  • 7/28/2019 CO CNB2 JPN Display PO for Project

    1/12

    Work Instruction CNB2 - JPN - Display PO for Project

    PurposeUse this procedure to display the purchase orders per project.TriggerPerform this transaction when you need to display the purchase orders based on its project or WBS element.Menu PathUse the following SAP Easy Access menu path(s) to begin this transaction:

    Transaction code CNB2 via the Command or Keycode edit field.

    Transaction Code

    CNB2

    Wednesday, July 15, 2009 CO_CNB2_JPN_Display PO forProject.udc

    1/12

  • 7/28/2019 CO CNB2 JPN Display PO for Project

    2/12

    Work Instruction CNB2 - JPN - Display PO for Project

    Screen Flow

    Wednesday, July 15, 2009 CO_CNB2_JPN_Display PO forProject.udc

    2/12

  • 7/28/2019 CO CNB2 JPN Display PO for Project

    3/12

    Work Instruction CNB2 - JPN - Display PO for Project

    Procedure

    1. In SAP, start the transaction using the menu path or transaction code.SAP Easy Access

    2. As required, complete/review the following fields:

    Example:Field

    CNB2

    R/O/C Description

    RCommand

    Wednesday, July 15, 2009 CO_CNB2_JPN_Display PO forProject.udc

    3/12

  • 7/28/2019 CO CNB2 JPN Display PO for Project

    4/12

    Work Instruction CNB2 - JPN - Display PO for Project

    3. Click the Enter button .

    Wednesday, July 15, 2009 CO_CNB2_JPN_Display PO forProject.udc

    4/12

  • 7/28/2019 CO CNB2 JPN Display PO for Project

    5/12

    Work Instruction CNB2 - JPN - Display PO for Project

    Enter profile

    4. Click the Database prof. edit field .5. Click the Database prof . possible entries button .Profile for logical database PSJ (1) 10 Entries found

    Wednesday, July 15, 2009 CO_CNB2_JPN_Display PO forProject.udc

    5/12

  • 7/28/2019 CO CNB2 JPN Display PO for Project

    6/12

    Work Instruction CNB2 - JPN - Display PO for Project

    Wednesday, July 15, 2009 CO_CNB2_JPN_Display PO forProject.udc

    6/12

  • 7/28/2019 CO CNB2 JPN Display PO for Project

    7/12

    Work Instruction CNB2 - JPN - Display PO for Project

    6. Double-click the 000000000001 | Standard selection (structure) lineitem .

    Enter profile

    7. Click the Continue button .Purchasing Documents per Project

    Wednesday, July 15, 2009 CO_CNB2_JPN_Display PO forProject.udc

    7/12

  • 7/28/2019 CO CNB2 JPN Display PO for Project

    8/12

    Work Instruction CNB2 - JPN - Display PO for Project

    8. As required, complete/review the following fields:

    Wednesday, July 15, 2009 CO_CNB2_JPN_Display PO forProject.udc

    8/12

  • 7/28/2019 CO CNB2 JPN Display PO for Project

    9/12

    Work Instruction CNB2 - JPN - Display PO for Project

    Abusinessundertakinginvolvingapredeterminedgoal toachievewith

    prescribed fundsandoperatingresources, to anagreedlevel of quality,and by aparticular

    date.Field

    Example:I-IC-08003

    R/O/C Description

    R

    Project9. Click the Execute button .Purchasing Documents per Project

    Wednesday, July 15, 2009 CO_CNB2_JPN_Display PO forProject.udc

    9/12

  • 7/28/2019 CO CNB2 JPN Display PO for Project

    10/12

    Work Instruction CNB2 - JPN - Display PO for Project

    10.

    Click the Exit button .

    Wednesday, July 15, 2009 CO_CNB2_JPN_Display PO forProject.udc

    10/12

  • 7/28/2019 CO CNB2 JPN Display PO for Project

    11/12

    Work Instruction CNB2 - JPN - Display PO for Project

    Result

    You have successfully displayed PO per project.

    Wednesday, July 15, 2009 CO_CNB2_JPN_Display PO forProject.udc

    11/12

  • 7/28/2019 CO CNB2 JPN Display PO for Project

    12/12

    Work Instruction CNB2 - JPN - Display PO for Project

    Scenario

    Instructions In this simulation you are required to: Display PO for Project in SAP ECC 6.0.

    Required Data This section provides the field data required to complete this exercise. Refer to this data sheet as necessary while performing the exercise.I-IC-08003 Field

    Project

    Value

    CNB2

    Command

    Wednesday, July 15, 2009 CO_CNB2_JPN_Display PO forProject.udc

    12/12