![Page 1: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/1.jpg)
FY2018 BUSINESS PLAN 01
COMMERCIAL BUILDING DESIGN FOR COVID-19 & BEYONDJune 18th, 2020
Luke Leung, PE, P ENG, LEED Fellow
1
![Page 2: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/2.jpg)
ENVIRONMENT
SPACES
SYSTEMS
![Page 3: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/3.jpg)
ENVIRONMENT
SPACES
SYSTEMS
![Page 4: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/4.jpg)
ACCELERATORS TO OCCUPANCY
SKIDMORE, OWINGS & MERRILL LLP
OUTDOOR VS. INDOOR
Indoor transmission of SARS-CoV-2 Hua QIAN, Te MIAO2, Li LIU , Xiaohong ZHENG , Danting LUO , and Yuguo Li,
2 7322
![Page 5: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/5.jpg)
5
SOLAR IMPACTSARS-COV2 :
TOP: AIR90% reduction from 200 minutes to 4.5 minutes
BOTTOM: STAINLESS STEEL90% reduction in 7 minutes
![Page 6: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/6.jpg)
6https://projects.iq.harvard.edu/files/covid-pm/files/pm_and_covid_mortality.pdf
AIR QUALITY
“…increase of only 1 g/m3 in PM2.5 is associated with a 15% increase in the COVID-19 death rate..”
Harvard T.H. Chan School of Public Heath
![Page 7: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/7.jpg)
ENVIRONMENT
Indirect Health Effects of Relative Humidity Indoor EnvironmentArundel AV, Sterling EM et al.
Relative Humidity:• 40-60%
![Page 8: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/8.jpg)
ENVIRONMENT
Indirect Health Effects of Relative Humidity Indoor EnvironmentArundel AV, Sterling EM et al.
Relative Humidity:• 40-60%
viruses
Viruses
![Page 9: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/9.jpg)
ENVIRONMENT
![Page 10: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/10.jpg)
RESUSPEND - FLOOR
Detection of air and surface contamination by SARS-CoV-2 in hospital rooms of infected patientsPo Ying Chia, Kristen Kelli Coleman, for the Singapore 2019 Novel Coronavirus Outbreak Research Team
![Page 11: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/11.jpg)
https://www.pinterest.com/pin/368732288234236219/
CARPET VS. HARD FLOOR
Almost 20 Times More Material
![Page 12: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/12.jpg)
ENVIRONMENT
SPACES
SYSTEMS
![Page 13: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/13.jpg)
#
Epidemic plan from base building
BASE BUILDING CONSIDERATIONS
“Employees should wear a cloth face covering to cover their nose and mouth in all areas of the business.”COVID-19 Employer Information for Office Buildings
![Page 14: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/14.jpg)
LOBBY
1. Pressurized2. Sanitized3. Time - touchless
![Page 15: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/15.jpg)
![Page 16: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/16.jpg)
RESUSPEND - TOILET
Detection of air and surface contamination by SARS-CoV-2 in hospital rooms of infected patientsPo Ying Chia, Kristen Kelli Coleman, for the Singapore 2019 Novel Coronavirus Outbreak Research Team
![Page 17: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/17.jpg)
Occupancy Indicator
Occupancy Indicator
TOILET
1. Continuous exhaust2. Door hold open3. Consider occupants indicator
![Page 18: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/18.jpg)
18
WILL OUTBREAKS IMPACTOTHER FLOORS?
• Korean Call Center:o 97 of the 811 employees tested positiveo 94 sat on the same floor
https://wwwnc.cdc.gov/eid/article/26/8/20-1274_article
![Page 19: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/19.jpg)
ATRIUM
![Page 20: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/20.jpg)
ENVIRONMENT
SPACES
SYSTEMS
![Page 21: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/21.jpg)
![Page 22: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/22.jpg)
![Page 23: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/23.jpg)
DOAS – RADIANT
![Page 24: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/24.jpg)
DOAS – CHILLED BEAM
![Page 25: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/25.jpg)
25
DOAS - NIST
https://pages.nist.gov/CONTAM-apps/webapps/FaTIMA/
Integrated Exposure: 1.5E4 (#s/M3)
Exposure Concentration: 2.3E0 (#s/M3)
![Page 26: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/26.jpg)
DOAS – FAN COIL OR VRF
![Page 27: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/27.jpg)
![Page 28: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/28.jpg)
VAV
![Page 29: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/29.jpg)
2980
%
Fan
Fan
20%
20%
VAV SYSTEMMINIMUM OUTSIDE AIR
Time
VirusCount
Enhanced Filter
![Page 30: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/30.jpg)
MERV 8
MERV 13
BETTER FILTERMERV 8 - MERV 13
![Page 31: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/31.jpg)
MERV 8
MERV 13
BETTER FILTERMERV 8 - MERV 13
![Page 32: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/32.jpg)
32
MERV 8 VS MERV 13
https://pages.nist.gov/CONTAM-apps/webapps/FaTIMA/
Integrated Exposure: 8.0E3 (#s/M3)
Exposure Concentration: 1.6E0 (#s/M3)
Integrated Exposure: 4.8E3 (#s/M3)
Exposure Concentration: 1.1E0 (#s/M3)VAV with MERV 13
(Minimum OA)
VAV with MERV 8(Minimum OA)
![Page 33: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/33.jpg)
33
VAV SYSTEM100% OUTSIDE AIR
Fan
Fan
Filter and Coil
Shutoff Return
100%
100%
![Page 34: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/34.jpg)
34
MERV 8 VS 100% OUTSIDE AIR
https://pages.nist.gov/CONTAM-apps/webapps/FaTIMA/
Integrated Exposure: 8.0E3 (#s/M3)
Exposure Concentration: 1.6E0 (#s/M3)
Integrated Exposure: 4.5E3 (#s/M3)
Exposure Concentration: 1.0E0 (#s/M3)VAV with
100% Outside Air
VAV with MERV 8Minimum OA
![Page 35: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/35.jpg)
35https://pages.nist.gov/CONTAM-apps/webapps/FaTIMA/
Integrated Exposure: 8.0E3 (#s/M3)
Exposure Concentration: 1.6E0 (#s/M3)
Integrated Exposure: 4.5E3 (#s/M3)
Exposure Concentration: 1.0E0 (#s/M3)VAV with
100% Outside Air
VAV with MERV 8(Minimum OA)
Integrated Exposure: 4.8E3 (#s/M3)
Exposure Concentration: 1.1E0 (#s/M3)VAV with MERV 13
(Minimum OA)
VAV MINI VS 100% OA
![Page 36: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/36.jpg)
36
DOAS VS VAV
https://pages.nist.gov/CONTAM-apps/webapps/FaTIMA/
Integrated Exposure: 1.0E4 (#s/M3)
Exposure Concentration: 2.3E0 (#s/M3)
Integrated Exposure: 8.0E3 (#s/M3)
Exposure Concentration: 1.6E0 (#s/M3)
Integrated Exposure: 4.8E3 (#s/M3)
Exposure Concentration: 1.1E0 (#s/M3)
DOAS
VAV with MERV 13(Same OA as DOAS)
VAV with MERV 8(Same OA as DOAS)
![Page 37: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/37.jpg)
#
UVC LIGHTS
![Page 38: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/38.jpg)
EMERGING TECHNOLOGIES
• Emerging light spectrum technologies:o 315-400 nm UVa fixtureso 220 nm Far UVc lampso 405 nm visible spectrum lamps
• Pulsed Xenon (Pulsed UV)
• Bipolar Ionization/Corona Discharge
• Photocatalytic Oxidation (PCO)
http://2bize.com/uv%20spectrum.html
![Page 39: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/39.jpg)
HEALTH THREATS (UN WHO)3. Pandemic
![Page 40: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/40.jpg)
HEALTH THREATS (UN WHO)2. Chronic Diseases
![Page 41: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/41.jpg)
HEALTH THREATS (UN WHO)1. Climate Change
![Page 42: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/42.jpg)
FY2018 BUSINESS PLAN 01
COMMERCIAL BUILDING DESIGN FOR COVID-19 & BEYONDJune 18th, 2020
Luke Leung, PE, P ENG, LEED Fellow
42
![Page 43: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/43.jpg)
#
ELEVATORS
1. Prolong exposure – 15 minutes
http://www.elitecabs.com/index.php/cab-designs/elite-cab-design1205/freight-and-s?fID=65
![Page 44: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/44.jpg)
#
ELEVATORS
1. Prolong exposure – 15 minutes
2. Turn on elevator lift ventilation fan- 6’x6’x8’- 95% Elimination of material in the air: - 200 CFM ( 340 M3/Hr) = 4.3 minutes
http://www.elitecabs.com/index.php/cab-designs/elite-cab-design1205/freight-and-s?fID=65
Exhaust Fan
![Page 45: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,](https://reader035.vdocuments.net/reader035/viewer/2022070902/5f596663f02c412837109633/html5/thumbnails/45.jpg)
#
ELEVATORS
1. Prolong exposure – 15 minutes
2. Turn on elevator lift ventilation fan- 6’x6’x8’- 95% Elimination of material in the air: - 200 CFM ( 340 M3/Hr) = 4.3 minutes
3. Consider portable cleaner with HEPA filter
4. Open every doorhttp://www.elitecabs.com/index.php/cab-designs/elite-cab-design1205/freight-and-s?fID=65