Common Vendor Master File Project. Shared Services SA Presented by David Sharpe, Project Manager, Reform. What Are We Doing?. Single Masterpiece Enterprise Common Vendor Master File Standard data format conventions Data consolidation and cleansing SDK Wizard Front End. Scope. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Common Vendor Master File Project

GovernmentServicesGroup

Common Vendor Master File Project

Shared Services SA

Presented by David Sharpe, Project Manager, Reform

Friday, 21 April 2023

Page 2: Common Vendor Master File Project

GovernmentServicesGroup What Are We Doing?

• Single Masterpiece Enterprise

• Common Vendor Master File

– Standard data format conventions

– Data consolidation and cleansing

• SDK Wizard Front End

2

Page 3: Common Vendor Master File Project

GovernmentServicesGroup Scope

• Shared Services SA Accounts Payable Clients

• SYS1 & SYSH Masterpiece Environments

• Vendor maintenance activity

• Excludes:

– Non-Shared Services SA client agencies

– Unix environments

– DoHA

3

Page 4: Common Vendor Master File Project

GovernmentServicesGroup Current State

• Each agency in separate Masterpiece enterprise

• Separate vendor files across in-scope agencies

• Over 50% duplication in records with valid ABNs

• High maintenance effort

• No data format conventions

• Inconsistent field usage

• 23 separate extracts into Basware

4

Page 5: Common Vendor Master File Project

GovernmentServicesGroup Business Requirements

• Streamlined data entry

• Electronic storage of supporting documentation

• Pre-existing vendor check

• Require completion of required fields

• Data validation (e.g. ABN, suburb, post code)

• Common format

• Allow government-mandated categorisation

• Automated vendor maintenance audit reporting

• Allow multiple trading names per legal entity5

Page 6: Common Vendor Master File Project

GovernmentServicesGroup Existing Masterpiece Enterprise

6

Page 7: Common Vendor Master File Project

GovernmentServicesGroup Future Single Masterpiece Enterprise

7

Page 8: Common Vendor Master File Project

GovernmentServicesGroup Single Masterpiece Enterprise

• Benefits of future state:

– Provides infrastructure for common vendor master file

– Streamlines Machinery of Government process

– Lays foundation for:

• Further standardisation of parameters and processes

• Common customer master file

• Standardised or common chart of accounts

• Whole of Government consolidated reporting

• Streamlined Hyperion process

8

Page 9: Common Vendor Master File Project

GovernmentServicesGroup Common Vendor Master File – Future State

• One consolidated master file (for SYSH and SYS1)

– Including cleansed data

– Maintained by Shared Services SA

– Agencies have read-only access

• Standard data format

• Consistent Masterpiece field usage

9

Page 10: Common Vendor Master File Project

GovernmentServicesGroup Common Vendor Master File

• Benefits:

– Reduced vendor maintenance effort

– Increased accuracy and completeness of vendor data

– Increased data integrity

– Reduced risk of duplicate payments

– Streamlined links to Basware

– Provides for future consolidation and standardisation of financial systems across government

– Lays foundation for further improvement initiatives e.g. automation of payment run process for in-scope agencies

10

Page 11: Common Vendor Master File Project

GovernmentServicesGroup AP Vendor Maintenance Wizard

• SDK Wizard is Windows-based

• Replaces navigating through multiple ‘green screen’ panels

• Real-time data validation

• Increases data consistency through rules-driven standardised data capture

• Reduces duplication of effort

• No direct impact on agencies

11

Page 12: Common Vendor Master File Project

GovernmentServicesGroup Timeline

• Business case completed Aug 2012

• Approved by Program Governance Board Sept 2012

• Estimated 14 month project duration

• Implementation planning commenced Nov 2012

• Milestones

– Design

– Data Cleansing

– Implementation

12

Page 13: Common Vendor Master File Project

GovernmentServicesGroup Considerations

• Sector reporting

– Incorporated into standard vendor master file format

• Feeder systems

– Adjustments to cater for new vendor file format and naming conventions

– Data mapping

• Agency-specific vendor reporting

• Historical data

– Access to and storage of vendor payment history

13

Page 14: Common Vendor Master File Project

GovernmentServicesGroup Discussion

• Questions?

14