CUSTOMER GASCO PLANT LOCATION RUWAISABU DHABI GAS INDUSTRIES LTD. (GASCO)

PROJECT RUWAIS 4th NGL TRAIN Doc. No. 5248-00-FA-4049

Agreement No. 13524801 Rev. 1

PROJECT No. 5248

EARLY WORKS CONSTRUCTION INTERFACE PLAN

DOC. CLASS : 1 1 0 B A Rev. 23 Apr. 10 05 Jan. 10 28 Nov. 09 26 Nov 09 Date 13 13 13 13 Page Isssued for Construction Issued for Approval Issued for Company Review Issued for Internal Review Description DC DC DC DC Prepared RH RH RH RH Checked KR KR KR KR Approved

Page 1 of 13

RUWAIS 4th NGL TRAIN

Petrofac GS CONTRACTORAgreement No. 13524801

GASCOABU DHABI GAS INDUSTRIES LTD.

CONSTRUCTION INTERFACE PLAN

Doc. No. . 5248-00-FA-4049

Rev. 1

Table of Contents1. INTRODUCTION .............................................................................................................3 1.1 Purpose.................................................................................................................3 1.2 Objective..............................................................................................................3 1.3 Definitions and Abbreviations ..............................................................................3 1.4 Scope....................................................................................................................4 1.5 References ...........................................................................................................4 1.6 Responsibilities ....................................................................................................5 1.7 Correspondence ...................................................................................................6 LIST OF CONTACTS .......................................................................................................6 GASCO PROJECT MANAGEMENT TEAM......................................................................6 GASCO MAJOR PROJECTS GROUP .............................................................................7 CONTRACTORS E&P / SUPPORT LOCATIONS ...............................................................7 5.1 Seoul.....................................................................................................................7 5.2 Abu Dhabi .............................................................................................................7 SUBCONTRACTORS .......................................................................................................8 OTHER CONTRACTORS .................................................................................................8 CNIA...............................................................................................................................9 POLICE...........................................................................................................................9 MUNICIPALITY ...............................................................................................................9 HEALTH AUTHORITY ABU DHABI ...............................................................................10 HOSPITAL(S)................................................................................................................10 CIVIL DEFENCE............................................................................................................10 TAKREER .....................................................................................................................10 BOROUGE ....................................................................................................................11 IRSHAD ........................................................................................................................11 ADNOC.........................................................................................................................11 RUWAIS PORT .............................................................................................................11 ABU DHABI PORT AUTHORITY....................................................................................12 AIRPORT(S)..................................................................................................................12 ABU DHABI ELECTRICITY & WATER AUTHORITY .......................................................12 TRAVEL POLICE DEPARTMENT ...................................................................................12 ETISALAT.....................................................................................................................13 VENDORS .....................................................................................................................13 LOCAL SUPPLIERS .......................................................................................................13 ATTACHMENTS............................................................................................................13

2. 3. 4. 5.

6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. 24. 25. 26.

Page 2 of 13

RUWAIS 4th NGL TRAIN

Petrofac GS CONTRACTORAgreement No. 13524801

GASCOABU DHABI GAS INDUSTRIES LTD.

CONSTRUCTION INTERFACE PLAN

Doc. No. . 5248-00-FA-4049

Rev. 1

1.

INTRODUCTION 1.1 PURPOSE The purpose of this plan is to outline CONTRACTORS major interfaces with other Companies, Governmental Bodies and Entities required during the execution of the NGL4 Works on the Ruwais Facility site and the building and operation of the Project Camp.

1.2

OBJECTIVE The plan identifies the names of the major interface parties, brief scope and reason for the interface plus the interface contact details. This document will be treated as a live plan which will be maintained and up dated as necessary.

1.3

DEFINITIONS AND ABBREVIATIONS GASCO COMPANY CONTRACTOR ABU DHABI GAS INDUSTRIES LTD. GASCO Petrofac GS JV

SUBCONTRACTOR Contractors engaged by the CONTRACTOR to perform specific portions of the Work Works CONTRACTORS total scope in accordance with the Contract. Project CNIA ADNOC HAAD IRSHAD ADEWA UAE PTW VRD ODC CIM Ruwais 4th NGL Train Critical National Infrastructure Authority Abu Dhabi National Oil Company Health Authority Abu Dhabi Abu Dhabi Petroleum Ports Operating Company Abu Dhabi Electricity Water Authority United Arab Emirates Permit To Work Vehicle Renting Department Over Dimensional Consignments Construction Interface Manager

Page 3 of 13

RUWAIS 4th NGL TRAIN

Petrofac GS CONTRACTORAgreement No. 13524801

GASCOABU DHABI GAS INDUSTRIES LTD.

CONSTRUCTION INTERFACE PLAN

Doc. No. . 5248-00-FA-4049

Rev. 1

1.4

SCOPE This plan addresses the major interfaces required to support CONTRACTORS scope execution as agreed under the Contract. The scope in broad terms will cover the following categories:

The location and Camp construction / operation. Security Access to the Ruwais Facilities for manpower, plant, equipment and materials. GASCO controlled areas within the Ruwais Facility Other Stakeholders within the Ruwais Facility e.g. Takreer, Borouge, etc. CONTRACTOR Operations within the Ruwais Facility Other Contractors Utilities Companies Etisalat and ADEWA Vendors Licensing and Governmental requirements

Within each category there will be requirements to be met by the CONTRACTOR involving formal processes and specific deliverables which will be confirmed and provided in line with the individual interface needs. The CIM will be tasked with ensuring all the necessary documentation has been identified, submitted and approvals obtained from the relevant party(s) in order that the scheduled execution of the Works is not affected.

1.5

REFERENCES Site Administration Procedure 5248-00-FA-4050 Exhibit A4 Interface Plan 5248-00-AA-4090 Tie-in & Interface Schedule 5248-00-AA-4091

Page 4 of 13

RUWAIS 4th NGL TRAIN

Petrofac GS CONTRACTORAgreement No. 13524801

GASCOABU DHABI GAS INDUSTRIES LTD.

CONSTRUCTION INTERFACE PLAN

Doc. No. . 5248-00-FA-4049

Rev. 1

1.6

RESPONSIBILITIES

1.6.1 Construction Director Contractors Construction Director will be the main contact and focal point for all interfaces with the COMPANY onsite representatives. He is the focal point of the site and responsible for all the Construction activities on the site. He will ensure this procedure is implemented on the Project. 1.6.2 Construction Manager Will be responsible for the execution of works associated with the Temporary Facilities including the Camp through the designated SUBCONTRACTORS.

1.6.3 Construction Interface Manager (CIM) Will be the main contact and focal point for all CONTRACTOR interfaces. The CIM will be tasked with ensuring all the necessary documentation has been identified, submitted and approvals obtained from the relevant party(s) in order that the scheduled execution of the Works is not affected. Provide daily / weekly / monthly liaison as required by the requisite scope. Regular meetings will be required and the CIM will be responsible for the coordination all meetings and ensuring the attendance of the necessary personnel from its party to review / discuss all interface needs. The CIM shall maintain and an action list capturing all actions arising from the various meetings especially those with external bodies. Actions will have agreed due dates for closure. This action list will be up dated and distributed on a weekly basis to CONTRACTOR, attendees and COMPANY. The CIM will maintain the live list of contact information for all interfaces. CIM shall as soon as practicable prepare a meeting schedule and issue to COMPANY for comment.

1.6.4 HSSE Manager Will provide assistance to the Administration Manager on the HSE topics as covered by this procedure. 1.6.5 Administration Manager The Administration Manager is responsible for human resources, government interface, personnel and transportation administration and site office administration. He will be directly responsible for the administrative topics contained within this procedure and their compliance with the GASCO standards / procedures and the Governmental Bodies as identified within the procedure.

Page 5 of 13

RUWAIS 4th NGL TRAIN

Petrofac GS CONTRACTORAgreement No. 13524801

GASCOABU DHABI GAS INDUSTRIES LTD.

CONSTRUCTION INTERFACE PLAN

Doc. No. . 5248-00-FA-4049

Rev. 1

1.6.6 COMPANY Interface Coordinator Will provide assistance to the CONTRACTORS CIM on all interface matters. 1.7 CORRESPONDENCE All official correspondence, both in and out will be through the CONTRACTORS designated representative The Construction Director.

2.

LIST OF CONTACTS Attachment A is a listing of the personnel and contact details where CONTRACTOR has identified an interface requirement.

3.

GASCO PROJECT MANAGEMENT TEAM The CONTRACTOR will require to interface with the PROJECT MANAGEMENT TEAM typically on the following but not limited to: 1. Contractual matters concerning execution of the works 2. Assistance with identified interfaces within this plan 3. Access to operational areas such as Trains 1, 2 & 3 for scope execution. 4. Document review process 5. HSE & Security requirements 6. QA / QC requirements 7. Plans and procedures 8. Progress / Performance 9. Invoicing / Payments 10. Completions work 11. Testing 12. Turnover of Works

Page 6 of 13

RUWAIS 4th NGL TRAIN

Petrofac GS CONTRACTORAgreement No. 13524801

GASCOABU DHABI GAS INDUSTRIES LTD.

CONSTRUCTION INTERFACE PLAN

Doc. No. . 5248-00-FA-4049

Rev. 1

4.

GASCO MAJOR PROJECTS GROUP The CONTRACTOR will require to interface with MAJOR PROJECTS GROUP typically on the following but not limited to: 1. Access to the COMPANY Existing Operating Facilities personnel, plant and equipment 2. Access to operational areas such as Trains 1,2 & 3 3. Assistance for Security of CONTRACTORS Areas with relation to GASCO plant 4. H2S monitoring 5. HSE Inductions 6. Permit to work system 7. Vehicle Checks for compliance with GASCO requirements 8. Early work demolition isolations 9. Early work fencing / emergency gate installation acceptance

5.

CONTRACTORS E&P / SUPPORT LOCATIONS The CONTRACTOR from its site location will require to interface INTERNALLY with typically the following but not limited to: 5.1 SEOUL 1. CONTRACTOR will maintain the interface with the Project head office during the Engineering and Procurement execution period. 2. This will be by means of telecommunications initially until the IT link provides connectivity for direct transfer / email between the site and Seoul. 5.2 ABU DHABI 1. CONTRACTOR will maintain a group in the Abu Dhabi Office which will support Construction during the execution of the Project. This office will provide liaison with the head office. 2. This office also provides support to the head office.

Page 7 of 13

RUWAIS 4th NGL TRAIN

Petrofac GS CONTRACTORAgreement No. 13524801

GASCOABU DHABI GAS INDUSTRIES LTD.

CONSTRUCTION INTERFACE PLAN

Doc. No. . 5248-00-FA-4049

Rev. 1

6.

SUBCONTRACTORS CONTRACTOR will have a number interfaces with key SUBCONTRACTORS performing the execution of part of the Works in accordance with Contract requirements. They will be fully supervised, controlled and they will comply with all the Contract requirements. The major SUBCONTRACTS typically will be as follows but not limited to: 1. Pioneer Camp 2. Site Temporary Facilities and Early Works 3. Topo & Geotech Surveys 4. Civil & Buildings 5. Mechanical two (2) : East and West Scope split 6. E&I 7. Seawater Intake including offshore 8. Structural Steel Pre-fabrication two (2) : East and West Scope split 9. Piping Pre-fabrication two (2) : East and West Scope split 10. Catering & Camp / Office Services 11. Camp / Infrastructure Operation

7.

OTHER CONTRACTORS The CONTRACTOR will require to interface with OTHER CONTRACTORS typically on the following but not limited to and listed in the Tie-in and Interface Schedule & DGS 5208 ADD1300-100/003 Piping Tie-ins: 1. CB & I who is responsible for the tanks and associated works in WBS areas 601 / 602 / 603. CONTRACTOR is required to tie-in to the CB & I works. 2. NGL3 CONTRACTOR identified in case demobilisation has not been completed or otherwise with GASCO end user operating NGL3 at that time.

Page 8 of 13

RUWAIS 4th NGL TRAIN

Petrofac GS CONTRACTORAgreement No. 13524801

GASCOABU DHABI GAS INDUSTRIES LTD.

CONSTRUCTION INTERFACE PLAN

Doc. No. . 5248-00-FA-4049

Rev. 1

8.

CNIA The CONTRACTOR will require to interface with CNIA typically on the following but not limited to: 1. CONTRACTORS camp location approval 2. CONTRACTORS personnel oil field passes 3. CONTRACTORS vehicle oil field passes 4. CONTRACTORS camera oil field passes 5. CONTRACTORS designated camera / photographers oil field passes

9.

POLICE The CONTRACTOR will require to interface with POLICE typically on the following but not limited to: 1. CONTRACTORS vehicle rental and purchasing program 2. Identification of the access gates to be assigned to the Project (in case there will be a dedicated one). 3. Photography process on site 4. Security issues 5. Traffic / Logistical land transportation

10.

MUNICIPALITY The CONTRACTOR will require to interface with THE MUNICIPALITY typically on the following but not limited to: 1. Provision of Camp location and approvals. 2. Waste management approvals

Page 9 of 13

RUWAIS 4th NGL TRAIN

Petrofac GS CONTRACTORAgreement No. 13524801

GASCOABU DHABI GAS INDUSTRIES LTD.

CONSTRUCTION INTERFACE PLAN

Doc. No. . 5248-00-FA-4049

Rev. 1

11.

HEALTH AUTHORITY ABU DHABI The CONTRACTOR will require to interface with HAAD typically on the following but not limited to: 1. HAAD will be inspecting and provide approvals on the use of the completed Clinic in the Camp. 2. HAAD will be inspecting and provide approvals on the use of the completed Clinic in the Site Temporary Facilities. 3. HAAD has to approve any medical personnel to be used on the Project (typically doctors and nurses).

12.

HOSPITAL(S) CONTRACTOR will establish arrangements with both local hospitals and Abu Dhabi City hospitals for use in case of emergency situations during the life of the Project.

13.

CIVIL DEFENCE The CONTRACTOR will require to interface with CIVIL DEFENSE typically on the following but not limited to: 1. Inspections / approvals of the Site Pioneer Office Compound prior to use. 2. Inspections / approvals of the Site Temporary Facilities (Offices and all support buildings including Fire and Gas systems) prior to use. 3. Inspections / approvals of the Camp prior to use.

14.

TAKREER The CONTRACTOR will require to interface with TAKREER typically on the following but not limited to: 1. Setting up of the Temporary Facilities 2. Utilities supply for Temporary Facilities water and power 3. Demolition of Avenue B 4. Erection of the new East boundary fence 5. Installation of the new out fall line

Page 10 of 13

RUWAIS 4th NGL TRAIN

Petrofac GS CONTRACTORAgreement No. 13524801

GASCOABU DHABI GAS INDUSTRIES LTD.

CONSTRUCTION INTERFACE PLAN

Doc. No. . 5248-00-FA-4049

Rev. 1

6. Installation of the new HP Flare line under the existing lines which run to the TAKREER jetty 7. Permits to work 8. Cooling water works All the above will require utilization of the TAKREER PTW system. All necessary personnel will be trained accordingly in advance of any work.

15.

BOROUGE The CONTRACTOR will require to interface with BOROUGE typically on the following but not limited to: 1. Transportation of permanent equipment received via the Ruwais Port, through, adjacent or over the Borouge existing facilities depending upon the final agreed Ruwais Facility internal routing. 2. New piping work that will be executed to the south of WBS area 403/001 which will affect CONTRACTORS access to the East scope.

16.

IRSHAD The CONTRACTOR will require to interface with IRSHAD typically on the following but not limited to: 1. Offshore works related to the Seawater Intake and associated subsea lines. 2. Transportation of permanent equipment received via the Ruwais Port

17.

ADNOC The CONTRACTOR will require to interface with ADNOC typically on the following but not limited to: 1. Supply of the CONTRACTORS fuel cards.

18.

RUWAIS PORT The CONTRACTOR will require to interface with RUWAIS PORT AUTHORITY typically on the following but not limited to:

Page 11 of 13

RUWAIS 4th NGL TRAIN

Petrofac GS CONTRACTORAgreement No. 13524801

GASCOABU DHABI GAS INDUSTRIES LTD.

CONSTRUCTION INTERFACE PLAN

Doc. No. . 5248-00-FA-4049

Rev. 1

1. Equipment, columns and vessels shipments to the port. 2. Offloading 3. Transportation to site 19. ABU DHABI PORT AUTHORITY The CONTRACTOR will require to interface with ABU DHABI PORT AUTHORITY typically on the following but not limited to: 1. Port passes 2. Customs clearance 3. Onward shipping to Ruwais where necessary 20. AIRPORT(S) The CONTRACTOR will require to interface with CUSTOMS AUTHORITY typically on the following but not limited to: 1. Custom clearance of air freighted items. 2. Shipment of items to site. 21. ABU DHABI ELECTRICITY & WATER AUTHORITY The CONTRACTOR will require to interface with ABU DHABI ELECTRICITY & WATER AUTHORITY typically on the following but not limited to: 1. Supply from the main grid power for the JV and GASCO Camp. This will be by the Camp provider but is ultimately the responsibility of the CONTRACTOR. 2. Supply of water for both the camp and the Site Temporary Facilities. This will be by the Camp provider but is ultimately the responsibility of the CONTRACTOR.

22.

TRAVEL POLICE DEPARTMENT The CONTRACTOR will require to interface with the TRAVEL POLICE DEPARTMENT typically on the following but not limited to:

Page 12 of 13

RUWAIS 4th NGL TRAIN

Petrofac GS CONTRACTORAgreement No. 13524801

GASCOABU DHABI GAS INDUSTRIES LTD.

CONSTRUCTION INTERFACE PLAN

Doc. No. . 5248-00-FA-4049

Rev. 1

1. Advise and seek approvals for overland material / equipment shipments classified asODCs.

23.

ETISALAT The CONTRACTOR will require to interface with ETISALAT typically on the following but not limited to: 1. Supply of the IT and Communications connectivity for the JV and GASCO Camp. 2. Supply of the IT and Communications connectivity for the Site Temporary Facilities.

24.

VENDORS The CONTRACTOR will require to interface with VENDORS typically on the following but not limited to: 1. Vendors required assisting construction in the physical completion of systems ready for turnover to Pre-Commissioning / Commissioning. 2. Vendors required assisting the completions group in reaching systems readiness for Start up and Performance Testing as per Exhibit 4. 3. CONTRACTOR will develop a Vendor Schedule covering the requirements of items 1 & 2.

25.

LOCAL SUPPLIERS The CONTRACTOR will require to interface with LOCAL SUPPLIERS typically on the following but not limited to: 1. CONTRACTOR will have purchase orders for office supplies draw down. 2. CONTRACTOR will have purchase orders and service agreements for office equipment 3. CONTRACTOR will perform local purchasing as necessary.

26.

ATTACHMENTS A List of Contact Information (This is a live document and will be regularly up dated with new information).

Page 13 of 13

GASCO NGL4 Project Construction Interface Plan Appendice A Listing of Interface ContactsUnder Population Last Update : 17th Dec 2009

Company GASCO PMT

Contact NameRaafat Fayek Abdul Aziz Al Badi Assaad Abdallah Jose Luis Gameiro Bob Al Borzi Hisham Mansour Firose Hassan

Designation

Office Telephone

Mobile0097150 - 61 38 734 0097150 - 4443608 0097150 - 6227495 0097150 - 6689690 0097150 - 6412140 0097150 - 8121798 0097150 - 5725868

Email [email protected] [email protected] [email protected] [email protected] [email protected] [email protected] [email protected]

Major Projects manager(Ruwais) Not Available SR.Project Manager Project Coordinator Project Manager Project Manager Project Manager Secretary Major Projects Co-ordination Department Superintendent Senior Operations Engineer Project Director Project Controls Manager Lead Project Coordinator - Mech. Senior Engineer - Process Principal Engineer - Instrument Principal Engineer - Electrical Project Procurement Manager Senior Buyer Project Engineer

Not Available Not Available Not Available Not Available Not Available Not Available

GASCO RUWAIS ( EU )

A. Moussa Cyril Pereira

Not Available Not Available+82 2 2005 8493 +82 2 2005 8491 +82 2 2005 8400 +82 2 2005 8429 +82 2 2005 8424 +82 2 2005 8425 +82 2 2005 8428 +82 2 2005 8432 +82 2 2005 8433

0097150-4152770 0097150-6721765 +971 50 633 6196

[email protected] [email protected] [email protected] [email protected] [email protected] [email protected] [email protected] om [email protected] [email protected] om [email protected] [email protected]

CONTRACTOR - Seoul ( Petrofac )

Kurt Reeves Christopher Joyce Vivek Tandon Utkarsh D.Kulkarni N.S.S. Venkateswaran Kiran Sheth S.Thilagaraj Prasad Pradhan Poulose Moolan

Page 1 of 6

GASCO NGL4 Project Construction Interface Plan Appendice A Listing of Interface ContactsUnder Population Last Update : 17th Dec 2009

Company

Contact NameT.Chandra Umerfarook Deshmukh V. Saibaba Sardana Yuvraj Bachir Chaaya Vijaykumar Nair Pradeep Agrawal

DesignationLead Engineer - Civil Planning Engineer Project Manager Interface Manager Junior Project Engineer Lead Document Controller Project Accountant Deputy Project Director Deputy Site Manager Construction Planner-1 Construction Planner-2 Discipline SI (CSA) Discipline SI (Mechanical) Discipline SI (Piping) Discipline SI (Instrument) Discipline SI (QA/QC) HSSE Manager Project Procurement Manager

Office Telephone+82 2 2005 8419 +82 2 2005 8418 +82 2 2005 8974 +82 2 2005 8402 +82 2 2005 8421 +82 2 2005 8417 +82 2 2005 8430 +82 2 2005 8430 +82 2 2005 7200 +82 2 2005 7240 +82 2 2005 7291 +82 2 2005 7243 +82 2 728 1264 +82 2 2005 7249 +82 2 2005 7285 +82 2 2259 3467 +82 2 2259 5131 +82 2 2005 9915 +82 2 2005 8403

Mobile

Email [email protected] Umerfarook.Deshmukh@petrofac. com [email protected] [email protected] Bachir.Chaaya@petrofacemirates. ae Nair.Vijaykumar@petrofacemirate s.ae [email protected]

CONTRACTOR - Seoul (GS )

Tom Yu Chan-Hee Chang Soo-Kang Shim Jung-Ho Lee Yong-Kyu Lee Duk-In Eum Yoon-Tae Kim Eun-Kyun Shin Myung-Ha Kim Robert Berry Hee-Byum No

+82 10 5898 5505 +82 19 334 3135 +82 10-8634-8537 +82 10 2834 8288 +82 11 9558 4946 +82 11 788 4853 +82 11 363 7912 +82 10 6600 4302

[email protected] [email protected] [email protected] [email protected] [email protected] [email protected] [email protected] [email protected] [email protected] [email protected] [email protected]

+82 10 2901 2251 +82 10 8752 3136

CONTRACTOR - Abu Dhabi

Milad Azar

Commercial & Contract Manager

+971 2 656 1107

[email protected]

Page 2 of 6

GASCO NGL4 Project Construction Interface Plan Appendice A Listing of Interface ContactsUnder Population Last Update : 17th Dec 2009

Company

Contact NameDick Cunningham Archana Matte Gopala Goud Altaf Khan Avinash Gosavi Dineshkar Singh Katoch Nigel Butler Jeganathan Kumaresan Kalyana Kumar T. Rohit Bakshi Roy Hanks Brown Vijay Kumar Brian Stewart

DesignationDirector Construction Support Project Secretary S/C Project Engineer

Office Telephone+971 2 656 1026 +971 2 656 1078 +971 2 656 1008

Mobile

Email AddressDick.Cunningham@petrofacemirat es.ae Archana.Matte@petrofacemirates. ae [email protected] [email protected] [email protected] [email protected] [email protected] Jeganathan.Kumaresan@petrofac .com [email protected] [email protected] [email protected] [email protected] e [email protected] [email protected] Muhammad.Khan@petrofacemirat es.ae

Dy. Project Director +971 2 656 1014 Projects & Construction Support +971 2 656 1036 Manager Admin. Manager +971 2 656 1038 Sub Contracts Manager Contracts Engineer Senior Planning Engineer Senior QA Engineer Construction Director Deputy Manager - Logistics HSSE Manager +971 2 656 1076 +971 2 656 1113 +971 2 656 1052 +971 2 656 1053 +971 2 656 1086 +971 6 518 4590 +971 2 656 1061 +971 2 656 1017 +971 2 656 1068

Marc Taylor (Support Procurement Manager Member) Muhammad Khan Finance Manager (Support Member)

SUBCONTRACTORS

Page 3 of 6

GASCO NGL4 Project Construction Interface Plan Appendice A Listing of Interface ContactsUnder Population Last Update : 17th Dec 2009

CompanyCB&I DODSAL ACC

Contact NameNaaman M Farah Nael Salloum Ezzat Aziz Nabil Karmi Tony Shaheen Chehade M. Zinati

DesignationCB&I Project Manager General Services Manager Construction Manager Tech & Commercial Manager Project Manager Tender & Estimate Manager Head of Tendering Tendering Engineer

Office TelephoneNot Available Not Available Not Available 02 - 4109810 02 - 4109810 02 - 6771225 02 - 6444700 02 - 6440445

Mobile0097150 - 6587637 0097150 - 4569613 0097150 - 4576866 050 6125502 050 6610078 050 7318516 050 7125604

Email [email protected] [email protected] [email protected]

[email protected] [email protected] [email protected] [email protected] [email protected]

IMECO

Souhel Salloum Anil Ramachandran

CNIA POLICE MUNICIPALITY Gayathi Madina Zayed Office Abu Dhabi 02 - 8082300 02 - 8988888 02 - 6777929

HEALTH AUTHORITY ABU DHABI HOSPITAL(S) Ruwais Adnoc Al Mafrak Musaffah 02 - 6022340 02 - 5823100

Page 4 of 6

GASCO NGL4 Project Construction Interface Plan Appendice A Listing of Interface ContactsUnder Population Last Update : 17th Dec 2009

Company

Contact NameAl Noor, AD Central Hospital, AD Al Jazira, AD NMC, AD Emergency

Designation

Office Telephone02 - 67272222 02 - 621 46666 02 - 6214800 02 - 6332255

Mobile

Email Address

998 02 - 88440004 Engineering Development Section Head

CIVIL DEFENCE

Madina Zayed Office

TAKREER

Sharif Abd El-Rahman Cyril Prem Kumar

Not Available Not Available

0097150-4152770 0097150-5986504

[email protected] [email protected]

BOROUGE IRSHAD ADNOC RUWAIS PORT ABU DHABI PORT AUTHORITY AIRPORT(S)

Norman Grant Sultan Al Shehhi

Construction Manager Sr. Project Manager

Not Available Not Available

Not Available 0097150-6166868

[email protected] [email protected]

Page 5 of 6

GASCO NGL4 Project Construction Interface Plan Appendice A Listing of Interface ContactsUnder Population Last Update : 17th Dec 2009

CompanyAbu Dhabi Dubai

Contact Name

Designation

Office Telephone

Mobile

Email Address

ABU DHABI ELECTRICITY & WATER AUTHORITY TRAVEL POLICE DEPARTMENT Police HQ, AD Emergency ELIXER Ahmed Habib Froilan Manez ETISALAT VENDORS LOCAL SUPPLIERS Ruwais Plant Manager Senior Engineer 02 - 446 1461 02 - 808 2300 02 - 4461461 Not Available Not Available 0097150 - 6150932 Not Available 999 [email protected] [email protected]

Page 6 of 6