cocog13.02 boyd freeman headgate - anderson … · 2016-06-29 · microsoft word - cocog13.02 boyd...
TRANSCRIPT
cocog13.02 Boyd Freeman Headgate.docx 1 of 2 Anderson Consulting Engineers, Inc.
View Downstream at Headgate Structure
Erosion at Headgate Structure
Boyd and Freeman Headgate Rehabilitation and Return Structure Project
Greeley, Colorado
Client: Mr. Phill Carter
The Boyd Irrigation Company
1100 10th Street, 3rd Floor
Greeley, Colorado 80631
(970) 350-9826
The Cache La Poudre River (Poudre) flooding in May and June 2010 directed overbank flows
into the Boyd and Freeman Ditch (BFD) that resulted in considerable damage to the ditch and
diversion facilities. The BFD headgate and check dam are located on the main channel of the
Poudre approximately 8,500 feet west of 35th
Avenue and 500 feet north of F Street.
Approximately 200 feet west of the diversion dam/headgate structure there is a high flow bypass
channel with a second check dam. The BFD headgate and check dam, both concrete, have long
been in overall poor condition. Water
rights for the BFD were first
appropriated on March 15, 1862, which
gives an indication of the potential age
of the existing headgate facility.
During the spring of 2010 flooding
event on the Poudre, debris in the
bypass channel may have exacerbated
flooding conditions at the headgate.
The headgate diversion dam was
severely damaged and the headgate
structure concrete walls experienced
erosion damage when the 2010 flood
flows overtopped the structure. A head
differential flow measurement structure
is presently located at the BFD
headgate slidegates. Due to the limited
functionality of the existing slide gates,
and high tailwater conditions in ditch,
the measurement structure has not
gained acceptance by the Colorado
Division of Water Resources (CDWR).
The objective of this project was to
develop alternative concepts for
replacing/repairing the headgate and check
dam with the addition of an integral
measured return flow structure, develop
alternatives for replacing the measurement
device with one acceptable to the CDWR,
assist the ditch company with selecting an
alternatives, and complete final designs
based the selected alternatives. This
project consisted of the following:
cocog13.02 Boyd Freeman Headgate.docx 2 of 2 Anderson Consulting Engineers, Inc.
Debris at Bypass Channel
• Formulation and hydraulic evaluation of conceptual alternatives to meet the project objective;
• Formulation of cost estimates for conceptual alternatives;
• Hydraulic analysis and final design of concrete check dam and headgate, incorporating floating
debris and sediment handling systems;
• Hydraulic analysis and final design of meter vault for 48-inch diameter electromagnetic flow
meter and associated valving;
• Hydraulic analysis and final design
of a 100-foot long, 48-inch diameter
PVC pipe conveyance to direct flow
through the 48-inch meter;
• Hydraulic analysis and final design
of meter vault for 18-inch diameter
electromagnetic flow meter and
associated valving;
• Hydraulic analysis and final design
of a 35-foot long, 18-inch diameter
PVC pipe conveyance to direct flow through the 18-inch meter;
• Removal of debris to enhance capacity
of bypass channel;
• Project area grading and reclamation;
• Preparation of final design drawings
and contract documents; and
• Project observation during the approximately 2-month construction time period.
Headgate Structure Grading Plan