conductor integrity management & solutions · 2018-02-12 · 1 safety integrity teamwork trust...
TRANSCRIPT
Safety Integrity Teamwork Trust
Conductor Integrity
Management &
Solutions
Delivering safe, reliable,
cost effective solutions to
the North Sea.
Contents 1. Late Life Asset Management
2. Conductors
3. Loadings
4. Internals
5. External
6. Integrity Issues
7. Integrity Issues (2)
8. Integrity Issues (3)
9. What were we dealing with?
10. Analysis
11. Approach by SETS
12. Rope Access Solution
13. Cleaning & Inspection
14. Repair Types
15. Remote Repair
16. Inspection & Install Tooling
17. No Vessel for Subsea Work
Safety Integrity Teamwork Trust
1
Safety Integrity Teamwork Trust
Late Life Asset Management
• > 150 Fixed Assets in the North Sea at
an average age of 18yrs +
• Beyond field life expectation
• Continued operation in a low $/bbl
environment
• Asset Integrity and Well / Asset Value
balance of utmost importance for
sustainability
• Highest Value Data, gained by
economic methods, allows a
sustainable Integrity management
system
Safety Integrity Teamwork Trust
8
Conductors 2
• Asset structural component
• Well load sharing
• Implications for well integrity management
• Environmental sheathing for well casings
• Corrosion protection for surface casing
• Run during early phase operations
• Robust design has permitted field life
extension
• Not necessarily fit for purpose for late life
operations
Safety Integrity Teamwork Trust
8
Loadings 3
In service, the conductor is subject to:
• Environmental loading due to waves
and currents
• Impact loads due to contact with
conductor guides
• Operational loads (BOP weight during
work‐over scenarios)
• Corrosive environments
Safety Integrity Teamwork Trust
8
Internals 4
• Annuli contents will vary and may not
be understood, especially in older wells
• Surface casing (generally) carries well
load across underwater zone
• Load sharing can be complex and
affected by deterioration of conductor
• Casing integrity – implications for well
barriers to maintain safe operations
Safety Integrity Teamwork Trust
8
External 5
Conductors
• Standard heavy walled pipe, typically
26” - 32” diameter
• Spanning between horizontal guide
frames
• Joint connector integrity. Older asset
connectors susceptible to corrosion and
low fatigue life
• Connector structural capacities of
considerable importance
6
Safety Integrity Teamwork Trust
Integrity Issues
A few of our favourite things:
• Fretting at guides
• Internal corrosion (@LAT)
• External corrosion (at connectors)
• Connector integrity
• Casing integrity
• Poor subsea inspection
• Poor data management
7
Safety Integrity Teamwork Trust
Integrity Issues (2)
1) Fretting, Cracking and through
wall material loss
2) Failed – 60% Circumferential crack
in fretted area running up through
unfretted conductor (now
cleaned)
3) Failed CGF – Through wall defect
and water ingress to surface
casing
8
Safety Integrity Teamwork Trust
Integrity Issues (3)
1) Failed Connector in Air Gap,
usually repaired when found with
Structural clamp
2) Failed connector Subsea, requires
more thought and there are
numerous horror stories of repair
attempts
3) Failed connector – Threads appear
to have been machined.
Unknown until conductor pulled as
cleaning proved difficult with
inspection not being on priority list
9
Safety Integrity Teamwork Trust
What were we dealing with? Range of fretting noted during ROV flyby
At least 8 Conductors with “heavy fretting” and TWD
Conductor guide bucket damage – multi level
Annuli integrity & at risk?
Splash zone operations so specific levels unknown but some tracking by historical ROV footage
possible.
An Asset which is economic, but borderline as to how fragile that level of economic is.
Marine Growth and access issues impacting any semblance of Asset Integrity requirements or
Risk Based Inspection criteria
“Could we have done something sooner to prevent bigger maintenance spend now?”
10
Safety Integrity Teamwork Trust
Analysis
• Understand current condition & determine implications of identified damage
• Build model across all conductors based on current condition and loadings
• Consideration of unique defect situations: separation at guide & connector above
Safety Integrity Teamwork Trust
SETS believe, a ‘third eye’ look at any challenge can give a clearer picture to what can be achieved. Our approach is based on Minimising Risk, Maximising Value for all projects, through Early Engagement and
Disruptive Thinking methods. SETS can guide an operator through a Phase stage gate process to de-risk any the project.
ROV/DSV Is not the
only option. SETS approach will ensure all options are considered whether using an ROV , DSV or Rope access technique. We will ensure the focus is on
Minimising Risk, Maximising Value
DSV
£100k/day
a £65k/day £20k/day
r ROV
11
Approach by SETS
r SETS
1
4
Safety Integrity Teamwork Trust
Rope Access Solution
• No Vessels – Under deck Rope access deployed solution
• Ability to clean and Inspect material loss within Conductor guide
Frame at circa -15m
• Repeatable, economic method to allow build of Integrity management
solution
• Ability to analyse and advise repair / maintenance requirement from
SETS pre-prepared solutions
12
8
Safety Integrity Teamwork Trust
Cleaning & Inspection
1) Cleaning & Inspection Tool Installed in the Airgap to the Conductor by
the Rope Access team
2) The Tool is run down the conductor, cleaning using HP water Jet
nozzles rotating around the conductor
3) The Tool cleans do to and through the Conductor guide frame
4) The Tools attached Laser arm allows the measurement of material loss
due to Fretting down through the guide Frame
13
8
Safety Integrity Teamwork Trust
Repair Types
1) Type 1: Is a pretty standard Wear sleeve, for minimal damage and
protection
2) Type 2: Will provide Shear Support were Fretting / TWD has occurred
3) Type 3 / 4: Provides shear & Axial support through guide where this is
not present due to condition
4) Type 5: Where connector has failed, full moment clamp
14
8
Safety Integrity Teamwork Trust
Remote Repair
1) Repair Clamp installed in the Airgap by the Rope Access Team
2) SETS Installation Tool interfaced to clamp within the Airgap
3) Clamp & Install Tool Run to Repair Site & Torqued as required
4) SETS Install Tooling detaches from Repair and recovered to surface by
RA Team
15
8
Safety Integrity Teamwork Trust
Inspection & Install Tooling 1) Cleaning & Inspection Tool
2) Type 1 Wear Sleeve
3) Type 2 RA install in Airgap
4) Type 2 in location ready for
install
16
14
Safety Integrity Teamwork Trust
No Vessels for Subsea works 17
Safety Integrity Teamwork Trust
www.setsltd.com
Early engagement. Disruptive thinking.