[[click on topic to view page]] > environmental and physical considerations > accommodations...
TRANSCRIPT
[[Click on topic to view page]]
> environmental and Physical considerations> accommodations and security on-site> construction space and storage of materials on the site> special requirements based on the design plans and site environment> documentations and specifications e.g. building permit> plan drawings of Foundation system, Structural system, external envelope
e.g. portal frame design - a clients engages an architect and consulting engineer who prepare structural design
drawings of the portal frame and submit the project to the tender- the builder sub-contracts the structural steelwork to steel fabricator on the basis of the consulting engineer drawing
- steel fabrication is started by following the detail shop drawings drawn by draftsmen> site set out, excavation, foundations, structural frame set up, external envelope system, internal finish
BACK to main page
next >>
Pre-fabrication considerations of off-site production
> logistic - storage- transport- site- management
> procurement- contract form- management- manufacture
> motivation- costs- skills- project management
> site assembly- site environment- labour- management
> Design- rationalisation- standardisation- co-ordination- decisions
BACK to main page
next >>
Pre-fabricated metal ideal for roofing and walling
STEEL
Advantages- no waster material- capacity for long clear span- quick construction times
Disadvantage- some reduction in thermal insulation- low thermal mass ( high temperature variation) - sound transmission may be problem is not detailed well
BACK to main page
next >>
[[Click on topic to view page]]
BACK to main page
[[Click on image to start video]]
next >>
architect engineer
fabricator Shop drawings
steelworkeron-site construction
Finish building
Concrete panel labour
builder tender
off-site fabrication
Pre construction process
Under construction process
next >>
BACK to main page
Preparation of Pad Footing Floating the bolts (Fig. C003)
> hole excavated ready for concrete foundation
> holding down bolts are then inserted and fixed to a timber base plate, which is same size as the steel base plate and holes are in the same position.
> timber base plate fixed to a temporary timber frame
> temporary timber frame fixed to correct level by pegged into the surrounding ground and held at the correct position
> concrete can be poured around the bolts after level checked
(Fig.C003)
BACK to main page
next >>
BACK to main page
Section Drawings of Pad Footing drawn by architect and engineer
next >>
[[Click on topic to view page]]
Steel Portal Frame> economic alternative to warehouse structure
> To be effective a pitched roof portal frame should have as low a pitch as practical to minimize spread at the knee joint.
> the connection to the column haunched at the knee joint to make the connection deeper and stiffer
> the haunching can be fabricated by welding a I-section to the rafter, which is the most economic in steel fabrication.
- Design by architect - Liasion with structural engineer - Tender documents - Quotes from steel fabricator - Shop drawings—accurate details by draftsperson - Fabrication—off site - erection of steelwork
BACK to main page
next >>
Column attached to Pad Footing
> Large washer fixed to bolt to prevent pull out > holding down bolts set into the concrete foundation
> non shrinkable grout filled void left below steel base plate > steel packing shims fixed under base plate at correct level
> Base plate welded to bottom of column
Base Plate of Steel Column
> steel base plae welded or fixed with bolted connection with angle cleats
BACK to main page
next >>
BACK to main page
next >>Stages of setting up stanchion
BACK to main page
[[Click on topic to view page]]
Apex JointStiffening at ridge of steel portal frame at apex joint
> the junction of the rafter at the ridge is often stiffened by welding I-section haunching to the underside of the rafter> end plates welded to rafter and hauncing and bolted together
BACK to main page
next >><< back
Knee JointHaunch to the steel portal frame at knee joint
> The haunched connection of the rafter to the column can be fabricated by welding a I-cut section haunching to the underside of the rafter> the haunch length is usually of the order of 10%-15% of the span of the rafter> with the depth of the section at the haunch is about twice of rafter depth> web stiffener welded to top of column
bolt connection from column to haunching
BACK to main page
next >><< back
Roof bracing
bracing between stanchion to stanchion
BACK to main page
Cross Bracing
- secure the structural elements from wind loads- avoid bending of the structural elements- resist lateral forces
next >>
[[Click on topic to view page]]
BACK to main page
Precast Concrete Panel
Advantage- good sound reduction- good fire resistance- loadbearing capacity- high thermal mass (less variation of temperture)
Disadvantage- large amount of work required on-site- negerates waste on-site (drilling holes for services- units are heavy- high degree of finishing required on-site
next >>
Precast Concrete Panel
- bolted to stanchion-Typical shop drawing of panel details required
BACK to main page
next >>
Lifting up Concrete Panel
Standard concrete panels and units are stored ready for delivery
Panel can be assembled around a frame or can from self supporting structure
Mobile crane may be required
BACK to main page
next >>
Connection between stanchion and concrete panel
BACK to main page
Steel Sheet Cladding
- Roof/wall sheeting: approx. 0.4mm thick- Made from zincalume (Zinc & aluminium coated steel)- Available in a variety of profiles, including traditional corrugated and concealed fixed products- Sheeting is usually ‘custom cut’ by the manufacturer to suit the requirements for a particular job- Spanning capabilities:
roof: 1200mm – corrugated sheeting; 2700mm –stronger, deeper profileswalls: can be 25 – 50% greater than roof spans
Advantages
- Cost effective- Lightweight- High structural capacity- Low maintenance- Consistency of quality- Zincalume steel: high solar reflectance qualities; rapid heat dissipation
Disadvantages
- Limitation to heights that can be reached by sheeting
BACK to main page
next >>
Steel Sheet Cladding
BACK to main page
next >>
[[Click on topic to view page]]
The construction of buildings. Volume 4, Foundations and sub-structures, steel frames, concrete, concrete frames, external walls of framed buildings, R. Barry , BSP Professional Books, 1992, c1986
Construction and Structures 2 Reading, Deakin university 2006
Roofing, Walling, Rainwater & Structural Products, Stramit Corporation Pty Ltd, may 2004
Barry Advanced Construction of Buildings, Stepen E & Christopher G, Blackwell, 2006
http://www.roger-bullivant.co.uk/web/products_services.htm, accessed 24.05.2006
BACK to main page
[ RETURN home]