clinic construction update shelter installed on west and south concrete wall for waterproofing...
TRANSCRIPT
CLINIC CONSTRUCTION UPDATE December 19, 2014 Issue As we head into the Holiday weeks ahead, this is our current status. Progress can also be viewed live on the Park Region/Otter Tail Telcom Construction Cam at www.prtel.com/constructioncam
Crane is on site. Currently working on core wall construction Foundations are complete along the south building line. Steel set to arrive between Jan 5th and 12th Steel erection will continue until the end of Feb.
See photos of the progress on the following pages. As always, if you have questions or concerns about the project, send us an email [email protected] or call 218.736.8191.
Construction Progress Update through 12/17/2014
Interior pad footings are 90% complete.
Foundation footings and Grade beams now 90% complete.
Forming second level of double elevator core wall.
Poured first level of Stair B core walls.
Formed and poured 2nd level of Stair B core walls.
Heat shelter installed on west and south concrete walls for waterproofing install.
Exterior wall pad footing poured. Trench dug for last grade beam.
Grade beam section poured on north side.
Setting forms for the second level of the elevator core walls.
Pouring second level of Stair B core walls.
Stair B core walls formed and ready for pour.
Heat shelter installed on west and south concrete wall for waterproofing install.