Software for creation of pipe classes and mechanical calculation of piping components. Software for the design and mechanical calculation of pressure vessels and heat exchangers. The presentation shows the calculation of a standard piping flange in the VES application. You are here: CM-PE-910 Planning Procedure 1. 2. 3. 4. 5. 6. 7. The purpose of this procedure is to provide information and instructions in order to establish a standard method for the planning of a project and facilitate the execution of the project in a structured manner. This procedure shall apply to all projects, unless otherwise directed by the Project Manager. Described are the main activities that are required to make a project plan. The project plan as described includes Home Office project activities and the preparation of a basic construction plan. The Construction Plan is to be further detailed by the Construction Planning Engineer. The Project Manager and Lead Engineer are responsible for the contents herein. The Planning Engineer is delegated to obtain required information. Procurement, Construction, Lead Discipline Engineers and other parties involved in the preparation of the project plan will provide CM-PE-910 Planning Procedure http://www.red-bag.com/general-procedures/47-cm-pe-910-planning-pro... 1 trong 10 10/16/2015 8:27 AM

Upload: luong-anh

Post on 20-Feb-2016

214 views

Category:

Documents


0 download

DESCRIPTION

Planning procedure

TRANSCRIPT

Page 1: CM PE 910 Planning Procedure

Software for creation of

pipe classes and

mechanical calculation of

piping components.

Software for the design

and mechanical

calculation of pressure

vessels and heat exchangers.

The presentation shows

the calculation of a

standard piping flange in

the VES application.

You are here: CM-PE-910 Planning Procedure

1.

2.

3.

4.

5.

6.

7.

The purpose of this procedure is to provide information and instructions in order to establish a

standard method for the planning of a project and facilitate the execution of the project in a

structured manner.

This procedure shall apply to all projects, unless otherwise directed by the Project Manager.

Described are the main activities that are required to make a project plan.

The project plan as described includes Home Office project activities and the preparation of a

basic construction plan. The Construction Plan is to be further detailed by the Construction

Planning Engineer.

The Project Manager and Lead Engineer are responsible for the contents herein. The Planning

Engineer is delegated to obtain required information. Procurement, Construction, Lead Discipline

Engineers and other parties involved in the preparation of the project plan will provide

CM-PE-910 Planning Procedure http://www.red-bag.com/general-procedures/47-cm-pe-910-planning-pro...

1 trong 10 10/16/2015 8:27 AM

Page 2: CM PE 910 Planning Procedure

information as required.

The planning and scheduling of a project is carried out using a four level planning system. Each

level contributes specific parts to the project organization.

Level 1 is a general overview used as a management document. It represents the highest level

and least detailed schedule. Level 1 schedules display in bar chart format the major work

functions, targets, project objectives and constraints. The subcontract strategy must be set when

construction is part of the project scope. The overall objectives defined by the level 1 schedule

must have agreement and Support of all key personnel involved with the project. The Level 1

plan can be supplemented with manpower schedules and progress curves.

See attachment 2 for an example of a Level 1 plan.

Level 2 is a summarization of Level 3 in a bar chart format. It is used for project control

purposes. The level 2 can only be finalized after the level 3 is completed. The summarization

must be in accordance with the Work Breakdown Structure (WBS) of the project.

Level 3 is the most detailed level of planning done by the Planning Engineer and is set up in a

network format. Each task contains information such as weighted manhours, planned number of

deliverables and manpower requirements. The level 3 schedules are the basis on which

schedule deviations to the project execution plan are identified and contains basic information

used for the preparation of reports.

Level 4 plan is made by the Lead Engineer. This plan shall match with the requirements from the

level 3 plan. The preparation of the level 4 plan is not described in this procedure.

The following functions in the project organization have responsibilities described in this

procedure:

Project Manager (or his delegate)

Lead Engineer

Planning Engineer

The Project Manager and the Lead Engineer are responsible for the contents herein. The

Planning Engineer is delegated to obtain required information.

3.1 Project Manager

The responsibilities of the Project Manager:

Provide the Planning Engineer with all necessary information to enable project planning.

Approve the scope of work for the Planning Engineer.

Establish a WBS. This WBS should be defined in-line with other project control tools, such

as Document Control and Cost Control.

Define key work package milestones for project work packages.

Approve the work packages and planning work items.

Approve all project planning schedules.

Review the project status.

Decide if the current plan can be maintained or re planning/ scheduling is necessary.

3.2 Lead Engineer

The responsibilities of the Lead Engineer:

Provide the Planning Engineer with a list of work packages and planning work items needed

for the execution of his scope of work.

Obtain agreement with the Project Manager and the Planning Engineer on the timing of his

activities in the project plan.

Provide Progress Information on his part of the project.

Establish and maintain a Level 4 plan. This plan shall match with the requirements from the

Level 3 plan.

CM-PE-910 Planning Procedure http://www.red-bag.com/general-procedures/47-cm-pe-910-planning-pro...

2 trong 10 10/16/2015 8:27 AM

Page 3: CM PE 910 Planning Procedure

3.3 Planning Engineer

The responsibilities of the Planning Engineer:

Prepare, if required, or agree with planning scope of work.

Prepare a level 1 plan and regular updates.

Prepare a level 3 plan and regular updates, if required in the planning scope of work.

Support the Lead Engineers with advice and assistance regarding the level 4 plans.

Establish agreement with the Lead Engineers on the timing of activities.

Establish agreement on the project status with the Lead Engineers and the Project Manager.

Analyze the project status.

Provide planning reports and narratives in accordance with the Planning scope of work.

At the job end create a job close report and archiving.

The Planning Engineer is responsible for obtaining the information that is needed to make

and maintain the project plan.

The following phases are identified when creating a project plan:

Planning Scope Definition

Acquiring Planning Information

Creating the Project Schedule

Maintaining the Project Schedule

Project Close Out

4.1 Description of the Phases

Planning Scope Definition

The Project Manager provides the Planning Engineer basic project data, contractual

requirements and project requirements. With this information the Planning Engineer defines his

scope of work. The Project Manager approves the planning scope of work.

Acquiring Planning Information

The Planning Engineer is proactive in obtaining the required information to make a project plan.

The Project Manager and the Lead Engineer are responsible for the contents of the provided

information.

Creating the Project Schedule

With the provided information the Planning Engineer creates a project schedule according to the

planning scope definition.

Maintaining the Project Schedule

During the project the Planning Engineer acquires actual data. The actual data is used to update

the schedule. The updated schedule is analyzed by the Planning Engineer. After analyzing, the

Planning Engineer reports the results to the Project Manager.

Project Close Out

When the project has ended, the Planning Engineer makes a planning job close report and takes

care of proper archiving of planning information of the project.

4.2 Flowchart Description

Description of each box of the flow chart in section 5.

Project Manager

Planning information and requirements. The Project Manager has to provide the Lead Planning

Engineer with information, based on contractual and internal requirements. The information shall

be provided early in the project, up to date and contain at least the project scope (EPC),

planning budget, planning resources and project milestones.

CM-PE-910 Planning Procedure http://www.red-bag.com/general-procedures/47-cm-pe-910-planning-pro...

3 trong 10 10/16/2015 8:27 AM

Page 4: CM PE 910 Planning Procedure

Planning Scope

Project Manager decides whether a planning scope description is necessary for his project. If a

planning scope description is not required, the Planning Engineer makes only a Level 1 plan.

Planning Engineer

Definition of the planning scope of work. This is a description of the planning deliverables for this

project (include timing and frequency). The planning scope shall also contain information such

as staffing, budget and manhour estimate for the Planning Department. See attachment 1.

Project Manager

Approval of the planning scope. If not approved, redefine the planning scope until it is approved.

Planning Engineer

Level 1 Planning Schedule. This is a bar chart that shows the major work functions, targets,

project objectives and constraints. See attachment 2 for an example.

Approval and agreement Level 1

Agreement with the Lead Engineers on the planning schedule is required. The Project Manager

approves the Level 1. This schedule masters time frames for engineering, procurement and

construction activities. The time frames are required for the preparation of the Level 3 network.

Project Manager

Establish a WBS and define key deliverable milestones. A WBS is required to divide the project

in controllable parts. Key deliverable milestones are required for project control purposes.

Lead Engineer

Submit a list of all work packages and planning work items in the project for his discipline,

grouped by WBS. This list must cover his scope of work.

Project Manager

Approval of the work packages and planning work items. If not approved, the Lead Engineer

updates the list of work packages and planning work items until it is approved.

Planning Engineer

The Planning Engineer creates, with all provided information, when a logic is made timing and

resources are added. This results in a level 3 bar chart schedule plan. This schedule is the basis

of further activities of the Planning Engineer.

All Participants

Review of the Level 3 bar chart schedule. The Project Manager, Lead Engineers and the

Planning Engineer shall review the level 3 bar chart schedule and give their opinion. All opinions

shall be taken into consideration and as far as possible incorporated in the Level 3 plan.

Project Manager

The Project Manager approves the Level 3 Schedule. After approval from the Project Manager

the Level 3 schedule is a project controls document, which shows the timing of project activities.

Now a level 2 planning schedule can be made by summarizing the level 3 schedule.

In-line with the level 1 schedule.

The time frames in the Level 1 schedule shall be the same as the time frames in the Level 3

schedule. However, because more details are known from the project, adjustment of the Level 1

schedule is possible. The Project Manager decides if adjustments shall be made.

Planning Engineer

Update Level 1 Planning Schedule. During the project the Planning Engineer inputs actual data

to the level 1 schedule and writes a report on the project status.

CM-PE-910 Planning Procedure http://www.red-bag.com/general-procedures/47-cm-pe-910-planning-pro...

4 trong 10 10/16/2015 8:27 AM

Page 5: CM PE 910 Planning Procedure

All participants

During the project a progress measurement system will be used to indicate the status of each

network task.

Planning Engineer

Analysis and regular planning reports and narratives. The Planning Engineer analyzes the

project status and reports his conclusion to the Project Manager. In the planning scope of work is

listed which reports, narratives and their frequency the Planning Engineer shall make.

Project Manager

Review of the project status.

Maintain Current Plan.

The Project Manager decides if the current plan can be maintained or needs rescheduling.

CM-PE-910 Planning Procedure http://www.red-bag.com/general-procedures/47-cm-pe-910-planning-pro...

5 trong 10 10/16/2015 8:27 AM

Page 6: CM PE 910 Planning Procedure

CM-PE-910 Planning Procedure http://www.red-bag.com/general-procedures/47-cm-pe-910-planning-pro...

6 trong 10 10/16/2015 8:27 AM

Page 7: CM PE 910 Planning Procedure

Document Number Title Level

6.1 CM-PE-119 Procedure for Document Control 2

6.2 BN-W-UE301 Work Instruction for the Numbering of Project

Documents

4

CM-PE-910 Planning Procedure http://www.red-bag.com/general-procedures/47-cm-pe-910-planning-pro...

7 trong 10 10/16/2015 8:27 AM

Page 8: CM PE 910 Planning Procedure

6.3 CM-PE-920 Project Executive Control 2

7.1 Planning Scope Information Sheet

7.2 Typical Level 1 Schedule

CM-PE-910 Planning Procedure http://www.red-bag.com/general-procedures/47-cm-pe-910-planning-pro...

8 trong 10 10/16/2015 8:27 AM

Page 9: CM PE 910 Planning Procedure

Advanced Piping Design

book from Gulf Publishing

Company for which Red-Bag

The Library section of the

Red-Bag website contains

information for the process

Preferably use the e-mail

form for your first contact.

InIPED, provider

of choice for high

quality training.

CM-PE-910 Planning Procedure http://www.red-bag.com/general-procedures/47-cm-pe-910-planning-pro...

9 trong 10 10/16/2015 8:27 AM

Page 10: CM PE 910 Planning Procedure

provided the co-author. industry.

'reliability is yet to become the most important characteristic of modern companies'