cocomo

32
The CoCoMo Model (The Constructive Cost Model) Tom Rethard based on a presentation by Jim Paulson of Novatel Wireless

Upload: abhishek-aby

Post on 14-Nov-2014

130 views

Category:

Documents


14 download

DESCRIPTION

The Power Point Presentation on the Cost Constructive Model, which is quite significant for cost maintenance in any project.

TRANSCRIPT

Page 1: Cocomo

The CoCoMo Model(The Constructive Cost Model)

Tom Rethardbased on a presentation by Jim Paulson of Novatel

Wireless

Page 2: Cocomo

CSE 4310/5392 2

COCOMOOutline Introduction The Basic Model

Equations When You Should Use It Limitations

Intermediate Model Detailed Model

Page 3: Cocomo

CSE 4310/5392 3

COCOMO COCOMO is one of the most widely used

software estimation models in the world It was developed by Barry Boehm in 1981 COCOMO predicts the effort and schedule

for a software product development based on inputs relating to the size of the software and a number of cost drivers that affect productivity

Page 4: Cocomo

CSE 4310/5392 4

COCOMO: Three Models

COCOMO has three different models that reflect the complexity: the Basic Model the Intermediate Model and the Detailed Model

Page 5: Cocomo

CSE 4310/5392 5

The Development Modes: Project Characteristics

Organic Mode developed in a familiar, stable environment, similar to the previously developed projects relatively small and requires little innovation

Semidetached Mode intermediate between Organic and Embedded

Embedded Mode tight, inflexible constraints and interface requirements The product requires great innovation

Page 6: Cocomo

CSE 4310/5392 6

COCOMO:Some Assumptions

Primary cost driver is the number of Delivered Source Instructions (DSI) developed by the project

COCOMO estimates assume that the project will enjoy good management by both the developer and the customer

Assumes the requirements specification is not substantially changed after the plans and requirements phase

Page 7: Cocomo

CSE 4310/5392 7

Basic COCOMO Model

Basic COCOMO model estimates the software development effort using only a single predictor variable (size in DSI) and three software development modes

Page 8: Cocomo

CSE 4310/5392 8

Basic COCOMO Model:Equations

Mode Effort Schedule

Organic E=2.4*(KDSI)1.05 TDEV=2.5*(E)0.38

Semidetached E=3.0*(KDSI)1.12 TDEV=2.5*(E)0.35

Embedded E=3.6*(KDSI)1.20 TDEV=2.5*(E)0.32

Page 9: Cocomo

CSE 4310/5392 9

Basic COCOMO Model: When Should You Use It

Basic COCOMO is good for quick, early, rough order of magnitude estimates of software costs

Page 10: Cocomo

CSE 4310/5392 10

Basic COCOMO Model:Limitations

Its accuracy is necessarily limited because of its lack of factors which have a significant influence on software costs

The Basic COCOMO estimates are within a factor of 1.3 only 29% of the time, and within a factor of 2 only 60% of the time

Page 11: Cocomo

CSE 4310/5392 11

Basic COCOMO Model:An Example

We have determined our project fits the characteristics of Semi-Detached mode

We estimate our project will have 32,000 Delivered Source Instructions. Using the formulas, we can estimate:

Effort = 3.0*(32) 1.12 = 146 man-months Schedule = 2.5*(146) 0.35 = 14 months Productivity = 32,000 DSI / 146

MM = 219 DSI/MM

Average Staffing = 146 MM /14 months = 10 FSP

Page 12: Cocomo

CSE 4310/5392 12

Intermediate COCOMO Model

The Intermediate Model estimates the software development effort by using fifteen cost driver variables besides the size variable used in Basic COCOMO

Page 13: Cocomo

CSE 4310/5392 13

Intermediate COCOMO Model

Four areas for drivers Product itself Computer Personnel Project itself

Page 14: Cocomo

CSE 4310/5392 14

Intermediate Model:Cost Driver Categories

Product Attributes RELY --- Required Software

Reliability DATA --- Data Base Size CPLX --- Software Product

Complexity

Page 15: Cocomo

CSE 4310/5392 15

Intermediate Model:Cost Driver Categories

Computer Attributes TIME --- Execution Time Constraint STOR --- Main Storage Constraint VIRT --- Virtual Machine Volatility TURN --- Computer Turnaround

Time

Page 16: Cocomo

CSE 4310/5392 16

Intermediate Model:Cost Driver Categories

Personnel Attributes ACAP --- Analyst Capability AEXP --- Applications Experience PCAP --- Programmer Capability VEXP --- Virtual Machine Experience LEXP --- Programming Language

Experience

Page 17: Cocomo

CSE 4310/5392 17

Intermediate Model:Cost Driver Categories

Project Attributes MODP --- Modern Programming

Practices TOOL --- Use of Software Tools SCED --- Required Development

Schedule

Page 18: Cocomo

CSE 4310/5392 18

Intermediate Model:Effort Multipliers

Table of Effort Multipliers for each of the Cost Drivers is provided with ranges depending on the ratings

Cost DriverVery Low Low Nom High

Very High

Extra High

CPLX Product Complexity 0.70 0.85 1.00 1.15 1.30 1.65

Page 19: Cocomo

CSE 4310/5392 19

Intermediate Model:Equations

Mode Effort Schedule

Organic E=EAF*3.2*(KDSI)1.05 TDEV=2.5*(E)0.38

Semi- E=EAF*3.0*(KDSI)1.12 TDEV=2.5*(E)0.35

detached

Embedded E=EAF*2.8*(KDSI)1.20 TDEV=2.5*(E)0.32

Page 20: Cocomo

CSE 4310/5392 20

Intermediate Model:When Should You Use It

The Intermediate Model can be applied across the entire software product for easily and rough cost estimation during the early stage

or it can be applied at the software product component level for more accurate cost estimation in more detailed stages

Page 21: Cocomo

CSE 4310/5392 21

Intermediate Model:Limitations

The Intermediate Model estimates are within 20% of the actuals 68% of the time

Its effort multipliers are phase-insensitive

It can be very tedious to use on a product with many components

Page 22: Cocomo

CSE 4310/5392 22

Intermediate Model:An Example Project A is to be a 32,000 DSI semi-

detached software. It is in a mission critical area, so the reliability is high (RELY=high=1.15). Then we can estimate:

Effort = 1.15*3.0*(32)1.12 = 167 man-months

Schedule = 2.5*(167)0.35 = 15 months Productivity = 32,000 DSI/167 MM

= 192 DSI/MM Average Staffing = 167 MM/15 months

= 11 FSP

Page 23: Cocomo

CSE 4310/5392 23

Detailed COCOMO Model:How is it Different?

Phase-sensitive Effort MultipliersThe effort multipliers for every cost drivers are different during the software development phases

Module-Subsystem-System HierarchyThe software product is estimated in the three level hierarchical decomposition. The fifteen cost drivers are related to module or subsystem level

Page 24: Cocomo

CSE 4310/5392 24

Detailed COCOMO Model:Module-Subsystem-System Module level

cost drivers tend to vary at the lowest level CPLX, PCAP, VEXP, LEXP

Subsystem Level cost drivers tend to vary from subsystem to

subsystem, but are the same for modules in a sub-system

RELY, DATA, TIME, STOR, VIRT System Level

overall project relations such as nominal effort and schedule equations

Page 25: Cocomo

CSE 4310/5392 25

Detailed COCOMO Model:Equations Detailed Model uses the same

equations for estimations as the Intermediate Model

Detailed Model uses a very complex procedure to calculate estimation. The procedure uses the DSIs for subsystems and modules, and module level and subsystem level effort multipliers as inputs

Page 26: Cocomo

CSE 4310/5392 26

Detailed COCOMO Model:When Should You Use It? The Detailed Model can estimate the

staffing, cost, and duration of each of the development phases, subsystems, modules

It allows you to experiment with different development strategies, to find the plan that best suits your needs and resources

Page 27: Cocomo

CSE 4310/5392 27

Detailed COCOMO Model:Limitations

Requires substantially more time and effort to calculate estimates than previous models

Detailed Model estimates are within 20% of the actuals 70% of the time

Page 28: Cocomo

CSE 4310/5392 28

Summary Cost estimation models are not a

substitute for a detailed estimate by task by project management

Cost estimation models highly depend on the user’s knowledge of application domain, analysis ability and the understanding of the cost model itself

The process of meeting the estimate is equally critical to the process of making the estimate

Page 29: Cocomo

CSE 4310/5392 29

Links

COCOMO II web page can be found at: sunset.usc.edu/research/COCOMOII/index.html

Page 30: Cocomo

CSE 4310/5392 30

Questions / Discussion

Issues to discuss: Do you think cost multipliers are

project phase dependent like COCOMO’s detailed model suggests?

Is cost estimation only suitable for the Waterfall lifecycle, or can it be used with other life cycles, such as incremental?

Page 31: Cocomo

CSE 4310/5392 31

Questions / Discussion

Issues to discuss: Your cost estimate uses three methods

which return widely varying results? How do you determine which method is right?

What methods or models have you seen used in the workplace? How successful were they?

Page 32: Cocomo

CSE 4310/5392 32

Questions / Discussion

Issues to discuss: Is it possible to estimate the size

using soft requirements?