Clubhouse Accomplishment Report of August 2016
Clubhouse Accomplishment Report of August 2016
View at A
View at C
A C
FUNCTION
BUILDING
Ground Floor
A,B – Erection
and application
of skimcoat
C – Construction
of reinforced
concrete ribs
B
View at B
Clubhouse Accomplishment Report of August 2016
A
B
C
View at B
View at A
FUNCTION
BUILDING
Ground Floor
A – Construction
of reinforced
concrete ribs for
Pre-Function Area
B – Construction
of Ceiling frames
for Meeting Rooms
C – Erection of
partition walls for
kitchen
View at C
Clubhouse Accomplishment Report of August 2016
A
View at A
Main
Building
Ground Floor
A – Installation of
aluminum furring
in and mock-up
of the ceiling of
Lobby
B – Construction
of reinforced
concrete ribs
along the bridge
B
View at B
Clubhouse Accomplishment Report of August 2016
Health & Leisure
Building
Lower Ground
Floor
A – Concreting of
Veranda
B – Erection of
the partition walls
for Gym lockers
& restrooms
A
B
View at A View at B