comparison between pwd form 203a and pwd form design and built

Upload: meor-syahmi

Post on 10-Feb-2018

1.667 views

Category:

Documents


71 download

TRANSCRIPT

  • 7/22/2019 Comparison Between PWD Form 203A and PWD Form Design and Built

    1/16

    Abstract

    All standard forms of construction contract contain clauses for determination of contracts.

    For example, PWD 203A forms, PWD Design and Built, PAM 2006 form and etc. It is the same

    with the PWD 203A form where the PWD 203A (Rev. 10/83) has been replaced by the PWD

    203A (Rev. 2007). These are the traditional forms of contract based on drawings and

    specification (203) or bills of quantities (203A) produced for use in public sector or government

    projects in both building and civil engineering contracts. Generally it can be said that a majority

    of the risks have been transferred to the contractor under these standard forms of contract and

    this remains true with the 2007 version.

    The standard form is generally used in conjunction with the accompanying standard

    administrative forms which have been produced specifically for use with the contract forms and

    in many instances enhance the obligations contained within the conditions of contract. However,

    based on a preliminary study that had been conducted for the research, it has been found out that

    both of the employers and contractors may not actually realize their rights, procedures and

    effects in determining the contractors employment under the new forms.

    Hence, this study will focus on comparison between PWD 203a and PWD Design and

    Built, procedures and effects as a result of determination of the contractors employment under

    the forms.

  • 7/22/2019 Comparison Between PWD Form 203A and PWD Form Design and Built

    2/16

    1.1 Introduction

    A contract is a legally binding agreement between the parties identified in the agreement

    to fulfill all the terms and conditions outlined in the agreement. A prerequisite requirement for

    the execution of a contract, amongst other things, is the condition that all the parties to the

    contract accept the terms of the claimed contract. Construction contracts are basically different

    from major service contracts. There are various types of construction contract. The choice of

    contract depends on the basis of pricing and the contract strategy that best meets the project

    objectives. The various types offer different ways of handling pricing, risk transfer,

    responsibility for performance, cost certainty, and complexity.

    The purpose of standard forms of contract is to facilitate the contractual arrangements

    between actors in a project. Standard forms of contract are readymade terms and conditions

    when making a contract (Kwakye 1997). The standards vary from country to country and from

    one type of project to another. These standards are generally used and accepted by different

    contracting parties. It would be practically impossible to devise a standard form of contract that

    would take account of all eventualities that might occur in a construction project (Andersson andGunnarsson, 2002). Standard forms of contracts are often criticized as being a compromise

    containing some defective aspects. However, the advantage of their adoptions is that with the

    passage of time, persons using them become familiar withtheir overall content as well as their

    particular strengths and weaknesses (Kwakye 1997).

  • 7/22/2019 Comparison Between PWD Form 203A and PWD Form Design and Built

    3/16

    1.2 Comparison between PWD (203a) and PWD (D & B)

    There are different specialists or parties during the process of building procurement. It leads to

    the fragmentation process in construction industry (Murdoch and Hughes, 2000). Each project

    participant has particular aims and objectives and it is rare to find contract structures that

    encourage harmony among these aims. According to the scale and requirement of the project the

    parties may differ in types of contract. Figure 2 provides parties organization in PWD DB form

    of contract and figure 3 shows parties relation in PWD 203A form of contract.

    Figure 1: Organization chart of PWD DB form of contract

    Client

    Turnkey Contractor

    Architect

    Architect

    C & S

    Builders

    C & S

    Project

    Engineer

    Joint Venture Contractor

    Project Director

    M & E

    Engineer

    Design and

    Implementation Project

    Validation

    Team

    Accreditation

    Team

  • 7/22/2019 Comparison Between PWD Form 203A and PWD Form Design and Built

    4/16

    Figure 2: Organization chart of PWD 203A form of contract

    Architect

    Client

    Contractor

    Nominated Sub-Contractor

    M & E Services

    C & S

    Engineer

    Quantity

    Surveyor

    Safety

    Officer

    Superintending

    Officer

    M & E

    Engineer

    Executive

    Director

    Site

    Supervisor

    Assistant of Site

    Supervisor

    Assistant of Quantity

    Surveyor

  • 7/22/2019 Comparison Between PWD Form 203A and PWD Form Design and Built

    5/16

    MAIN PARTY ROLES PWD D & B PWD 203A

    Client

    Consultant

    Contractor

    Representative

    Advisor

    Stakeholder

    Design Leadership

    Management

    Design

    Administration

    Site inspectorOverall responsibility

    Constructors staff

    Partial responsibility

    Project director

    Advisory group,

    feasibility consultantEnd-user, general

    public, tenant-

    -

    -

    -

    -Consultant(architect),main contractor, joint

    venture contractor,

    design and buildproject manager

    Contract manager,

    project engineer,

    supervision team,builders

    Architect, C & Ssub-contractor, M &E sub-contractor,

    supplier

    Superintending Officer

    Advisory group,

    feasibility consultantEnd-user, general

    public, tenantArchitect(management

    function)Consultant team

    manager

    Architect(designfunction)

    Architect, contract

    administrator,

    supervising officer,project administration

    Clerk of workBuilder, maincontractor,

    principal contractor,

    executive director

    Project manager, site

    supervisor, builders

    C&S sub-contractor,M&Esub-contractor,

    quantity

    surveyor, supplier

    Table 1: Comparison of PWD DB and PWD 203A form of contract parties

  • 7/22/2019 Comparison Between PWD Form 203A and PWD Form Design and Built

    6/16

    According to table 1; PWD DB. form, there is no consultant party which directly would

    be employed by the client. In fact, the client employs the contractor to design and build which

    means the consultant is included in the package of the contractor. Therefore the design

    leadership, design management, administration team and site inspector roles are under

    contractors responsibilities. The contract management is the method in use in PWD DB. The

    contract manager controls, monitors and maintains the project since the earliest stage of a

    project.

    One of the benefits for the client is that the client does not have to be so active during the

    project, because most of the responsibility of the project is allocated to the contractor (Sderberg

    1993). Architect (management function), consultant team manager, design manager, architect

    (design function), engineer, consultant, contract administrator, supervising officer, planning

    supervisor, project administration, clerk of work are the roles involved in consultant which are

    the subordinates of contract manager. In PWD DB the contractor is compensated for all costs

    incurred. Also failing such deductions will be recovered from the performance bond or as a debt

    from contractor. Identifying and controlling (by avoiding or minimizing) the risks to a project is

    a vital part of managing it. This includes those risks that have been transferred to the contractor

    under PWD DB contract. The reason of popularity for using this type of contract is that the client

    does not take the risk as much as the contractor has.

    Hence the contractor consists of a contract manager to control over the cost and time. However

    in PWD 203A the client employs consultant separately which is directly linked. In this type of

    contract there is a separation of construction and design. There is a designing team, which is

    contracted by the client, and they shall provide the contractor with a complete design (Ashworth

    1991). The contractor subordinates include executive director who is the person in charge at site

    for complementation. Any problem happens during project development or any difference

    between designed and built documents in details, the executive director informs the superior and

    handles all.

  • 7/22/2019 Comparison Between PWD Form 203A and PWD Form Design and Built

    7/16

    The executive director includes site supervisor, quantity surveyor and safety officer who occupy

    positions at the site of construction. The quantity surveyor monitors all required materials

    quantities, proper cost and suggests to the client. The site supervisor manages all works, workers,

    daily reports (site dairy) and the quality of work. Arranging the masonries, material maintenance

    and all machines installation are the site supervisors responsibilities. In occurrence of a

    problem, they refer to the project manager for handling. The different method of organizing and

    maintaining the project is used in PWD 203A which is project management.

    The project manager controls and monitors the work through schedule of planning during

    constructing. The important aspect in PWD 203A is bills of quantities. Therefore the contractor

    has the responsibility to complete the work according to the requested quantities referred to the

    contract documents. In PWD 203A the government is entitled to deduct such costs, expenses and

    on-cost charges or any part from any monies due to the contractor or to recover it from

    performance bond as debt due from the contractor. That is the reason of being popular for this

    type of contract for government sector in Malaysia.

  • 7/22/2019 Comparison Between PWD Form 203A and PWD Form Design and Built

    8/16

    1.3 Categories of Comparison

    In this report, the comparison will be carried out based on these categories:

    1. Parties who involves in payment2. Type of payment3. Interim payment stages statement4. Advance payment5. Procedure of Interim Payment6. Schedule of issuing interim certificates7. Requirement upon issuing interim certificates8. Contractors obligation in applying payment9. Procedure of payment upon completion10.Wages of workmen affects the final payment11.Retention fund/performance bond12.Payment for liquidated damages13.Payments upon termination14.Performance bond15.Direct payment to the third party16.Late payment by government/employer

  • 7/22/2019 Comparison Between PWD Form 203A and PWD Form Design and Built

    9/16

  • 7/22/2019 Comparison Between PWD Form 203A and PWD Form Design and Built

    10/16

    8 Contractors

    obligation in applying

    payment

    To make a works is done and SP

    can make a valuation

    1. The value of works done andproperly executed

    2. The amount on any valuationof variations or the

    instructions by the PD

    (clause 24

    3. The amount in regard to theexpenditure of provisional

    sums executed or expended

    (clause 25)

    4. The value of any goods orunfixed materials delivered

    to or adjacent to the site

    intended for use or to be

    incorporated into the works

    5. The upervision reports asrequired by the PD under

    clause 13.1

    9 Procedure of paymentupon completion

    1.

    Within 3 month after theissuance of the certificate of

    practical completion, the

    contractor shall submit

    application to enable the final

    account prepared by the SO.

    If contractor failed, SO shall

    forthwith make the

    assessment based on available

    document for the final

    account

    1.

    Within 3 month afterissuance of the certificate of

    completion of making good

    defects or the certificate of

    completion of maintenance

    (if any), Contractor shall

    submit to PD a statement of

    the final account showing in

    detail the value

  • 7/22/2019 Comparison Between PWD Form 203A and PWD Form Design and Built

    11/16

    2. Within 3 months after theexpiry of the defects liability

    period for the whole of the

    works or 3 month after the

    issue of the certificate of

    completion of making good

    defects under clause 48

    hereof, SO shall issue the

    final certificate that consists

    of supported documents, full

    particulars complete with

    receipt, vouchers, final

    valuation, any amount

    determined in clause 31.1

    3. Final payment is paid by thegovernment to the contractor.

    Final payment will not be

    paid unless the contractor

    satisfied the SO in hisobligation due to the

    workmen

    2. PD proceed to verify the finalaccount based on the

    document which is given by

    contractor

    3. If final account is verified,PD shall issues Final

    certificate which consists of

    balance sum

    4. Final payment is paid by thegovernment to the contractor.

    Final payment will not be

    paid unless the contractor

    satisfied the SO in his

    obligation due to the

    workmen

    10 Wages of workmen

    affects the final

    payment

    Wages of all the workmen has to

    be paid and all contributions

    under the Employment Act 1955,

    The Employee;s Social Security

    act 1969, The Employees

    provident Fund Act 1991 and any

    other laws relevant to the

    employment of workmen have

    been paid.

    Wages of all the workmen has to

    be paid and all contributions

    under the Employment Act

    1955, The Employee;s Social

    Security act 1969, The

    Employees provident Fund Act

    1991 and any other laws relevant

    to the employment of workmen

    have been paid.

  • 7/22/2019 Comparison Between PWD Form 203A and PWD Form Design and Built

    12/16

    11 Retention fund No retention fund is applied in

    government standard form.

    No retention fund is applied in

    government standard form.

    12 Payment for

    liquidated damages

    If the contractor fails to complete

    the works by the date for

    completion or within any

    extended time granted pursuant to

    clause 43, the SO shall issues a

    certificate of non completion to

    the contractor and notice the

    intention of the Government to

    impose liquidated and ascertained

    damages that stated in appendix.

    If the contractor fails to complete

    the works by the date for

    completion or within any

    extended time granted pursuant

    to clause 49, the PD shall issues

    a certificate of non completion to

    the contractor and notice the

    intention of the Government to

    impose liquidated and

    ascertained damages that stated

    in appendix.

    13 Payment upon

    termination

    Base on reasonable valuation. If

    contract is terminated under

    clause 50 and 52, the amount to

    be paid (in so far as such amounts

    or items have not already been

    covered by payments on accountmade to the contractor) shall be

    the following:

    a. The value of all work carriedout up to the date of

    termination

    Base on reasonable valuation. If

    contract is terminated under

    clause 50 and 52, the amount to

    be paid (in so far as such

    amounts or items have not

    already been covered bypayments on account made to the

    contractor) shall be the

    following:

    a. The value of all work carriedout up to the date of

    termination

  • 7/22/2019 Comparison Between PWD Form 203A and PWD Form Design and Built

    13/16

    b. The amounts payable inrespect of any preliminary

    items so far as the work of

    service comprised therein has

    been carried out or performed

    and a proper proportion of

    any such items which have

    been partially carried out or

    performed

    c. The cost of materials or goodsreasonably ordered for the

    works which have been

    delivered to the contractor or

    of which the contractor is

    legally liable to accept

    delivery

    d. A sum being the amount ofany expenditure reasonably

    incurred by the contractor inthe expectation of completing

    the whole of the works in so

    far such expenditure has not

    been recovered by any other

    payments

    e. The reasonable cost of anyprotection works and removal

    of equipment and site

    facilities pursuant to

    termination as provided under

    the contract.

    b. The amounts payable inrespect of any preliminary

    items so far as the work of

    service comprised therein

    has been carried out or

    performed and a proper

    proportion of any such items

    which have been partially

    carried out or performed

    c. The cost of materials orgoods reasonably ordered for

    the works which have been

    delivered to the contractor or

    of which the contractor is

    legally liable to accept

    delivery

    d. A sum being the amount ofany expenditure reasonably

    incurred by the contractor inthe expectation of

    completing the whole of the

    works in so far such

    expenditure has not been

    recovered by any other

    payments

    e. The reasonable cost of anyprotection works and

    removal of equipment and

    site facilities pursuant to

    termination as provided

    under the contract.

  • 7/22/2019 Comparison Between PWD Form 203A and PWD Form Design and Built

    14/16

    14 Performance bond If the contractor fails to performs

    any of his obligations under the

    contract and such failure is non

    remedied in accordance with this

    contract, the government shall be

    entitled to call upon the

    performance bond, wholly or

    partially.

    The performance bond may be

    released or refunded to the

    contractor upon the completion of

    works.

    If the contractor fails to performs

    any of his obligations under the

    contract and such failure is non

    remedied in accordance with this

    contract, the government shall be

    entitled to call upon the

    performance bond, wholly or

    partially.

    The performance bond may be

    released or refunded to the

    contractor upon the completion

    of works.

    15 Direct Payment to the

    third party

    Government shall paid the

    nominated sub

    contractor/suppliers according to

    interim certificates/final

    certificates

    Applied in direct payment to the

    contractors consultants. Forthe

    purpose of payment to the

    consultant, the contractor and the

    consultant shall enter an

    irrevocable Deed of Assignment

    for the assignment of any moneydue to the consultant to be paid

    directly by the government.

    16 Late payment by

    employer/government

    No provision No provision

  • 7/22/2019 Comparison Between PWD Form 203A and PWD Form Design and Built

    15/16

    Conclusion

    In conclusion, the main differences in construction contract are the extent to which the

    client is responsible for the management of the project, risk allocation and the internal

    responsibilities of the project members. According to the comparison which is given above, the

    roles link are depended on the type of contract and it would lead the liabilities and risk to the

    parties. In PWD DB, contractors responsibilities vary from PWD 203A. The contractors

    responsibilities in PWD DB are the design leadership, design management, administration team

    and site inspection roles.

    The traditional contractual arrangement sets out the legal relationship the parties wish to

    establish and the rights, obligations and procedures for resolving contractual disputes .There are

    several factors that affect what type of contract is suitable for a certain project such as the

    amount of involvement from the client, the location of the project, technical complexity.

    The project manager controls and monitors the work through schedule of planning during

    constructing.

    The trend of the faster development of the construction industry in Malaysia make Design &

    Build contract more familiar and efficient because it may avoid the delay in completing the

    project. The increasingly of complex projects, and the search for quicker and cheaper solutions

    and achievement of value for money will influence the need for new organisational and

    management methods. This will have a positive influence in terms of the integration of main

    project stakeholders and phases, as well as the ultimate success of the entire construction project.

    In an initial stage of the design phase, the client has to adopt a suitable contractual arrangement

    for the project and a corresponding standard form of contract in order to attain the proper

    management and organization in project.

  • 7/22/2019 Comparison Between PWD Form 203A and PWD Form Design and Built

    16/16

    References

    Malaysian Construction and Contract Law, Retrieved from

    http://simplymalaysia.wordpress.com/standard-forms-of-contract/domestic-standard-contract-

    forms/p-w-d-form-of-contract-203-2007/

    Determination Of Contractors Employment UnderPWD 203a (Rev. 2007) And PAM2006 Standard

    Forms Of Contract Retrieved from

    http://fab.utm.my/files/2012/07/ThesisUGBQS2010ChenKianMun.pdf

    http://simplymalaysia.wordpress.com/standard-forms-of-contract/domestic-standard-contract-forms/p-w-d-form-of-contract-203-2007/http://simplymalaysia.wordpress.com/standard-forms-of-contract/domestic-standard-contract-forms/p-w-d-form-of-contract-203-2007/http://simplymalaysia.wordpress.com/standard-forms-of-contract/domestic-standard-contract-forms/p-w-d-form-of-contract-203-2007/http://fab.utm.my/files/2012/07/ThesisUGBQS2010ChenKianMun.pdfhttp://fab.utm.my/files/2012/07/ThesisUGBQS2010ChenKianMun.pdfhttp://fab.utm.my/files/2012/07/ThesisUGBQS2010ChenKianMun.pdfhttp://simplymalaysia.wordpress.com/standard-forms-of-contract/domestic-standard-contract-forms/p-w-d-form-of-contract-203-2007/http://simplymalaysia.wordpress.com/standard-forms-of-contract/domestic-standard-contract-forms/p-w-d-form-of-contract-203-2007/