comprehensive campus energy master plan final … of replacement and expansion options ... •...
TRANSCRIPT
Comprehensive Campus Energy Master Plan
Final Presentation
December 2014
Presentation of Energy Master Plan
• Review individual utilities systems
• Future growth impact
• Recommendations
• Follow up of sustainability goals and projections discussion
• Implementation plan
Comprehensive Campus Energy Master Plan
1. Develop a thorough understanding of existing utility systems – Reliability limitations – Efficiency – Capital renewal requirements
2. Evaluation of replacement and expansion options – Future campus growth – Life cycle cost analysis and comparison – Feasibility assessment (operational, sustainability, etc…)
3. Implementation plan – A utility project list synchronized with the 10-year campus plan – A schedule of funding requirements – A benchmark of current efficiencies with future milestones
Summary of Campus Energy Challenges
• Fiscal Year 2014 – Natural gas* 1,700,000 Million Btu’s $16.4 M/yr – Liquid natural gas 194,000 Million Btu’s $4.6 M/yr – Oil 96,000 Million Btu’s $2.4 M/yr – Electric Purchased 150,000 Million Btu’s $6.0 M/yr TOTAL 2,140,000 Million Btu’s $29.4 M/yr
* Includes fuel for on-site cogeneration
• Utility infrastructure is a significant asset (value ~$800 M)
• Campus operations rely upon uninterrupted utility services
• Goals to reduce energy use, fuel costs and carbon footprint
• Need to support future expansion
1,690,000 Million Btu’s
150,000 Million Btu’s
80,000 Million Btu’s
150,000 Million Btu’s
Review of Campus Energy System
LNG
Oil
Natural Gas
Regional Power Supply
Regional Fuel Supply Capacity Cost Carbon emissions
Distribution Capacity Reliability Efficiency
District CHW
Plants
Generation Plants / Utility Supply Capacity Reliability Efficiency Balance energy
CEP (cogeneration)
Electric Substation
(~33% of site load)
Steam
Electric
Chilled Water
Buildings • Heating • Electric • Cooling
Future Planning
• Near Term (2014-2022) – 2012-2021 Capital
Improvements Projects – Input from Design &
Construction Management and Campus Planning
• Long Term(>2022) – Campus Master Plan
Campus Planning (Near Term)
• 1.2 M sf of net new growth – 60% Academic – 10% Lab – 5% Assembly – 25% Parking
Campus Planning (Long Term)
• Near Term (2014-2022) – 1.2 M sf of net new growth
• 60% Academic • 10% Lab • 5% Assembly • 25% Parking
• Long Term (>10 years) – 5.7 M sf of new growth
• 60% Academic • 5% Lab • 25% Assembly • 10% Parking
Steam Generation System HRSG 100
BOILER NOS. 200, 300, 400
• Boiler Capacity
• Turbine Summary
HRSG/Boiler
No.
Boiler Capacity
(pph)
Firm Capacity
(pph) Second
Fuel
100 100,000 100,000 ---
200 125,000 --- Diesel
300 125,000 125,000 Diesel
400 125,000 125,000 Diesel
Total 475,000 350,000 ---
Turbine No. Turbine Type
Capacity (kW)
G-1 Comb. Turb. 10,000
STG-1 Steam Gen. 2,000
STG-2 Steam Gen. 4,000
Total --- 16,000
Space for
Future Capacity
• On Site Fuel Storage Fuel Type
Capacity (gal) Comment
LNG 36,000 Short Term
72,000 Space For Add.
Fuel Oil 500,000
Existing Steam Fuel Use Profile Becauseof pipeline limitations burning LNG and Diesel increases annual fuel costs by ~ $4.7 million based on current load profile.
Near Term Steam Load
Long Term Future Growth
Option Consideration
• Install natural gas boiler • Install 8 MW combustion turbine
– W/ absorption chiller – W/ additional HP steam turbine
• Install 10 MW combustion turbine (new plant) – W/ absorption chiller – W/ additional HP steam turbine
• Install 12 MW combustion turbine (new plant) – W/ absorption chiller – W/ add. HP steam turbine
• Install biomass (new plant) – Just to replace secondary fuel usage – Base loaded boiler
Steam Generation Options - Annual
Opt No. Description
Capital Costs ($M)
Annual Costs
($M/yr)
Present Value ($M)
Total Energy
(MMBtu/YR)
Regional Energy Equiv.
(MMBtu/YR)
CO2 Savings
(TPY)
1 Install N.G. Boiler 10.8 26.8 555 2,260,000 2,520,000 ---
2A 8 MW CT 34.8 23.5 532 2,290,000 2,350,000 3,600
2B 8 MW CT W/ Abs 35.8 23.5 532 2,290,000 2,350,000 3,600
2C 8 MW CT W/ STM TURB 37.9 23.4 534 2,290,000 2,350,000 3,800
3A 10 MW CT 55.3 23.9 555 2,360,000 2,400,000 300
3B 10 MW CT W/ Abs 56.2 23.9 555 2,360,000 2,400,000 300
3C 10 MW CT W/ STM TURB 58.3 23.8 557 2,360,000 2,400,000 400
4A 12 MW CT 61.3 23.6 557 2,360,000 2,390,000 800
4B 12 MW CT W/ Abs 62.2 23.6 552 2,360,000 2,390,000 800
4C 12 MW CT W/ STM TURB 64.3 23.6 559 2,360,000 2,390,000 900
5A Biomass (60 KPPH) 44.0 27.5 593 2,350,000 2,620,000 400
5B Biomass (60 KPPH Base) 44.0 26.5 581 2,420,000 2,690,000 34,000
5C Biomass (100 KPPH) 68.1 26.3 599 2,490,000 2,750,000 51,800
With Pipeline Limits
Opt No. Description
Capital Costs ($M)
Annual Costs
($M/yr)
Present Value ($M)
Total Energy
(MMBtu/YR)
Regional Energy Equiv.
(MMBtu/YR)
CO2 Savings
(TPY)
1 Install N.G. Boiler 10.8 30.9 613 2,260,000 2,520,000 ---
2A 8 MW CT 34.8 27.9 594 2,290,000 2,350,000 3,500
2B 8 MW CT W/ Abs 35.8 27.9 594 2,290,000 2,350,000 3,500
2C 8 MW CT W/ STM TURB 37.9 27.8 595 2,290,000 2,350,000 3,700
3A 10 MW CT 55.3 28.5 620 2,360,000 2,400,000 100
3B 10 MW CT W/ Abs 56.2 28.7 623 2,360,000 2,400,000 100
3C 10 MW CT W/ STM TURB 58.3 28.7 625 2,360,000 2,400,000 100
4A 12 MW CT 61.3 28.4 623 2,360,000 2,390,000 600
4B 12 MW CT W/ Abs 62.2 28.4 623 2,360,000 2,390,000 600
4C 12 MW CT W/ STM TURB 64.3 28.4 626 2,360,000 2,390,000 600
5A Biomass (60 KPPH) 44.0 31.5 649 2,350,000 2,620,000 500
5B Biomass (60 KPPH Base) 44.0 27.5 595 2,420,000 2,690,000 39,200
5C Biomass (100 KPPH) 68.1 26.5 605 2,490,000 2,750,000 53,000
Steam Generation Recommendation
• Recommendation (if New Gas Pipe Line is Available) – Install 8 MW combustion turbine (Economics and reliability)
• Natural Gas Pipe Line Contingency Plan – Install second phase on LNG storage – Determine the value of carbon reduction – 8 MW combustion turbine option is preferred pending value of
carbon reduction
Steam Distribution System • Distribution:
– 8,700 LF Walkable tunnel – 7,000 LF Trench – 35,000 LF Direct buried piping
• Piping condition – 65% Good condition (46,700 LF) – 20% Fair condition (14,800 LF) – 15% Poor condition (9,300 LF)
• Steam efficiency – Estimated distribution loss 15%
(Representative of piping condition) – 70% of steam generated is utilized
by building
Steam Distribution System • Distribution:
– 8,700 LF Walkable tunnel – 7,000 LF Trench – 35,000 LF Direct buried piping
• Piping condition – 65% Good condition (46,700 LF) – 20% Fair condition (14,800 LF) – 15% Poor condition (9,300 LF)
• Steam efficiency – Estimated distribution loss 15%
(Representative of piping condition) – 70% of steam generated is utilized
by building
Near Term Distribution Analysis
720 LF 2 BLDG 7,500 PPH
780 LF 3 BLDG 8,550 PPH
4,850 LF 27 BLDG 32,500 PPH
1,800 LF 11 BLDG 1,270 PPH
940 LF 20 BLDG 31,290 PPH
• Existing distribution can support near term growth – Piping needed to connect
future buildings
• Opportunities to improve reliability – Strategic pipe segments for
redundancy – Medium pressure and low
pressure augmentation stations
Chilled Water System
• Existing system summary – 7 District chiller plants – 12 Individual cooling systems
• Chiller summary – 13,280 tons of W/C – 5,730 tons of absorption – 930 tons of A/C – 19,940 tons Total
• Chiller age – 11,810 tons of 0-10 years – 2,550 tons 11-20 years – 5,580 tons > 20years – 600 Ton utilize CFC or HCFC
Energy for chilled water generation represents ~10% of the total building energy use
Existing Chilled Water Capacity
13,800 tons: Total Load (Incl. Indiv. System) 19,940 tons: Total Chiller Capacity
District Name
Peak Load
(Tons)
Total Chiller
Capacity (Tons)
Chiller Firm
Capacity (Tons)
Available Capacity
(Tons)
ISB* 3,400 5,650 4,150 750
Polymer* 2,270 2,620 1,720 -550
LGRC* 1,440 1,550 900 -540
Whitmore 1,150 1,550 1,150 ---
Honors 1,350 1,900 1,400 50
Mullins 320 1,300 650 330
* Research / Lab facilities
Near Term Chilled Water Capacity
District Name
Replace Aging Chillers
& Ex. Redundancy
(Tons)
Chillers for New
Buildings (Tons)
Chillers to add ex.
Buildings to Districts (Tons)
Total New Chiller
Capacity (Tons)
ISB 390 970 --- 1,360
Polymer 3,560 420 1,270 5,250
LGRC 540 --- --- 540
Whitmore --- --- --- ---
Honors --- --- --- ---
Mullins 1,300 --- --- 1,300
New Library 340 290 520 1,150
Indiv. System 880 3,550 --- 4,430
Total 5,480 5,230 1,790 14,280
Future near term chilled water load 20,180 tons (potential) Continue to use 14,360 tons of existing chiller capacity through near term
Future Chilled Water System Options
• Potential future options – District CHW system (status quo) – Central chilled water plant – Indiv. system for future only
• Chiller generation options – Electric centrifugal – Steam driven chiller
• Absorption • Steam turbine
– Thermal Energy Storage • Chilled water storage • Ice storage
Individual District Comparison
Advantages to District System • Facilitates dispatch of select units
to manage load profile • Reduces cooling tower water
treatment • Reduces appearance of industrial
equipment on campus • Facilitates winter cooling • Extends equipment life and
reduces unplanned outages by continually monitor equipment functions
• Reduces equipment repair costs through fewer units centrally located
• Reduces building electrical requirements allowing existing electric feeders to be re-allocated
Recommended District Site Plan
Cost to centralize entire campus ~$50 M, with an annual savings of $700,000 per year.
Existing Electrical Main Substation
• 26.1 MW campus peak load in September 2013 – Maximum power
generation 16 MW – Current utility feeder firm
capacity is 27 MW • 37.0 MW campus peak at
near term growth – Lab space – Data center – Cooling for building not
currently air conditioned – Tillson Farm Substation
Tillson Farm Substation
• New High Voltage Substation
• New Feeders to existing switch stations – (2) 14.3 MW Feeders to
each Switch Station – Firm capacity 42.9 MW
Existing Campus Feeder Capacity
Future Campus Feeder Capacity
Transfer Feeder Loads
Opt 1 Increase Feeder Capacity
Option No. 1 - Larger Feeders
Opt 2 – New North Switch Station
Option No. 2 – New North Switch Station
Electrical Option Comparison
Top 20 Building Unitary Energy Use
Total Energy Consumed by Top 50 Bldgs
Campus Wide Energy Conservation Average Energy Reduction per Building
Dynamic System Operation
LNG
Oil
Natural Gas
Regional Power Supply
District CHW
Plants
Steam
Electric
Chilled Water
BUILDING LOAD
PROFILES
Renewables
33% of total electric load
Renewables
Cogeneration System
(70% efficient)
Are buildings operating efficiently?
Which renewable energy systems are cost effective?
Will there be times when grid power is cheaper then cogen power?
When is cost effective to operate absorption cooling?
Some Variables: Renewable fuels cost Electric Rate Gas Rate Load Profile
Management & Flexibility
LNG
Oil
Natural Gas
Regional Power Supply
District CHW
Plants
Steam
Electric
Chilled Water
BUILDING LOAD
PROFILES
Renewables
Real-time Campus-wide Energy Management System
33% of total electric load
Utility Rates
Building Operation
Site Loads
Steam or Electric
Cogen Operation
Renewables
Cogeneration System
(70% efficient)
Load Management Summary
• Reduce Existing Building Energy Use 177 Kbtu/gsf – At least 5% to 10% energy reduction possible
• A 10% site energy reduction is an average of 20% reduction for top 25 buildings (~$25 Million in capital)
• Capital renewal projects could reduce energy use another 5%
• Coordination of the existing energy rates with ongoing DCAMM study is crucial
• Load management projects would include…
• Steam Distribution Improvements
• Chilled Water Capital Renewal
• Chilled Water System Optimization
• Load shifting (thermal storage)
• Building Design Enhancements
• Building Energy Conservation Measures
• Renewable Energy Systems
• Alternative Technologies
Renewable Projects (PPA)
• ~8.0 MW Solar Project – Parking lots – Rooftops – Off Site
• Anaerobic Digester
Sustainable UMass
• Executive Order 484 – Directives – Energy Related Targets
• Energy Use (Kbtu/sf) • Greenhouse Gas Emissions (absolute basis) • Renewable Power Purchasing
• UMass Challenges – Future Campus Development (through 2022)
• 12% increase in area results in a 26% increase in load – 29% increase in lab area – 12% increase in air conditioning for existing buildings
– Many of the cost effective Energy Conservation Measures have been performed
– Executive Order 484 Accounting
164
155
131 135 133 126 123
136
125 128 131
140 142 143 141 138 136 136 138
0%
6%
20% 18% 19%
23% 25%
17%
24% 22% 20%
15% 13% 13% 14% 16% 17% 17% 16%
-
20
40
60
80
100
120
140
160
180
FY04 FY05 FY06 FY07 FY08 FY09 FY10 FY11 FY12 FY13 FY14 FY15 FY16 FY17 FY18 FY19 FY20 FY21 FY22
Ener
gy U
se (m
easu
red
at th
e bu
ildin
g) K
Btu/
sf
Historical Energy Use at the Buildings
Executive Order 484 Energy Target 2 35% Reduction by Fiscal Year 2020 (based on Fiscal Year 2004)
Currently there are no cost effective means to achieve Target 2
Does not include fuel use for on-site power generation
Master Plan Projects
-
20
40
60
80
100
120
140
160
180
200
2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
KBtu
/yr/
gsf Executive Order 484 Target
Net Campus Energy Use
Campus Energy Use (w/ Cogeneration) • Based on Total Campus Energy Use (electric and fuel)
Campus Energy Use with Regional Credit
Projects TBD
Solar PV (Regional)
Cogen (Regional)
Master Plan Projects
-
20
40
60
80
100
120
140
160
180
200
2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
KBtu
/yr/
gsf Executive Order 484 Target
Net Campus Energy Use
Campus Energy w/ Regional Savings
Equivalent Carbon Emissions
-
20,000
40,000
60,000
80,000
100,000
120,000
140,000
160,000
180,000
200,000
Met
ric To
nnes
per
yea
r
Campus Efficiency
Solar PV
Additional Reductions Needed to MeetEO484
Executive Order 484 Target
~34,000 TPY short of the target in Fiscal Year 2020
Carbon Emissions on a per SF Basis
-
2.00
4.00
6.00
8.00
10.00
12.00
14.00
16.00
18.00
20.00
2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
Tonn
es p
er p
er 1
000
gsf/
yr
Campus Efficiency
Solar PV
Additional Reductions Needed to Meet EO484
Executive Order 484 Target
Executive Order 484 Plan
• Establish that the existing targets as stated cannot be achieved with cost effective projects
• Identify cost implications for not complying with Executive Order 484 targets as currently written
• Develop a standard approach for comparison of projects that are not self-funding
• The initial framework of the plan can be established in the Energy Master Plan
• Review with state agencies
Sustainability Message Board
Sustainability – Flat Screen Display
Schedule / Implementation Plan
RISK AND POTENTIAL LOST OPPORTUNITY
Summary
• Campus growth projected 12% over the next 8 years • Projected $190 million identified in utility projects to address
– Reliability – Efficiency
• Sustainability – Develop a plan to address Executive Order 484 and establish
sustainability goals – Recognize all previous campus efforts – Develop the process to prioritize projects to meet sustainability
goals
Additional Slides for Questions
Difference in Energy Accounting
UMass Amherst
Regional Power Plant
Fuel
Fuel
Electric
UMass Amherst
Regional Power Plant
Fuel
Fuel
Electric
Local Regional
Solar Solar
Recommended Redundancy Guideline
Building or System Type Heating Cooling Electric
Laboratory/Research 100% 100% 100%
Academic 100% 100% 100%
Administrative 100% 100% 100%
Residence / housing 50% 50% 100%
Support 0% 0% 100%
District / Central 100% 100% 100%
Notes: 100% - refers to one full standby unit or service 50% - refers to two units each sized at 75% of the load 0% - refers to capacity sized for system peak load
Utility Feeder Capacity
Switch Station Description
Total Capacity (MW)
West Feeder Outage (MW)
East Feeder Outage (MW)
West Feeder 18G1 14.3 --- 14.3
Feeder 18G2 14.3 14.3 14.3
East Feeder 17K3 5.0 5.0 5.0
Feeder 17K7 8.0 8.0 ---
Total --- 41.6 27.3 33.6