Community Liaison Group West & North Joint Meeting 6 December 2018

Upload: others

Post on 21-May-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

Community Liaison Group

West & North Joint Meeting

6 December 2018

Page 2: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

JIM WILLIAMSON

Introduction

Page 3: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

Time Item Topic

5:30pm 1 Welcome and actions from previous meeting

5:40pm 2 Year in review – West Gate Tunnel Authority

5:50pm 3 Landscaping and Open Space

6:10pm 4 Year in review – Construction

6:20pm 5 Construction Update (East, West & Tunnels)

6:50pm 6 Tea break

7.05pm 7 Year ahead

7.15pm 8 Feedback on CLG from members

7.30pm 9 Questions from members

Page 4: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

PETER SAMMUT

WEST GATE TUNNEL AUTHORITY

Year in review

Page 5: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

West Gate Tunnel Project - parties

Manages project on behalf

of State

Project Co.

Design and Construction Operation and Management

Independent Reviewer and

Environmental Auditor

Page 6: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

Major Transport Infrastructure Projects

A vital alternative to the West

Gate Bridge to free up traffic

and remove thousands of

trucks from residential streets

in Melbourne’s west.

Victoria's biggest road project -

connecting the missing link in

Melbourne's freeway network.

Removing 75 level crossings

across metropolitan

Melbourne

Untangling the City Loop so

more trains can run more often

across Melbourne

Planning and delivering major

road projects for Victoria.

Coordinating an unprecedented

number of transport projects across

Victoria.

The proposed Suburban Rail

Loop is a new underground

rail network connecting

Melbourne’s suburbs.

Page 7: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

Mismatch between population & job growth

Page 8: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

Why we are building the project

• Managing a growing Melbourne

• 24/7 truck bans on key inner-west streets

• 9,000 trucks taken off local roads

• Reliable travel times

• Better quality of living

• Improved connectivity & better accessibility

• Safer roads

• Less traffic noise 70 kilometres of new traffic lanes over 17 kilometres – from Kororoit

Creek Road to Wurundjeri Way

Up to 20 minutes in travel time savings between the city and

Melbourne’s west

A 16 per cent reduction in serious crashes

Improved incident response systems

Up to 13 minute faster trips to the Port of Melbourne

Page 9: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

Environment Effects Statement Initiatives

• Hobsons Bay Transport Study

• Corridor Study

• North and West Melbourne and Docklands Transport

• Moonee Ponds Master Plan

• Inner West Air Quality Community Reference Group

• Community Involvement and Participation Plan

• Noise mitigation for properties fronting Millers Road

• Significant funding to councils

Page 10: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

Hobsons Bay Transport

Strategy

Corridor Study North and West

Melbourne and

Docklands

Transport

Moonee Ponds Master

Plan

Inner West Air

Quality Community

Reference Group

Community

Involvement and

Participation Plan

Noise mitigation for

properties fronting

Millers Rd (WGF to

Geelong Rd)

First steering committee

meeting 31 Oct

Membership and

Terms of Reference

agreed

Central City

Transport Committee

established

Scope of work agreed

and steering committee

appointed

EOI process

complete

Draft plan issued to

HBCC and MCC

Residents contacted

through letters and

door knocks

Terms of Reference agreed Meetings held 20 Sept

& 25 Oct

Draft MOU under

discussion

First steering

committee meeting 26

Sept

Appointed members

and chair

Meetings held with

Councils

Noise monitoring

loggers installed in

Oct

MOU being agreed 3 groups brainstormed

60 issues at 2nd

meeting

Terms of Reference

agreed

First meeting

scheduled 10 Dec

Plan updated to

reflect feedback

Dec: follow-up letter

to property owners

Communication &

engagement plan being

developed with HBCC

Upcoming: 3rd meeting

early 2019 to focus on

solutions

Issues workshop for

government

depts/agencies 15 Nov

Upcoming: final

stages of

consultation with

HBCC and MCC

Commence

consultation

condition surveys

Meeting HBCC

communications and

engagement 22 Nov

Upcoming: update CoM

Moonee Ponds Creek

Strategic Opportunities

Plan

Upcoming: launch

and allocate first

round of grants H1

2019

Transport brief &

communication plans -

steering committee 3 Dec

Upcoming: alignment

with government

stakeholders

EES Initiatives - Engagement status

Page 11: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

Thank you for your contributionKevin Redfern – Seabrook

Philip Auciello – Brooklyn

Michael Kwon Sin Koy – Point Cook

Marlon de Leon – Tarneit

James Cox – Avondale Heights

BayWest Bicycle User Group

Bicycle Network

Friends of Lower Kororoit Creek

Friends of Stony Creek

LeadWest

Maribyrnong Truck Action Group (MTAG)

RACV

Victorian Transport Association (VTA)

Brimbank City Council

Hobsons Bay City Council

Wyndham City Council

Matt Monger – Docklands

Victor Ng – Seddon

Tony Le-Nguyen – Footscray

Sarah Grace – Yarraville

Nathan Hang – Kensington

Con Frescos – Yarraville

Concerned Locals of Yarraville

North and West Melbourne Association

Kensington Association

Friends of Moonee Ponds Creek

City of Melbourne

Maribyrnong City Council

Jim Williamson – Independent Chair

We welcome your feedback.

Page 12: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

DIETER LIM

TRACT

Landscaping and open space

Page 13: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

To bring the Community Liaison Group up to

date with the design process and status of

project packages

Demonstrate that Urban Design is being

developed consistent with Urban Design

Framework

PURPOSE OF PRESENTATION

Page 14: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

Tract is a national planning and design

practice specialising in town planning, urban

design, landscape architecture and

associated digital media

As planners and designers our charter is to

deliver sustainable and memorable

solutions, shaping places for living, leisure

and work, and the infrastructure that supports

and connects these places. We do this by

harnessing the strength and diversity of our

collective expertise

Tract have extensive experience and

award winning infrastructure capabilities

having worked as both landscape architect

and as urban designer for a variety of

infrastructure projects

TRACT - WHO ARE WE

Page 15: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

WGTP TIMELINE

Page 16: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

Setting up construction compounds

Widening the freeway

Changes to high-voltage power lines

Upgrading the Federation Trail

Building new noise walls

Building the Hyde Street ramps

2018 2019 2020 2021 2022

CONSTRUCTION TIMELINE - WEST GATE FREEWAY

Page 17: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

Setting up construction compounds

North Yarra Main Sewer works

Tunnel portals

Tunnelling

Cycling and walking bridge

2018 2019 2020 2021 2022

CONSTRUCTION TIMELINE - TUNNELS

Page 18: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

Setting up construction compounds

Building the elevated road

Maribyrnong River bridges

Major cycling upgrades

2018 2019 2020 2021 2022

CONSTRUCTION TIMELINE - PORT TO CITY

Page 19: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

1. PRELIMINARY DESIGN (PINK ROOM REVIEW)

2. PRELIMINARY DESIGN (EXTERNAL REVIEW) - STAKEHOLDER LIAISON

3. DETAILED DESIGN (PINK ROOM REVIEW)

4. DETAILED DESIGN (EXTERNAL REVIEW) - STAKEHOLDER LIAISON

5. DRAFT CERTIFIED DESIGN - IREAREVIEW

6. CERTIFIED DESIGN

7. ISSUE FOR CONSTRUCTION

DESIGN PROCESS PER PACKAGE

Page 20: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

WEST GATE TUNNEL - PROJECT PRECINCT

Page 21: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

WesternDistributor

Improving Melbourne together

Urban Design Framework Report3b.4.1PackageOne

DESIGN NARRATIVE

Page 22: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

WEST GATE TUNNEL PROJECT ILLUSTRATIVE

Page 23: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

M 80 INTERCHANGE

ACTIVE PRELIMINARY

DESIGN

COMMENCE

2019WESTGATE FWY

ACTIVE DRAFT CERTIFIED

DESIGN

WURUNDJERI WAY

ACTIVE PRELIMINARY

DESIGN

KOROROIT CREEK

AC TIVE

DRAFT CERTIFIEDDESIGN

SOUTHERN PORTAL

ACTIVE DRAFT CERTIFIED

DESIGN

NORTHERN

PORTAL

ACTIVE DRAFT CERTIFIED

DESIGN

FOOTSCRAY RD & CITYLINK / CITY CONNECTIONS

ACTIVE DETAILED DESIGN

PACKAGE ACTIVITY STATUS

Page 24: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

KOROROIT CREEK - PART K ILLUSTRATION

Page 25: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

KOROROIT CREEK - PART K DESIGN

Page 26: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

SOUTHERN PORTAL - PART K ILLUSTRATION

Page 27: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

SOUTHERN PORTAL - PART K DESIGN

Page 28: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

NORTHERN PORTAL - PART K ILLUSTRATION

Page 29: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

NORTHERN PORTAL - PART K DESIGN

Page 30: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

FOOTSCRAY ROAD - PART K ILLUSTRATION

Page 31: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

CITYLINK CONNECTIONS - PART K ILLUSTRATION

Page 32: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

DAVID CLEMENTS

TRANSURBAN

Year in review

Page 33: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

January – March

Page 34: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting
Page 35: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

April – June

Page 36: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting
Page 37: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

July - September

Page 38: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting
Page 39: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting
Page 40: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

October – December

Page 41: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting
Page 42: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting
Page 43: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

Bella’s on her way to Melbourne!

Page 44: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

BRAD JACKSON

CPBJH JOINT VENTURE

Construction update

Page 45: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

West – Current and upcoming works Service relocations /

Rosala Avenue walking and cycling bridge

Freeway widening and temporary noise walls

Millers Road interchange

Service relocations

Fogarty Avenue /Newport Rail line

Williamstown Road interchange / West Gate Freeway

Temporary noise walls / Muir Street walking and cycling bridge

Page 46: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

Traffic changes

Page 47: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

Noise walls – temporary and permanent

Temporary Noise Walls Permanent Noise Walls

Page 48: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

Tunnels portal

Page 49: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

Tunnelling hub

Page 50: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

North Yarra Main Sewer

Page 51: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

Port to City precinct

Maribyrnong River crossings

Footscray Road preparations

City Connections (E-Gate and F-Gate)

Wurundjeri Way

Page 52: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

Maribyrnong River crossings

Page 53: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

Footscray Road update

Page 54: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

City Connections (E-Gate & F-Gate)

Page 55: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

BRAD JACKSON

CPBJH JOINT VENTURE

The year ahead

Page 56: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

The year ahead – East

River piling

Utility relocationsPiling for elevated road

MTM and Yarra Trams relocated Realignment of rail track

Removal of V/Line reversal loopRemoval of V/Line stabling

sidings and wagon yard

V/Line relocated to newfacilities at Melbourne Market

Page 57: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

The year ahead – East

Page 58: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

The year ahead – Tunnels

Spoil shed completion

TBM 1 and 2 arrival to siteTBM launch

Permanent power and sub station go live

Page 59: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

The year ahead – Tunnels

Page 60: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

The year ahead – West First noise walls

Rosala Street pedestrian bridge opens Muir Street pedestrian bridge opens HV relocation to monopoles

Excavation at Southern Portal

Page 61: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

The year ahead – West

Page 62: Community Liaison Group - West Gate Tunnelwestgatetunnelproject.vic.gov.au/__data/assets/pdf_file/0011/345773… · Time Item Topic 5:30pm 1 Welcome and actions from previous meeting

Questions from members