 new waveguides, splitter, directional coupler, on-off).UPDATED No more on-off units available.

Page 7: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report #2 - March 2014

7[19-Mar-2014] [CMWG Meeting] «BE/RF» 7

INPUTS. Integration of TBM. Probe beam

3D model is based on the document prepared by Wilfrid Farabolini: EDMS 1366387

Are implemented in the drawing CLIATCIN0005 (under way):

Page 8: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report #2 - March 2014

8[19-Mar-2014] [CMWG Meeting] «BE/RF» 8

INPUTS. Integration of TBM. Drive beam

Positions of the quadrupoles, input from Jacob Esberg: EDMS 136638821.33596587 '"QUADRUPOLE"' '"TL2.QDD10"' 0.575 UNCHANGED23.29201587 '"QUADRUPOLE"' '"CM.QFD0310"' 1.95605 UNCHANGED23.79201587 '"QUADRUPOLE"' '"CM.QDD0315"' 0.5 UNCHANGED24.29201587 '"QUADRUPOLE"' '"CM.QFD0320"' 0.5 UNCHANGED25.90225587 '"RFCAVITY"' '"P1"' 1.61024 UNCHANGED27.98793587 '"QUADRUPOLE"' '"CM.QFD0565A"' 2.08568 Has been increased28.39727587 '"QUADRUPOLE"' '"CM.QFD0565B"' 0.40934 Has been decreased

29.961016 '"RFCAVITY"' '"P2"' 1.56374 has been increased30.428016 '"QUADRUPOLE"' '"QTB1"' 0.467 0.467 As specified30.965016 '"RFCAVITY"' '"P3"' 0.537 0.537 As specified31.432016 '"QUADRUPOLE"' '"QTB2"' 0.467 0.467 As specified

33.19201587 '"QUADRUPOLE"' '"CM.QFD0560"' 1.76 1.76 As specified34.19201587 '"QUADRUPOLE"' '"CM.QFD0570"' 1 UNCHANGED37.19399775 '"RBEND"' '"CM.BHB0600"' 3.001982 UNCHANGED

Are implemented in the drawing CLIATCIN0005 (under way):

Page 9: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report #2 - March 2014

9[19-Mar-2014] [CMWG Meeting] «BE/RF» 9

TBM implantation in CLEXTask Duration Date

1 Remove the safety barriers 0.5 days 1.06

2 Preparation of the storage tables inside CLEX 0.5 days 1.06

3 Radioprotection Survey Visit 1 day 2.06

4 Dismantling of the shielding blocks (to get the direct access for new equipment)

1 day 2.06

5 Organizing of free access to CLEX building 1day 3.06

storage

Page 10: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report #2 - March 2014

10[19-Mar-2014] [CMWG Meeting] «BE/RF» 10

TBM implantation in CLEXTask Duration Date

6 Dismantling of TBTS PB and DB tanks- disconnection of electrical cables and water pipes

- disconnection and dismantling of RF network

7 days 03.0611.06

Page 11: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report #2 - March 2014

11[19-Mar-2014] [CMWG Meeting] «BE/RF» 11

TBM implantation in CLEXTask Duration Date

7 - dismantling and transport of the TBTS PB Tank to the buffer zone 1 day 10.06

Page 12: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report #2 - March 2014

12[19-Mar-2014] [CMWG Meeting] «BE/RF» 12

TBM implantation in CLEXTask Duration Date

8 - dismantling and transport of the TBTS DB Tank and transport to the storage

1 day 11.06

Page 13: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report #2 - March 2014

13[19-Mar-2014] [CMWG Meeting] «BE/RF»

TBM implantation in CLEXTask Duration Date

9 - Disconnection of all cables (+ labelling) and pipes in the working area

5.5 days 12.0619.06

~14 meters

Page 14: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report #2 - March 2014

14[19-Mar-2014] [CMWG Meeting] «BE/RF»

TBM implantation in CLEXTask Duration Date

10 - Removal of the equipment in the working area 4.5 days 16.0620.06Component Pic Quantity Component Pic Quantity

Quadrupoles 12 Supports 10

Correctors 10Sector

vacuum valves 4

BPMs and diagnostics chambers

8

Pumping ports

(including valves and

pumps)

5

Flashbox 1 Drift Tubes and bellows 20 + 22

Page 15: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report #2 - March 2014

15[19-Mar-2014] [CMWG Meeting] «BE/RF»

TBM implantation in CLEXTask Duration Date

11 - Dismantling of the yellow girders and feet 3 days 23.0625.06

12 - Removal of the cooling distribution (central line) 3 days 26.0630.06

13 - Precise Floor marking before drilling of the holes for installation of the TBM supporting system: 32 holes in total

For dimensions: DRAWING CLIATCIN0004

1 days 01.07

14 Drilling of the floor for all the supporting equipment 1.5 days 02.0703.07

Task Quantity

Feet to be removed from area 6

Feet to be replaced 2

Girders to be removed from area 6

Girders to be replaced 6

New girders to be manufactured(see on next slides)

3

Page 16: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report #2 - March 2014

16[19-Mar-2014] [CMWG Meeting] «BE/RF»

Supporting Elements for TBM and CLEX Components

2 Feet to be reused in different place (8 holes to be drilled)

New girders (x3)

TBM supporting benches (24 holes to be drilled for installation)

• All green feet will not be moved• Green girders will be moved by several cm.

Page 17: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report #2 - March 2014

17[19-Mar-2014] [CMWG Meeting] «BE/RF»

TBM implantation in CLEXTask Duration Date

15 - Installation of the supporting elements of the TBM and CLEX components

Installation of the new yellow supporting girders (1 day) Transport and Installation of the TBM extremity benches (1 day) Geometrical control of the extremity benches (1 day)

3 days 07.0709.07

16 - TBM installation and assemblySee next slides

22 days 10.0708.08

Page 18: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report #2 - March 2014

18[19-Mar-2014] [CMWG Meeting] «BE/RF»

Installation of the TBM supporting systemTask Duration Date

17 Installation of the TBM supporting system 5 days 10.07-16.0718 Geometrical control of the TBM supporting system 1 day 17.0719 Alignment of the girders (with respect to the existing beam) 1 day 18.0720 Installation of alignment’s device (wire, cable, sensors, data acquisition, …) 2 days 21.07-22.0721 Absolute measurement (cWPS sensors vs AT401 tracker) 1 day 23.0722 Test of actuators displacement on 1 mm range (girder unloaded) - OPTIONALLY 1 day 24.0723 Test of the Articulation Point (girder unloaded) - OPTIONALLY 1 day 25.07

Page 19: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report #2 - March 2014

19[19-Mar-2014] [CMWG Meeting] «BE/RF»

1. (DBQ+BPM) x 2; SAS x 2; PETS x 2; + fixating clamps2. Vacuum equipment (minipumps; valves; gauges)

Installation of the components of the TBM + alignment control

Task Duration Date24 Installation of the components of the TBM + alignment control + cooling test 5.5 days 28.07-04.0825 Cables for TBM routing and connection to the equipment in the external shelter 2.5 days 04.08-08.08

3. Supporting frame + RF load

4. Supporting frame + RF network

5. Cooling tubes (fittings are pre-installed)

The TBM assembly is performed by subassemblies:

Transport of the girders with installed components requires the design (+safety validation) of the transport tooling. Subassemblies will reduce the overall installation time.

Page 20: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report #2 - March 2014

20[19-Mar-2014] [CMWG Meeting] «BE/RF»

TBM implantation in CLEXTask Duration Date

26 Primary RF Network installation• Installation of the RF components on the TBTS tank (2 days)• Installation of the waveguides between TBTS tank and TBM Including supports, pumping port etc. (1 day)

3.5 days 04.0807.08

Waveguide support based on standard components will be delivered soon.

Page 21: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report #2 - March 2014

21[19-Mar-2014] [CMWG Meeting] «BE/RF»

TBM implantation in CLEXTask Duration Date

27 Installation of CLEX components according to new configuration (not all the components are listed below, +5..10 components, final inventory under way)

12.5 days 08.0724.07

Component Pic Quantity Component Pic Quantity

Quadrupoles 12 Supports 18

Correctors 8Sector

vacuum valves 4

BPMs and diagnostics chambers

9

Pumping ports

(including valves and

pumps)

5

Flashbox 1 Drift Tubes and bellows 24 + 26

Page 22: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report #2 - March 2014

22[19-Mar-2014] [CMWG Meeting] «BE/RF»

CLEX working area after installation of components

Page 23: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report #2 - March 2014

23[19-Mar-2014] [CMWG Meeting] «BE/RF»

Final tests and cables reconnection

Task Duration Date28 Leak tightness test 2 days 08.08-11.0829 Final alignment tests 4 days 12.08-15.0830 Reconstruction of cable trays and cables pulling 5 days 18.08-22.08

31 Reconnection of all cables (according to labelling) and pipes in the working area 2.5 days 25.08-27.08

32 Cooling system test 2 days 27.08-28.0833 Cleaning the area 3 days 29.08-02.0934 Closing the shielding 1 day 03.0935 Safety chain test 1 day 04.0936 Commissioning 5 days 05.09-12.09

Page 24: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report #2 - March 2014

24[19-Mar-2014] [CMWG Meeting] «BE/RF»

Resources

Cooling system: final integration is under way by Vadim Soldatov and Alexios Lorens Vamvakas

Installation: FSU108, Andrey Olyunin, Wilfrid Farabolini (CLEX equipment coordination)

Vacuum for CLEX: Esa Antero Paju

Fiducialization, alignment: ABP-SU

Special tasks: external companies or other groups of CERN are involved

The planning must take into account the summer holidays of people involved in the installation. The holidays periods can be integrated in the personal calendar of each person (MS Project).

Page 25: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report #2 - March 2014

25[19-Mar-2014] [CMWG Meeting] «BE/RF»

Status of components. TBM

Component Design Production Status Exp.

3D % 2D % Parts % Assembly

SAS 100 100 100 Brazing Mar’14

PETS 100 100 100 100 done

RF Network waveguides 100 100 100 brazing Apr’14

DB BPM 100 100 100 50 Apr’14

Vacuum minitanks and equipment 100 100 100 100 done

Vacuum drift tubes 100 100 0 0 Apr’14

RF Loads 100 100 Production, Ext. Comp. done

Directional Couplers 100 100 Production, Ext. Comp. done

Cooling tubes/fittings 100 90 0 - done

Supporting system 100 100 Test is under way done

U-clamps 100 100 50 0 Apr’14

Standard Supporting Frames 100 100 100 80 Apr’13

TBM ASSEMBLY May’13

Page 26: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report #2 - March 2014

26[19-Mar-2014] [CMWG Meeting] «BE/RF»

Status of components. TBM. Primary RF Network

Component Design Production Status Expected

3D % 2D % Parts % Assembly

RF Network waveguides 100 100 100 50 Apr’14

Vacuum fittings 100 100 0 0 done

Supporting system elements 100 100 0 0 done

Standard Supporting Frames 100 100 0 0 done

Page 27: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report #2 - March 2014

27[19-Mar-2014] [CMWG Meeting] «BE/RF»

Status of components. CLEX working area

Component Design Production Status Expected

3D % 2D % Parts % Assembly

Vacuum fittings and bellows (drift tubes)

100 - 0 0 Apr’14

Supporting girders 100 0 0 0 Apr’14

Implantation drawings (under way) 100 95 0 0 Mar’13

Cooling pipe

Page 28: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report #2 - March 2014

28[19-Mar-2014] [CMWG Meeting] «BE/RF»

Documentation

• EDMS 1366387 – INPUT. Integration of TBM in CLEX. Probe beam

• EDMS 1366388 – INPUT. Integration of TBM in CLEX. Drive beam

• CLIATCIN0004 (under way) – Integration of TBM in CLEX. Supporting system

• CLIATCIN0005 (under way) - Integration of TBM in CLEX. RF components

• EDMS 1366389 – TBM installation in CLEX. Detailed planning (preliminary)