©2014 MFMER | slide-1 COGENERATION PLANT SWITCHGEAR REPLACEMENT IMPROVES SAFETY AND RELIABILITY WHILE MAINTAINING SERVICE TO CRITICAL LOADS Presented to: Minnesota Power Systems Conference November 5, 2014 Rachel Mueller, Mayo Clinic Timothy Coyle, PCT, Inc.

Upload: others

Post on 28-Feb-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-1

COGENERATION PLANT SWITCHGEAR REPLACEMENT IMPROVES SAFETY

AND RELIABILITY WHILE MAINTAINING SERVICE TO CRITICAL LOADS

Presented to: Minnesota Power Systems Conference

November 5, 2014

Rachel Mueller, Mayo Clinic Timothy Coyle, PCT, Inc.

Page 2: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-2

Franklin Heating Station Statistics

• Established in 1927

• 390 KPH steam, 12,000 tons cooling, 16.1 MW generation

• One of two plants serving the 7.2 million square feet of Clinic campus buildings

• Generation: • Condensing turbines TG1 and TG2: 2.5 MW each

• Backpressure turbine TG3: 6.3 MW

• Dual-fuel engines DG6 and DG7: 2.4 MW each

• Distribution: • Approximately 4 MW to buildings via 13.8 kV and 2400V

feeders

• Emergency/standby power from DG6 and DG7

2

Page 3: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-3

G G TG1 2.5 MW

TG2 2.5 MW

37.5 MVA

G TG3 6.3 MW

161 KV Line

To Silver Lake

161 KV Line

To Byron 345

To SMH

Franklin

Heating

Station

BUS 6

RPU Crosstown

Substation

G TG6 6.4 MW

Prospect Utility Plant

Ozmun

DAHLC

Harwick

~7MW

~4.3MW

Gonda

Charlton/

Harwick

~6.5 MW

RMH

~3.7MW

BUS 3 BUS 4

BUS 7 BUS 8

Harwick

~1.4MW

Hilton/Gugg ~2.2MW Mayo

37.5 MVA

BUS 5

Page 4: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-4

4

Page 5: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-5

Justification for Replacement

• Age and Condition

• Inadequate Working Clearance

• Short Circuit Ratings Exceeded

• Protection Shortcomings • Many breakers in

series • Long current

differential circuits • Complex hard-wired

load shedding scheme

5

Page 6: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-6

Pre-Project Short Circuit Duties

6

Page 7: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-7

Upgraded Short Circuit Duties

7

Page 8: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-8

Design Constraints

• No Additional Space Available on Turbine Floor or in Proximity

• Maintain Crane Access to Basement through Grating in Front of Existing Switchgear

• Maintain Service to Loads and Generation Capacity During Installation and Commissioning

• Narrow Time Window for Taking TG3 Out of Service

• Highly Congested Cable Space Below Existing Switchgear

8

Page 9: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-9

9

Selected Option: Three 13.8 kV Buses (Sync Bus)

Page 10: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-10

G G TG1 2.5 MW

TG2 2.5 MW

37.5 MVA

G TG3 6.3 MW

161 KV Line

To Silver Lake

161 KV Line

To Byron 345

To SMH

Franklin

Heating

Station

BUS 6 G TG6 6.4 MW

Prospect Utility Plant

Ozmun

DAHLC

Harwick

~7MW

~4.3MW

Gonda

Proton

~2MW + Buildout

Charlton/Harwick

~6.5 MW

RMH

~3.7MW

BUS 3 BUS 4

Sync

BUS 7 BUS 8

Harwick

~1.4MW

Block 12

~MW ??

Hilton/Gugg ~2.2MW Mayo

BUS 5A

BUS Z

37.5 MVA

BUS 5B

Page 11: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-11

G G TG1 2.5 M

TG2 2.5 MW

37.5 MVA

G TG3 6.3 MW

161 KV Line

To Silver Lake

161 KV Line

To Byron 345

To SMH

Franklin

Heating

Station

BUS 6 G TG6 6.4 MW

Prospect Utility Plant

Ozmun

DAHLC

Harwick

~7MW

~4.3MW

Gonda

Proton

~2MW + Buildout

Charlton/Harwick

~6.5 MW

RMH

~3.7MW

BUS 3 BUS 4

Sync

BUS 7 BUS 8

Harwick

~1.4MW

Block 12

~MW ??

Hilton/

Guggenheim

~2.2MW Mayo

BUS 5A

BUS Z

37.5 MVA

BUS 5B

Page 12: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-12

Protection System Criteria

12

Provide Primary and Backup Protection for all Buses and Circuits

Provide Zoned Primary Protection of Buses and Tie Circuits

Utilize Micro-Processor Based Relays Consistent with Existing Installed Base

Provide Metering Data for All Circuits over Ethernet

Implement Simplified Under-frequency Load Shedding

Page 13: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-13

Protection System Design

13

Based on GE UR Platform: F60, F35, G30

Protection Schemes:

Buses: Traditional High Impedance Differential, MIB

Tie Circuits: Directional Comparison Permissive Tripping with Backup Time Overcurrent, F60

Load Feeders: Time Overcurrent, F60 and F35

Generator: C37.102 with Redundant G30s

IEC 61850 Communications for Tie Circuit Protection

Redundant Fiber Optic Networks

Monitoring at Engineering Workstation

Page 14: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-14

Protection Network Diagram

14

Page 15: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-15

Network Detail at Bus 3 and Bus Z

15

Page 16: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-16

Tie Feeder Protection Logic (F60 - Z5)

16

Page 17: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-17

Load Shed System Design

17

Implemented from RPU ties at Buses 7 and 8 through Bus 5B to Bus Z

Manual Enable/Disable switch at FHS

Separate from RPU at Buses 7 and 8 on UF and RCOF

Arm feeder load shedding at each plant based on separation from RPU and Enable/Disable switch position

Shed plant chiller load and feeders based on underfrequency setpoints

IEC 61850 Signals:

Enable/Disable status from Bus Z to Bus 7

Separation from RPU from Bus 7 to Bus Z

Separation from RPU from Bus 5B to Bus Z

Page 18: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-18

G G TG1 2.5 M

TG2 2.5 MW

37.5 MVA

G TG3 6.3 MW

161 KV Line

To Silver Lake

161 KV Line

To Byron 345

G TG6

RMH

BUS 3 BUS 4

Sync

BUS 7

Harwick

Block 12

Hilton/

Guggenheim

Mayo

BUS Z

37.5 MVA

BUS 5B

Load Shed System Design

Breaker R4 or R5: Trip

for f <= 59.95 Hz AND

df/dt > - 3.0 Hz/s BUS 8

Shed Plant Load at

f <= 59.90 Hz

Shed Plant Load at

f <= 59.90 Hz

Shed Feeders

at Staggered

Frequencies

No Shed at

Bus 5B

Page 19: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-19

Bus 7 Load Shed Logic –Trip RPU Tie

19

Page 20: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-20

Bus 7 Load Shed Logic: Shed Plant Loads

20

Page 21: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-21

Bus Z Load Shed Logic

21

Page 22: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-22

Bus Z Load Shed Logic

22

Page 23: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-23

DEMOLITION, INSTALLATION AND COMMISSIONING

Reliability Expectations

Tasks

What led to things going smoothly?

Page 24: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-24

Mayo Clinic Campus Utility Expectations

• Zero Electrical or Utility Outages

• 6 Week Turbine Outage

• Plant Staff expected to

“Maintain” Plant Operations

• New Gear but Existing Infrastructure

• 3 Phases of Project Required

“Temporary” Connections

Page 25: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-25

TASKS

End – to – End Relay Testing

Electrical Switching Procedures

Operation of Electrical System

Page 26: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-26

GPS

End-to-End Relay Testing

REMOTE

BUS

PLANT

REMOTE

BUS

PLANT

TYPICAL INSTALLATION OUR INSTALLATION

GOAL: Function test

system components

simultaneously

• Settings

• Communication

• Fiber Optics

• Network

• Coordination

Page 27: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-27

TEST STATION

Created Test Stations to Simulate End-to-End Installation

Tested Protective Relaying Elements

Tested Load Shed Signals

Verified Functionality and Operation of Gear

REMOTE

BUS

PLANT

TEST STATION

Page 28: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-28

On-Line Live Verification using GE UR Software

At project completion we used On Line Monitoring to verify Remote I/O

Page 29: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-29

Electrical Switching Procedures

• Live-Transfer Switching Done Off Hours (night/weekend)

• Procedures Allowed Safer Practice for Switching Load

• Insured Safety of Personnel - LOTO

• Updated Procedure Led to Zero Switching Outages

Page 30: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-30

Electrical Switching Procedures

Page 31: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-31

TIME AND EFFORT

21 PROCEDURES

=

336 HOURS

DEDICATED TO WRITING AND PERFORMING SAFE SWITCHING

• DRAFT PROCEDURE WRITING

• 1 PERSON ~4 HOURS

• WALKDOWN • 3 PERSON ~1 HOUR

• FINAL PROCEDURE AND REVIEW

• 1 PERSON ~ 1 HOUR

• PERFORMING SWITCHING PROCEDURE

• 4 PERSON ~ 1 HOUR before

• 4 PERSON ~ 1 HOUR after

Page 32: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-32

Operation of the Electrical System

• Configuration was Complex During the Installation Process

• Electrical System was Changing Daily and was Difficult to Operate

• Management Utilized Tools to Protect from Operation Error

Page 33: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-33

Simplified One-Lines

Page 34: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-34

What led to things going smoothly?

• PRIORITIZING

• Safety First

• Reliability

• PLANT PREPARATION

• Utilized other project opportunities to prepare

• Field verification

• CULTURE

• Communicate openly

• Team

Page 35: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-35

NEW GEAR

Page 36: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-36

NEW GEAR

Bus Diff CT

Page 37: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-37

What Happened?

• We Got Comfortable

• Started with a Schedule Change….

• We Didn’t Allow for any Mistakes to Occur – Failed to Plan for

Human Error

Page 38: COGENERATION PLANT SWITCHGEAR REPLACEMENT …cce.umn.edu/documents/CPE-Conferences/MIPSYCON...• WALKDOWN • 3 PERSON ~1 HOUR • FINAL PROCEDURE AND REVIEW • 1 PERSON ~ 1 HOUR

©2014 MFMER | slide-38