click here to view a presentation about the ccct

30
Country Club Creek Trail Preliminary Engineering Report Public Outreach Jessica V. Salinas COA Project Manager December 9, 2014

Upload: lamtu

Post on 04-Feb-2017

224 views

Category:

Documents


5 download

TRANSCRIPT

Page 1: Click here to view a presentation about the CCCT

Country Club Creek TrailPreliminary Engineering Report

Public Outreach

Jessica V. SalinasCOA Project Manager

December 9, 2014

Page 2: Click here to view a presentation about the CCCT

Country Club Creek Trail Agenda

Introduction of Project Team Overall Program Goals for Urban Trails Country Club Creek Trail Summary Preliminary Engineering Report Overview

– Outline of PER– Evaluation Criteria– Recommended Route

Next Steps Questions

12/9/14 jvsalinas2

Page 3: Click here to view a presentation about the CCCT

Project Team

City Project Sponsor – Nadia Barrera, PWD City Project Manager – Jessica Salinas, PWD Project Consultant & Subconsultants:

– Civil Engineering Consultants – Gary Martin & Ken Thomas– CAS Consulting, Inc. – Cost Estimating and Utility Coordination– Harutunian Engineering, Inc. – Lighting Options– Hicks & Company – Environmental Investigation– HVJ – Geotechnical Investigation– Jaster Quintanilla San Antonio, LLP – Preliminary Structural Design– Macias & Associates, L.P. – Surveying and Parcel Information

12/9/14 jvsalinas3

Page 4: Click here to view a presentation about the CCCT

12/9/14 nbarrera4

Program Goals for Urban Trails

Easy access for transportation & recreation users. Link to bicycle & sidewalk network. Adequate size to accommodate recreation & transportation

uses. Incorporate amenities & features that transform them into

unique greenways that reflect the City around them. Provide adequate resources to maintain & operate. Ensure context-sensitivity & environmentally sustainability as

well as preservation and improvement upon wildlife habitat.

Page 5: Click here to view a presentation about the CCCT

12/9/14 jvsalinas5

Country Club Creek Trail Project Summary

Project Funded by 2010 Prop 1 & 2012 Prop 12 Preliminary Engineering Report: April 2014 – February 2015 Design Phase: Spring 2015 – Spring 2016

– Construction Estimate (w/20% Contingency) - $4,519,892 Construction – Pending Project Funding

– Anticipated start Fall 2016 Project website: http://www.austintexas.gov/urbantrails

Page 6: Click here to view a presentation about the CCCT

Trail Vicinity Map

12/9/2014 jvsalinas6

Page 7: Click here to view a presentation about the CCCT

Country Club Creek Trail

12/9/14 jvsalinas7

• Approximately 3-mile multi-use path generally running along Country Club Creek connecting Lady Bird Lake to Mabel Davis Park in southeast Austin.

• Two segments of the trail that need to be constructed

• 0.5 mile trail section - from Ventura Drive to Burleson Road through an existing City of Austin electric easement.

• Note: Existing segment along Pleasant Valley from Burleson Road to East Oltorf.

• 1 mile section - from East Oltorf to the existing gravel trail just north of Elmont Drive.

Page 8: Click here to view a presentation about the CCCT

Preliminary Engineering Report

The Preliminary Engineering Report consists of the following sections:Executive Summary Environmental IssuesIntroduction Utilities ImpactPreliminary Trail Routes Structural Preliminary DesignEvaluation Criteria Lighting OptionsCritical Water Quality Zone Opinion Of Probable CostErosion Hazard Zone Route EvaluationDrainage and Floodplain Recommended OptionRight-of-Way Summary & Next StepsTrees

12/9/14 cec8

Page 9: Click here to view a presentation about the CCCT

Evaluation Factors

The following factors were used to evaluate the different trail segments:Accessibility Right-of-WayConnectivity ObstructionsCritical Water Quality Zone Tree ImpactsErosion Hazard Zone EnvironmentalFloodplain/Drainage Impacts Cost

12/9/14 cec9

Page 10: Click here to view a presentation about the CCCT

TRAIL ROUTE

12/8/14 cec10

Page 11: Click here to view a presentation about the CCCT

12/9/14 jvsalinas11

Existing Austin Energy Easement

SEGMENT 1 Austin Energy right-of-way (ROW) from Ventura Drive to Burleson Rd

Page 12: Click here to view a presentation about the CCCT

12/9/14 jvsalinas12

Electric power ROW looking north from Ventura.

SEGMENT 1 Austin Energy right-of-way (ROW) from Ventura Drive to Burleson Rd

Page 13: Click here to view a presentation about the CCCT

Segment 2 – Existing Route along S. Pleasant Valley from Burleson to Oltorf

12/9/14 jvsalinas13

Page 14: Click here to view a presentation about the CCCT

SEGMENT 3 starting at S. Pleasant Valley Rd & E. Oltorf to Riverside Dr.

12/9/14 jvsalinas14

Page 15: Click here to view a presentation about the CCCT

SEGMENT 3 starting at S. Pleasant Valley Rd & E. Oltorf to Riverside Dr.

12/9/14 jvsalinas15

Oltorf facing west towards Pleasant Valley Looking south towards Riverside Dr.

Page 16: Click here to view a presentation about the CCCT

SEGMENT 3B Segment near Sheringham Dr

12/9/14 jvsalinas16

Page 17: Click here to view a presentation about the CCCT

SEGMENT 4 Riverside Dr. & Wickersham Intersection

12/9/14 jvsalinas17

Page 18: Click here to view a presentation about the CCCT

SEGMENT 4 starting at Riverside Dr. to Elmont Dr.

12/9/14 jvsalinas18

Wickersham Dr lookingnorth from E. Riverside Dr.

Northern Bridge of E. Riverside Dr from Wickersham Lane.

Page 19: Click here to view a presentation about the CCCT

SEGMENT 4 Riverside Dr. to Elmont Dr.

12/9/14 jvsalinas19

Page 20: Click here to view a presentation about the CCCT

SEGMENT 4 Riverside Dr. to Elmont Dr.

12/9/14 jvsalinas20

Page 21: Click here to view a presentation about the CCCT

SEGMENT 4 Wickersham Pavement Markings (West Side)

12/9/14 jvsalinas21

Page 22: Click here to view a presentation about the CCCT

SEGMENT 4 Wickersham Pavement Markings (West Side)

12/9/14 jvsalinas22

Page 23: Click here to view a presentation about the CCCT

SEGMENT 4 Wickersham Pavement Markings (East Side)

12/9/14 jvsalinas23

Page 24: Click here to view a presentation about the CCCT

12/9/14 jvsalinas24

Construction Estimate Section 1 & 2

Section                 Base Estimate                    20% Contingency           w/Lighting1                              $371,575                              $445,890                  $692,6442                              $35,362                 $42,435            $352,345

Page 25: Click here to view a presentation about the CCCT

12/9/14 jvsalinas25

Construction Estimate Section 3 & 4

Section                 Base Estimate                    20% Contingency            w/Lighting3B1                         $1,166,366                           $1,399,640                $1,840,3363C                           $1,406,156                           $1,687,387                $1,834,2864B1                         $787,116                              $944,539                   $1,549,733

TOTAL                   $3,766,575                           $4,519,891                   $6,269,344

Page 26: Click here to view a presentation about the CCCT

Next Steps

Dec 2014: Collect Public Input to PER– Open House– City Website

Jan 2015: Project Team to incorporate Feedback and update PER Jan 2015: City Stakeholder Final Review of PER Feb 2015: Follow-up Open House to present Final PER Spring 2015: Design Phase

12/9/14 jvsalinas26

Page 27: Click here to view a presentation about the CCCT

12/9/14 jvsalinas27

QUESTIONS

Page 28: Click here to view a presentation about the CCCT

TRAIL ROUTE

12/8/14 cec28

Page 29: Click here to view a presentation about the CCCT

12/9/14 jvsalinas29

BACK-UP

Page 30: Click here to view a presentation about the CCCT

Evaluation Factors (continued)

Accessibility – Primarily deciding how easy it is to comply with ADA requirements in a segment.

Connectivity – The ease of reaching destinations from the proposed trail. Critical Water Zone (CWQZ) – Indicates whether or not the trail segment is located in this

zone. Erosion Hazard Zone (EHZ) – Indicates whether the trail segment is in the EHZ or not. Floodplain/Drainage Impacts – Indicates whether or not the trail segment is located in the

floodplain and if there are any negative impacts to drainage. Right-of-Way – Indicates if a new easement is required in a trail segment. Obstructions – Indicates if there are features that would impact the location of the trail. Tree Impact – Indicates the impact to trees in a trail segment. Environmental – Indicates the whether or not environmental permits would be required. Cost – Indicates the relative cost in relation to the other options.

12/9/14 cec30