CLINIC CONSTRUCTION UPDATE December 19, 2014 Issue As we head into the Holiday weeks ahead, this is our current status. Progress can also be viewed live on the Park Region/Otter Tail Telcom Construction Cam at www.prtel.com/constructioncam Crane is on site. Currently working on core wall construction Foundations are complete along the south building line. Steel set to arrive between Jan 5 th and 12 th Steel erection will continue until the end of Feb. See photos of the progress on the following pages. As always, if you have questions or concerns about the project, send us an email [email protected] or call 218.736.8191.

Upload: ngodieu

Post on 19-Mar-2018

215 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: CLINIC CONSTRUCTION UPDATE shelter installed on west and south concrete wall for waterproofing install. Title Microsoft Word - ConstructionUpdate_12192014.docx Created Date 20141219184610Z

 

 

CLINIC CONSTRUCTION UPDATE December 19, 2014 Issue As  we  head  into  the  Holiday  weeks  ahead,  this  is  our  current  status.  Progress  can  also  be  viewed  live  on  the  Park  Region/Otter  Tail  Telcom  Construction  Cam  at  www.prtel.com/constructioncam      

Crane  is  on  site.       Currently  working  on  core  wall  construction   Foundations  are  complete  along  the  south  building  line.       Steel  set  to  arrive  between  Jan  5th  and  12th   Steel  erection  will  continue  until  the  end  of  Feb.  

See photos of the progress on the following pages. As always, if you have questions or concerns about the project, send us an email [email protected] or call 218.736.8191.

Page 2: CLINIC CONSTRUCTION UPDATE shelter installed on west and south concrete wall for waterproofing install. Title Microsoft Word - ConstructionUpdate_12192014.docx Created Date 20141219184610Z

Construction Progress Update through 12/17/2014

Interior pad footings are 90% complete.

Foundation footings and Grade beams now 90% complete.

Forming second level of double elevator core wall.

Poured first level of Stair B core walls.

Formed and poured 2nd level of Stair B core walls.

Heat shelter installed on west and south concrete walls for waterproofing install.

Exterior wall pad footing poured. Trench dug for last grade beam.

Page 3: CLINIC CONSTRUCTION UPDATE shelter installed on west and south concrete wall for waterproofing install. Title Microsoft Word - ConstructionUpdate_12192014.docx Created Date 20141219184610Z

Grade beam section poured on north side.

Page 4: CLINIC CONSTRUCTION UPDATE shelter installed on west and south concrete wall for waterproofing install. Title Microsoft Word - ConstructionUpdate_12192014.docx Created Date 20141219184610Z

Setting forms for the second level of the elevator core walls.

Page 5: CLINIC CONSTRUCTION UPDATE shelter installed on west and south concrete wall for waterproofing install. Title Microsoft Word - ConstructionUpdate_12192014.docx Created Date 20141219184610Z

Pouring second level of Stair B core walls.

Page 6: CLINIC CONSTRUCTION UPDATE shelter installed on west and south concrete wall for waterproofing install. Title Microsoft Word - ConstructionUpdate_12192014.docx Created Date 20141219184610Z

Stair B core walls formed and ready for pour.

Page 7: CLINIC CONSTRUCTION UPDATE shelter installed on west and south concrete wall for waterproofing install. Title Microsoft Word - ConstructionUpdate_12192014.docx Created Date 20141219184610Z

Heat shelter installed on west and south concrete wall for waterproofing install.