Commissioning Geothermal Flash Plants
A Systematic Approach
Kevin Wallace, POWER Engineers, Inc.
![Page 2: Commissioning Geothermal Flash PlantsPre-Commissioning Checkouts •Mechanical Checks, Lubrication, Oil Filling •I&C Checks (Loop, Logic, Calibration) •Electrical Checks (Megger,](https://reader033.vdocuments.net/reader033/viewer/2022042213/5eb7f9ce4bf8925ec133522e/html5/thumbnails/2.jpg)
Kevin Wallace, P.E.Senior Project Manager
Renewables Director
• Nuclear & Geothermal
• Plant operations
• FEED, design, and startup/commissioning work
![Page 3: Commissioning Geothermal Flash PlantsPre-Commissioning Checkouts •Mechanical Checks, Lubrication, Oil Filling •I&C Checks (Loop, Logic, Calibration) •Electrical Checks (Megger,](https://reader033.vdocuments.net/reader033/viewer/2022042213/5eb7f9ce4bf8925ec133522e/html5/thumbnails/3.jpg)
Objectives of Commissioning
Schedule & Timing
Phases to Completion
Performance, Guarantees, Reliability
Q&A Session
![Page 4: Commissioning Geothermal Flash PlantsPre-Commissioning Checkouts •Mechanical Checks, Lubrication, Oil Filling •I&C Checks (Loop, Logic, Calibration) •Electrical Checks (Megger,](https://reader033.vdocuments.net/reader033/viewer/2022042213/5eb7f9ce4bf8925ec133522e/html5/thumbnails/4.jpg)
Systematic Handover of Plant to Owner’s Operating Staff
Demonstration of Operability and Performance Guarantees
Information Traceability for Equipment and Construction
![Page 5: Commissioning Geothermal Flash PlantsPre-Commissioning Checkouts •Mechanical Checks, Lubrication, Oil Filling •I&C Checks (Loop, Logic, Calibration) •Electrical Checks (Megger,](https://reader033.vdocuments.net/reader033/viewer/2022042213/5eb7f9ce4bf8925ec133522e/html5/thumbnails/5.jpg)
Design ConstructionCommissioning/
Startup
![Page 6: Commissioning Geothermal Flash PlantsPre-Commissioning Checkouts •Mechanical Checks, Lubrication, Oil Filling •I&C Checks (Loop, Logic, Calibration) •Electrical Checks (Megger,](https://reader033.vdocuments.net/reader033/viewer/2022042213/5eb7f9ce4bf8925ec133522e/html5/thumbnails/6.jpg)
Construction Completion
•Constructed Per Design
(All Disciplines)
•QA/QC Inspections/
Certifications
•Testing (e.g. hydro)
•Flushing & Steam Blow
Pre-Commissioning
Checkouts
•Mechanical Checks,
Lubrication, Oil Filling
•I&C Checks (Loop, Logic,
Calibration)
•Electrical Checks
(Megger, OEM, NETA)
•Control System
Commissioning &
Startup
•Testing Actual Startup,
Operating, & Shutdown
Procedures
•Verifying Protections
•Plant Tuning &
Optimization
•Performance Testing
![Page 7: Commissioning Geothermal Flash PlantsPre-Commissioning Checkouts •Mechanical Checks, Lubrication, Oil Filling •I&C Checks (Loop, Logic, Calibration) •Electrical Checks (Megger,](https://reader033.vdocuments.net/reader033/viewer/2022042213/5eb7f9ce4bf8925ec133522e/html5/thumbnails/7.jpg)
P&IDs, Lists, Specs, & Layout Drawings
![Page 8: Commissioning Geothermal Flash PlantsPre-Commissioning Checkouts •Mechanical Checks, Lubrication, Oil Filling •I&C Checks (Loop, Logic, Calibration) •Electrical Checks (Megger,](https://reader033.vdocuments.net/reader033/viewer/2022042213/5eb7f9ce4bf8925ec133522e/html5/thumbnails/8.jpg)
Thermal Cycling
Cleanliness (CFR)
Unique approaches in multi-flash plants
“Cleaning Force Ratio" = FSB/FDES ≥ 1.2
![Page 9: Commissioning Geothermal Flash PlantsPre-Commissioning Checkouts •Mechanical Checks, Lubrication, Oil Filling •I&C Checks (Loop, Logic, Calibration) •Electrical Checks (Megger,](https://reader033.vdocuments.net/reader033/viewer/2022042213/5eb7f9ce4bf8925ec133522e/html5/thumbnails/9.jpg)
System by System Checks◦ Safety, Support, then Process◦ Controls and System
Protections Verified
Wellfield◦ Pumps, CVs, Sampling
Separation Station ◦ Pumps, Vessels, Tanks, CVs,
Steam Vents, Sampling
![Page 10: Commissioning Geothermal Flash PlantsPre-Commissioning Checkouts •Mechanical Checks, Lubrication, Oil Filling •I&C Checks (Loop, Logic, Calibration) •Electrical Checks (Megger,](https://reader033.vdocuments.net/reader033/viewer/2022042213/5eb7f9ce4bf8925ec133522e/html5/thumbnails/10.jpg)
Main Plant◦ Startup, Operating, and
Shutdown Procedures
◦ Tuning and Optimization
CV Calibration and Adjustment of Set Points
Match Final Design Conditions
◦ Operator Training and Final Documentation (Manuals)
![Page 11: Commissioning Geothermal Flash PlantsPre-Commissioning Checkouts •Mechanical Checks, Lubrication, Oil Filling •I&C Checks (Loop, Logic, Calibration) •Electrical Checks (Megger,](https://reader033.vdocuments.net/reader033/viewer/2022042213/5eb7f9ce4bf8925ec133522e/html5/thumbnails/11.jpg)
Agreed Protocol and Data Collection
Test Conditions vs. Design Conditions
Correction Curves
Reliability Run and Warranty Period
![Page 12: Commissioning Geothermal Flash PlantsPre-Commissioning Checkouts •Mechanical Checks, Lubrication, Oil Filling •I&C Checks (Loop, Logic, Calibration) •Electrical Checks (Megger,](https://reader033.vdocuments.net/reader033/viewer/2022042213/5eb7f9ce4bf8925ec133522e/html5/thumbnails/12.jpg)
Q&A Session Share Experiences