construction engg

17
CONSTRUCTION ENGINEERING FOR INSTRUMENTATION GUIDELINE FOR INSTRUMENT LAYOUT Overview The purpose of writing this document is to brief the fundamental points to be considered for Instrumentation Construction Engineering. Detail Engineering: 1. Plant General Layout & Shop Layout is based on the process and equipment data of basic engineering documents, plant general layout as well as the shop layouts for the various plant units and facilities will be developed. While developing the layout, site conditions will be kept in view and provision will be made for future expansion. 2. Division List of Supplies The preparation of division list of supplies of PLANT & EQUIPMENT to be obtained from indigenous and foreign sources. 3. Technical Specification Prepare technical specification and related drawings to invite tenders for supply of plant & equipment. Also evaluate the tenders and submit technical recommendations for award of contract. 4.0 Architectural, Civil & Structural Designs & Drawings 4.1 Civil Work Prepare working drawings for the following: Main Plant buildings Auxiliary buildings Buildings & Equipment foundations 4.2 Structural Steel Work Prepare design drawings, for structural steel work in buildings, staging and platforms. Shop detailed drawings (fabrication drawings) as in customary will be prepared by the fabricators. 5.0 Design & Drawings For Utilities & Services 5.1 Plant Water System Make arrangement for availability of adequate water at one point within the plant boundary. From this point onwards, design internal plant water distribution system including pumping, treatment & cooling facilities. Also design a suitable fire fighting system based on fire hydrants. 5.2 Power Supply & Distribution Make arrangements for getting adequate high-tension power at one point within the plant boundary. From this point design the plant substation power distribution and lighting systems including single line diagram. Also design a suitable emergency power system, if required. 5.3 Communication and Instrumentation System Prepare schematic drawing and specifications for the supply and installation of the communication and instrumentation system for the plant.

Upload: dattatray-nikam

Post on 12-Nov-2014

5.122 views

Category:

Documents


3 download

DESCRIPTION

This document will basically cover the following topics.1.Detail Engineering2.Construction Layouts3.Instrument Hook-Ups4.Material Tak-off for instrument items.This document is very good for the begineers who are starting their early carrer in the field of Detail Engineering.

TRANSCRIPT

Page 1: Construction Engg

CONSTRUCTION ENGINEERING FOR INSTRUMENTATION

GUIDELINE FOR INSTRUMENT LAYOUT

Overview The purpose of writing this document is to brief the fundamental points to be considered for Instrumentation

Construction Engineering.

Detail Engineering:

1. Plant General Layout & Shop Layout is based on the process and equipment data of basic engineering

documents, plant general layout as well as the shop layouts for the various plant units and facilities will be developed.

While developing the layout, site conditions will be kept in view and provision will be made for future expansion.

2. Division List of Supplies The preparation of division list of supplies of PLANT & EQUIPMENT to be obtained

from indigenous and foreign sources.

3. Technical Specification Prepare technical specification and related drawings to invite tenders for supply of plant &

equipment. Also evaluate the tenders and submit technical recommendations for award of contract.

4.0 Architectural, Civil & Structural Designs & Drawings

4.1 Civil Work Prepare working drawings for the following: Main Plant buildings Auxiliary buildings Buildings &

Equipment foundations

4.2 Structural Steel Work Prepare design drawings, for structural steel work in buildings, staging and platforms. Shop

detailed drawings (fabrication drawings) as in customary will be prepared by the fabricators.

5.0 Design & Drawings For Utilities & Services 5.1 Plant Water System Make arrangement for availability of adequate water at one point within the plant boundary.

From this point onwards, design internal plant water distribution system including pumping, treatment & cooling facilities.

Also design a suitable fire fighting system based on fire hydrants.

5.2 Power Supply & Distribution Make arrangements for getting adequate high-tension power at one point within the

plant boundary. From this point design the plant substation power distribution and lighting systems including single line

diagram. Also design a suitable emergency power system, if required.

5.3 Communication and Instrumentation System Prepare schematic drawing and specifications for the supply and

installation of the communication and instrumentation system for the plant.

Page 2: Construction Engg

CONSTRUCTION ENGINEERING FOR INSTRUMENTATION

GUIDELINE FOR INSTRUMENT LAYOUT

5.4 Plant air, instrument air, Fuel, Steam & Other Utilities Design the Plant air, instrument air, fuel, steam and other

utility systems and prepare outline drawings and specification.

5.5 Ventilation, Air Conditioning, Extraction System Design the ventilation, air conditioning, dust & fume control

systems and prepare outline drawings and specification.

5.6 Storm Water Drainages & Effluent Disposal Systems For contaminated process water which need treatment before

being discharged into plant drainage, prepare a scheme for treatment according to existing STANDARD and prepare

drawings and specifications.

5.7 Sewerage System Design a sewerage system and prepare drawings and specifications for the construction of the

same.

5.8 Roads, Fences & Gates Design and prepare drawings and specifications for construction of roads, fences and gates

within the plant boundary.

5.9 Material Handling & Storage Design of storage and handling facilities within the plant boundary for raw materials

and finished products and prepare outline drawings and specifications.

5.10 Auxiliary Facilities & Ancillary Buildings Design and prepare drawings for auxiliary facilities like repair &

maintenance shop, central stores, plant laboratory and ancillary buildings such as administrative building, gate house, fire

station, canteen, first aid station, charge rooms, parking lots, shop offices, garages, etc.

6.0 Assistance in Commissioning Render technical assistance during commissioning of the plant and equipment. Also

witness the performance guarantee tests to be conducted by the equipment suppliers and assist for issuing Acceptance

Certificate for taking over the equipment on satisfactory completion of the tests.

7.0 Master Network/Progress Schedule

7.1 Prepare overall project construction schedules including the initial master network. This will be updated and

finalised taking into account the actual placement of order on different parties. Advise for corrective measures to be taken

to maintain the overall time schedule.

7.2 Prepare quarterly progress reports indicating progress of construction and erection of the plant and equipment.

These reports will indicate achievement against targets and spell out actions to be taken in specific areas, if any, to

maintain the time schedule.

8.0 Designer's Supervision means: Interpretation of drawings, Interpretation of specifications and codes of practices,

Variation in design and materials Design modifications due to site condition, Interpretation of test results, preliminary

acceptance and final acceptance tests of the erected plant & equipment.

Available resources are taken note of, as also the resources further needed and they are allocated. Contract

documents are prepared keeping in the mind the role of the participating agencies to avoid ambiguities, duel responsibility

and confusion at a later date.

In case of small building projects, where the owner is the promoter, he arranges the finance himself and engages the

contractors or suppliers, without going into the complexities of preparation of tender documents. But he also gets a detailed

design from his consultant and fixes his terms, conditions and rate with his contractors and suppliers.

Engineering is the activities where all the details study is being carried out such as preparation of instrument

datasheets and all the construction details.

Page 3: Construction Engg

CONSTRUCTION ENGINEERING FOR INSTRUMENTATION

GUIDELINE FOR INSTRUMENT LAYOUT

Construction Layout:

Layout is a systematic arrangement of an instrument items installation in Oil & Gas field as well as Refineries and

Petrochemical complex. Types of Layouts are categories as follows.

Construction Layouts: To prepare construction layout for Overall Instrument Cable tray trench routing basic input

information required is overall plot plan where one can see or marked detail of all equipment, skids and packages are

installed. With this one can start planning for instrumentation construction work like preparation of cable trench tray

routing layout, JB location and Instrument location plans.

Fig.1: Overall Plot Plan Construction layouts are broadly categories as follows.

1. Overall Tray/Trench Layouts.

2. Instrument Location Layouts.

3. JB Location Layouts.

Other, deliverable of Instrumentation design departments related to construction activities are as follows.

1. Hook Diagrams.

a. Pneumatic Hook-ups

b. Process Hook-ups

2. Cable schedule

3. Wiring Diagrams

4. Material MTO.

5. Details sections are explain in the subsequent article as follows.

1. Overall Tray /Trench Layouts: In this type of layout documents, entire cable tray /trench routing are shown for cable laying.

Interconnections between control room to field are shown by this layout. Refer following fig for reference of such

layout drawings.

Page 4: Construction Engg

CONSTRUCTION ENGINEERING FOR INSTRUMENTATION

GUIDELINE FOR INSTRUMENT LAYOUT

The tray /trench routing, elevation and type of cable tray, size of tray and all detail section are generally shown

as minimum.

Fig. 2: Cable Tray layout

Fig. 3: Cable tray section detail

Page 5: Construction Engg

CONSTRUCTION ENGINEERING FOR INSTRUMENTATION

GUIDELINE FOR INSTRUMENT LAYOUT

Fig. 4 Actual Cable tray layouts

2. Instrumentation Location Layouts and JB Layouts: In this type of drawings generally instrument locations are marked at their respective elevation which is provided to us

by piping departments.

In some of the organization Instrument location layout and JB grouping are shown in the same layouts. Please refer

layout as marked in below for Instruments as well as JBs.

Page 6: Construction Engg

CONSTRUCTION ENGINEERING FOR INSTRUMENTATION

GUIDELINE FOR INSTRUMENT LAYOUT

Instrument Hookup Drawings An engineering drawing prepared or it represents mechanical arrangement techniques for instrument installation.

Instrument Hookup Drawings provides a utility that manages the installation details and components. The

Hookup Diagram provides a dynamic Bill of Materials for Instrumentation.

Types of Hook-Ups:

1. Pneumatic Hookups.

Pneumatic hook up means it is independent of process connection. This is basically a tubing/piping work.

2. Process Hookups:

Process hook ups means instruments are installed directly on process line.

Page 7: Construction Engg

CONSTRUCTION ENGINEERING FOR INSTRUMENTATION

GUIDELINE FOR INSTRUMENT LAYOUT

Page 8: Construction Engg

CONSTRUCTION ENGINEERING FOR INSTRUMENTATION

GUIDELINE FOR INSTRUMENT LAYOUT

Page 9: Construction Engg

CONSTRUCTION ENGINEERING FOR INSTRUMENTATION

GUIDELINE FOR INSTRUMENT LAYOUT

Pneumatic Hook Ups

Page 10: Construction Engg

CONSTRUCTION ENGINEERING FOR INSTRUMENTATION

GUIDELINE FOR INSTRUMENT LAYOUT

Page 11: Construction Engg

CONSTRUCTION ENGINEERING FOR INSTRUMENTATION

GUIDELINE FOR INSTRUMENT LAYOUT

Cable Schedule:

Page 12: Construction Engg

CONSTRUCTION ENGINEERING FOR INSTRUMENTATION

GUIDELINE FOR INSTRUMENT LAYOUT

Material Take –Off (MTO):

This is the total MTO of all the instrument items such as Cable tray, Cables (IS & Non-IS),JBs and instrument tube/pipe

fittings. Also in these MTO depends upon the scope of work all structural steel required can be added.

CONSTRUCTION MTO FOR INSTRUMENTATION ITEMS

Sr.nos. Description of items Unit ST-T1

ST-T2

ST-B

ST-S ST-W1

72-SBV-31

Total Rema

rks

1 Instrument cable trays - (Refer General Instrument specification for Packaged equipement:1806-5018-3 clause 5.4)

Note 1

a 50mm W x 20 mm H ( SS316) M - - 35 - - - 35

b 300mm W x 50 mm H (SS316) M - - 86 - - - 86

c 450mm W x 60 mm H(SS316) M - - 90 - - - 90

2 160 dia. PVC Conduit for direct buried M 370 160 - 50 30 30 640

3 160 dia. GI Conduit in Trench M 330 - - - - - 330

4 Instrument Cables - (Refer General Instrument specification for Packaged equipement:1806-5018-3 clause 5.1)

a IS Cables

TYPE 1(IS)-1P X 1.5 mm² M 676 160 64 128 64 - 1092

TYPE 1(IS)-1P X 2.5 mm² M - - - - - 80 80

TYPE 3(IS)-2P X 1.5 mm² M 96 - - - - - 96

TYPE 3(IS )-5P X 1.5 mm² M 112

0 - 284 208 336 - 1948

TYPE 3(IS)-10P X 1.5 mm² M 464 - - 104 - - 568

TYPE 3 (IS)-10P X 2.5 mm² M - 2080

- - - 1040 3120

TYPE 3(IS)-20P X 1.5 mm² M 208 - - - - - 208

TYPE 4(IS)-2P X 1.5 mm² M - - - 48 - - 48

TYPE 4(IS)-10P X 1.5 mm² M 744 - 16 - 32 - 792

Page 13: Construction Engg

CONSTRUCTION ENGINEERING FOR INSTRUMENTATION

GUIDELINE FOR INSTRUMENT LAYOUT

TYPE 4(IS)-10P X 2.5 mm² M - - - - - 16 16

Sr.nos. Description of items Unit ST-T1

ST-T2

ST-B

ST-S ST-W1

72-SBV-31

Total Rema

rks

TYPE 4(IS)-20P X 1.5 mm² M 476 2080

136 32 224 1040 3988

TYPE 7 (IS)-1T X 1.5 mm² M 24 - 8 - - - 32

TYPE 7 (IS)-1T X 2.5 mm² M - - - - - 16 16

TYPE 7 (IS)-2T X 2.5 mm² M - 32 - - - - 32

b Non IS Cables

TYPE 1(NIS)-1P X 1.5 mm² M 628 - 48 - 64 - 740

TYPE 1(NIS)-1P X 2.5 mm² M - 160 - - - 32 192

TYPE 3 (NIS)-1P X 1.5 mm² M 448 - - - - - 448

TYPE 3 (NIS)-2P X 1.5 mm² M - - 228 - 224 - 452

TYPE 3 (NIS)-5P X 1.5 mm² M - - 112 - - - 112

TYPE 3 (NIS)-10P X 1.5 mm² M 48 - 48 96 32 - 224

TYPE 4(NIS)-1P X 1.5 mm² M - 2080

32 - - - 2112

TYPE 4(NIS)-1P X 2.5 mm² M - 64 - - - - 64

TYPE 4(NIS)-10P X 2.5 mm² M - 32 - - - 1088 1120

TYPE 4(NIS)-5P X 1.5 mm² M 604 - 280 - 64 - 948

TYPE 4(NIS)-10P X 1.5 mm² M 564 50 190 146 306 50 1306

TYPE 4(NIS)-20P X 1.5 mm² M 100 50 370 258 162 50 990

TYPE 4(NIS)-30P X 1.5 mm² M 160 - 136 208 112 - 616

Page 14: Construction Engg

CONSTRUCTION ENGINEERING FOR INSTRUMENTATION

GUIDELINE FOR INSTRUMENT LAYOUT

TYPE 4(NIS)-30P X 2.5 mm² M - - - - - 1040 1040

Sr.nos. Description of items Unit ST-T1

ST-T2

ST-B

ST-S ST-W1

72-SBV-31

Total Rema

rks

NON IS-10P X 2.5 mm² M - - - - - 1040 1040

CU/XLPE/SWB/PVC-1P X 1.5 mm² M 416 - - - 224 - 640

CU/XLPE/SWB/PVC-2C X 2.5 mm² M - - 228 - - - 228

c Earthing wire Note 2

Cable tray continuity: 16sqmm M - - 85 - - - 85

Panel earth to electrical earthgrid: 6sqmm M 400 400 400 400 400 400 2400

JB earths : 6sqmm M 190 50 100 50 80 40 510

Instrument earthing: 4sqmm M 770 140 220 120 140 100 1490

5 Instrument Junction boxes - (Refer General Instrument specification for Packaged equipement:1806-5018-3 clause 5.5)

5.1. a JB-IS (SS304 , IP 65) Note 3

20 terminal JBs ( IS ) NOS 6 - 1 1 - - 8

40 terminal JBs ( IS ) NOS 3 - - 1 2 1 7

70 terminal JBs ( IS ) NOS 4 3 1 - - 1 9

100 terminal JBs ( IS ) NOS - - - - 1 - 1

5.1. b Spare plugs for JB-IS Note 4

20 terminal JBs NOS 12 - 2 2 - - 16

40 terminal JBs NOS 9 - - 3 6 3 21

70 terminal JBs NOS 24 18 6 - - 6 54

100 terminal JBs NOS - - - - 9 - 9

Page 15: Construction Engg

CONSTRUCTION ENGINEERING FOR INSTRUMENTATION

GUIDELINE FOR INSTRUMENT LAYOUT

5.1. c Instrument Cable Glands (SS316, complete with shroud) for IS JBs - (Refer General Instrument specification for Packaged equipement:1806-5018-3 clause 5.3)

Cable gland (M20S) NOS 82 0 4 22 12 - 120

Sr.nos. Description of items Unit ST-T1

ST-T2

ST-B

ST-S ST-W1

72-SBV-31

Total Rema

rks

Cable gland (M20) NOS 16 26 4 - - 14 60

Cable gland (M25) NOS 12 - 6 2 6 - 26

Cable gland (M32) NOS 22 - 2 4 2 - 30

Cable gland (M40) NOS 8 12 2 0 4 4 30

Cable gland (M50) NOS - 4 2 - - 2 8

5.2.a JB-Non -IS (EExe,SS304, IP 65) Note 3

20 terminal JBs ( IS ) NOS 3 - 2 - - - 5

40 terminal JBs ( IS ) NOS 2 - 2 1 3 1 9

70 terminal JBs ( IS ) NOS 1 2 3 1 1 0 8

100 terminal JBs ( IS ) NOS - - 1 1 1 1 4

5.2.b Spare plugs for JB-Non IS Note 4

20 terminal JBs NOS 6 - 4 - - - 10

40 terminal JBs NOS 6 - - 3 9 3 21

70 terminal JBs NOS 6 12 18 - - 0 36

100 terminal JBs NOS - - - - 9 - 9

5.2.c Instrument Cable Glands (SS316, complete with shroud) for Non IS JBs - (Refer General Instrument specification for Packaged equipement:1806-5018-3 clause 5.3)

Cable gland (M20S) NOS 42 - 12 12 - - 66

Cable gland(M20) NOS 8 18 12 - 16 4 58

Page 16: Construction Engg

CONSTRUCTION ENGINEERING FOR INSTRUMENTATION

GUIDELINE FOR INSTRUMENT LAYOUT

Cable gland(M25) NOS 6 - 22 - 8 - 36

Cable gland(M32) NOS 20 - 14 12 16 - 62

Sr.nos. Description of items Unit ST-T1

ST-T2

ST-B

ST-S ST-W1

72-SBV-31

Total Rema

rks

Cable gland(M40) NOS - 4 6 2 4 10 26

Cable gland(M50) NOS - 4 - - - - 4

Cable gland(M50S) NOS 2 - 2 2 2 - 8

Cable gland(M60) NOS - - - - - 2 2

6 MTO -HOOK-UPS (Refer Inst. Process hook -up diagrams (Typical) : 1806-5022 & Inst. Pneumatic hook -up diagrams (Typical) :1806-5029 )

a Tubes

1/2"OD Tube x 0.065"WT (SS316L) M 100 30 5 45 10 12 202

1/2"OD Tube x 0.049"WT(SS316L) M 50 40 30 0 40 12 172

1/4" OD Tube x 0.035"WT(SS316L) M 11 6 1 7 2 2 29

3/8"OD x 0.049"WT(SS316L) M 130 - - 30 - - 160

b Tube fittings

1/2"NPT(M) X 1/2"OD Male Connector(SS316L)

NOS 35 6 1 15 2 2 61

1/2"NPT(M) X 1/2"OD Male Connector(SS316)

NOS 40 32 24 - 32 10 138

1/4"NPT(M) X 1/4"OD Male Connector(SS316L)

NOS 22 12 2 14 4 5 59

1/4" NPT(F) Ball Valve(SS316L) NOS 11 6 1 7 2 2 29

1/2" NPT(F) Ball Valve(SS316L) NOS 5 - - 2 - - 7

1/4"Plug(SS316L) NOS 11 6 1 7 2 2 29

1/2" OD Tube union(SS316L) NOS 20 6 1 9 2 2 40

Page 17: Construction Engg

CONSTRUCTION ENGINEERING FOR INSTRUMENTATION

GUIDELINE FOR INSTRUMENT LAYOUT

1/2" OD Tube union(SS316)

NOS 15 12 9 - 12 4 52

Sr.nos. Description of items Unit ST-T1

ST-T2

ST-B

ST-S ST-W1

72-SBV-31

Total Rema

rks

Tube adaptor 1/2"OD(SS316L) NOS 18 12 2 10 4 5 51

1/2"NPT x 3/8"OD Male connector(SS316) NOS 10 - - 2 - - 12

1/4" NPT x 3/8"OD(SS316) NOS 6 - - 2 - - 8

3/8"OD Tube union(SS316) NOS 20 - - 4 - - 24

1/2"OD Tube Tee compression type(SS316)

NOS 10 8 6 - 8 2 34

1/2" NPTF Pneumatic lock up valve(SS316) NOS 5 4 3 - 4 1 17

c Others

Non return valve(SS316) 1/2"NPT NOS 5 4 3 - 4 1 17.2

Monoflange double block-bleed valve(SS316L)

NOS 17 6 3 5 6 4 41

Gauge adaptor(SS316L) 1/2" NPT(F) x 1/2" NPT(M)

NOS 17 6 3 5 6 4 41

1/2" 150#RF Blind Flange(SS316L) NOS 20 - - 8 - - 28

Sunshade(GRP) NOS 9 6 1 5 2 2 25 Note 5

Note 1.Instrument cable tray heights are considerd as : Upto 100 mmW tray 20mm H, upto 400 mmW 50mmH & above 400mmW 60mmH

Note 2. Earthing cable sizes and lengths are assumed.

Note 3.No of terminals in JBs decided on size of mutlipair cables.

Note 4. As per specifiction 30% spare plugs.

Note 5. Sunshades for instruments in package, VEM flowmeterpackage considered as under vendor scope.

fw9983
Text Box
Dattatray K. Nikam Design Engineer ( Instrument)