construction and facility services (cfs)...schematic design / design charette design development...

30
Customer Focused . . . Always Responsive! Office: 713-556-9299 Fax: 713-676-9582 CONSTRUCTION AND FACILITY SERVICES (CFS) 3200 Center Street, Houston TX 77007-5909 Facilities Planning Project Advisory Team Meeting Minutes Waltrip High School MEETING NO.: 009 LOCATION: Waltrip High School, College Prep Room DATE / TIME: January 27, 4:30-6:30pm ATTENDEES: Bill Chambers, CMAR Contractor; Catherine Clay, Teacher; Daisy Cnagcya, Student HOSA; Dr. Enloe, Waltrip Alumni; Jesse Espinosa, Band Director; Scott Fendrick, HISD Project Manager; Steve Hoyt; HISD Sr. Project Manager; Mary Gibson, Teacher/Alumni; Kimberly Hickson, Gensler Architects; Cynthia Krohn; Staff Member; Nina Murrell, Gensler Architects; Jeff Turner, Staff Member; Elizabeth Villareal, Parent; Stephanie Witherspoon, Teacher; PURPOSE: The purpose of this meeting was to discuss 21 st Century Learning and review photos provided by those who attended the site tours in Seattle Washington. Many of these ideas could be considered and incorporated into the Waltrip HS 21 st century leaning environment. Programming/ Capacity Model/ Ed. Specs. Community Meeting 1 Schematic Design/ Design Charette Design Development Community Meeting 2 Contract Documents Permitting Community Meeting 3 Construction AGENDA ITEMS: Review progress with Milestone Schedule 2007 Bond Project Update/Summer Package Design Charrette Outline/Discussion, January 29, and 30. Determine action items to complete before next meeting. Next Project Advisory Team meeting March 24, 2014, 4:30pm (4 th Monday) What to expect at next Project Advisory Team meeting. NOTES: 1. Mr. Scott Fendrick opened the meeting with a review of the milestone schedule 2. Scott also reviewed the 2007 Bond Project and relayed that a mini project is being prepared with a construction start near the end of the school year. This is to avoid disrupting classes and allow time for the documents to be prepared in a thoughtful manner and verify inclusion in the upcoming 2012 project. 3. A question was asked about items previously under construction still being incomplete. Scott Fendrick responded that incomplete work identified in the contract documents will be completed. He also offered to evaluate work to determine what scope it could be attributed to. If the scope is identified as incomplete he will assist in getting it completed. If the work is not in the contract documents we will look into alternative resolutions.

Upload: others

Post on 15-Jul-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CONSTRUCTION AND FACILITY SERVICES (CFS)...Schematic Design / Design Charette Design Development Community Meeting 2 Contract Documents Permitting Community Meeting 3 Construction

Customer Focused . . . Always Responsive!

Office: 713-556-9299 Fax: 713-676-9582

CONSTRUCTION AND FACILITY SERVICES (CFS)

3200 Center Street, Houston TX 77007-5909

Facilities Planning Project Advisory Team Meeting Minutes

Waltrip High School

MEETING NO.: 009

LOCATION: Waltrip High School, College Prep Room

DATE / TIME: January 27, 4:30-6:30pm

ATTENDEES: Bill Chambers, CMAR Contractor; Catherine Clay, Teacher; Daisy Cnagcya, Student HOSA; Dr. Enloe, Waltrip

Alumni; Jesse Espinosa, Band Director; Scott Fendrick, HISD Project Manager; Steve Hoyt; HISD Sr. Project

Manager; Mary Gibson, Teacher/Alumni; Kimberly Hickson, Gensler Architects; Cynthia Krohn; Staff Member;

Nina Murrell, Gensler Architects; Jeff Turner, Staff Member; Elizabeth Villareal, Parent; Stephanie Witherspoon,

Teacher;

PURPOSE: The purpose of this meeting was to discuss 21st Century Learning and review photos provided by those who

attended the site tours in Seattle Washington. Many of these ideas could be considered and incorporated into the

Waltrip HS 21st century leaning environment.

Programming/ Capacity

Model/ Ed. Specs.

Community

Meeting 1

Schematic Design/

Design Charette

Design

Development

Community

Meeting 2

Contract

Documents

Permitting Community

Meeting 3

Construction

AGENDA ITEMS:

� Review progress with Milestone Schedule � 2007 Bond Project Update/Summer Package � Design Charrette Outline/Discussion, January 29, and 30. � Determine action items to complete before next meeting. � Next Project Advisory Team meeting March 24, 2014, 4:30pm (4th Monday) � What to expect at next Project Advisory Team meeting.

NOTES:

1. Mr. Scott Fendrick opened the meeting with a review of the milestone schedule

2. Scott also reviewed the 2007 Bond Project and relayed that a mini project is being prepared with a construction start near

the end of the school year. This is to avoid disrupting classes and allow time for the documents to be prepared in a

thoughtful manner and verify inclusion in the upcoming 2012 project.

3. A question was asked about items previously under construction still being incomplete. Scott Fendrick responded that

incomplete work identified in the contract documents will be completed. He also offered to evaluate work to determine

what scope it could be attributed to. If the scope is identified as incomplete he will assist in getting it completed. If the

work is not in the contract documents we will look into alternative resolutions.

Page 2: CONSTRUCTION AND FACILITY SERVICES (CFS)...Schematic Design / Design Charette Design Development Community Meeting 2 Contract Documents Permitting Community Meeting 3 Construction

Customer Focused . . . Always Responsive!

Office: 713-556-9299 Fax: 713-676-9582

ACTION ITEMS:

• HISD Facilities Planning to arrange tours to other facilities.

NEXT MEETING:

• Presentation of more developed design and scope concepts as by Gensler Architects.

Please review the meeting minutes and submit any changes or corrections to Scott Fendrick

After five (5) days, the minutes will be assumed to be accurate.

Sincerely,

Scott Fendrick

Project Manager

HISD – Construction & Facility Services

3200 Center Street, Houston, TX 77007

Phone: (713) 556-9322

[email protected]

Page 3: CONSTRUCTION AND FACILITY SERVICES (CFS)...Schematic Design / Design Charette Design Development Community Meeting 2 Contract Documents Permitting Community Meeting 3 Construction

Customer Focused . . . Always Responsive!

Office: 713-556-9299 Fax: 713-676-9582

CONSTRUCTION AND FACILITY SERVICES (CFS)

3200 Center Street, Houston TX 77007-5909

Facilities Planning Project Advisory Team Meeting Minutes

Waltrip High School

MEETING NO.: 009

LOCATION: Waltrip High School, College Prep Room

DATE / TIME: January 27, 4:30-6:30pm

ATTENDEES: Bill Chambers, CMAR Contractor; Catherine Clay, Teacher; Daisy Cnagcya, Student HOSA; Dr. Enloe, Waltrip

Alumni; Jesse Espinosa, Band Director; Scott Fendrick, HISD Project Manager; Steve Hoyt; HISD Sr. Project

Manager; Mary Gibson, Teacher/Alumni; Kimberly Hickson, Gensler Architects; Cynthia Krohn; Staff Member;

Nina Murrell, Gensler Architects; Jeff Turner, Staff Member; Elizabeth Villareal, Parent; Stephanie Witherspoon,

Teacher;

PURPOSE: The purpose of this meeting was to discuss 21st Century Learning and review photos provided by those who

attended the site tours in Seattle Washington. Many of these ideas could be considered and incorporated into the

Waltrip HS 21st century leaning environment.

Programming/ Capacity

Model/ Ed. Specs.

Community

Meeting 1

Schematic Design/

Design Charette

Design

Development

Community

Meeting 2

Contract

Documents

Permitting Community

Meeting 3

Construction

AGENDA ITEMS:

� Review progress with Milestone Schedule � 2007 Bond Project Update/Summer Package � Design Charrette Outline/Discussion, January 29, and 30. � Determine action items to complete before next meeting. � Next Project Advisory Team meeting March 24, 2014, 4:30pm (4th Monday) � What to expect at next Project Advisory Team meeting.

NOTES:

1. Mr. Scott Fendrick opened the meeting with a review of the milestone schedule

2. Scott also reviewed the 2007 Bond Project and relayed that a mini project is being prepared with a construction start near

the end of the school year. This is to avoid disrupting classes and allow time for the documents to be prepared in a

thoughtful manner and verify inclusion in the upcoming 2012 project.

3. A question was asked about items previously under construction still being incomplete. Scott Fendrick responded that

incomplete work identified in the contract documents will be completed. He also offered to evaluate work to determine

what scope it could be attributed to. If the scope is identified as incomplete he will assist in getting it completed. If the

work is not in the contract documents we will look into alternative resolutions.

Page 4: CONSTRUCTION AND FACILITY SERVICES (CFS)...Schematic Design / Design Charette Design Development Community Meeting 2 Contract Documents Permitting Community Meeting 3 Construction

Customer Focused . . . Always Responsive!

Office: 713-556-9299 Fax: 713-676-9582

ACTION ITEMS:

• HISD Facilities Planning to arrange tours to other facilities.

NEXT MEETING:

• Presentation of more developed design and scope concepts as by Gensler Architects.

Please review the meeting minutes and submit any changes or corrections to Scott Fendrick

After five (5) days, the minutes will be assumed to be accurate.

Sincerely,

Scott Fendrick

Project Manager

HISD – Construction & Facility Services

3200 Center Street, Houston, TX 77007

Phone: (713) 556-9322

[email protected]

Page 5: CONSTRUCTION AND FACILITY SERVICES (CFS)...Schematic Design / Design Charette Design Development Community Meeting 2 Contract Documents Permitting Community Meeting 3 Construction

Customer Focused . . . Always Responsive!

Office: 713-556-9299 Fax: 713-676-9582

CONSTRUCTION AND FACILITY SERVICES (CFS)

3200 Center Street, Houston TX 77007-5909

Facilities Planning Project Advisory Team Meeting Minutes

Waltrip High School

MEETING NO.: 009

LOCATION: Waltrip High School, College Prep Room

DATE / TIME: January 27, 4:30-6:30pm

ATTENDEES: Bill Chambers, CMAR Contractor; Catherine Clay, Teacher; Daisy Cnagcya, Student HOSA; Dr. Enloe, Waltrip

Alumni; Jesse Espinosa, Band Director; Scott Fendrick, HISD Project Manager; Steve Hoyt; HISD Sr. Project

Manager; Mary Gibson, Teacher/Alumni; Kimberly Hickson, Gensler Architects; Cynthia Krohn; Staff Member;

Nina Murrell, Gensler Architects; Jeff Turner, Staff Member; Elizabeth Villareal, Parent; Stephanie Witherspoon,

Teacher;

PURPOSE: The purpose of this meeting was to discuss 21st Century Learning and review photos provided by those who

attended the site tours in Seattle Washington. Many of these ideas could be considered and incorporated into the

Waltrip HS 21st century leaning environment.

Programming/ Capacity

Model/ Ed. Specs.

Community

Meeting 1

Schematic Design/

Design Charette

Design

Development

Community

Meeting 2

Contract

Documents

Permitting Community

Meeting 3

Construction

AGENDA ITEMS:

� Review progress with Milestone Schedule � 2007 Bond Project Update/Summer Package � Design Charrette Outline/Discussion, January 29, and 30. � Determine action items to complete before next meeting. � Next Project Advisory Team meeting March 24, 2014, 4:30pm (4th Monday) � What to expect at next Project Advisory Team meeting.

NOTES:

1. Mr. Scott Fendrick opened the meeting with a review of the milestone schedule

2. Scott also reviewed the 2007 Bond Project and relayed that a mini project is being prepared with a construction start near

the end of the school year. This is to avoid disrupting classes and allow time for the documents to be prepared in a

thoughtful manner and verify inclusion in the upcoming 2012 project.

3. A question was asked about items previously under construction still being incomplete. Scott Fendrick responded that

incomplete work identified in the contract documents will be completed. He also offered to evaluate work to determine

what scope it could be attributed to. If the scope is identified as incomplete he will assist in getting it completed. If the

work is not in the contract documents we will look into alternative resolutions.

Page 6: CONSTRUCTION AND FACILITY SERVICES (CFS)...Schematic Design / Design Charette Design Development Community Meeting 2 Contract Documents Permitting Community Meeting 3 Construction

Customer Focused . . . Always Responsive!

Office: 713-556-9299 Fax: 713-676-9582

ACTION ITEMS:

• HISD Facilities Planning to arrange tours to other facilities.

NEXT MEETING:

• Presentation of more developed design and scope concepts as by Gensler Architects.

Please review the meeting minutes and submit any changes or corrections to Scott Fendrick

After five (5) days, the minutes will be assumed to be accurate.

Sincerely,

Scott Fendrick

Project Manager

HISD – Construction & Facility Services

3200 Center Street, Houston, TX 77007

Phone: (713) 556-9322

[email protected]

Page 7: CONSTRUCTION AND FACILITY SERVICES (CFS)...Schematic Design / Design Charette Design Development Community Meeting 2 Contract Documents Permitting Community Meeting 3 Construction

Customer Focused . . . Always Responsive!

Office: 713-556-9299 Fax: 713-676-9582

CONSTRUCTION AND FACILITY SERVICES (CFS)

3200 Center Street, Houston TX 77007-5909

Facilities Planning Project Advisory Team Meeting Minutes

Waltrip High School

MEETING NO.: 009

LOCATION: Waltrip High School, College Prep Room

DATE / TIME: January 27, 4:30-6:30pm

ATTENDEES: Bill Chambers, CMAR Contractor; Catherine Clay, Teacher; Daisy Cnagcya, Student HOSA; Dr. Enloe, Waltrip

Alumni; Jesse Espinosa, Band Director; Scott Fendrick, HISD Project Manager; Steve Hoyt; HISD Sr. Project

Manager; Mary Gibson, Teacher/Alumni; Kimberly Hickson, Gensler Architects; Cynthia Krohn; Staff Member;

Nina Murrell, Gensler Architects; Jeff Turner, Staff Member; Elizabeth Villareal, Parent; Stephanie Witherspoon,

Teacher;

PURPOSE: The purpose of this meeting was to discuss 21st Century Learning and review photos provided by those who

attended the site tours in Seattle Washington. Many of these ideas could be considered and incorporated into the

Waltrip HS 21st century leaning environment.

Programming/ Capacity

Model/ Ed. Specs.

Community

Meeting 1

Schematic Design/

Design Charette

Design

Development

Community

Meeting 2

Contract

Documents

Permitting Community

Meeting 3

Construction

AGENDA ITEMS:

� Review progress with Milestone Schedule � 2007 Bond Project Update/Summer Package � Design Charrette Outline/Discussion, January 29, and 30. � Determine action items to complete before next meeting. � Next Project Advisory Team meeting March 24, 2014, 4:30pm (4th Monday) � What to expect at next Project Advisory Team meeting.

NOTES:

1. Mr. Scott Fendrick opened the meeting with a review of the milestone schedule

2. Scott also reviewed the 2007 Bond Project and relayed that a mini project is being prepared with a construction start near

the end of the school year. This is to avoid disrupting classes and allow time for the documents to be prepared in a

thoughtful manner and verify inclusion in the upcoming 2012 project.

3. A question was asked about items previously under construction still being incomplete. Scott Fendrick responded that

incomplete work identified in the contract documents will be completed. He also offered to evaluate work to determine

what scope it could be attributed to. If the scope is identified as incomplete he will assist in getting it completed. If the

work is not in the contract documents we will look into alternative resolutions.

Page 8: CONSTRUCTION AND FACILITY SERVICES (CFS)...Schematic Design / Design Charette Design Development Community Meeting 2 Contract Documents Permitting Community Meeting 3 Construction

Customer Focused . . . Always Responsive!

Office: 713-556-9299 Fax: 713-676-9582

ACTION ITEMS:

• HISD Facilities Planning to arrange tours to other facilities.

NEXT MEETING:

• Presentation of more developed design and scope concepts as by Gensler Architects.

Please review the meeting minutes and submit any changes or corrections to Scott Fendrick

After five (5) days, the minutes will be assumed to be accurate.

Sincerely,

Scott Fendrick

Project Manager

HISD – Construction & Facility Services

3200 Center Street, Houston, TX 77007

Phone: (713) 556-9322

[email protected]

Page 9: CONSTRUCTION AND FACILITY SERVICES (CFS)...Schematic Design / Design Charette Design Development Community Meeting 2 Contract Documents Permitting Community Meeting 3 Construction

Customer Focused . . . Always Responsive!

Office: 713-556-9299 Fax: 713-676-9582

CONSTRUCTION AND FACILITY SERVICES (CFS)

3200 Center Street, Houston TX 77007-5909

Facilities Planning Project Advisory Team Meeting Minutes

Waltrip High School

MEETING NO.: 009

LOCATION: Waltrip High School, College Prep Room

DATE / TIME: January 27, 4:30-6:30pm

ATTENDEES: Bill Chambers, CMAR Contractor; Catherine Clay, Teacher; Daisy Cnagcya, Student HOSA; Dr. Enloe, Waltrip

Alumni; Jesse Espinosa, Band Director; Scott Fendrick, HISD Project Manager; Steve Hoyt; HISD Sr. Project

Manager; Mary Gibson, Teacher/Alumni; Kimberly Hickson, Gensler Architects; Cynthia Krohn; Staff Member;

Nina Murrell, Gensler Architects; Jeff Turner, Staff Member; Elizabeth Villareal, Parent; Stephanie Witherspoon,

Teacher;

PURPOSE: The purpose of this meeting was to discuss 21st Century Learning and review photos provided by those who

attended the site tours in Seattle Washington. Many of these ideas could be considered and incorporated into the

Waltrip HS 21st century leaning environment.

Programming/ Capacity

Model/ Ed. Specs.

Community

Meeting 1

Schematic Design/

Design Charette

Design

Development

Community

Meeting 2

Contract

Documents

Permitting Community

Meeting 3

Construction

AGENDA ITEMS:

� Review progress with Milestone Schedule � 2007 Bond Project Update/Summer Package � Design Charrette Outline/Discussion, January 29, and 30. � Determine action items to complete before next meeting. � Next Project Advisory Team meeting March 24, 2014, 4:30pm (4th Monday) � What to expect at next Project Advisory Team meeting.

NOTES:

1. Mr. Scott Fendrick opened the meeting with a review of the milestone schedule

2. Scott also reviewed the 2007 Bond Project and relayed that a mini project is being prepared with a construction start near

the end of the school year. This is to avoid disrupting classes and allow time for the documents to be prepared in a

thoughtful manner and verify inclusion in the upcoming 2012 project.

3. A question was asked about items previously under construction still being incomplete. Scott Fendrick responded that

incomplete work identified in the contract documents will be completed. He also offered to evaluate work to determine

what scope it could be attributed to. If the scope is identified as incomplete he will assist in getting it completed. If the

work is not in the contract documents we will look into alternative resolutions.

Page 10: CONSTRUCTION AND FACILITY SERVICES (CFS)...Schematic Design / Design Charette Design Development Community Meeting 2 Contract Documents Permitting Community Meeting 3 Construction

Customer Focused . . . Always Responsive!

Office: 713-556-9299 Fax: 713-676-9582

ACTION ITEMS:

• HISD Facilities Planning to arrange tours to other facilities.

NEXT MEETING:

• Presentation of more developed design and scope concepts as by Gensler Architects.

Please review the meeting minutes and submit any changes or corrections to Scott Fendrick

After five (5) days, the minutes will be assumed to be accurate.

Sincerely,

Scott Fendrick

Project Manager

HISD – Construction & Facility Services

3200 Center Street, Houston, TX 77007

Phone: (713) 556-9322

[email protected]

Page 11: CONSTRUCTION AND FACILITY SERVICES (CFS)...Schematic Design / Design Charette Design Development Community Meeting 2 Contract Documents Permitting Community Meeting 3 Construction

Customer Focused . . . Always Responsive!

Office: 713-556-9299 Fax: 713-676-9582

CONSTRUCTION AND FACILITY SERVICES (CFS)

3200 Center Street, Houston TX 77007-5909

Facilities Planning Project Advisory Team Meeting Minutes

Waltrip High School

MEETING NO.: 009

LOCATION: Waltrip High School, College Prep Room

DATE / TIME: January 27, 4:30-6:30pm

ATTENDEES: Bill Chambers, CMAR Contractor; Catherine Clay, Teacher; Daisy Cnagcya, Student HOSA; Dr. Enloe, Waltrip

Alumni; Jesse Espinosa, Band Director; Scott Fendrick, HISD Project Manager; Steve Hoyt; HISD Sr. Project

Manager; Mary Gibson, Teacher/Alumni; Kimberly Hickson, Gensler Architects; Cynthia Krohn; Staff Member;

Nina Murrell, Gensler Architects; Jeff Turner, Staff Member; Elizabeth Villareal, Parent; Stephanie Witherspoon,

Teacher;

PURPOSE: The purpose of this meeting was to discuss 21st Century Learning and review photos provided by those who

attended the site tours in Seattle Washington. Many of these ideas could be considered and incorporated into the

Waltrip HS 21st century leaning environment.

Programming/ Capacity

Model/ Ed. Specs.

Community

Meeting 1

Schematic Design/

Design Charette

Design

Development

Community

Meeting 2

Contract

Documents

Permitting Community

Meeting 3

Construction

AGENDA ITEMS:

� Review progress with Milestone Schedule � 2007 Bond Project Update/Summer Package � Design Charrette Outline/Discussion, January 29, and 30. � Determine action items to complete before next meeting. � Next Project Advisory Team meeting March 24, 2014, 4:30pm (4th Monday) � What to expect at next Project Advisory Team meeting.

NOTES:

1. Mr. Scott Fendrick opened the meeting with a review of the milestone schedule

2. Scott also reviewed the 2007 Bond Project and relayed that a mini project is being prepared with a construction start near

the end of the school year. This is to avoid disrupting classes and allow time for the documents to be prepared in a

thoughtful manner and verify inclusion in the upcoming 2012 project.

3. A question was asked about items previously under construction still being incomplete. Scott Fendrick responded that

incomplete work identified in the contract documents will be completed. He also offered to evaluate work to determine

what scope it could be attributed to. If the scope is identified as incomplete he will assist in getting it completed. If the

work is not in the contract documents we will look into alternative resolutions.

Page 12: CONSTRUCTION AND FACILITY SERVICES (CFS)...Schematic Design / Design Charette Design Development Community Meeting 2 Contract Documents Permitting Community Meeting 3 Construction

Customer Focused . . . Always Responsive!

Office: 713-556-9299 Fax: 713-676-9582

ACTION ITEMS:

• HISD Facilities Planning to arrange tours to other facilities.

NEXT MEETING:

• Presentation of more developed design and scope concepts as by Gensler Architects.

Please review the meeting minutes and submit any changes or corrections to Scott Fendrick

After five (5) days, the minutes will be assumed to be accurate.

Sincerely,

Scott Fendrick

Project Manager

HISD – Construction & Facility Services

3200 Center Street, Houston, TX 77007

Phone: (713) 556-9322

[email protected]

Page 13: CONSTRUCTION AND FACILITY SERVICES (CFS)...Schematic Design / Design Charette Design Development Community Meeting 2 Contract Documents Permitting Community Meeting 3 Construction

Customer Focused . . . Always Responsive!

Office: 713-556-9299 Fax: 713-676-9582

CONSTRUCTION AND FACILITY SERVICES (CFS)

3200 Center Street, Houston TX 77007-5909

Facilities Planning Project Advisory Team Meeting Minutes

Waltrip High School

MEETING NO.: 009

LOCATION: Waltrip High School, College Prep Room

DATE / TIME: January 27, 4:30-6:30pm

ATTENDEES: Bill Chambers, CMAR Contractor; Catherine Clay, Teacher; Daisy Cnagcya, Student HOSA; Dr. Enloe, Waltrip

Alumni; Jesse Espinosa, Band Director; Scott Fendrick, HISD Project Manager; Steve Hoyt; HISD Sr. Project

Manager; Mary Gibson, Teacher/Alumni; Kimberly Hickson, Gensler Architects; Cynthia Krohn; Staff Member;

Nina Murrell, Gensler Architects; Jeff Turner, Staff Member; Elizabeth Villareal, Parent; Stephanie Witherspoon,

Teacher;

PURPOSE: The purpose of this meeting was to discuss 21st Century Learning and review photos provided by those who

attended the site tours in Seattle Washington. Many of these ideas could be considered and incorporated into the

Waltrip HS 21st century leaning environment.

Programming/ Capacity

Model/ Ed. Specs.

Community

Meeting 1

Schematic Design/

Design Charette

Design

Development

Community

Meeting 2

Contract

Documents

Permitting Community

Meeting 3

Construction

AGENDA ITEMS:

� Review progress with Milestone Schedule � 2007 Bond Project Update/Summer Package � Design Charrette Outline/Discussion, January 29, and 30. � Determine action items to complete before next meeting. � Next Project Advisory Team meeting March 24, 2014, 4:30pm (4th Monday) � What to expect at next Project Advisory Team meeting.

NOTES:

1. Mr. Scott Fendrick opened the meeting with a review of the milestone schedule

2. Scott also reviewed the 2007 Bond Project and relayed that a mini project is being prepared with a construction start near

the end of the school year. This is to avoid disrupting classes and allow time for the documents to be prepared in a

thoughtful manner and verify inclusion in the upcoming 2012 project.

3. A question was asked about items previously under construction still being incomplete. Scott Fendrick responded that

incomplete work identified in the contract documents will be completed. He also offered to evaluate work to determine

what scope it could be attributed to. If the scope is identified as incomplete he will assist in getting it completed. If the

work is not in the contract documents we will look into alternative resolutions.

Page 14: CONSTRUCTION AND FACILITY SERVICES (CFS)...Schematic Design / Design Charette Design Development Community Meeting 2 Contract Documents Permitting Community Meeting 3 Construction

Customer Focused . . . Always Responsive!

Office: 713-556-9299 Fax: 713-676-9582

ACTION ITEMS:

• HISD Facilities Planning to arrange tours to other facilities.

NEXT MEETING:

• Presentation of more developed design and scope concepts as by Gensler Architects.

Please review the meeting minutes and submit any changes or corrections to Scott Fendrick

After five (5) days, the minutes will be assumed to be accurate.

Sincerely,

Scott Fendrick

Project Manager

HISD – Construction & Facility Services

3200 Center Street, Houston, TX 77007

Phone: (713) 556-9322

[email protected]

Page 15: CONSTRUCTION AND FACILITY SERVICES (CFS)...Schematic Design / Design Charette Design Development Community Meeting 2 Contract Documents Permitting Community Meeting 3 Construction

Customer Focused . . . Always Responsive!

Office: 713-556-9299 Fax: 713-676-9582

CONSTRUCTION AND FACILITY SERVICES (CFS)

3200 Center Street, Houston TX 77007-5909

Facilities Planning Project Advisory Team Meeting Minutes

Waltrip High School

MEETING NO.: 009

LOCATION: Waltrip High School, College Prep Room

DATE / TIME: January 27, 4:30-6:30pm

ATTENDEES: Bill Chambers, CMAR Contractor; Catherine Clay, Teacher; Daisy Cnagcya, Student HOSA; Dr. Enloe, Waltrip

Alumni; Jesse Espinosa, Band Director; Scott Fendrick, HISD Project Manager; Steve Hoyt; HISD Sr. Project

Manager; Mary Gibson, Teacher/Alumni; Kimberly Hickson, Gensler Architects; Cynthia Krohn; Staff Member;

Nina Murrell, Gensler Architects; Jeff Turner, Staff Member; Elizabeth Villareal, Parent; Stephanie Witherspoon,

Teacher;

PURPOSE: The purpose of this meeting was to discuss 21st Century Learning and review photos provided by those who

attended the site tours in Seattle Washington. Many of these ideas could be considered and incorporated into the

Waltrip HS 21st century leaning environment.

Programming/ Capacity

Model/ Ed. Specs.

Community

Meeting 1

Schematic Design/

Design Charette

Design

Development

Community

Meeting 2

Contract

Documents

Permitting Community

Meeting 3

Construction

AGENDA ITEMS:

� Review progress with Milestone Schedule � 2007 Bond Project Update/Summer Package � Design Charrette Outline/Discussion, January 29, and 30. � Determine action items to complete before next meeting. � Next Project Advisory Team meeting March 24, 2014, 4:30pm (4th Monday) � What to expect at next Project Advisory Team meeting.

NOTES:

1. Mr. Scott Fendrick opened the meeting with a review of the milestone schedule

2. Scott also reviewed the 2007 Bond Project and relayed that a mini project is being prepared with a construction start near

the end of the school year. This is to avoid disrupting classes and allow time for the documents to be prepared in a

thoughtful manner and verify inclusion in the upcoming 2012 project.

3. A question was asked about items previously under construction still being incomplete. Scott Fendrick responded that

incomplete work identified in the contract documents will be completed. He also offered to evaluate work to determine

what scope it could be attributed to. If the scope is identified as incomplete he will assist in getting it completed. If the

work is not in the contract documents we will look into alternative resolutions.

Page 16: CONSTRUCTION AND FACILITY SERVICES (CFS)...Schematic Design / Design Charette Design Development Community Meeting 2 Contract Documents Permitting Community Meeting 3 Construction

Customer Focused . . . Always Responsive!

Office: 713-556-9299 Fax: 713-676-9582

ACTION ITEMS:

• HISD Facilities Planning to arrange tours to other facilities.

NEXT MEETING:

• Presentation of more developed design and scope concepts as by Gensler Architects.

Please review the meeting minutes and submit any changes or corrections to Scott Fendrick

After five (5) days, the minutes will be assumed to be accurate.

Sincerely,

Scott Fendrick

Project Manager

HISD – Construction & Facility Services

3200 Center Street, Houston, TX 77007

Phone: (713) 556-9322

[email protected]

Page 17: CONSTRUCTION AND FACILITY SERVICES (CFS)...Schematic Design / Design Charette Design Development Community Meeting 2 Contract Documents Permitting Community Meeting 3 Construction

Customer Focused . . . Always Responsive!

Office: 713-556-9299 Fax: 713-676-9582

CONSTRUCTION AND FACILITY SERVICES (CFS)

3200 Center Street, Houston TX 77007-5909

Facilities Planning Project Advisory Team Meeting Minutes

Waltrip High School

MEETING NO.: 009

LOCATION: Waltrip High School, College Prep Room

DATE / TIME: January 27, 4:30-6:30pm

ATTENDEES: Bill Chambers, CMAR Contractor; Catherine Clay, Teacher; Daisy Cnagcya, Student HOSA; Dr. Enloe, Waltrip

Alumni; Jesse Espinosa, Band Director; Scott Fendrick, HISD Project Manager; Steve Hoyt; HISD Sr. Project

Manager; Mary Gibson, Teacher/Alumni; Kimberly Hickson, Gensler Architects; Cynthia Krohn; Staff Member;

Nina Murrell, Gensler Architects; Jeff Turner, Staff Member; Elizabeth Villareal, Parent; Stephanie Witherspoon,

Teacher;

PURPOSE: The purpose of this meeting was to discuss 21st Century Learning and review photos provided by those who

attended the site tours in Seattle Washington. Many of these ideas could be considered and incorporated into the

Waltrip HS 21st century leaning environment.

Programming/ Capacity

Model/ Ed. Specs.

Community

Meeting 1

Schematic Design/

Design Charette

Design

Development

Community

Meeting 2

Contract

Documents

Permitting Community

Meeting 3

Construction

AGENDA ITEMS:

� Review progress with Milestone Schedule � 2007 Bond Project Update/Summer Package � Design Charrette Outline/Discussion, January 29, and 30. � Determine action items to complete before next meeting. � Next Project Advisory Team meeting March 24, 2014, 4:30pm (4th Monday) � What to expect at next Project Advisory Team meeting.

NOTES:

1. Mr. Scott Fendrick opened the meeting with a review of the milestone schedule

2. Scott also reviewed the 2007 Bond Project and relayed that a mini project is being prepared with a construction start near

the end of the school year. This is to avoid disrupting classes and allow time for the documents to be prepared in a

thoughtful manner and verify inclusion in the upcoming 2012 project.

3. A question was asked about items previously under construction still being incomplete. Scott Fendrick responded that

incomplete work identified in the contract documents will be completed. He also offered to evaluate work to determine

what scope it could be attributed to. If the scope is identified as incomplete he will assist in getting it completed. If the

work is not in the contract documents we will look into alternative resolutions.

Page 18: CONSTRUCTION AND FACILITY SERVICES (CFS)...Schematic Design / Design Charette Design Development Community Meeting 2 Contract Documents Permitting Community Meeting 3 Construction

Customer Focused . . . Always Responsive!

Office: 713-556-9299 Fax: 713-676-9582

ACTION ITEMS:

• HISD Facilities Planning to arrange tours to other facilities.

NEXT MEETING:

• Presentation of more developed design and scope concepts as by Gensler Architects.

Please review the meeting minutes and submit any changes or corrections to Scott Fendrick

After five (5) days, the minutes will be assumed to be accurate.

Sincerely,

Scott Fendrick

Project Manager

HISD – Construction & Facility Services

3200 Center Street, Houston, TX 77007

Phone: (713) 556-9322

[email protected]

Page 19: CONSTRUCTION AND FACILITY SERVICES (CFS)...Schematic Design / Design Charette Design Development Community Meeting 2 Contract Documents Permitting Community Meeting 3 Construction

Customer Focused . . . Always Responsive!

Office: 713-556-9299 Fax: 713-676-9582

CONSTRUCTION AND FACILITY SERVICES (CFS)

3200 Center Street, Houston TX 77007-5909

Facilities Planning Project Advisory Team Meeting Minutes

Waltrip High School

MEETING NO.: 009

LOCATION: Waltrip High School, College Prep Room

DATE / TIME: January 27, 4:30-6:30pm

ATTENDEES: Bill Chambers, CMAR Contractor; Catherine Clay, Teacher; Daisy Cnagcya, Student HOSA; Dr. Enloe, Waltrip

Alumni; Jesse Espinosa, Band Director; Scott Fendrick, HISD Project Manager; Steve Hoyt; HISD Sr. Project

Manager; Mary Gibson, Teacher/Alumni; Kimberly Hickson, Gensler Architects; Cynthia Krohn; Staff Member;

Nina Murrell, Gensler Architects; Jeff Turner, Staff Member; Elizabeth Villareal, Parent; Stephanie Witherspoon,

Teacher;

PURPOSE: The purpose of this meeting was to discuss 21st Century Learning and review photos provided by those who

attended the site tours in Seattle Washington. Many of these ideas could be considered and incorporated into the

Waltrip HS 21st century leaning environment.

Programming/ Capacity

Model/ Ed. Specs.

Community

Meeting 1

Schematic Design/

Design Charette

Design

Development

Community

Meeting 2

Contract

Documents

Permitting Community

Meeting 3

Construction

AGENDA ITEMS:

� Review progress with Milestone Schedule � 2007 Bond Project Update/Summer Package � Design Charrette Outline/Discussion, January 29, and 30. � Determine action items to complete before next meeting. � Next Project Advisory Team meeting March 24, 2014, 4:30pm (4th Monday) � What to expect at next Project Advisory Team meeting.

NOTES:

1. Mr. Scott Fendrick opened the meeting with a review of the milestone schedule

2. Scott also reviewed the 2007 Bond Project and relayed that a mini project is being prepared with a construction start near

the end of the school year. This is to avoid disrupting classes and allow time for the documents to be prepared in a

thoughtful manner and verify inclusion in the upcoming 2012 project.

3. A question was asked about items previously under construction still being incomplete. Scott Fendrick responded that

incomplete work identified in the contract documents will be completed. He also offered to evaluate work to determine

what scope it could be attributed to. If the scope is identified as incomplete he will assist in getting it completed. If the

work is not in the contract documents we will look into alternative resolutions.

Page 20: CONSTRUCTION AND FACILITY SERVICES (CFS)...Schematic Design / Design Charette Design Development Community Meeting 2 Contract Documents Permitting Community Meeting 3 Construction

Customer Focused . . . Always Responsive!

Office: 713-556-9299 Fax: 713-676-9582

ACTION ITEMS:

• HISD Facilities Planning to arrange tours to other facilities.

NEXT MEETING:

• Presentation of more developed design and scope concepts as by Gensler Architects.

Please review the meeting minutes and submit any changes or corrections to Scott Fendrick

After five (5) days, the minutes will be assumed to be accurate.

Sincerely,

Scott Fendrick

Project Manager

HISD – Construction & Facility Services

3200 Center Street, Houston, TX 77007

Phone: (713) 556-9322

[email protected]

Page 21: CONSTRUCTION AND FACILITY SERVICES (CFS)...Schematic Design / Design Charette Design Development Community Meeting 2 Contract Documents Permitting Community Meeting 3 Construction

Customer Focused . . . Always Responsive!

Office: 713-556-9299 Fax: 713-676-9582

CONSTRUCTION AND FACILITY SERVICES (CFS)

3200 Center Street, Houston TX 77007-5909

Facilities Planning Project Advisory Team Meeting Minutes

Waltrip High School

MEETING NO.: 009

LOCATION: Waltrip High School, College Prep Room

DATE / TIME: January 27, 4:30-6:30pm

ATTENDEES: Bill Chambers, CMAR Contractor; Catherine Clay, Teacher; Daisy Cnagcya, Student HOSA; Dr. Enloe, Waltrip

Alumni; Jesse Espinosa, Band Director; Scott Fendrick, HISD Project Manager; Steve Hoyt; HISD Sr. Project

Manager; Mary Gibson, Teacher/Alumni; Kimberly Hickson, Gensler Architects; Cynthia Krohn; Staff Member;

Nina Murrell, Gensler Architects; Jeff Turner, Staff Member; Elizabeth Villareal, Parent; Stephanie Witherspoon,

Teacher;

PURPOSE: The purpose of this meeting was to discuss 21st Century Learning and review photos provided by those who

attended the site tours in Seattle Washington. Many of these ideas could be considered and incorporated into the

Waltrip HS 21st century leaning environment.

Programming/ Capacity

Model/ Ed. Specs.

Community

Meeting 1

Schematic Design/

Design Charette

Design

Development

Community

Meeting 2

Contract

Documents

Permitting Community

Meeting 3

Construction

AGENDA ITEMS:

� Review progress with Milestone Schedule � 2007 Bond Project Update/Summer Package � Design Charrette Outline/Discussion, January 29, and 30. � Determine action items to complete before next meeting. � Next Project Advisory Team meeting March 24, 2014, 4:30pm (4th Monday) � What to expect at next Project Advisory Team meeting.

NOTES:

1. Mr. Scott Fendrick opened the meeting with a review of the milestone schedule

2. Scott also reviewed the 2007 Bond Project and relayed that a mini project is being prepared with a construction start near

the end of the school year. This is to avoid disrupting classes and allow time for the documents to be prepared in a

thoughtful manner and verify inclusion in the upcoming 2012 project.

3. A question was asked about items previously under construction still being incomplete. Scott Fendrick responded that

incomplete work identified in the contract documents will be completed. He also offered to evaluate work to determine

what scope it could be attributed to. If the scope is identified as incomplete he will assist in getting it completed. If the

work is not in the contract documents we will look into alternative resolutions.

Page 22: CONSTRUCTION AND FACILITY SERVICES (CFS)...Schematic Design / Design Charette Design Development Community Meeting 2 Contract Documents Permitting Community Meeting 3 Construction

Customer Focused . . . Always Responsive!

Office: 713-556-9299 Fax: 713-676-9582

ACTION ITEMS:

• HISD Facilities Planning to arrange tours to other facilities.

NEXT MEETING:

• Presentation of more developed design and scope concepts as by Gensler Architects.

Please review the meeting minutes and submit any changes or corrections to Scott Fendrick

After five (5) days, the minutes will be assumed to be accurate.

Sincerely,

Scott Fendrick

Project Manager

HISD – Construction & Facility Services

3200 Center Street, Houston, TX 77007

Phone: (713) 556-9322

[email protected]

Page 23: CONSTRUCTION AND FACILITY SERVICES (CFS)...Schematic Design / Design Charette Design Development Community Meeting 2 Contract Documents Permitting Community Meeting 3 Construction

Customer Focused . . . Always Responsive!

Office: 713-556-9299 Fax: 713-676-9582

CONSTRUCTION AND FACILITY SERVICES (CFS)

3200 Center Street, Houston TX 77007-5909

Facilities Planning Project Advisory Team Meeting Minutes

Waltrip High School

MEETING NO.: 009

LOCATION: Waltrip High School, College Prep Room

DATE / TIME: January 27, 4:30-6:30pm

ATTENDEES: Bill Chambers, CMAR Contractor; Catherine Clay, Teacher; Daisy Cnagcya, Student HOSA; Dr. Enloe, Waltrip

Alumni; Jesse Espinosa, Band Director; Scott Fendrick, HISD Project Manager; Steve Hoyt; HISD Sr. Project

Manager; Mary Gibson, Teacher/Alumni; Kimberly Hickson, Gensler Architects; Cynthia Krohn; Staff Member;

Nina Murrell, Gensler Architects; Jeff Turner, Staff Member; Elizabeth Villareal, Parent; Stephanie Witherspoon,

Teacher;

PURPOSE: The purpose of this meeting was to discuss 21st Century Learning and review photos provided by those who

attended the site tours in Seattle Washington. Many of these ideas could be considered and incorporated into the

Waltrip HS 21st century leaning environment.

Programming/ Capacity

Model/ Ed. Specs.

Community

Meeting 1

Schematic Design/

Design Charette

Design

Development

Community

Meeting 2

Contract

Documents

Permitting Community

Meeting 3

Construction

AGENDA ITEMS:

� Review progress with Milestone Schedule � 2007 Bond Project Update/Summer Package � Design Charrette Outline/Discussion, January 29, and 30. � Determine action items to complete before next meeting. � Next Project Advisory Team meeting March 24, 2014, 4:30pm (4th Monday) � What to expect at next Project Advisory Team meeting.

NOTES:

1. Mr. Scott Fendrick opened the meeting with a review of the milestone schedule

2. Scott also reviewed the 2007 Bond Project and relayed that a mini project is being prepared with a construction start near

the end of the school year. This is to avoid disrupting classes and allow time for the documents to be prepared in a

thoughtful manner and verify inclusion in the upcoming 2012 project.

3. A question was asked about items previously under construction still being incomplete. Scott Fendrick responded that

incomplete work identified in the contract documents will be completed. He also offered to evaluate work to determine

what scope it could be attributed to. If the scope is identified as incomplete he will assist in getting it completed. If the

work is not in the contract documents we will look into alternative resolutions.

Page 24: CONSTRUCTION AND FACILITY SERVICES (CFS)...Schematic Design / Design Charette Design Development Community Meeting 2 Contract Documents Permitting Community Meeting 3 Construction

Customer Focused . . . Always Responsive!

Office: 713-556-9299 Fax: 713-676-9582

ACTION ITEMS:

• HISD Facilities Planning to arrange tours to other facilities.

NEXT MEETING:

• Presentation of more developed design and scope concepts as by Gensler Architects.

Please review the meeting minutes and submit any changes or corrections to Scott Fendrick

After five (5) days, the minutes will be assumed to be accurate.

Sincerely,

Scott Fendrick

Project Manager

HISD – Construction & Facility Services

3200 Center Street, Houston, TX 77007

Phone: (713) 556-9322

[email protected]

Page 25: CONSTRUCTION AND FACILITY SERVICES (CFS)...Schematic Design / Design Charette Design Development Community Meeting 2 Contract Documents Permitting Community Meeting 3 Construction

Customer Focused . . . Always Responsive!

Office: 713-556-9299 Fax: 713-676-9582

CONSTRUCTION AND FACILITY SERVICES (CFS)

3200 Center Street, Houston TX 77007-5909

Facilities Planning Project Advisory Team Meeting Minutes

Waltrip High School

MEETING NO.: 009

LOCATION: Waltrip High School, College Prep Room

DATE / TIME: January 27, 4:30-6:30pm

ATTENDEES: Bill Chambers, CMAR Contractor; Catherine Clay, Teacher; Daisy Cnagcya, Student HOSA; Dr. Enloe, Waltrip

Alumni; Jesse Espinosa, Band Director; Scott Fendrick, HISD Project Manager; Steve Hoyt; HISD Sr. Project

Manager; Mary Gibson, Teacher/Alumni; Kimberly Hickson, Gensler Architects; Cynthia Krohn; Staff Member;

Nina Murrell, Gensler Architects; Jeff Turner, Staff Member; Elizabeth Villareal, Parent; Stephanie Witherspoon,

Teacher;

PURPOSE: The purpose of this meeting was to discuss 21st Century Learning and review photos provided by those who

attended the site tours in Seattle Washington. Many of these ideas could be considered and incorporated into the

Waltrip HS 21st century leaning environment.

Programming/ Capacity

Model/ Ed. Specs.

Community

Meeting 1

Schematic Design/

Design Charette

Design

Development

Community

Meeting 2

Contract

Documents

Permitting Community

Meeting 3

Construction

AGENDA ITEMS:

� Review progress with Milestone Schedule � 2007 Bond Project Update/Summer Package � Design Charrette Outline/Discussion, January 29, and 30. � Determine action items to complete before next meeting. � Next Project Advisory Team meeting March 24, 2014, 4:30pm (4th Monday) � What to expect at next Project Advisory Team meeting.

NOTES:

1. Mr. Scott Fendrick opened the meeting with a review of the milestone schedule

2. Scott also reviewed the 2007 Bond Project and relayed that a mini project is being prepared with a construction start near

the end of the school year. This is to avoid disrupting classes and allow time for the documents to be prepared in a

thoughtful manner and verify inclusion in the upcoming 2012 project.

3. A question was asked about items previously under construction still being incomplete. Scott Fendrick responded that

incomplete work identified in the contract documents will be completed. He also offered to evaluate work to determine

what scope it could be attributed to. If the scope is identified as incomplete he will assist in getting it completed. If the

work is not in the contract documents we will look into alternative resolutions.

Page 26: CONSTRUCTION AND FACILITY SERVICES (CFS)...Schematic Design / Design Charette Design Development Community Meeting 2 Contract Documents Permitting Community Meeting 3 Construction

Customer Focused . . . Always Responsive!

Office: 713-556-9299 Fax: 713-676-9582

ACTION ITEMS:

• HISD Facilities Planning to arrange tours to other facilities.

NEXT MEETING:

• Presentation of more developed design and scope concepts as by Gensler Architects.

Please review the meeting minutes and submit any changes or corrections to Scott Fendrick

After five (5) days, the minutes will be assumed to be accurate.

Sincerely,

Scott Fendrick

Project Manager

HISD – Construction & Facility Services

3200 Center Street, Houston, TX 77007

Phone: (713) 556-9322

[email protected]

Page 27: CONSTRUCTION AND FACILITY SERVICES (CFS)...Schematic Design / Design Charette Design Development Community Meeting 2 Contract Documents Permitting Community Meeting 3 Construction

Customer Focused . . . Always Responsive!

Office: 713-556-9299 Fax: 713-676-9582

CONSTRUCTION AND FACILITY SERVICES (CFS)

3200 Center Street, Houston TX 77007-5909

Facilities Planning Project Advisory Team Meeting Minutes

Waltrip High School

MEETING NO.: 009

LOCATION: Waltrip High School, College Prep Room

DATE / TIME: January 27, 4:30-6:30pm

ATTENDEES: Bill Chambers, CMAR Contractor; Catherine Clay, Teacher; Daisy Cnagcya, Student HOSA; Dr. Enloe, Waltrip

Alumni; Jesse Espinosa, Band Director; Scott Fendrick, HISD Project Manager; Steve Hoyt; HISD Sr. Project

Manager; Mary Gibson, Teacher/Alumni; Kimberly Hickson, Gensler Architects; Cynthia Krohn; Staff Member;

Nina Murrell, Gensler Architects; Jeff Turner, Staff Member; Elizabeth Villareal, Parent; Stephanie Witherspoon,

Teacher;

PURPOSE: The purpose of this meeting was to discuss 21st Century Learning and review photos provided by those who

attended the site tours in Seattle Washington. Many of these ideas could be considered and incorporated into the

Waltrip HS 21st century leaning environment.

Programming/ Capacity

Model/ Ed. Specs.

Community

Meeting 1

Schematic Design/

Design Charette

Design

Development

Community

Meeting 2

Contract

Documents

Permitting Community

Meeting 3

Construction

AGENDA ITEMS:

� Review progress with Milestone Schedule � 2007 Bond Project Update/Summer Package � Design Charrette Outline/Discussion, January 29, and 30. � Determine action items to complete before next meeting. � Next Project Advisory Team meeting March 24, 2014, 4:30pm (4th Monday) � What to expect at next Project Advisory Team meeting.

NOTES:

1. Mr. Scott Fendrick opened the meeting with a review of the milestone schedule

2. Scott also reviewed the 2007 Bond Project and relayed that a mini project is being prepared with a construction start near

the end of the school year. This is to avoid disrupting classes and allow time for the documents to be prepared in a

thoughtful manner and verify inclusion in the upcoming 2012 project.

3. A question was asked about items previously under construction still being incomplete. Scott Fendrick responded that

incomplete work identified in the contract documents will be completed. He also offered to evaluate work to determine

what scope it could be attributed to. If the scope is identified as incomplete he will assist in getting it completed. If the

work is not in the contract documents we will look into alternative resolutions.

Page 28: CONSTRUCTION AND FACILITY SERVICES (CFS)...Schematic Design / Design Charette Design Development Community Meeting 2 Contract Documents Permitting Community Meeting 3 Construction

Customer Focused . . . Always Responsive!

Office: 713-556-9299 Fax: 713-676-9582

ACTION ITEMS:

• HISD Facilities Planning to arrange tours to other facilities.

NEXT MEETING:

• Presentation of more developed design and scope concepts as by Gensler Architects.

Please review the meeting minutes and submit any changes or corrections to Scott Fendrick

After five (5) days, the minutes will be assumed to be accurate.

Sincerely,

Scott Fendrick

Project Manager

HISD – Construction & Facility Services

3200 Center Street, Houston, TX 77007

Phone: (713) 556-9322

[email protected]

Page 29: CONSTRUCTION AND FACILITY SERVICES (CFS)...Schematic Design / Design Charette Design Development Community Meeting 2 Contract Documents Permitting Community Meeting 3 Construction

Customer Focused . . . Always Responsive!

Office: 713-556-9299 Fax: 713-676-9582

CONSTRUCTION AND FACILITY SERVICES (CFS)

3200 Center Street, Houston TX 77007-5909

Facilities Planning Project Advisory Team Meeting Minutes

Waltrip High School

MEETING NO.: 009

LOCATION: Waltrip High School, College Prep Room

DATE / TIME: January 27, 4:30-6:30pm

ATTENDEES: Bill Chambers, CMAR Contractor; Catherine Clay, Teacher; Daisy Cnagcya, Student HOSA; Dr. Enloe, Waltrip

Alumni; Jesse Espinosa, Band Director; Scott Fendrick, HISD Project Manager; Steve Hoyt; HISD Sr. Project

Manager; Mary Gibson, Teacher/Alumni; Kimberly Hickson, Gensler Architects; Cynthia Krohn; Staff Member;

Nina Murrell, Gensler Architects; Jeff Turner, Staff Member; Elizabeth Villareal, Parent; Stephanie Witherspoon,

Teacher;

PURPOSE: The purpose of this meeting was to discuss 21st Century Learning and review photos provided by those who

attended the site tours in Seattle Washington. Many of these ideas could be considered and incorporated into the

Waltrip HS 21st century leaning environment.

Programming/ Capacity

Model/ Ed. Specs.

Community

Meeting 1

Schematic Design/

Design Charette

Design

Development

Community

Meeting 2

Contract

Documents

Permitting Community

Meeting 3

Construction

AGENDA ITEMS:

� Review progress with Milestone Schedule � 2007 Bond Project Update/Summer Package � Design Charrette Outline/Discussion, January 29, and 30. � Determine action items to complete before next meeting. � Next Project Advisory Team meeting March 24, 2014, 4:30pm (4th Monday) � What to expect at next Project Advisory Team meeting.

NOTES:

1. Mr. Scott Fendrick opened the meeting with a review of the milestone schedule

2. Scott also reviewed the 2007 Bond Project and relayed that a mini project is being prepared with a construction start near

the end of the school year. This is to avoid disrupting classes and allow time for the documents to be prepared in a

thoughtful manner and verify inclusion in the upcoming 2012 project.

3. A question was asked about items previously under construction still being incomplete. Scott Fendrick responded that

incomplete work identified in the contract documents will be completed. He also offered to evaluate work to determine

what scope it could be attributed to. If the scope is identified as incomplete he will assist in getting it completed. If the

work is not in the contract documents we will look into alternative resolutions.

Page 30: CONSTRUCTION AND FACILITY SERVICES (CFS)...Schematic Design / Design Charette Design Development Community Meeting 2 Contract Documents Permitting Community Meeting 3 Construction

Customer Focused . . . Always Responsive!

Office: 713-556-9299 Fax: 713-676-9582

ACTION ITEMS:

• HISD Facilities Planning to arrange tours to other facilities.

NEXT MEETING:

• Presentation of more developed design and scope concepts as by Gensler Architects.

Please review the meeting minutes and submit any changes or corrections to Scott Fendrick

After five (5) days, the minutes will be assumed to be accurate.

Sincerely,

Scott Fendrick

Project Manager

HISD – Construction & Facility Services

3200 Center Street, Houston, TX 77007

Phone: (713) 556-9322

[email protected]