collector system design

Upload: jomoran

Post on 08-Apr-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/7/2019 Collector System Design

    1/17

    1

    Collector System DesignCollector System DesignConsiderations for Wind FarmsConsiderations for Wind Farms

    Sean CarrSean Carr

    Ernst CammErnst Camm

    S&C Electric Co.S&C Electric Co.

  • 8/7/2019 Collector System Design

    2/17

    2

    OverviewOverview

    Challenges in wind farmChallenges in wind farm

    collector systemscollector systems Design considerationsDesign considerations

    for collector systemsfor collector systems

    SummarySummary

    The presentation will discuss theThe presentation will discuss themost prevalent collector systemmost prevalent collector systemdesign for land based wind farmsdesign for land based wind farmswith underground collectorwith underground collectorsystems.systems.

  • 8/7/2019 Collector System Design

    3/17

    3

    Challenges in Wind Farm CollectorChallenges in Wind Farm Collector

    SystemsSystems

    Location and terrain of windLocation and terrain of wind

    farm sitefarm site Installation methodologyInstallation methodology

    and constructabilityand constructability

    Ice throw from windIce throw from windturbinesturbines

    Length of collector systemLength of collector system

    cable circuitscable circuits

    Cable testing and faultCable testing and fault

    locating of collector circuitslocating of collector circuits

  • 8/7/2019 Collector System Design

    4/17

    4

    Design Considerations for CollectorDesign Considerations for Collector

    SystemsSystems

    Most common voltage levels for collector systemsMost common voltage levels for collector systems

    15 kV15 kV

    25 kV25 kV

    35 kV (most typical)/46 kV (Canada)35 kV (most typical)/46 kV (Canada) 35 kV is the most common system voltage utilized35 kV is the most common system voltage utilized

    for wind farm collector systems because of the longfor wind farm collector systems because of the longcircuit lengths and loading requirementscircuit lengths and loading requirements

    UK voltages typically 11 kV and 33 kVUK voltages typically 11 kV and 33 kV

  • 8/7/2019 Collector System Design

    5/17

    5

    Cable DesignCable Design

    Cable insulation levelsCable insulation levels

    Cable type and sizesCable type and sizes CableCable ampacitiesampacities

    Load factorLoad factor

    Number of circuitsNumber of circuits Cable installation geometryCable installation geometry

    and methodand method

    ThermalThermal resistivityresistivity andand

    temperaturetemperature

    Cable shield voltages andCable shield voltages and

    bonding methodbonding method

  • 8/7/2019 Collector System Design

    6/17

    6

    Circuit Configuration and Soil ThermalCircuit Configuration and Soil Thermal

    ResistivityResistivity Impact on AmpacityImpact on Ampacity

    1 Circuit, 3 Cables, Trefoil, 90 C, 1/3 Neutral, 35 kV, 40 Direct Buried,Spaced 12 Between Circuits

    270

    241

    2

    20

    19

    5

    162

    142

    134

    117

    0

    50

    100

    150

    200

    250

    300

    Ampacity

    90 150 300 450

    RHO

    Ampacity vs RHO for Single and Parallel Circuits

    Trefoil

    Double Ckt. Trefoil

  • 8/7/2019 Collector System Design

    7/17

    7

    Cable Sheath Bonding and GroundingCable Sheath Bonding and Grounding

    Three basic methods ofThree basic methods of

    sheath bondingsheath bonding singlesingle--point bondingpoint bonding

    solid bondingsolid bonding

    cross bondingcross bonding

    NESC Sec. 9 Rule 92CNESC Sec. 9 Rule 92C

    4 grounds per mile4 grounds per mile includes grounds atincludes grounds at

    transformers, splices, etc.transformers, splices, etc.

    Parallel groundingParallel groundingconductorconductor

  • 8/7/2019 Collector System Design

    8/17

    8

    Surge Protection Considerations for CollectorSurge Protection Considerations for Collector

    SystemsSystems

    Surge protection typically installed at last padSurge protection typically installed at last pad--

    mounted transformer on each feeder string ofmounted transformer on each feeder string ofcollector circuitcollector circuit

    Considerations in application of surge arrestersConsiderations in application of surge arresters location of arresters, type of mountinglocation of arresters, type of mounting

    system groundingsystem grounding

    circuit lengthcircuit length

    transient analysis (EMTP) may be requiredtransient analysis (EMTP) may be required

  • 8/7/2019 Collector System Design

    9/17

    9

    System Protection Considerations forSystem Protection Considerations for

    Collector SystemsCollector Systems Considerations for protection of collector systemsConsiderations for protection of collector systems

    long circuit lengths may not allow for easy detection oflong circuit lengths may not allow for easy detection ofground faultsground faults system grounding (grounded vs. ungrounded)system grounding (grounded vs. ungrounded) selective coordination of collector system circuitsselective coordination of collector system circuits selective coordination with upstream padselective coordination with upstream pad--mountedmounted

    transformers at WTGtransformers at WTG temporary overvoltages caused by ground faultstemporary overvoltages caused by ground faults

    loss of phase during fault with single phase tripping andloss of phase during fault with single phase tripping andreclosingreclosing on transmission system or downed conductoron transmission system or downed conductor WTG may feed faults for several cyclesWTG may feed faults for several cycles

  • 8/7/2019 Collector System Design

    10/17

    10

    Collection SwitchgearCollection Switchgear

    Underground distributionUnderground distribution

    switchgearswitchgear MetalMetal--enclosed switchgearenclosed switchgear

    Circuit breakersCircuit breakers

  • 8/7/2019 Collector System Design

    11/17

    11

    Reactive Power CompensationReactive Power Compensation

    Reactive powerReactive power

    compensation systems forcompensation systems formeeting interconnectmeeting interconnectrequirements (FERC 661requirements (FERC 661--A)A)for power factor and LVRT:for power factor and LVRT:

    powerpower--electronicallyelectronicallyswitched capacitorsswitched capacitors

    distributed staticdistributed static

    compensatorscompensators mechanicallymechanically--switchedswitched

    capacitorscapacitors

  • 8/7/2019 Collector System Design

    12/17

    12

    Other ConsiderationsOther Considerations

    FerroresonanceFerroresonance

    can occur in collector system circuits with ungrounded wyecan occur in collector system circuits with ungrounded wyeor delta primary transformer connections because of:or delta primary transformer connections because of:

    single pole switching or reclosingsingle pole switching or reclosing

    single phasing during faulted conditionssingle phasing during faulted conditions

    preventing ferroresonance on collector systemspreventing ferroresonance on collector systems

    provide grounding transformersprovide grounding transformers size of grounding transformers > 5% of feeder loadsize of grounding transformers > 5% of feeder load

  • 8/7/2019 Collector System Design

    13/17

    13

    Other ConsiderationsOther Considerations

    Fault locatingFault locating

    long circuit lengths can make locating and isolation oflong circuit lengths can make locating and isolation offaults difficultfaults difficult

    provide sectionalizing points for circuits that do notprovide sectionalizing points for circuits that do not

    exceed capabilities of fault locating equipmentexceed capabilities of fault locating equipment

    include sectionalizing points for isolation and restorationinclude sectionalizing points for isolation and restoration

    Use directional fault indicators at WTG transformers toUse directional fault indicators at WTG transformers to

    provide for fault detection and isolationprovide for fault detection and isolation

  • 8/7/2019 Collector System Design

    14/17

    14

    Other ConsiderationsOther Considerations

    SCADA systemsSCADA systems

    typically installed as a part of the collector systemtypically installed as a part of the collector system design considerationsdesign considerations

    circuit lengthcircuit length number of turbines on a circuitnumber of turbines on a circuit

    communications protocolcommunications protocol

    fiber typefiber typesinglesingle--mode fibermode fiber

    multimulti

    --mode fibermode fiber

  • 8/7/2019 Collector System Design

    15/17

    15

    Analytical Studies for Collector SystemsAnalytical Studies for Collector Systems

    Analytical studies typically performed during theAnalytical studies typically performed during the

    design phase:design phase:

    cable ampacitycable ampacity

    system lossessystem losses voltage drop/regulationvoltage drop/regulation

    shortshort--circuit and coordinationcircuit and coordination

    transients and insulation coordination (EMTP)transients and insulation coordination (EMTP)

    harmonicsharmonics

  • 8/7/2019 Collector System Design

    16/17

    16

    SummarySummary

    Key considerations in collector system designKey considerations in collector system design

    system voltagesystem voltage insulation levelsinsulation levels

    cable ampacity parameterscable ampacity parameters

    load factor, installation method, bonding method,load factor, installation method, bonding method,thermal considerationsthermal considerations

    other factorsother factors

    surge protection, system protection, ferroresonance,surge protection, system protection, ferroresonance,SCADASCADA

    collection switchgear and compensation requirementscollection switchgear and compensation requirements

  • 8/7/2019 Collector System Design

    17/17

    17

    IEEE PES Support for Wind Farm CollectorIEEE PES Support for Wind Farm Collector

    System DesignSystem Design

    Recommended practices/standardsRecommended practices/standards

    Equipment application guidelinesEquipment application guidelines

    Development and validation of equipment modelsDevelopment and validation of equipment models

    TrainingTraining