condition monitoring - new initiative in cesc

Upload: saikatchoudhuri

Post on 03-Jun-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/13/2019 Condition Monitoring - New Initiative in CESC

    1/10

    Condition Monitoring:New Initiative in CESC

    &

    A Case Study on 6 / 11 kV RMU

    A Report prepared by CESCs Core Team associated with Singapore Power

  • 8/13/2019 Condition Monitoring - New Initiative in CESC

    2/10

    Condition Monitoring: New Initiative in CESC

    Condition Monitoring is the process of monitoring some Key parameters of the equipment, such

    that a significant change in the value of the parameter can provide information regarding the

    deteriorating health of the equipment. It involves either continuous or periodic assessment of the

    condition of a plant/equipment component while it is in operation.

    The main objectives for the condition monitoring can be listed asa) Prediction of faultsb) Diagnosis of faultsc) Enhanced safety at work place4) Less down time

    5) Better inventory management

    Singapore Power recommended CESC to adopt condition monitoring of equipment as the key

    measure to prevent failure. The same will enable the health of the network elements to be

    monitored regularly and its status kept updated.

    The CESCs Core Team associated with Singapore Power along with a set up of five engineers

    from Mains, Testing and Sub-Station Departments started Condition Monitoring exercise from

    April09 and so far has covered condition assessment of all the indoor switchgears of Receiving

    Stations, Sub-Stations and Distribution Stations and also all the downstream network elements of

    around 100 nos of fault prone 6/11 KV Feeders.

    Condition monitoring technique includes detection of partial discharge (PD) using acoustic

    technique and Transient Earth Voltage (TEV) measurements using PDL (Partial Discharge

    Locator).

    Ultraprobe Partial Discharge Locator (PDL)

  • 8/13/2019 Condition Monitoring - New Initiative in CESC

    3/10

    A. The Ultraprobe translates the high frequency noise developed due to arcing, tracking and

    corona into the audible ranges. Electrical discharges are heard as a cracking or buzzing

    sound.

    B. The Partial Discharge Locator (PDL1) uses the technique of Transient Earth Voltage

    (TEV) measurement: When the PD occurs, electromagnetic waves propagate away from

    the discharge site and a very small quantity (pico-coulombs) of electrical charge is

    transferred (in a few nanoseconds) capacitively from the high voltage conductor system to

    the earthed metal-cladding. At an opening in the metal cladding such as through gaskets,

    the electromagnetic waves propagate out into free space. The wave then generates a

    transient earth voltage on the metal surface. Two probes are used to accurately locate the

    discharge site.

    The Condition monitoring exercise will set up condition based maintenance technique for

    different groups of equipments that range from purely reactive to reasonably planned. The

    deep down root cause analysis of each finding may also suggest changes in design of

    equipments and the work practice to a great extent to arrest similar failures in future.

    A Case Study on 6/11 kV RMU

    We have so far covered online Condition Monitoring on 383 nos of RMUs of different make

    in 6/11 kV downstream network where Partial Discharge (PD) were observed at 23

    locations with varying degree of measurements starting from 2 dB to a maximum of 42 dB.

    Subsequently on thorough examination of such affected equipments with high PD, we

    gather significant knowledge particularly on the deficiencies in the design criteria.

    Appropriate remedial measures against such defects will not only rectify these definite

    potential failures but will also arrest similar occurrences which otherwise would have been

    cropped-up in future.

    The details of the findings, analysis and remedial actions are mentioned in this report.

  • 8/13/2019 Condition Monitoring - New Initiative in CESC

    4/10

    Partial Discharge as Detected in RMUs at Different

    Voltage Level till Oct-2009

    11KV 6KV

    Make Nos

    >10dB 10dB

  • 8/13/2019 Condition Monitoring - New Initiative in CESC

    5/10

    Findings

    Out of total 23 cases 17 were detected Partial discharge in AREVA RMU i.e.74% of total

    detection

    The balance 6 cases are ABB RMU, where except one all others(5) are having measuredfor very low noise (10dB and maximum 42 dB)

    Maximum PD was observed outside the cable chamber of AREVA RMU

    Thorough Investigations were carried out at the following 5 installations

    Investigation of AREVA RMUs where high PD were detected :

    LOCATION PD Measured Voltage levelMake of Cable

    Boot

    AREVA RMU at Anandapur O/T 41 11 kV 3M

    AREVA RMU at Calcutta Green O/T 1 42 11 kV 3M

    AREVA RMU 1 at Survey park T/H 5 30 11 kV 3M

    AREVA RMU 2 at Survey park T/H 5 42 11 kV 3M

    AREVA RMU 1 at Ruby General

    Hospital 42 11 kV 3M

  • 8/13/2019 Condition Monitoring - New Initiative in CESC

    6/10

    Observations During further investigation:

    1. Sound level as detected at these locations are on the high side and in the tune of 30-42

    dB and continuous in nature

    2. Partial Discharge generation were pin-pointed at the cable termination

    3. All these RMUs are provided with 3M make Cable Termination Boots

    4. Black marks (tracking)on the outer surface of cable boots and also on the inside wall of the

    cable chamber

    5. Colour of boots changed to greenish with sticky solutions on the outer surface

    6. Inter-phase boots are found touching each other

    Photographs

    Fig -1 : Fig-2 :

    AREVA RMU with 3M Boot Tracking on outer surface of the 3M Boot

    Fig-3: Fig-4:

    Colour of cable boots changed to greenish with sticky solutions on the outer surface

  • 8/13/2019 Condition Monitoring - New Initiative in CESC

    7/10

    Fig-5 : Fig-6:

    Black spots on the side wall of Cable Chamber

    Fig-7: Fig-8:

    Inter-phase boots touching each other in AREVA RMU Cable Chamber

  • 8/13/2019 Condition Monitoring - New Initiative in CESC

    8/10

    Comparative studies of AREVA & ABB RMU having 3M Boots

    AREVA RMU ABBRMU

    HIGH PD DETECTED NO PD DETECTED

    Fig-9: Fig-10:

    Inter-phase boots touch each other Gap exists between inter-phase boots

    Comparative studies of Raychem & 3M Boots on AREVA RMU

    Fig-11: Fig-12:

    AREVA RMU with Raychem boot AREVA RMU with 3M boot

    Analysis

  • 8/13/2019 Condition Monitoring - New Initiative in CESC

    9/10

    1. ForABB RMU gap between bushing centre to centre is 107 mm creates an air insulation of

    approx 10 12 mm with 3M Boots.

    2. For ABB RMU even with 3M make Boots, no abnormal noise was detected in such

    arrangement

    3. For AREVA RMU gap between bushing center to center is 95 mm, Hence 3M Boots are

    touching each other.

    4. For AREVA RMU with Raychem make Boots, a small gap exists between the Boots of

    different phases.

    5. For AREVA RMU with Raychem make Boots no abnormality was detected

    6. Connections at the terminating point on bushings are bare (without any insulation covering

    i.e. Tape etc.) inside the boots. The charges due to induced voltage surrounding the

    termination points accumulate more on the surface of the boots.

    7. Since the adjacent cable bushings are also affected by the induced voltages at different

    phase potentials, this difference in potential leads to discharges on the surface of two

    adjacent boots resulting in carbonizing of the local area. Black spots are produced due to

    the concentration of electric charges.

    8. The above phenomenon gradually increases the tracking on the boots & generates more

    discharges.

    9. These types of problems are not noticed in 6kV systems since the induced voltages across

    the bushings are comparatively less than 11kV systems to cause discharges.

  • 8/13/2019 Condition Monitoring - New Initiative in CESC

    10/10

    Remedial Action Plan

    Phase-1: Henceforth All AREVA RMUs are to be commissioned (both for 6 & 11 KV) with

    Raychem make Boots instead of 3M make Boots

    Phase-2: AREVA RMUs charged at 11kv having detected high PD - All Terminal Protectors

    (Cable Boots) of 3M make are being replaced with Raychem make Boots.

    Phase-3: 3M make Cable Boots for all existing AREVA RMUs charged at 11KV are to be

    replaced with Raychem make Cable Boots.

    Periodic repeat measurements on these sites to ascertain the effectiveness of the

    above proposals

    Inference

    Condition monitoring exercise thus carried out above enabled us to diagnose the root cause of

    potential failure points in RMUs before occurrence of the actual failure which would have resulted

    severe damage and longer interruption of customer service. One most significant aspect of

    condition monitoring exercise is the root cause finding and taking appropriate corrective

    measures against the potential failure which would otherwise have remained probably

    undetected during post failure analysis.

    ------- -----------x-----------------------