cm24 1 1 june 2009 aspirational schedule mechanics is reassembled; survived basic tests but more...
TRANSCRIPT
CM24 1 1 June 2009
ASPIRATIONAL SCHEDULE
Mechanics is reassembled; survived basic tests but more required – including positioning accuracy, bedding-in of gears….Electronics & Air Crates working; LabView controls starting (EPICS can wait)Developing ‘Disc transfer Mechanism’ – critical item – next slides
Done
Ongoing
Started
Starting
Done
Done
CM24 2 1 June 2009
DISC TRANSFER CONCERNS Simplified
Disc Holder Disc Carrier
Carousel rotation
D-H Rotation Carrier motion
Discs are transferred between Disc Holders and Carrier
Each disc has 4 pins to fit 4 holes on each side
Each disc has 2 SidesThere are 5 DiscsEach has (up to) 4 Orientations
160 pins & holes to align reliably & reproducibly – or something will bend / break / jam & it’s buggered
Pin – hole clearance is +/– 0.5mm
3 sigma positioning < 0.5mm
Position to < 0.15mm for varying loads on Carousel
CM24 3 1 June 2009
• Not easy to achieve required accuracy• Air motors overrun by several mm, depending....
• Now use piston to align Carousel arm• Measured misalignments are ~ 0.5 – 1mm
• Depend on loading (lead is heavy)
• Design is (was) not forgiving of any misalignments• Have incorporated ‘float’ + springs in carrier
• For L – R and U – D misalignment (1mm / 0.3mm)
• Designing & developing overrun & locking mechanisms for discs• To keep pins aligned in disc-holders & absorb overruns
• More springs / ‘Terry clips’ …. (? Lead times if custom items?)
• Shall build mock-up of Disc-Holder – Carrier arrangement• To test various ideas for locking the pins & overrun ‘buffers’• To develop transfer procedure – almost invisible on real device
• Have allowed 9 weeks in schedule for this (+ other tests)• May need more inspiration & imagination
• Transfer operation development on critical path