commonwealth of virginia · 2017-08-08 · commonwealth of virginia department of environmental...
TRANSCRIPT
Molly Joseph WardSecretary of Natural Resources
COMMONWEALTH of VIRGINIADEPARTMENT OF ENVIRONMENTAL QUALITY
Street address: 629 East Main Street, Richmond, Virginia 23219Mailing address: P.O. Box 1105, Richmond, Virginia 23218
www.deq.virginia.govDavid K. Paylor
Director
(804)698-40001-800-592-5482
November 29, 2016
Mr. Chris Swanson, State MS4/SWM EngineerVirginia Department of Transportation (VDOT)1401 East Broad Street
Richmond, Virginia 23219
RE: Virginia Dept. of Transportation (VDOT), Permit #VAR0401 15MS4 Annual Report review
Dear Mr. Swanson:
Your annual report, received on October 1, 2016, has been reviewed for completeness andaccuracy, and is hereby accepted as complete. Thank you for your submittal and for your effortsin implementing the VDOT MS4 program. If you have any questions regarding this letter pleasecontact me at (804) 698-4023, or by e-mail at mason. harper(%deq. Virginia, gov . DEQ looksforward to working with you as you continue to develop and refine your MS4 Program.
Sincerely,
\ / (/^CL^l^^;
J. Mason HarperMS4 Compliance Coordinator
File
``
MS4 YEAR THREE ANNUAL REPORT
JULY 1, 2015 TO JUNE 30, 2016
FOR
URBANIZED AREAS OF VIRGINIA
Virginia Department of Transportation Small
Municipal Separate Storm Sewer System (MS4)
Registration # VAR040115
Coverage from November 1, 2013 to June 30, 2018
OCTOBER 1, 2016
FINAL
Virginia Department of Transportation
Location and Design Division
1401 East Broad Street
Richmond, Virginia 23219
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 2
TABLE OF CONTENTS
VDOT MS4 PROGRAM PLAN BACKGROUND ........................................................................................................1
VDOT RESPONSBILITIES ........................................................................................................................................2
MCM #1: PUBLIC EDUCATION AND OUTREACH ON STORMWATER IMPACTS.....................................................3
BMP 1(A)1 – Public Education and Outreach Plan ...........................................................................................4
BMP 1(A)2 – Public Education and Outreach Plan ...........................................................................................5
BMP 1(A)3 – Public Education and Outreach Plan ...........................................................................................6
BMP 1(A)4 – Public Education and Outreach Plan ...........................................................................................7
MCM #2: PUBLIC INVOLVEMENT/PARTICIPATION ...............................................................................................8
BMP 2(A) – Availability of MS4 Program Plan and Annual Reports .................................................................9
BMP 2(B)1 – Participation with Other Stakeholders......................................................................................10
BMP 2(B)2 – Participation with Other Stakeholders......................................................................................11
BMP 2(B)3 – Participation with Other Stakeholders......................................................................................12
BMP 2(B)4 – Participation with Other Stakeholders......................................................................................13
BMP 2(C) – Public Comment and Consideration............................................................................................14
MCM #3: ILLICIT DISCHARGE DETECTION AND ELIMINATION............................................................................15
BMP 3(A) – Storm Sewer Map .......................................................................................................................16
BMP 3(B) – Interconnection Notification.......................................................................................................17
BMP 3(C)1 - Prohibition of Non-Stormwater Discharge ................................................................................18
BMP 3(C)2 - Prohibition of Non-Stormwater Discharge ................................................................................19
BMP 3(C)3 – Prohibition of Non-Stormwater Discharge................................................................................20
BMP 3(D)1 – Illicit Discharge Detection and Elimination Program ................................................................21
BMP 3(D)2 – Illicit Discharge Detection and Elimination Program ................................................................22
MCM #4: CONSTRUCTION SITE STORMWATER RUNOFF CONTROL...................................................................24
BMP 4(A) – Applicable Oversight ...................................................................................................................25
BMP 4(B) – Require Contractors to Prepare SWPPP......................................................................................26
BMP 4(C)1 – SWPPP Implementation, Compliance, and Enforcement..........................................................27
BMP 4(C)2 – SWPPP Implementation, Compliance, and Enforcement..........................................................28
MCM #5: POST-CONSTRUCTION STORMWATER MANAGEMENT ......................................................................29
BMP 5(A) – Applicable Oversight Requirements............................................................................................30
BMP 5(B) – SWM Plan Preparation and Implementation ..............................................................................31
BMP 5(C) – Long-Term Care and Maintenance of SWM Facilities .................................................................32
MCM #6: POLLUTION PREVENTION/GOOD HOUSEKEEPING FOR VDOT OPERATIONS......................................33
BMP 6(A)1 – Procedures for Operation and Maintenance Activities.............................................................34
BMP 6(A)2 – Procedures for Operation and Maintenance Activities.............................................................35
BMP 6(B) – Pollution Prevention at Maintenance Facilities ..........................................................................36
BMP 6(C) – Turf and Landscape Management...............................................................................................37
BMP 6(D)1 – Training of VDOT Forces ...........................................................................................................38
BMP 6(D)2 – Training of VDOT Forces ...........................................................................................................39
BMP 6(D)3 – Training of VDOT Forces ...........................................................................................................40
BMP 6(D)4 – Training of VDOT Forces ...........................................................................................................41
BMP 6(E) – Oversight of VDOT Maintenance Contractors .............................................................................42
SPECIAL CONDITIONS FOR APPROVED TMDLS...................................................................................................43
BMP 7(A) – Action Plans for Approved Local TMDLs .....................................................................................44
BMP 7(B) – Action Plan for Chesapeake Bay Watershed TMDL.....................................................................45
PROGRAM EVALUATION, MODIFICATION, AND REPORTING.............................................................................46
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 3
APPENDICES
Appendix A TMDL and IP Meetings during the Reporting Year
Appendix B New Stormwater Management Facilities Brought Online During the Reporting Year
Appendix C BMP Inventory and Inspections Performed during the Reporting Year
Appendix D VDOT Employee Training Summary
Appendix E Local TMDL Action Plans
Appendix F Chesapeake Bay TMDL Action – FY16 Progress and FY17 Schedule
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 4
ACRONYMS
AASHTO American Association of State Highway and Transportation Officials
BMP Best Management Practice
CGP Construction General Permit
CRCIF Construction Runoff Control Inspection Form
CWA Clean Water Act
DCR Virginia Department of Conservation and Recreation
DEQ Virginia Department of Environmental Quality
DOD Department of Defense
EPA Environmental Protection Agency
ERAC Environmental Research Advisory Committee
ESC Erosion and Sediment Control
ESCCC Erosion and Sediment Control Contractor Certification
HUC Hydrologic Unit Code
IDDE Illicit Discharge Detection and Elimination
IP Implementation Plan
L&D Location & Design
LDA Land-Disturbing Activity
LUP Land Use Permit
MCM Minimum Control Measure
MEP Maximum Extent Practicable
MS4 Municipal Separate Storm Sewer System
NMP Nutrient Management Plan
O&M Operations & Maintenance
ORI Outfall Reconnaissance and Inventory
P2 Pollution Prevention
POD Point of Discharge
PSA Public Service Announcement
RLD Responsible Land Disturber
RLDA Regulated Land Disturbance Activity
SWM Stormwater Management
SWPPP Stormwater Pollution Prevention Plan
TMDL Total Maximum Daily Load
TRB Transportation Research Board
VAC Virginia Administrative Code
VDOT Virginia Department of Transportation
VESCLR Virginia Erosion and Sediment Control Law and Regulations
VSMP Virginia Stormwater Management Program
VPDES Virginia Pollutant Discharge Elimination System
WIP Watershed Implementation Plan
WLA Wasteload Allocation
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 1
VDOT MS4 PROGRAM PLAN BACKGROUND
The Virginia Department of Transportation (VDOT) is authorized to discharge stormwater from its
municipal separate storm sewer system (MS4) by coverage under the Virginia Pollutant Discharge
Elimination System (VPDES) General Permit for Discharge of Stormwater from Small MS4s (the
Permit) within the urbanized areas of Virginia. As part of the original permit authorization, VDOT
developed and implemented an MS4 Program Plan (the Plan) with best management practices
(BMPs) to address the six minimum control measures (MCMs) and the special conditions for
applicable total maximum daily loads (TMDLs) outlined in the Permit.
As part of VDOT’s coverage under the 2013 Permit, VDOT has updated this MS4 Program Plan to
address new permit requirements as well as enhance BMPs through the adaptive management
process. Implementation of these BMPs is consistent with the provisions of an iterative MS4
Program, which constitutes compliance with the standard of reducing pollutants to the "maximum
extent practicable” or MEP.
BMPs that are included in this Plan follow a prescribed alpha-numeric nomenclature that is based
from the respective MCMs, the numbers of BMPs for each MCM, and the responsible Division. For
example, BMP 6(D)4 refers to the following:
BMP 6 MCM 6: Pollution Prevention and Housekeeping
(D) The fourth BMP to address the requirements of MCM 6
4 The fourth VDOT Division to be assigned responsibility under the BMP
Note: BMPs associated with the special conditions for approved TMDLs are assigned a BMP of “7”.
The area regulated by the MS4 Permit (herein referred to as the regulated area) covers areas
discharging to an MS4 that is owned and/or operated by VDOT and located within one of the
urbanized areas of Virginia. Urbanized areas as identified by the 2000 and 2010 Decennial Census
are listed below.
Blacksburg Richmond
Bristol Roanoke
Charlottesville Virginia Beach
Danville Washington, DC
Fredericksburg Winchester
Harrisonburg Staunton-Waynesboro
Kingsport Williamsburg
Lynchburg
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 2
VDOT RESPONSBILITIES
The Virginia Department of Transportation, under the leadership of the VDOT Commissioner, is
organized into several divisions within the Central Office, each serving under a designated Program
Chief. The nine VDOT Construction Districts are each managed by a District Administrator who
operates under the direct authority of the Chief Engineer. In general, VDOT employs a
decentralized implementation strategy; overall program policy and guidance is provided by the
appropriate Program Chiefs, while the day to day operation and implementation of VDOT's road
construction and maintenance programs fall under the authority of the District Administrators.
Division Responsibilities
General oversight of the MS4 Program is assigned to the Location & Design (L&D) Division. The
Stormwater Policy Committee Chairman and MS4 Steering Committee Chairman are represented by
L&D staff. However, individual VDOT Central Office Divisions are responsible for the continued
development and/or implementation of specific BMPs identified in this MS4 Program Plan as
follows:
Lead Division Associated BMPs
Construction 4(C)1, 6(D)3
Environmental 2(B)1, 3(C)2, 3(D)2, 6(A)2, 6(B), 6(D)1, 7(A), 7(B)
Learning Center 6(D)4
Location & Design 2(B)2, 3(B), 4(A), 4(B), 4(C)2, 5(A), 5(B)
Maintenance 1(A)2, 2(B)3, 3(A), 3(C)1, 3(D)1, 5(C), 6(A)1, 6(C), 6(D)2, 6(E)
Communications 1(A)1, 2(A), 2(B)4, 2(C)
Traffic Engineering 1(A)4
Land Use Office 1(A)3, 3(C)3
District Responsibilities
Each District will generally be responsible for program implementation within the specific Urbanized
Areas. VDOT Central Office staff will provide ongoing support to the Districts, and will also develop
the required annual reports with data provided by the Districts.
Stormwater Policy Committee Responsibilities
The Stormwater Policy Committee generally meets on an annual basis to discuss the status of
Program Implementation and address other administration concerns. The Policy Committee is
largely comprised of Division and District Administrators.
MS4 Steering Committee Responsibilities
The MS4 Steering Committee generally meets on a quarterly basis to discuss and develop program-
wide policies and procedures, including implementation, reporting, and assessment tools.
Responsibilities of Sub-Committees
The Stormwater Policy Committee and/or MS4 Steering Committee may establish other standing or
special committees, as they deem advisable, to address specific elements or components of the
MS4 Program Plan.
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 3
MCM #1: PUBLIC EDUCATION AND OUTREACH ON STORMWATER IMPACTS
The following BMPs have been selected to address MCM#1:
BMP 1(A)1 through 1(A)4 – Public Education and Outreach Plan
VDOT has a formal Public Education and Outreach Plan that identifies three high-priority water quality issues
including 1) Chesapeake Bay POCs 2) local bacteria TMDLs and 3) maintenance activities at VDOT facilities
and within its right-of-way.
For purposes of the MS4 Program, the terms “target audience” and “public” are used synonymously. VDOT
has defined the public/target audience as the population that has the most likely potential to have significant
impacts on stormwater runoff. This will allow VDOT to focus vital resources where they will generate the
most benefit. Note: the MS4 Permit does not define the term “public”. However, VDOT concurs with EPA
and DEQ’s statement “…that the minimum measures are flexible enough that they can be implemented by
[non-traditional MS4s].” Using similar language that EPA provided for Department of Defense (DOD)
facilities, VDOT defines its public as its employees, its contractors, and travelers using VDOT’s fixed facilities
such as welcome centers, rest areas and other properties owned/operated by VDOT.
VDOT does not consider travelers along the roadway system as part of the “public” for use in this Education
Plan as their activities do not likely have the most significant impact to water quality. However, VDOT has
developed education material that may incidentally reach these travelers, which could have a positive
benefit outside of VDOT’s right-of-way. For example, VDOT has developed an external stormwater webpage,
installed watershed signs along primaries and interstates throughout the Commonwealth, installed pet waste
stations at all rest areas, and implemented a storm drain stenciling program. Given these education
materials are spatially static, VDOT believes the material is 100% accessible to all individuals that visit the
VDOT website, utilize the VDOT rest areas, travel the roadways where watershed signs are located or
participate in a storm drain stenciling program.
The population for VDOT’s targeted audience for the 2015/2016 reporting year was approximately 1,300
individuals, which is reported in BMP 6D(1) through 6D(4). VDOT estimates 100% of the people in the
targeted audience for training was reached.
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 4
BMP 1(A)1 – Public Education and Outreach Plan
Description and
Measurable Goal:
Continue to implement the Public Education and Outreach Plan to increase
knowledge about high priority water quality issues.
Lead Division: Communications
(for division specific elements of Public Education and Outreach Plan)
Reference Documents: Public Education and Outreach Plan*
VDOT Stormwater Webpage
Stormwater Fact Sheet
Efforts and Expected
Results in Meeting
Measurable Goal
Implementation
ScheduleAnnual Report Information
Continue to maintain
VDOT Stormwater
Webpage, in accordance
with Education Plan.
Webpage was
previously developed.
VDOT will update
webpage with necessary
information as discussed
in others parts of this
Program Plan.
VDOT has maintained its stormwater webpage
with educational information including copies of
the MS4 Program Plan and copies of the annual
reports. VDOT will continue to maintain the
website throughout the next permit year.
(http://www.virginiadot.org//stormwater)
VDOT is in the process of updating the look and
content of its stormwater webpage. The updated
webpage will include contact information, program
announcements, program documents, and other
useful resources. The updated webpage is
expected to go live in the Fall of 2016.
Develop Fact Sheet, in
accordance with Education
Plan.
The fact sheet (trifold
brochure) is complete
and is going into
production. Additional
education material is
under development for
the next permit year.
Upon further evaluation of VDOT’s Public
Education and Outreach efforts, VDOT has
developed several education materials in addition
to the fact sheet (trifold brochure). VDOT is
currently developing a litter sign to be installed at
several rest areas and a pull-up display to be used
at conferences. These additional materials are
expected to be implemented during the next
permit year.
Present stormwater
messages via posters/
signage and Electronic
Bulletin Boards at VDOT at
VDOT facilities, in
accordance with Education
Plan.
The IDDE video has been
uploaded to the EBB.
The litter signs are
expected to be installed
during the next permit
year.
VDOT has developed and uploaded an illicit
discharge detection and elimination (IDDE) video
to our Electronic Bulletin Boards that are accessible
at VDOT facilities throughout the Commonwealth.
VDOT is in the process of printing the litter signs
that are to be installed in several areas throughout
the Commonwealth.
Notes: * A copy of The VDOT MS4 Public Education and Outreach Plan is available at Location & Design
Division’s Central Office location.
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 5
BMP 1(A)2 – Public Education and Outreach Plan
Description and
Measurable Goal:
Continue to implement the Public Education and Outreach Program to
increase knowledge about high priority water quality issues.
Lead Division: Maintenance
(for division specific elements of Public Education and Outreach Plan)
Reference Documents: Public Education and Outreach Plan*
Template for Pet Waste Signage
Expected Efforts and
Results in Meeting
Measurable Goal
Implementation
ScheduleAnnual Report Information
Continue to install and
maintain Pet Waste
Signage at rest areas and
welcome centers within
urbanized areas, in
accordance with the
Education Plan.
Message sign was
previously developed,
and reported to DEQ.
VDOT will continue to
identify fixed facilities
where signs can be
installed.
The pet waste stations maintenance and restocking
is part of VDOT’s Monthly Quality Assessment
Review/Safety Rest Area Inspection. This
inspection reviews the Pet Stations for
functionality and to assure they are being
maintained and stocked. The pet waste stations
are stocked with disposal bags as part of the
normal maintenance operation. As part of the
daily good housekeeping procedures for trash and
debris removal, any pet waste discovered is picked
up and placed in the appropriate trash receptacle.
The number of pet stations remains the same as
previously reported. No new Safety Rest Areas
were established and no major rebuilds were
completed this last year. During the last year
deteriorated or damaged pet stations were
replaced as needed.
Note: * A copy of The VDOT MS4 Public Education and Outreach Plan is available at Location & Design
Division’s Central Office location.
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 6
BMP 1(A)3 – Public Education and Outreach Plan
Description and
Measurable Goal:
Continue to implement the public education and outreach program to increase
knowledge about high priority water quality issues.
Lead Division: Land Use Office (formerly part of Transportation Planning)
(for division specific elements of Public Education and Outreach Plan)
Reference Documents: Public Education and Outreach Plan*
System to Track Land Use Permits
VDOT’s Stormwater Webpage**
Expected Efforts and
Results in Meeting
Measurable Goal
Implementation
ScheduleAnnual Report Information
Continue to promote
Storm Drain Stenciling, in
accordance with the
Public Education and
Outreach Plan.
Annually promote storm
drain stenciling through
use of VDOT’s
stormwater webpage.
VDOT did not issue any storm drain stenciling
permits in the urbanized areas.
While no permits were issued, VDOT has
determined this BMP is still appropriate to the
program. During the updates to the stormwater
webpage, VDOT will include a link to the Land Use
Permit program should individuals desire additional
information.
Notes: * A copy of The VDOT MS4 Public Education and Outreach Plan is available at Location & Design
Division’s Central Office location.
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 7
BMP 1(A)4 – Public Education and Outreach Plan
Description and
Measurable Goal:
Continue to implement the public education and outreach program to increase
knowledge about high priority water quality issues.
Lead Division: Traffic Engineering
(for division specific elements of Public Education and Outreach Plan)
Reference Documents: Public Education and Outreach Plan*
Watershed Signs
Expected Efforts and
Results in Meeting
Measurable Goal
Implementation
ScheduleAnnual Report Information
Continue to participate in
Watershed Sign
Installation Program, in
accordance with
Education Plan.
Number of signs
installed will be in
accordance with the
Public Education and
Outreach Plan.
VDOT has continued to implement the Chesapeake
Bay Watershed sign plan that was originally
developed in coordination with DCR. During the
reporting year, VDOT installed 2 signs:
One sign was a reinstallation of a fallen sign
for Smith Mountain Lake Roanoke River
(Watershed 2008) (located on Rt. 122 on
the line between Franklin and Bedford
County).
One sign was a new installation for Cedar
Creek (only one direction was completed in
FY16, second sign to be installed in FY17 –
both on I-81 in Warren County)
To date, VDOT has installed 81 watershed signs as
part of this effort.
For FY16, VDOT expects to install the second sign
for the Cedar Creek location and install a pair of
signs for Christians Creek on I-64 in Augusta County.
Note: * A copy of The VDOT MS4 Public Education and Outreach Plan is available at Location & Design
Division’s Central Office location.
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 8
MCM #2: PUBLIC INVOLVEMENT/PARTICIPATION
The following BMPs have been selected to address MCM#2:
BMP 2(A) – Availability of MS4 Program Plan and Annual Reports
BMP 2(B)1 through 2(B)4 – Participation with Other Stakeholders
BMP 2(C) – Public Comment and Consideration
Note: VDOT traditionally participates in numerous stakeholder meetings and events that exceed the
annual minimum of four events. VDOT believes there is value to the meetings and will continue to
participate in these events as they are consistent with VDOT’s environmental goals and objectives.
Furthermore, VDOT will continue to report any events it attends that have a stormwater/water
quality aspect. However, for purposes of this MCM, VDOT considers four annual activities amongst
BMPs 2(B)1 through 2(B)3 to meet the Permit requirement, and additional participation does not
set a precedent for future activities or result in a Program modification. The number of events will
vary from year to year based on availability.
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 9
BMP 2(A) – Availability of MS4 Program Plan and Annual Reports
Description and
Measurable Goal:
Make MS4 Program Plan and Annual Reports available to comply with
applicable federal, state, and local public notice requirements.
Lead Division: Communications
Reference Documents: VDOT Stormwater Webpage
Expected Efforts and
Results in Meeting
Measurable Goal
Implementation
Schedule
Annual Report Information
Continue to post Program
Plans and Annual
Reports.
The Program Plan will be
posted on the VDOT
webpage within 30 days
after submittal to DEQ.
Within 30 days of any
modification to the
Program Plan, the latest
version will be posted.
Annual reports will be
posted on the web page
within 30 days of
submittal to DEQ, or by
November 1st of each
year.
VDOT has continued to post its MS4 Program Plan
and annual reports on its stormwater webpage
located at:
(http://www.virginiadot.org//stormwater)
This annual report will be posted within 30 days of
final submittal to DEQ.
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 10
BMP 2(B)1 – Participation with Other Stakeholders
Description and
Measurable Goal:
Participate in stakeholder meetings and events, as applicable, to ensure that provisions
for linear development projects are incorporated into local watershed planning.
Lead Division: Environmental
(for topics related to Environmental’s responsibilities under the MS4 Program)
Reference Documents: Spreadsheet to track participation efforts
Expected Efforts and
Results in Meeting
Measurable Goal
Implementation
Schedule
Annual Report Information
Continue to participate
in meetings with
environmental
organizations.
Annually
participate in
meetings, when
applicable.
VDOT participated in the following meetings with environmental
organizations during the reporting year:
Meeting Name Date(s)
Watershed Resources Registry Introduction in VA 8/27/15
Coastal Policy Team meeting 9/29/15
2015 VA Water Monitoring Council Conference 11/19/15
Coastal Policy Team meeting 2/9/16
Choose Clean Water Coalition’s “Chesapeake Hill Day” 3/2/16
VLWA Spring Conference 3/14-15/16
Environment Virginia 4/5-7/16
VAWP 2016 Annual Spring Meeting 5/18/16
Continue to participate
in MS4 coordination
meetings with other
MS4 permittees to
discuss program efforts,
approved TMDLs and
associated Action Plans.
Annually meet
with various MS4s,
when applicable.
VDOT participated in the following coordination meetings with other
MS4s to discuss MS4 and infrastructure coordination:
Meeting Name Date(s)
James City County 9/11/15
Henrico County 9/21/15
Chesterfield County 11/9/15
Fairfax County 3/10/16
Prince William County Schools 5/11/16
Prince William County 5/27/16
Continue to participate
in TMDL and
Implementation Plan
(IP) development
meetings.
Annually
participate in
TMDL and IP
development
meetings, when
applicable.
VDOT participated in 35 TMDL and IP meetings during the reporting
year. A list of these meetings is provided in Appendix A.
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 11
BMP 2(B)2 – Participation with Other Stakeholders
Description and
Measurable Goal:
Participate in local activities aimed at increasing public awareness of water
quality and stormwater issues.
Lead Division: Location & Design
(for topics related to L&D’s responsibilities under the MS4 Program)
Reference Documents: Spreadsheet to track participation efforts
Expected Efforts and
Results in Meeting
Measurable Goal
Implementation
Schedule
Annual Report Information
Continue to
participate in
meetings with
environmental
organizations.
Annually
participate in
meetings, when
applicable.
VDOT participated in the following meetings with environmental
organizations during the reporting year:
Meeting Name Date(s)
HRPDC Monthly Meeting 3/3/16
Environment Virginia 4/5-7/16
VWEA Spring Conference 4/27/16
HRPDC IDDE Workshop 6/13/16
Continue to
participate in MS4
coordination
meetings with other
MS4 permittees to
discuss program
efforts and approved
TMDLs and
associated Action
Plans.
Annually meet
with various
MS4s, when
applicable.
VDOT participated in the following coordination meetings with other
MS4s to discuss MS4 and infrastructure coordination:
Meeting Name Date(s)
James City County 9/11/15
Henrico County 9/21/15
Chesterfield County 11/9/15
City of Hampton 3/7/16
Fairfax County 3/10/16
Prince William County Schools 5/11/16
Prince William County 5/27/16
HRPDC regional environmental meetings Quarterly
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 12
BMP 2(B)3 – Participation with Other Stakeholders
Description and
Measurable Goal:
Participate in local activities aimed at increasing public awareness of water
quality and stormwater issues.
Lead Division: Maintenance
(for topics related to Maintenance’s responsibilities under the MS4 Program)
Reference Documents: Spreadsheet to track participation efforts
Expected Efforts and
Results in Meeting
Measurable Goal
Implementation
Schedule
Annual Report Information
Continue to
participate in
meetings with
environmental
organizations.
Annually
participate in
meetings, when
applicable.
VDOT participated in the following meetings with environmental
organizations during the reporting year:
Meeting Name Date(s)
HRPDC Monthly Meeting 3/3/16
Environment Virginia 4/5-7/16
HRPDC IDDE Workshop 6/13/16
Continue to
participate in MS4
coordination
meetings with other
MS4 permittees to
discuss program
efforts and approved
TMDLs and
associated Action
Plans and outfall
inventory.
Annually meet
with various
MS4s, when
applicable.
VDOT participated in the following coordination meetings with other
MS4s to discuss MS4 and infrastructure coordination:
Meeting Name Date(s)
James City County 9/11/15
Henrico County 9/21/15
Chesterfield County 11/9/15
Fairfax County 3/10/16
Prince William County Schools 5/11/16
Prince William County 5/27/16
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 13
BMP 2(B)4 – Participation with Other Stakeholders
Description and
Measurable Goal:
Participate in local activities aimed at increasing public awareness of water
quality and stormwater issues.
Lead Division: Communications
(for topics related to Communication’s responsibilities under the MS4 Program)
Reference Documents: Spreadsheet to track participation efforts
Expected Efforts and
Results in Meeting
Measurable Goal
Implementation
Schedule
Annual Report Information
Continue to participate in
local activities annually.
Annually participate in
activities , when
applicable
While VDOT has historically provided an
informational booth at the Statewide ROADEO, the
MS4 Program did not have a booth during the
reporting year. However, the ROADEO remains an
appropriate BMP, and the MS4 Program intends to
participate in future ROADEOs.
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 14
BMP 2(C) – Public Comment and Consideration
Description and
Measurable Goal:
Provide opportunity for public to comment on VDOT’s MS4 Program and
associated efforts.
Lead Division: Communications
Reference Documents: VDOT Stormwater Webpage
Expected Efforts and
Results in Meeting
Measurable Goal
Implementation
Schedule
Annual Report Information
Continue to maintain the
stormwater webpage,
and an email address on
the webpage for the
public to provide
comment.
Annually maintain
webpage.
VDOT has continued to provide opportunity for the
public to submit comments regarding its MS4
Program through its stormwater webpage located
at:
(http://www.virginiadot.org//stormwater)
There were no comments submitted related to the
MS4 Program in this reporting year.
As part the draft
Chesapeake Bay TMDL
Action Plan development,
provide an opportunity
for receipt and
consideration of public
comment.
Prior to the finalization
of the Chesapeake Bay
TMDL Action Plan.
VDOT posted a copy of the draft Action Plan on its
stormwater webpage
(http://www.virginiadot.org//stormwater)
from September 15 through September 30, 2015.
VDOT received two comment letters and gave
those comments due consideration.
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 15
MCM #3: ILLICIT DISCHARGE DETECTION AND ELIMINATION
The following BMPs have been selected to address MCM#3:
BMP 3(A) – Storm Sewer Map
BMP 3(B) – Interconnection Notification
BMP 3(C)1 through 3(C)3 – Prohibition of Non-Stormwater Discharges
BMP 3(D)1 & 3(D)2 – Illicit Discharge Detection and Elimination Program
Note: VDOT has developed an Illicit Discharge Detection and Elimination (IDDE) Program to address
illicit discharges that originate within VDOT’s property and right-of-way as well those that originate
outside of VDOT’s right-of-way, but enter VDOT’s MS4. VDOT actively screens, investigates, and
eliminates illicit discharges that originate within its right-of-way to the MEP. VDOT actively screens
and investigates illicit discharges that enter its MS4 from an external source. However, VDOT does
not have direct control to eliminate these sources, as VDOT has limited enforcement authority
outside its right of way or property boundaries. As such, VDOT has actively worked with regulatory
agencies and other MS4s to report such discharges to the appropriate authority for investigation
and resolution.
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 16
BMP 3(A) – Storm Sewer Map
Description and
Measurable Goal:
Develop a storm sewer map and an information table that supports a successful
Illicit Discharge Detection and Elimination (IDDE) Program that includes
screening, investigation, and coordinating elimination of illicit discharges. The
map, at a minimum, will:
Include the mapped location of MS4 regulated outfalls with a unique
identifier that corresponds to the related data in the information table.
The information table, at a minimum, will include for each regulated outfall the:
Unique identifier;
Estimated VDOT MS4 acreage served;
The name and location of waters receiving discharges from VDOT’s MS4
regulated outfalls and the associated sixth order hydrologic unit code
(HUC) from Virginia's 6th Order National Watershed Boundary Dataset;
An indication as to whether the receiving water is listed as impaired on
the Virginia 2010 303(d)/305(b) list; and
Name of any applicable TMDL(s).
Lead Division: Maintenance
Reference Documents: Storm Sewer Map and Geodatabase
VDOT Outfall Reconnaissance & Inventory (ORI) Manual*
Expected Efforts
and Results in
Meeting
Measurable Goal
Implementation
Schedule
Annual Report Information
Complete storm
sewer system map
and information
table.
Annually
demonstrate
progress is being
made to complete
map by October 30,
2017.
VDOT inventoried 4,597 MS4 outfalls during the reporting
year.
VDOT has completed its initial collection of MS4 Outfalls and
Point of Discharges using tablet computers and a cloud based
GIS Online software. VDOT continues to populate the
required information table with an expected completion date
prior to October 30, 2017.
VDOT is reviewing its mapping program in order to
successfully transition into data maintenance to maintain the
accuracy and completeness of the map.
Continue to
identify other
points of
discharge (PODs)
when such points
are collected
during the outfall
inventory process.
Annually
demonstrate
progress is being
made to complete
map by October 30,
2017.
VDOT inventoried 650 points of discharges (POD’s) during the
reporting year.
Note: * A copy of the VDOT ORI Manual is available at Maintenance Division’s Central Office location.
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 17
BMP 3(B) – Interconnection Notification
Description and
Measurable Goal:
Increase awareness of interconnections with other MS4s
Lead Division: Location & Design
Reference Documents: Storm Sewer Map and Geodatabase
ORI Manual*
Notification Letters
Expected Efforts and
Results in Meeting
Measurable Goal
Implementation
Schedule
Annual Report Information
Continue to provide
interconnection
notification to
downstream MS4s as
appropriate.
Provide notifications, as
applicable.
VDOT has provided written notifications letters to
all permitted MS4s, which was reported in previous
annual report.
During any coordination meeting with another MS4,
VDOT offers to electronically share its outfall and
POD information.
Copies of the notifications letters are available at
Location & Design Division’s Central Office location.
Note: * A copy of the VDOT ORI Manual is available at Maintenance Division’s Central Office location.
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 18
BMP 3(C)1 - Prohibition of Non-Stormwater Discharge
Description and
Measurable Goal:
Prohibit non-stormwater discharges into the storm sewer system
Lead Division: Maintenance
Reference Documents: Maintenance Best Practices Manuals*
Expected Efforts and
Results in Meeting
Measurable Goal
Implementation
Schedule
Annual Report Information
Continue to develop and
refine appropriate
practices in the
Maintenance Best
Practices Manuals to
prohibit non-stormwater
discharges from VDOT
operations.
This aspect of the BMP is
currently implemented
and is an ongoing effort.
Maintenance Division staff continues to implement
this responsibility consistent with procedures
established in the VDOT Maintenance Best Practices
Manual.
Note: * A copy of the Maintenance Best Practices Manual is available at Maintenance Division’s Central
Office location.
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 19
BMP 3(C)2 - Prohibition of Non-Stormwater Discharge
Description and
Measurable Goal:
Prohibit non-stormwater discharges into the storm sewer system
Lead Division: Environmental
Reference Documents: Waste Management and Pollution Prevention Guides*
Expected Efforts and
Results in Meeting
Measurable Goal
Implementation
Schedule
Annual Report Information
Continue to develop and
refine appropriate
practices in the Waste
Management & Pollution
Prevention Guides to
prohibit non-stormwater
discharges from VDOT
operations.
This aspect of the BMP is
currently implemented
and is an ongoing effort.
The January 2015 Waste Management and Pollution
Prevention Guide remains the current version.
During the next reporting year, we anticipate
reviewing the existing guide to update various
sections and to incorporate a new guide, currently
being developed, for the proper use, maintenance,
and storage of portable toilets.
Note: * Copies of the Waste Management and Pollution Prevention Guides are available at Environmental
Division’s Central Office location.
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 20
BMP 3(C)3 – Prohibition of Non-Stormwater Discharge
Description and
Measurable Goal:
Prohibit non-stormwater discharges into the storm sewer system
Lead Division: Land Use Office (formerly part of Transportation Planning )
Reference Documents: Land Use Permit Regulations Guidance Manual*
Expected Efforts and
Results in Meeting
Measurable Goal
Implementation
Schedule
Annual Report Information
Continue to develop and
refine appropriate
practices in the Land Use
Permit (LUP) program,
which allows VDOT to
take action against a LUP
permittee if their
operations generate an
illicit discharge to VDOT’s
MS4.
This aspect of the BMP is
currently implemented
and is an ongoing effort
There were no suspect illicit discharges that were
reported through the Land Use Permits process
during the reporting year.
Note: * A copy of the Land Use Permit Regulations Guidance Manual is available at Transportation
Planning Division’s Central Office location.
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 21
BMP 3(D)1 – Illicit Discharge Detection and Elimination Program
Description and
Measurable Goal:
Utilize written procedures to detect, identify, and address unauthorized non-
stormwater discharges, including illegal dumping, to VDOT’s MS4.
Lead Division: Maintenance
Reference Documents: VDOT IDDE Manual*
IDDE Geodatabase
Storm Sewer Map
Expected Efforts
and Results in
Meeting
Measurable Goal
Implementation
Schedule
Annual Report Information
Continue to
perform initial
screenings of
regulated outfalls
that are
inventoried for the
first time.
This aspect of the
BMP is currently
implemented and is
an ongoing effort –
initial screenings will
be performed during
the outfall inventory
process.
VDOT screened 4,865 outfalls and 650 points of discharge
(POD’s) during the reporting year.
Annually perform
at least 50 outfall
screenings.
This aspect of the
BMP is currently
implemented and is
an ongoing annual
effort.
VDOT screened 4,865 outfalls and 650 points of discharge
(POD) during the reporting year.
Note: * A copy of the VDOT IDDE Manual is available at Maintenance Division’s Central Office location.
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 22
BMP 3(D)2 – Illicit Discharge Detection and Elimination Program
Description and
Measurable Goal:
Utilize written procedures to detect, identify, and address unauthorized non-
stormwater discharges, including illegal dumping, to VDOT’s MS4.
Lead Division: Environmental
Reference Documents: VDOT IDDE Manual*
IDDE Geodatabase
Storm Sewer Map
Expected Efforts
and Results in
Meeting
Measurable Goal
Implementation
Schedule
Annual Report Information
Continue to perform
follow-up
investigations for
potential illicit
discharges as
appropriate using
VDOT’s IDDE
Program and
Manual. Effort is to
be coordinated with
Maintenance
Division and other
VDOT Divisions, as
appropriate.
This aspect of the
BMP is currently
implemented and is
an ongoing effort –
follow-up
investigations will
be performed in
accordance with the
VDOT IDDE Manual.
Of the 4,865 outfalls screened, VDOT investigated 29 potential illicit
discharges that were reported through the characterization process.
Follow up investigation determined that there was no illicit discharge
present at 19 of the 29 reported discharges. The follow-up efforts related
to the 10 verified discharges are discussed below.
District Investigated Re-classified Verified
Bristol 0 0 0
Culpeper 0 0 0
Fredericksburg 0 0 0
Hampton Roads 2 2 0
Lynchburg 0 0 0
Northern Virginia 14 3 1
Richmond 11 0 9
Salem 0 0 0
Staunton 2 2 0
Summary of IDDE’s verified:
1) What appeared to be an ongoing sewage release from a hotel along
Jefferson Davis Highway was reported by Chesterfield County. Sewage
was being released through straight pipes on the southern side of the
property into a wetland area leading to a pond, which drained to a culvert
crossing under Jeff Davis Highway. In addition, effluent from a septic tank
was also being released onto the east side of the property facing Jeff
Davis Highway. The ditchline along Jeff Davis Highway also drained to the
culvert crossing under the highway. Chesterfield County notified
Chesterfield County Building Inspections, as well as the Department of
Health and Department of Environmental Quality. The property owner
was required to correct both of these issues; a subsequent follow-up
investigation indicated no further discharge was occurring and the IDDE
report was closed.
2) A property located adjacent to the I-64 westbound rest area in
Goochland County was observed to have a discharge of sewage
originating from their drainfield and entering the east side of the rest area
property. The issue was referred to the Goochland County Health
Department for enforcement, and the landowner was also given notice by
VDOT regarding the problem and requesting them to cease the discharge.
On a subsequent visit, it was determined that the discharge was no longer
occurring, and the problem had been corrected. The IDDE report was
closed.
3) The Department of Environmental Quality reported that approximately
40 gallons of liquid deer scent blocker was discharged from a facility
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 23
located along Meadowbridge Road in Mechanicsville, and had drained
into a drop inlet which drains into a ditch on VDOT right-of-way. The
Department of Environmental Quality required the facility to clean up this
discharge. No further problems have been reported and the IDDE report
has been closed.
4) Chesterfield County reported a gasoline spill along the intersection of
Jefferson Davis Highway and Walmsley Blvd. Approximately 5 gallons of
fuel were spilled in the incident, and it appeared that some of the fuel
had entered the drop inlet. The spill was cleaned up by an emergency
response contractor. There were no signs of fuel or sheen beyond the
impacted drop inlet. A follow up investigation indicated there were no
traces of the spill. The case has been closed.
5) Chesterfield County reported a septic discharge from a private
landowner entering a roadside ditch on West Road. The County Health
Department and DEQ were contacted regarding the discharge. No further
problems have been reported and the IDDE report has been closed.
6) Chesterfield County reported that an individual had been observed
dumping approximately a gallon of gasoline into a roadside ditch and
culvert alongside Spring Run Road. DEQ was notified regarding this
incident. The gasoline appeared not to have travelled more than 10 feet
north of the culvert; and did not enter Third Branch Creek, which is
located approximately 400 feet north of the culvert. No further problems
have been reported from this location, and the IDDE report was closed.
7) VDOT personnel reported a potential illicit discharge of debris along
Jefferson Davis Highway in Woodbridge. The discharge appeared to
originate from an auto scrapyard lot located along the west side of
Jefferson Davis Highway. The debris consisted of what appeared to be
broken pieces of asphalt, gravel and sediment which were draining into a
drop inlet north of the lot. DEQ was contacted regarding the discharge.
No further problems have been reported and the IDDE report was closed.
8) DEQ reported dumping of cleaning chemicals into a drop inlet that
drained into VDOT right-of-way. Employees of a hotel along West Broad
Street in Henrico County were improperly disposing of cleaning chemicals
by discharging them into a privately owned drop inlet which drained into
VDOT right-of-way. A follow up investigation indicated that the material
was not present in the downstream outfall. No further problems have
been reported and the IDDE report was closed.
9) Chesterfield County reported a sewage overflow from a sewer cleanout
on a homeowner’s property located along Oriole Avenue that was
draining into a roadside ditch. Chesterfield County required the property
owner to correct the problem. A follow up investigation indicated that
the sewage issue had been resolved, and the IDDE report was closed.
10) Chesterfield County reported food grease had been improperly
disposed of from a service station on Woodpecker Road and the
discharge had entered a ditch line on VDOT right-of-way. DEQ was also
contacted regarding this discharge, and required the service station to
clean up the grease spill. No further problems have been reported and
the IDDE report was closed.
Note: * A copy of the VDOT IDDE Manual is available at Maintenance Division’s Central Office location.
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 24
MCM #4: CONSTRUCTION SITE STORMWATER RUNOFF CONTROL
The following BMPs have been selected to address MCM#4:
BMP 4(A) – Applicable Oversight
BMP 4(B) – SWPPP Preparation
BMP 4(C)1 & 4(C)2 – SWPPP Implementation, Compliance, and Enforcement
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 25
BMP 4(A) – Applicable Oversight
Description and
Measurable Goal:
VDOT will utilize its annual ESC and SWM Standards & Specifications to address
discharges entering the MS4 from VDOT land-disturbing activities regulated by
the VPDES and VSMP.
Lead Division: Location & Design
Reference Documents: VDOT’s Annual ESC and SWM Standards & Specifications*
Database to track land-disturbing activities regulated under CGP
Expected Efforts and
Results in Meeting
Measurable Goal
Implementation
Schedule
Annual Report Information
Continue to obtain annual
approval of VDOT’s ESC
and SWM Standards &
Specifications from DEQ.
Update components of
the Standards &
Specifications as
regulations and
operations warrant.
VDOT has continued coordination with DEQ on
annual approval of ESC and SWM Standards &
Specifications. VDOT submitted its annual
standards and specification for FY17.
VDOT has made continual modifications, revisions,
and updates to VDOT Road and Bridge
Specifications, Copied Notes, Special Provisions, and
Standards to maintain compliance with applicable
regulatory and permit requirements.
Continue to track the
total number of land
disturbing activities
registered for
Construction General
Permit
Coverage.
This aspect of the BMP is
currently implemented
and is an ongoing annual
effort.
There were 38 RLDAs registered for construction
permit coverage from July 01, 2015 to June 30, 2016
with a total of 657.47 acres of land disturbance.
Note: * A copy of VDOT’s Annual ESC and SWM Standards & Specifications is available at Location & Design
Division’s Central Office location.
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 26
BMP 4(B) – Require Contractors to Prepare SWPPP
Description and
Measurable Goal:
Prepare and implement Stormwater Pollution Prevention Plans (SWPPPs)
including an ESC Plan and Pollution Prevention Plans for regulated land-
disturbing activities.
Lead Division: Location & Design
Reference Documents: VDOT’s Annual ESC and SWM Standards & Specifications, including:*
Plan design and review procedures and associated documents
Expected Efforts and
Results in Meeting
Measurable Goal
Implementation
ScheduleAnnual Report Information
Continue to require the
ESC plan to be developed
in accordance with
VDOT’s annual ESC
Standards &
Specifications prior to
commencing land
disturbing activities.
This aspect of the BMP is
currently implemented
and is an ongoing annual
effort.
All ESC Plans for RLDAs were developed in
accordance with VDOT’s annual ESC Standards &
Specifications.
Continue to require
applicable RLDA to secure
the necessary state
permit authorizations
from DEQ to discharge
stormwater from
construction sites.
This aspect of the BMP is
currently implemented
and is an ongoing annual
effort.
There were 38 RLDAs registered for construction
permit coverage from July 01, 2015 to June 30, 2016
with a total of 657.47 acres of land disturbance.
Note: * A copy of VDOT’s Annual ESC and SWM Standards & Specifications is available at Location & Design
Division’s Central Office location.
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 27
BMP 4(C)1 – SWPPP Implementation, Compliance, and Enforcement
Description and
Measurable Goal:
Inspect and enforce compliance with the VPDES
Construction General Permit and attending regulations on applicable projects.
Lead Division: Construction
Reference Documents: VDOT’s Annual ESC and SWM Standards & Specifications, including:*
Section 107.16(a) – Erosion and Siltation
Section 107.16(b) – Pollution
Section 107.16(e) – Storm Water Pollution Prevention Plan and VPDES
General Permit for the Discharge of Stormwater from Construction
Activities
C-107: Construction Runoff Control Inspection Form (CRCIF)
Expected Efforts and
Results in Meeting
Measurable Goal
Implementation
Schedule
Annual Report Information
Perform construction
inspections for
compliance with VESCLR,
CGP and Annual ESC and
SWM Standards &
Specifications.
This aspect of the BMP
is currently
implemented and is an
ongoing effort – VDOT
will inspect regulated
land-disturbing activities
in accordance with the
Annual ESC and SWM
Standards &
Specifications.
There were 38 RLDAs registered for construction
permit coverage from July 01, 2015 to June 30,
2016 with a total of 657.47 acres of land
disturbance..
The inspection schedule of every five business days
and within 48 hours after any measurable storm
event (or once every four business days) is applied
statewide regardless of whether or not an
Impaired, TMDL, or Exceptional water is present.
Given this schedule and the total number of
projects, VDOT estimates the total number of
inspections performed to be approximately 1,600
for the reporting year.
Require compliance with
SWPPP plans including
the ESC Plan, and require
changes/ modifications to
SWPPPs, as necessary, to
maintain compliance with
applicable regulations.
Also, utilize enforcement
authority if necessary.
This aspect of the BMP
is currently
implemented and is an
ongoing effort.
VDOT identified a project that had not acquired
permit coverage prior to commencement of land
disturbance. VDOT ordered work to cease until
permit coverage was obtained. This effort was
coordinated and communicated with DEQ’s
Central and Regional office.
Create a central
electronic database of
construction records for
VDOT projects
throughout Virginia.
Develop the database
within 3 years of permit
coverage,
The Construction Division is developing a new
project document management system (PDMS) to
log inspection information. Implementation of
new PDMS system is anticipated by the end of the
2016 calendar year.
Note: * A copy of VDOT’s Annual ESC and SWM Standards & Specifications is available at Location & Design
Division’s Central Office location.
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 28
BMP 4(C)2 – SWPPP Implementation, Compliance, and Enforcement
Description and
Measurable Goal:
Annually inspect a select number of projects for compliance with the VPDES
Construction General Permit requirements.
Lead Division: Location & Design Division
Reference Documents: VDOT’s Annual ESC and SWM Standards & Specifications, including:*
Section 107.16(a) – Erosion and Siltation
Section 107.16(b) – Pollution
Section 107.16(e) – Storm Water Pollution Prevention Plan and VPDES
General Permit for the Discharge of Stormwater from Construction
Activities
C-107: Construction Runoff Control Inspection Form (CRCIF)
Expected Efforts and
Results in Meeting
Measurable Goal
Implementation
Schedule
Annual Report Information
Continue to perform
third-party SWPPP QA
construction Inspections
for compliance with
VESCLR, CGP and Annual
ESC and SWM Standards
& Specifications
This aspect of the BMP
is currently
implemented and is an
ongoing effort.
VDOT’s MS4 District coordinators performed a total
of 83 third-party SWPPP QA construction
inspections, while VDOT’s MS4 consultant
performed over 20 third-party SWPPP QA
construction inspections throughout the nine VDOT
districts.
Note: * A copy of VDOT’s Annual ESC and SWM Standards & Specifications is available at Location & Design
Division’s Central Office location.
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 29
MCM #5: POST-CONSTRUCTION STORMWATER MANAGEMENT
The following BMPs have been selected to address MCM#5:
BMP 5(A) – Applicable Oversight Requirements
BMP 5(B) – SWM Plan Preparation and Implementation
BMP 5(C) – Long-Term Care and Maintenance of SWM Facilities
Note: The local MS4 Authority shall implement a schedule designed to inspect all privately owned
stormwater management facilities that discharge into VDOT’s MS4 as they, not VDOT, will have
jurisdictional control over the design, construction, and maintenance of these facilities.
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 30
BMP 5(A) – Applicable Oversight Requirements
Description and
Measurable Goal:
VDOT will utilize its annual ESC and SWM Standards & Specifications to address
post-construction stormwater runoff that enters the MS4 from regulated land-
disturbing activities.
Lead Division: Location & Design
Reference Documents: VDOT’s Annual ESC and SWM Standards & Specifications*
Expected Efforts and
Results in Meeting
Measurable Goal
Implementation
Schedule
Annual Report Information
Continue to obtain annual
approval of VDOT’s ESC
and SWM Standards &
Specifications.
Update components of
the Standards &
Specifications as
regulations and
operations warrant.
VDOT has continued coordination with DEQ on
annual approval of ESC and SWM Standards &
Specifications. VDOT submitted its annual
standards and specification for FY17.
VDOT has made continual modifications, revisions,
and updates to VDOT Road and Bridge
Specifications, Copied Notes, Special Provisions, and
Standards to maintain compliance with applicable
regulatory and permit requirements.
Note: * A copy of VDOT’s Annual ESC and SWM Standards & Specifications is available at Location & Design
Division’s Central Office location.
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 31
BMP 5(B) – SWM Plan Preparation and Implementation
Description and
Measurable Goal:
Prepare and implement post-construction stormwater management plans in
accordance with VDOT’s annual ESC and SWM Standards and Specifications for
regulated land-disturbing activities.
Lead Division: Location & Design
Reference Documents: VDOT’s Annual ESC and SWM Standards & Specifications, including:*
Policies and procedures utilized to ensure that stormwater
management (SWM) facilities are designed and installed
Standards & Specifications for non-proprietary BMPs
Hydraulic and Maintenance BMP databases to track SWM facility information
Expected Efforts and
Results in Meeting
Measurable Goal
Implementation
Schedule
Annual Report Information
Continue to specify
design criteria for post-
construction stormwater
runoff controls.
This aspect of the BMP is
currently implemented
and is an ongoing annual
effort.
VDOT continues to require SWM Plans to
incorporate design criteria for post-construction
stormwater runoff controls in accordance with the
VDOT annual ESC and SWM Standards &
Specifications.
Continue to develop
stormwater management
plans that are in
accordance with VDOT’s
annual ESC and SWM
Standards &
Specifications
This aspect of the BMP is
currently implemented
and is an ongoing annual
effort.
All SWM Plans for RLDAs were developed in
accordance with VDOT’s annual ESC Standards &
Specifications.
Continue to inventory
post-construction SWM
facilities and related
hydraulic and design
information.
VDOT has previously
implemented this
requirement, and will
continue to inventory
new BMPs as they are
brought online.
A summary table of new stormwater facilities
brought online during the reporting period, as
reported through VDOT’s monthly termination
process, is provided in Appendix B.
Note: * A copy of VDOT’s Annual ESC and SWM Standards & Specifications is available at Location & Design
Division’s Central Office location.
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 32
BMP 5(C) – Long-Term Care and Maintenance of SWM Facilities
Description and
Measurable Goal:
Provide adequate long-term operation and maintenance of its SWM facilities in
accordance with the VDOT BMP Inspection and Maintenance Manuals.
Lead Division: Maintenance
Reference Documents: VDOT’s Annual ESC and SWM Standards and Specifications, including:*
VDOT BMP Inspection Manual
VDOT BMP Maintenance Manual
Expected Efforts and
Results in Meeting
Measurable Goal
Implementation
Schedule
Annual Report Information
Continue to annually
inspect VDOT post-
construction SWM
facilities in accordance
with VDOT BMP
Inspection Manual, and
record inspections in
SWM facility database.
This aspect of the BMP
is currently
implemented and is an
ongoing effort.
The inventory and inspections of stormwater
facilities within Census Urban Areas is provided
Appendix C.
Continue maintenance
on its post-construction
SWM facilities in
accordance with the
VDOT BMP Maintenance
Manual
This aspect of the BMP
is currently
implemented and is an
ongoing effort.
The Districts are maintaining the BMP’s in
accordance with the BMP Maintenance Manual.
Note: * A copy of VDOT’s Annual ESC and SWM Standards & Specifications is available at Maintenance
Division’s Central Office location.
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 33
MCM #6: POLLUTION PREVENTION/GOOD HOUSEKEEPING FOR VDOT OPERATIONS
The following BMPs have been selected to address MCM#6:
BMP 6(A)1 & 6(A)2 – Procedures for Operation and Maintenance Activities
BMP 6(B) – Pollution Prevention at Maintenance Facilities
BMP 6(C) – Turf and Landscape Management
BMP 6(D)1 through 6(D)4 – Training of VDOT Forces
BMP 6(E) – Oversight of VDOT Maintenance Contractors
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 34
BMP 6(A)1 – Procedures for Operation and Maintenance Activities
Description and
Measurable Goal:
Develop and refine written procedures designed to minimize or prevent
pollutant discharge from daily operations, equipment maintenance, and the
application, storage, transport, and disposal of pesticides, herbicides, and
fertilizers.
Lead Division: Maintenance
Reference Documents: Maintenance Best Practices Manual*
Expected Efforts and
Results in Meeting
Measurable Goal
Implementation
Schedule
Annual Report Information
Continue to develop and
refine applicable sections
of the Maintenance Best
Practices Manual for MS4
regulated activities
This aspect of the BMP
is currently
implemented and is an
ongoing effort.
Maintenance Division staff continues to implement
this responsibility consistent with procedures
established in the VDOT Maintenance Best
Practices Manual.
Note: * A copy of the Maintenance Best Practices Manual is available at Maintenance Division’s Central
Office location. The Maintenance Best Practices Manual makes reference to the Waste
Management and Pollution Prevention Guides discussed in BMP 6(A)2.
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 35
BMP 6(A)2 – Procedures for Operation and Maintenance Activities
Description and
Measurable Goal:
Develop and refine, as appropriate, written procedures designed to minimize or
prevent pollutant discharge from daily operations, equipment maintenance,
and the application, storage, transport, and disposal of pesticides, herbicides,
and fertilizers.
Lead Division: Environmental
Reference Documents: Waste Management and Pollution Prevention Guides
Expected Efforts and
Results in Meeting
Measurable Goal
Implementation
Schedule
Annual Report Information
Continue to develop and
refine applicable sections
of Waste Management
and Pollution Prevention
Guides that apply to MS4
regulated activities
This aspect of the BMP
is currently
implemented and is an
ongoing effort
The January 2015 Waste Management and
Pollution Prevention Guide remains the current
version. During the next reporting year, we
anticipate reviewing the existing guide to update
various sections and to incorporate a new guide,
currently being developed, for the proper use,
maintenance, and storage of portable toilets.
Note: * A copy of the Waste Management and Pollution Prevention Guides is available at Environmental
Division’s Central Office location.
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 36
BMP 6(B) – Pollution Prevention at Maintenance Facilities
Description and
Measurable Goal:
Develop and refine, as appropriate, procedures designed to minimize or
prevent pollutant discharge from maintenance facilities, as applicable.
Lead Division: Environmental
Reference Documents: List of High Priority Facilities*
Applicable Stormwater Pollution Prevention Plans (once developed)*
Expected Efforts and
Results in Meeting
Measurable Goal
Implementation
Schedule
Annual Report Information
Continue to develop and
refine applicable sections
of Waste Management
and Pollution Prevention
Guides that apply to
activities at maintenance
facilities
This aspect of the BMP
is currently
implemented and is an
ongoing effort.
The January 2015 Waste Management and
Pollution Prevention Guide remains the current
version. During the next reporting year, we
anticipate reviewing the existing guide to update
various sections and to incorporate a new guide,
currently being developed, for the proper use,
maintenance, and storage of portable toilets.
Identify high priority
facilities as defined by
the small MS4 General
Permit
The effort has been
completed. The list will
be annually evaluated to
determine if additional
facilities are determined
to be high priority.
VDOT maintains a list of high-priority facilities.
Currently, there are 69 facilities that are identified
as high-priority facilities, and require SWPPP
development and implementation.
Continue to develop and
refine SWPPPs for high
priority facilities
Develop SWPPPs for all
applicable high priority
facilities within 48
months from permit
coverage.
VDOT has developed SWPPPs for all high-priority
facilities in the VDOT MS4 regulated area. VDOT
provided SWPPP training to District personnel
during the reporting year.
VDOT will continue to implement the SWPPPs, and
will revise and modify SWPPPP as identified
appropriate.
Continue to perform
annual MS4 compliance
assessments at VDOT
high priority facilities
within the MS4 Areas
This aspect of the BMP
is currently
implemented and is an
ongoing effort.
VDOT performed MS4 compliance assessment for
all high-priority facilities within the MS4 areas.
Notes: * This list of the high-priority facilities and associated SWPPPs is available at Environmental
Division’s Central Office location.
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 37
BMP 6(C) – Turf and Landscape Management
Description and
Measurable Goal:
Develop and refine turf and landscape nutrient management plans (NMPs) that
have been developed by a certified turf and landscape nutrient management
planner.
Lead Division: Maintenance
Reference Documents: List of Applicable Lands that Require NMPs*
Applicable Nutrient Management Plans (once developed)*
Roadside Development Standards and Specifications**
Expected Efforts and
Results in Meeting
Measurable Goal
Implementation
Schedule
Annual Report Information
Identify all applicable
lands where nutrients are
applied to a contiguous
area of more than one
acre.
This effort has been
completed. The list will
be evaluated annually to
determine if updates are
required.
Nutrient Management Plans (NMP’s) for one facility,
the Norfolk Residency, remains active at the end of
this reporting year.
A total of 48 NMP’s for facilities have expired
during the permit cycle.
Continue to develop and
refine NMPs on all lands
where nutrients are
applied to a contiguous
area of more than one
acre.
This aspect of the BMP
is currently
implemented and is an
ongoing effort.
No new NMP’s were approved for VDOT Facilities
during this reporting period.
Continue to develop and
refine Nutrient
Management Standards
& Specifications as
approved by DCR for
roadside development
during construction and
maintenance activities.
This aspect of the BMP
is currently
implemented with
approved district
specific NMPs and is an
ongoing effort.
The Roadside NMP and Construction NMP have
been developed and approved by DCR. The revised
Roadside and Construction NMP incorporate the
most recent changes from the Urban Nutrient
Management Handbook published by DCR.
Note: * The list of the applicable lands and associated NMPs is available at Maintenance Division’s Central
Office location.
** The Roadside Development Standards & Specifications is available at Maintenance Division’s
Central Office location.
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 38
BMP 6(D)1 – Training of VDOT Forces
Description and
Measurable Goal:
Continue to implement VDOT’s efforts to prevent and reduce stormwater
pollution from VDOT-related activities.
Lead Division: Environmental
(for division specific elements of VDOT’s Employee Training Program for MS4
and Stormwater)
Reference Documents: VDOT Employee Training Program for MS4 and Stormwater*
Annual Environmental Training Plan**
In-Stream Maintenance Training Materials “Environmental Compliance for
Maintenance Activities”
VDOT IDDE Manual
VDOT IDDE Training Modules
Expected Efforts and
Results in Meeting
Measurable Goal
Implementation
Schedule
Annual Report Information
Develop and deliver a
training plan to
include, but not
limited to, training
on the IDDE program
and appropriate spill
prevention and
responses.
Starting in the
second year of
permit
coverage, VDOT
will provide
training to
applicable field
personnel.
VDOT Environmental Division provided MS4, SPCC, waste
management, and SWPPP training to 405 attendees during the
reporting year.
The objective of MS4 training consists of two components: 1)
Pollution Prevention and Good Housekeeping, to support pollution
prevention and good housekeeping practices on maintenance
operations within the right-of-way and at VDOT facilities, and 2) Illicit
Discharge Detection and Elimination Training.
Waste Management Training covers waste management procedures
and best management practices. Spill Prevention Control and
Countermeasures (SPCC) training is delivered at facilities that operate
under an SPCC plan.
Storm Water Pollution Prevention Plan (SWPPP) training is delivered
at high priority facilities that have site specific SWPPP plans.
An Introduction to IDDE video was released and posted on the
Electronic Bulletin Board. The video introduces VDOT’s IDDE
program and educates viewers as to what is and is not an illicit
discharge. A follow up video concerning performing initial field
investigations and follow up on illicit discharges will be released in the
2016-2017 permit year. A SWPPP training video will also be released
in the 2016-2017 permit year.
A list of these trainings is provided in Appendix D.
Note: * A copy of The VDOT Employee Training Program for MS4 and Stormwater is available at Location
& Design Division’s Central Office location.
** A copy of the Annual Environmental Training Plan is available at Environmental Division’s
Central Office location.
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 39
BMP 6(D)2 – Training of VDOT Forces
Description and
Measurable Goal:
Continue to develop and refine VDOT’s efforts to prevent and reduce
stormwater pollution from VDOT-related activities.
Lead Division: Maintenance
(for division specific elements of VDOT’s Employee Training Program for MS4
and Stormwater)
Reference Documents: VDOT Employee Training Program for MS4 and Stormwater*
Annual Maintenance Training Plan**
Expected Efforts and
Results in Meeting
Measurable Goal
Implementation
Schedule
Annual Report Information
Ensure that VDOT
employees and
contractors who
apply pesticides and
herbicides are
properly trained or
certified in
accordance with the
Virginia Pesticide
Control Act.
This aspect of
the BMP is
currently
implemented
and is an
ongoing effort.
The following is a summary of the 76 individuals that are currently trained
and certified Roadside Management pesticide applicators.
District Certified
Bristol 7
Culpeper 6
Fredericksburg 9
Hampton Roads 22
Lynchburg 7
Northern Virginia 1
Richmond 10
Salem 10
Staunton 4
Note: * A copy of The VDOT Employee Training Program for MS4 and Stormwater is available at Location
& Design Division’s Central Office location.
** A copy of the Annual Maintenance Training Plan is available at Maintenance Division’s Central
Office location.
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 40
BMP 6(D)3 – Training of VDOT Forces
Description and
Measurable Goal:
Continue to train VDOT forces to prevent and reduce stormwater pollution
from VDOT-related activities.
Lead Division: Construction
(for division specific elements of VDOT’s Employee Training Program for MS4
and Stormwater)
Reference Documents: VDOT Employee Training Program for MS4 and Stormwater*
Annual Construction Training Plan**
Expected Efforts and
Results in Meeting
Measurable Goal
Implementation
Schedule
Annual Report Information
Ensure applicable
construction personnel
receive training on the
IDDE program and
appropriate spill
responses discussed in
BMP 6(D)1.
Starting in the second
year of permit coverage,
provide training to
applicable field
personnel.
VDOT provided training on implementing VPDES construction
permit requirements at permitted RLDA projects in all nine
Districts. VDOT training elements include the Pollution
Prevention (P2) Field Guide, the revised C-107 inspection form,
the S107J30 Special Provision, and the revised SWPPP General
Information Sheets.
VPDES Construction Implementation Training:
District Date # of Employees
Bristol 10/14/15 22
Culpeper 10/19/15 23
Fredericksburg 10/20/15 & 2/8/16 43
Hampton Roads 10/26/15 & 2/17/16 53
Lynchburg 10/30/15 37
Northern Virginia 11/13/15 & 2/2/16 42
Richmond 10/22/15 & 2/1/16 46
Salem 10/16/15 31
Staunton 10/31/15 28
There were 325 individuals in total that were trained in VPDES
construction permit requirements during the reporting year
Note: * A copy of The VDOT Employee Training Program for MS4 and Stormwater is available at Location
& Design Division’s Central Office location.
** A copy of the Annual Construction Training Plan is available at Construction Division’s Central
Office location.
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 41
BMP 6(D)4 – Training of VDOT Forces
Description and
Measurable Goal:
Continue to implement VDOT’s efforts to prevent and reduce stormwater
pollution from VDOT-related activities.
Lead Division: Learning Center
(for division specific elements of VDOT’s Employee Training Program for MS4
and Stormwater)
Reference Documents: VDOT Employee Training Program for MS4 and Stormwater*
Expected Efforts and
Results in Meeting
Measurable Goal
Implementation
Schedule
Annual Report Information
Ensure that VDOT
employees and
consultants serving as
plan reviewers and
inspectors obtain the
appropriate certifications
as specified in VDOT’s
annual ESC and SWM
standards and
specifications.
This aspect of the
BMP is currently
implemented and
is an ongoing
effort.
A total of 839 VDOT individuals are certified through the DEQ ESC
and/or SWM Certification Program The following list identifies the
total number of VDOT individuals certified or re-certified this
reporting period.
DEQ ESC/SWM Certifications Certified Recertified
SWM Program Administrator 17 10
SWM Inspector 34 26
SWM Plan Reviewer 5 1
SWM Combined Administrator 7 6
ESC Program Administrators 3 0
ESC Inspector 559 108
ESC Plan Reviewer 17 1
ESC Combined Administrators 55 12
Responsible Land Disturber 101 29
Dual Combined Administrator 10 34
Dual Inspector 55 34
Dual Plan Reviewer 14 5
Provide training
opportunities through
the Erosion and Sediment
Control Contractor
Certification (ESCCC)
Program.
This aspect of the
BMP is currently
implemented and
is an ongoing
effort.
The VDOT ESCCC Program provides an integral service to VDOT
contractors, maintenance forces, and land-use permittees. The
course topics include: the VESCLR, the erosion process, ESC control
measures, and the VDOT contract enforcement process. The training
is provided by four outside vendors who schedule classes through
the year. There were 462 individuals trained during this reporting
year.
Note: * A copy of The VDOT Employee Training Program for MS4 and Stormwater is available at Location
& Design Division’s Central Office location.
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 42
BMP 6(E) – Oversight of VDOT Maintenance Contractors
Description and
Measurable Goal:
Contractual oversight procedures for VDOT contractors for maintenance of
roadway or operation and use of VDOT facilities.
Lead Division: Maintenance
Reference Documents: Maintenance contracts
Expected Efforts and
Results in Meeting
Measurable Goal
Implementation
Schedule
Annual Report Information
Continue to require that
contractors use
appropriate control
measures and procedures
for stormwater
discharges to the VDOT’s
MS4 System.
This aspect of the BMP
is currently
implemented and is an
ongoing effort
VDOT continues to require that contractors use
appropriate control measures and procedures for
stormwater discharges to the VDOT’s MS4 System.
ECIAL CONDITIONS FOR APPROVED TMDLS AND APPLICABLE WLA
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 43
SPECIAL CONDITIONS FOR APPROVED TMDLS
The following BMPs have been selected to address the Special Conditions for Approved TMDLs:
� BMP 7(A) – Action Plans for Approved Local TMDLs
� BMP 7(B) – Action Plan for Chesapeake Bay Watershed TMDL
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 44
BMP 7(A) – Action Plans for Approved Local TMDLs
Description and
Measurable Goal:
Develop and implement applicable TMDL Action Plans for approved TMDLs that
have assigned VDOT’s MS4 a wasteload allocation.
Lead Division: Environmental
Reference Documents: List of approved local TMDLs that have assigned VDOT’s MS4 a WLA*
Local TMDL Action Plans (once developed)*
Expected Efforts and
Results in Meeting
Measurable Goal
Implementation
Schedule
Annual Report Information
Update Existing Local
TMDL Action Plans
(TMDLs approved before
July 2008)* in accordance
with Special Conditions of
Permit.
Update Existing Local
TMDL Action Plans
within 24 months of
receiving permit
coverage.
Eight existing Local TMDL Action Plans were
updated within 24 months of permit coverage.
Copies of the existing Action Plans are provided in
Appendix E.
Develop New Local TMDL
Action Plans (TMDLs
approved between July
2008 and
June 2013)* in
accordance with Special
Conditions of Permit.
Develop Local TMDL
Action Plans within 36
months of receiving
permit coverage.
Twelve new Local TMDL Action Plans were
developed within 36 months of permit coverage.
Copies of the new Action Plans are provided in
Appendix E.
Implement Local TMDL
Action Plans.
Schedule to be
identified during the
development of the
Local TMDL Action
Plans.
Progress on implementation of the Updated Action
Plans will be reported in the next annual report.
Note: * Environmental’s Central Office maintains the list of the approved TMDLs that have assigned
VDOT’s MS4 a WLA and VDOT’s associated Action Plan for each.
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 45
BMP 7(B) – Action Plan for Chesapeake Bay Watershed TMDL
Description and
Measurable Goal:
Develop and implement TMDL Action Plans for the Chesapeake Bay Watershed
TMDL
Lead Division: Environmental
Reference Documents: Chesapeake Bay TMDL Action Plan (once developed)*
Expected Efforts
and Results in
Meeting
Measurable Goal
Implementation
Schedule
Annual Report Information
Develop
Chesapeake Bay
TMDL Action Plan
for the four river
basins.
Develop Action
Plan within 24
months of
receiving permit
coverage.
Chesapeake Bay TMDL Action Plan was developed within 24
months of permit coverage, submitted on November 9, 2015 and
approved on June 21, 2016.
Implementation
of Chesapeake
Bay Watershed
Action Plans.
Schedule to be
identified during
the development
of the respective
Basin Action
Plans.
Parameter
TN (lb/yr) TP (lb/yr) TSS (lb/yr)
James 443.88 87.40 7897.79
Potomac 2708.02 696.96 243282.30
Rappahannock 475.00 110.00 176378.35
York 117.05 28.13 11453.64
Total Reductions
Reported to Date (all
basins):
3743.95 922.49 439012.1
See Appendix F for details on implementation and credits achieved
to-date and the proposed FY17 schedule. The Urban BMP
Reporting Spreadsheet will be provided electronically as requested.
Note: * A copy of the Chesapeake Bay TMDL Action Plan is available at Environmental Division’s Central
Office location.
VDOT MS4 Program Plan
VPDES #: VAR040115
October 2016 Page 46
PROGRAM EVALUATION, MODIFICATION, AND REPORTING
VDOT has completed its annual assessment and evaluation through the MS4 Steering Committee
meetings and continual monitoring of program implementation. Based on the evaluation, VDOT’s
program compliance, the appropriateness of the identified BMPs, and VDOT’s progress towards
achieving the identified measurable goals are sufficient.
Appendix A
TMDL and IP Meetings during the Reporting Year
TMDL and IP Meetings during the Reporting Year
Meeting Name/Venue Date
Accotink Creek Benthic TMDL 7/6/15
Lower Chickahominy River and Tributaries Bacteria TMDLs 7/28/15
IP for Upper Roanoke River Watershed Bacteria and Sediment TMDLs 7/29/15
Chesapeake Bay Stakeholder Advisory Group 9/3/15
NCHRP 25-53 (The Efficacy of Treating Highway Runoff to Meet Watershed TMDL Goals) 10/1-2/15
Lower Chickahominy River and Tributaries Bacteria TMDLs 10/7/15
Mattaponi Tributaries Bacteria TMDL 10/26/15
Mattaponi Tributaries Bacteria TMDL 11/4/15
Mattaponi Tributaries Bacteria TMDL 11/9/15
IP for Upper Roanoke River Watershed Bacteria and Sediment TMDLs 12/3/15
Accotink Creek TAC meeting 12/14/15
Lower Chickahominy River and Tributaries Bacteria TMDLs 1/4/16
NCHRP 25-53 Approaches for Determining and Complying with TMDL Requirements Related
to Roadway Stormwater Runoff 2nd Panel Meeting
1/6/16
GoToWebinar - Sediment Modeling Part I 1/12/16
Lower Chickahominy River and Tributaries Bacteria TMDLs 1/19/16
Crooked Run, West Run, Stephens Run, and Willow Brook TMDL Implementation Plan 1/28/16
RAP Meeting for Nutrient Credit Certification Regulations, 9VAC25-900 2/26/16
MS4 meeting - Accotink Creek TMDL study 2/29/16
Beaver Creek Watershed Benthic and Bacterial TMDL Revision 3/1/16
Urban Stormwater Work Group 3/7/16
IP for Upper Roanoke River Watershed Bacteria and Sediment TMDLs 3/16/16
New River and Tributaries PCB TMDL 4/5/16
Crooked Run, West Run, Stephens Run, and Willow Brook TMDL Implementation Plan 4/7/16
Lower Chickahominy River and Tributaries Bacteria TMDLs 4/26/16
Accotink Creek Benthic TMDL 5/3/16
Chesapeake Bay Stakeholder Advisory Group 5/3/16
Nutrient Credit Certification - Restoration Workgroup Meeting 5/13/16
[Webcast] Crediting Floating Treatment Wetlands in the Chesapeake Bay 6/16/16
Crooked Run, West Run, Stephens Run, and Willow Brook TMDL Implementation Plan 5/24/16
New River and Tributaries PCB TMDL 5/26/16
Upper Goose Creek, Cromwells Run, and Little River IP Development 6/21/16
Urban Stormwater Work Group 6/21/16
Meeting with Fairfax County and DEQ re: Accotink Creek Modeling 6/22/16
Crooked Run, West Run, Stephens Run, and Willow Brook TMDL Implementation Plan 6/29/16
[Webcast] Crediting Street Sweeping and Storm Drain Cleaning in the Chesapeake Bay 6/30/16
Appendix B
New Stormwater Management Facilities Brought Online During the Reporting Year
New Stormwater Management Facilities Brought Online During the Reporting Year
Facility Type
Date
Brought
Online
Date of Last
InspectionLatitude Longitude
6th Order
HUCReceiving Water
Total Acres
Treated
Impervious
Acres
Treated
Pervious
Acres
Treated
Extended Detention
Basin7/15/15
New BMP for this
reporting year36.6861 -81.8869 TH14
Unnamed tributary to
Middle Fork Holston River39.9 4.8 35.1
Extended Detention
Basin7/15/15
New BMP for this
reporting year36.6786 -81.8686 TH14
Unnamed tributary to
Middle Fork Holston River19.7 5.5 14.2
Special Design Level
Spreader7/15/15
New BMP for this
reporting year36.6778 -81.8686 TH14
Unnamed tributary to
Middle Fork Holston River0.2 0.2 0.04
Special Design Level
Spreader7/15/15
New BMP for this
reporting year36.6711 -81.8614 TH07
Unnamed tributary to
Middle Fork Holston River0.8 0.0 0.8
Extended Detention
Basin7/15/15
New BMP for this
reporting year36.6703 -81.8619 TH07
Unnamed tributary to
Middle Fork Holston River4.2 2.3 1.9
Extended Detention
Basin7/15/15
New BMP for this
reporting year36.6686 -81.8619 TH107
Unnamed tributary to
Middle Fork Holston River2.3 1.2 1.1
Extended Detention
Basin7/15/15
New BMP for this
reporting year36.6617 -81.8550 TH07 Louse Creek 27.5 3.3 24.2
Grassed Swale 9/1/15New BMP for this
reporting year36.7435 -83.0559 TP09 Cane Creek 6.6 1.5 5.1
Tree Box Filter
(Filterra)9/17/15
New BMP for this
reporting year37.4125 -77.6458 JA42 Swift Creek 0.297 0.290 0.007
Tree Box Filter
(Filterra)9/17/15
New BMP for this
reporting year37.4167 -77.6417 JA42 Swift Creek 0.225 0.220 0.005
Extended Detention
Basin8/31/15
New BMP for this
reporting year37.3092 -82.2853 BS35 Grassy Creek 25.5 22.0 3.5
Extended Detention
Basin8/31/15
New BMP for this
reporting year37.3013 -82.2829 BS35 Hunts Creek 12.1 10.6 1.5
Extended Detention
Basin8/31/15
New BMP for this
reporting year37.2934 -82.2800 BS35 Hunts Creek 1.8 1.5 0.3
Water Quality Swale 10/14/15New BMP for this
reporting year38.0198 -78.3515 JR17 Carroll Creek 0.4 0.1 0.3
Water Quality Swale 10/14/15New BMP for this
reporting year38.0194 -78.3510 JR18 Carroll Creek 0.4 0.1 0.3
Water Quality Swale 10/14/15New BMP for this
reporting year38.0198 -78.3512 JR18
Unnamed tributary to
Mechunk Creek0.1 0.0 0.1
Water Quality Swale 10/14/15New BMP for this
reporting year38.0194 -78.3507 JR18
Unnamed tributary to
Mechunk Creek0.5 0.2 0.3
Facility Type
Date
Brought
Online
Date of Last
InspectionLatitude Longitude
6th Order
HUCReceiving Water
Total Acres
Treated
Impervious
Acres
Treated
Pervious
Acres
Treated
Extended Detention
Basin7/17/15
New BMP for this
reporting year38.8605 -77.4061 PL45 Big Rocky Run 11.6 7.2 4.4
Extended Detention
Basin7/17/15
New BMP for this
reporting year38.8771 -77.4093 PL45 Frog Branch 8.6 3.7 4.9
MTD (Filterra) 11/9/15New BMP for this
reporting year38.6599 -77.3586 PL49 Neabsco Creek 0.2 0.0 0.2
MTD (Filterra) 11/9/15New BMP for this
reporting year38.6596 -77.3573 PL49 Neabsco Creek 0.2 0.0 0.2
MTD (Filterra) 11/9/15New BMP for this
reporting year38.6597 -77.3566 PL49 Neabsco Creek 0.3 0.1 0.2
Grassed Swale 9/30/15New BMP for this
reporting year37.1626 -76.8506 JL32 Dark Swamp 6.4 6.4 0
Grassed Swale 10/30/15New BMP for this
reporting year36.8455 -76.0217 CB25 Wolfsnare Creek 1.5 0.8 0.68
Grassed Swale 10/30/15New BMP for this
reporting year36.8464 -76.0178 CB25 Great Neck Creek 1.4 0.7 0.61
Grassed Swale 10/30/15New BMP for this
reporting year36.8471 -76.0147 CB25 Great Neck Creek 1.5 0.7 0.86
Grassed Swale 10/30/15New BMP for this
reporting year36.8477 -76.0110 CB25 Great Neck Creek 1.7 0.9 0.8
Grassed Swale 10/30/15New BMP for this
reporting year36.8478 -76.0091 CB25 Great Neck Creek 1.8 0.9 0.85
Grassed Swale 10/30/15New BMP for this
reporting year36.8476 -76.0065 CB25 Great Neck Creek 0.9 0.5 0.42
Grassed Swale 10/30/15New BMP for this
reporting year36.8475 -76.0054 CB25 Great Neck Creek 0.7 0.4 0.31
Grassed Swale 10/30/15New BMP for this
reporting year36.8466 -75.9991 CB25
Unnamed tributary to Great
Neck Creek4.1 2.2 1.98
MTD 11/10/15New BMP for this
reporting year38.9922 -77.5640 PL14 Beaverdam Creek 1.8 1.3 0.5
Extended Detention
Basin2/4/16
New BMP for this
reporting year39.0073 -77.3568 PL21 Sugarland Run 6.3 4.0 2.3
Extended Detention
Basin2/4/16
New BMP for this
reporting year39.0018 -77.3491 PL21 Sugarland Run 6.3 4.0 2.3
Facility Type
Date
Brought
Online
Date of Last
InspectionLatitude Longitude
6th Order
HUCReceiving Water
Total Acres
Treated
Impervious
Acres
Treated
Pervious
Acres
Treated
Extended Detention
Basin7/1/15
New BMP for this
reporting year38.8670 -77.0737 PL24 Long Branch 3.2 3.2 0
Soil Amendments 7/30/15New BMP for this
reporting year37.1915 -80.7277 NE72 Little Walker Creek 1.3 1.3 0
Grassed Swale 9/23/15New BMP for this
reporting year36.6389 -79.9332 RD24
Unnamed tributary to
Grassy Creek1.6 1.2 0.4
Grassed Swale 9/23/15New BMP for this
reporting year36.6407 -79.9299 RD24
Unnamed tributary to
Grassy Creek1.6 1.2 0.4
Retention Basin I 5/10/16New BMP for this
reporting year37.2449 -76.7264 JL34
Unnamed tributary to
College Creek1.7 0.9 0.8
Grass Channel 5/10/16New BMP for this
reporting year37.2441 -76.7207 JL34
Unnamed tributary to
College Creek0.5 0.2 0.3
Grass Channel 5/10/16New BMP for this
reporting year37.2436 -76.7195 JL34
Unnamed tributary to
College Creek1.1 0.3 0.8
Appendix C
BMP Inventory and Inspections Performed during the Reporting Year
BMP Inventory and Inspections performed During the Reporting Year
District No. of BMP’sInspections
Completed*
Bristol 9 9
Culpeper 74 74
Fredericksburg 181 175
Hampton Roads 161 142
Lynchburg 101 101
Northern Virginia 478 470
Richmond 288 264
Salem 161 161
Staunton 154 151
Rest Areas 8 8
* Discrepancies in the number of inspections performed versus the total number
of BMPs is due to new BMPs being brought on-line during the permit year as
well as the BMP inspection cycle which follows the calendar year. Note: the first
year inspection is performed by the Construction Division at project close-out,
and not recorded in the BMP inspection database.
Appendix D
VDOT Employee Training Summary
Type of TrainingDate of
Training
# Employees
Trained
SWPPP Training 7/21/2015 8
SWPPP Training 7/21/2015 5
SWPPP Training 7/22/2015 6
SWPPP Training 7/23/2015 4
SWPPP Training 7/23/2015 7
SWPPP Training 7/24/2015 3
SWPPP Training 8/10/2015 7
MS4 10/6/2015 16
Waste Management 10/20/2015 18
SWPPP Training 10/26/2015 7
SWPPP Training 10/27/2015 2
SWPPP Training 10/27/2015 3
SWPPP Training 10/28/2015 1
SWPPP Training 10/28/2015 1
SWPPP Training 11/2/2015 10
SWPPP Training 11/2/2015 5
SWPPP Training 11/4/2015 4
SWPPP Training 11/4/2015 3
SWPPP Training 11/5/2015 2
SWPPP Training 11/5/2015 3
SWPPP Training 11/5/2015 9
SWPPP Training 11/6/2015 6
SWPPP Training 11/9/2015 3
SWPPP Training 11/9/2015 3
SWPPP Training 11/9/2015 1
SWPPP Training 11/10/2015 5
SWPPP Training 11/10/2015 2
SWPPP Training 11/10/2015 7
SWPPP Training 11/12/2015 12
SWPPP Training 11/12/2015 2
SWPPP Training 11/12/2015 4
SWPPP Training 11/12/2015 5
SWPPP Training 11/12/2015 2
SWPPP Training 11/16/2015 5
SWPPP Training 11/16/2015 3
SWPPP Training 11/16/2015 1
SWPPP Training 11/17/2015 2
SWPPP Training 11/17/2015 3
SWPPP Training 11/17/2015 4
Type of TrainingDate of
Training
Number of
Employees
Trained
SWPPP Training 11/16/2015 1
SWPPP Training 11/17/2015 2
SWPPP Training 11/17/2015 3
SWPPP Training 11/17/2015 4
SWPPP Training 11/17/2015 10
SWPPP Training 11/18/2015 1
Waste Management/
MS4/SPCC1/12/2016 18
Waste Management/
MS4/SPCC1/12/2016 12
SWPPP Training 2/7/2016 2
SWPPP Training 2/7/2016 5
SWPPP Training 2/8/2016 11
SWPPP Training 2/9/2016 5
SWPPP Training 2/10/2016 9
SWPPP Training 2/10/2016 8
SWPPP Training 2/10/2016 9
SWPPP Training 2/10/2016 7
SWPPP Training 2/11/2016 14
SWPPP Training 2/11/2016 15
SWPPP Training 2/11/2016 3
SWPPP Training 2/11/2016 5
Waste Management/
SPCC2/18/2016 17
SWPPP Training 2/19/2016 8
SWPPP Training 3/1/2016 17
SWPPP 4/6/2016 6
WM 4/19/2016 18
SPCC 5/10/2016 2
SPCC 6/8/2016 2
Appendix E
Local TMDL Action Plans
for the following Existing TMDLs:
Abrams and Opequon
Bull Run TMDL
Crab Creek TMDL
Popes Head Creek
Roanoke River
Goose Creek
Potomac River
Stroubles Creek
and for the following New TMDLs:
Chickahominy River
Difficult Run
Four Mile Run – Tidal
Hoffler Creek
Hunting Creek
James River – Lynchburg
James River – Richmond
Lower Accotink Creek
Occoquan River
Neabsco Creek
Rivanna River
Rappahannock River – Tidal
Appendix F
Chesapeake Bay TMDL Action – FY16 Progress and FY17 Schedule