construction contract variations .pptx

Upload: errajeshkumar

Post on 10-Feb-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/22/2019 Construction Contract Variations .Pptx

    1/24

    CONSTRUCTION CONTRACT VARIATIONS

    19 FEBRUARY 2014

    MICHAEL SERGEANT, PARTNER

    T: +44 20 7264 8034

    [email protected]

  • 7/22/2019 Construction Contract Variations .Pptx

    2/24

    Qatar Civil Code

    Article 709

    Under a lump sum contract to undertake works to an agreed plan,

    the contractor may not seek any additional monies because of

    some alteration or addition to the plan, unless it can be attributed to

    an act of the employer or the employer has authorised the change

    and has agreed with the contractor its entitlement.

  • 7/22/2019 Construction Contract Variations .Pptx

    3/24

    Basic Principles (1)

    A contractor must construct the Scope of Works described in the

    contract An employer has no automatic right to insist on a change to the

    Scope of Works

    Variations clauses are included in contracts to give the employer the

    right to insist on changes

    In order for a variation to be validly instructed it must be:

    Instructed in accordance with the rules & procedure within the contract

    A change that the employer is entitled to order (type of work, value,

    timing)

  • 7/22/2019 Construction Contract Variations .Pptx

    4/24

    Basic Principles (2)

    If an employer instructs a valid variation in accordance with the

    contract provisions then: The contractor must undertake the changed work

    The contractor will get extra money & time in accordance with the

    contract provisions

    If there is no a valid change instruction then:

    The contractor may not build something different to the contract Scope of

    Works

    The contractual rights to money & time for variations that arise under the

    contract are not triggered

  • 7/22/2019 Construction Contract Variations .Pptx

    5/24

    Basic Principles (3)

    The process of instructing variations is normally undertaken by the

    Engineer The Engineer acts as the agent of the employer when ordering

    variations

    As with any agent, the Engineer only has power to act within the

    scope of the powers he has been given (Qatar Civil Code, Articles

    81

    90)

    The construction contract sets out the scope of the Engineer's

    powers to instruct change

    It will typically be the case that the Engineer can only validly instruct

    changes that are ordered by a formal Variation Order

  • 7/22/2019 Construction Contract Variations .Pptx

    6/24

    Common problems

    What is within/ outside the Scope of Works?

    If the contractor carries out extra work without an instruction can itstill claim payment?

    Changes that are only needed because of the contractor's failure/

    default: Are these variations?

    Particular issues that arise when varying under Design & Buildcontracts

  • 7/22/2019 Construction Contract Variations .Pptx

    7/24

    What is within/outside the Scope of Works? (1)

    The contractor is typically required to undertake the Scope of Works

    as described in a large number of documents The Scope documents will often contain inconsistencies,

    ambiguities, gaps and contradictions

    The process of establishing what the Scope is will involve

    considering

    The relevant law on the interpretation of contracts, such as Qatar Civil

    Code Articles 169 & 170

    Priority of documents clause listing the order of importance of

    documents; e.g. FIDIC Red Book clause 1.5

    Clauses requiring the contractor to identify errors in the employer'sdocuments within a time-scale or take the risk; e.g. FIDIC Yellow Book

    clause 5.1.

  • 7/22/2019 Construction Contract Variations .Pptx

    8/24

    What is within/outside the Scope of Works (2)

    Having analysed the relevant rules/ law on interpretation the position can

    be either:

    1. There is a gap/ contradiction in the Scope so the contractor has no obligation

    to do extra work unless instructed as a variation

    2. The contract requires the contractor to undertake all work that is necessary to

    complete the project even though it is not specifically referred to

  • 7/22/2019 Construction Contract Variations .Pptx

    9/24

    What is within/outside the Scope of Works? (3)

    One of the benefits of a Design & Build contract is that it limits the

    risk of "gaps" in the Scope. A Design & Build contractor should be required to build the works

    according to a 2-stage test:

    1. The contractor must follow the specification, drawings etc. (i.e. the

    contractor's technical design)

    2. But the contractor must also ensure that this achieves the stipulated

    performance/ design standard (the Employer's Requirements)

    Gaps in the contractor's technical design do not mean variations

    because the contractor must resolve such problems in order to

    achieve the Employer's Requirements

  • 7/22/2019 Construction Contract Variations .Pptx

    10/24

    What is within/outside the Scope of Works? (4)

    Under a build-only contract there is a much greater risk of gaps in

    the description of the works The contractor will just be required to build in accordance with the

    technical description: the specification and the drawings

    There will not normally be overarching "project aims &

    requirements" that must be achieved

    Risk of a deadlock arising:

    The contractor says that it will not build certain work unless a variation

    instruction is issued

    The employer says that it will not issue the instruction because the work

    is within the Scope

  • 7/22/2019 Construction Contract Variations .Pptx

    11/24

  • 7/22/2019 Construction Contract Variations .Pptx

    12/24

    No variation instruction: Contractor still claims extra (2)

    Typical problem situations

    1. The contractor makes a change to the Scope because it thinks

    that it is an improvement. The employer is happy with the

    improvement but refuses to pay extra because there was no

    Variation Order.

    2. The employer refuses to issue a Variation Order because it thinks

    that the item of work is within the Scope. The contractor later

    establishes that the item of work is extra. The employer says it

    has no obligation to pay because no Variation Order was issued.

  • 7/22/2019 Construction Contract Variations .Pptx

    13/24

    No variation instruction: Contractor still claims extra (3)

    Typical problem situations

    3. The employer asks the contractor to do extra work but does not

    issue a formal Variation Order. The employer tells the contractor

    that this does not matter and will not affect his right to money. It

    later refuses to pay on the basis that there is no Variation Order.

    4. The contractor is undertaking excavation and hits unexpectedly

    bad ground and so cannot undertake the defined Scope. The

    employer refuses to give a Variation Order.

  • 7/22/2019 Construction Contract Variations .Pptx

    14/24

    No variation instruction: Contractor still claims extra (4)

    The common arguments raised by contractors:

    The contract itself has been varied:

    Distinction between a variation instructed under the contract and a

    variation to the contract terms

    The parties to a contract may agree to vary its terms, including the

    description of the product being sold

    The parties themselves must vary the contract The Engineer will not

    normally have authority to vary the contract itself

    The contract itself may stipulate that variations to the contract terms will

    only be valid if recorded in a stipulated format

  • 7/22/2019 Construction Contract Variations .Pptx

    15/24

  • 7/22/2019 Construction Contract Variations .Pptx

    16/24

    No variation instruction : Contractor still claims extra (6)

    The common arguments raised by contractors:

    The employer/ Engineer refuses to issue a Variation Order on thebasis that the work in question is within the Scope and therefore is

    not a change:

    In English law this is treated as an implied promise to pay; i.e. because

    the VO is refused on a false assumption

    Breach of a party's duty of good faith (Qatar Civil Code, Article 172)

  • 7/22/2019 Construction Contract Variations .Pptx

    17/24

    No variation instruction: Contractor still claims extra (7)

    The common arguments raised by contractors:

    The contractor cannot continue with/ complete the project unless itmakes a change to the Scope

    The employer & contractor have agreed that the defined Scope will be

    built

    The employer is not obliged to receive something that is different

    What is the Scope? e.g. under a D&B contract the contractor may be

    obliged to depart from the specification/ drawings in order to achieve the

    Employer's Requirements

    A contract will often give the contractor other rights to claim for the costs

    of necessary changes to the way the works are undertaken; e.g. Ground

    Conditions clauses (FIDIC Red Book clause 4.12) or loss & expenseclauses

  • 7/22/2019 Construction Contract Variations .Pptx

    18/24

    Variation required because of contractor's failure/risk (1)

    Examples of situations where this arises:

    The contractor delays in ordering the specified materials which have a

    long lead-in time. The contractor wants to order different (more

    expensive) materials instead to avoid delay.

    It becomes clear that the design & build contractor's foundations design

    is inadequate and therefore it needs to be changed.

    The employer may issue a Variation Order but may not expect to

    pay for the change

  • 7/22/2019 Construction Contract Variations .Pptx

    19/24

    Variation required because of contractor's failure/risk (2)

    The employer needs to be very careful in these situations

    Construction contracts often make no distinction concerning thereasons a variation is instructed - Normally a VO = money & time

    There can be a number of reasons why a VO was issued

    An employer should give the contractor permission to make the

    change rather than issue a VO If the contractor thinks that the change is not its fault then it may

    insist on a VO before doing the work

  • 7/22/2019 Construction Contract Variations .Pptx

    20/24

    Particular issues relating to design liability (1)

    Under a design & build contract the contractor has agreed to take

    design responsibility for the defined Scope of Works The employer can vary the Scope of Works:

    Is the contractor still responsible for the design integrity even though it is

    not the Scope as contained in the original contract?

    If not, then the employer no longer has a full design warranty

  • 7/22/2019 Construction Contract Variations .Pptx

    21/24

  • 7/22/2019 Construction Contract Variations .Pptx

    22/24

    Particular issues relating to design liability (3)

    Since the employer changes the Employer's Requirements (the

    output criteria) then it has limited control over the design solution This may mean that the employer has limited control over the cost

    of the change

    Potential for dispute as to whether the design solution is over

    engineered

    Provisions allowing for the employer to make requests for design

    change proposals and to agree on the change (plus cost & time) in

    advance

  • 7/22/2019 Construction Contract Variations .Pptx

    23/24

    Questions

  • 7/22/2019 Construction Contract Variations .Pptx

    24/24