CONSTRUCTION LOGISTIC PLAN

Our ref: SP103CLP Version 1 AXE ST, BARKING

Page 2: CONSTRUCTION LOGISTIC PLAN - LBBD

i

Table of Contents Table of Contents .............................................................................................................. i Summary ......................................................................................................................... 3 1 PROJECT MANAGEMENT DETAILS.............................................................................. 5 1.0 SUMMARY OF PROJECT INFORMATION ......................................................................5 1.1 SITE LAYOUT ...................................................................................................................5 1.2 MANAGEMENT ..............................................................................................................5 1.3 KEY DOCUMENTS ...........................................................................................................8 1.4 MEETING SCHEDULE ......................................................................................................8 1.5 LEGAL & OTHER REQUIREMENTS ..................................................................................9 1.6 ROLES AND RESPONSIBILITIES .....................................................................................10 1.7 EMERGENCY PLAN......................................................................................................12 2 CONSTRUCTION METHODOLOGY ............................................................................ 14 2.0 PROJECT OUTLINE .......................................................................................................14 2.1 IMPACT ON SURROUNDINGS .....................................................................................14 2.2 SITE ESTABLISHMENT .....................................................................................................14 2.3 SITE ACCESS .................................................................................................................15 2.4 SITE CONSTRAINTS .......................................................................................................17 2.5 SECURITY PROVISIONS ................................................................................................18 2.6 MATERIALS AND STORAGE .........................................................................................18 2.7 CONSTRUCTION METHODOLOGIES AND PROGRAMMING ...................................27 2.8 DESIGN ISSUE, REVIEW PRE-START PLANNING ..........................................................29 2.9 PROGRAMME AND PROGRESS REPORTS .................................................................30 3 HEALTH & SAFETY ................................................................................................... 32 3.0 SITE RULES .....................................................................................................................32 3.1 HAZARD IDENTIFICATION, RISK ASSESSMENTS & CONTROL MEASURES .................33 3.2 CONSTRUCTION METHOD STATEMENTS ....................................................................39 3.3 TRAFFIC MANAGEMENT & DELIVERY PLANS .............................................................39 3.4 TEMPORARY WORKS ...................................................................................................42 3.5 CORONAVIRUS / COVID 19 OR SIMILAR OUTBREAK ...............................................42 4 ENVIRONMENTAL ................................................................................................... 45 4.0 ENVIRONMENTAL CONTROL MEASURES ...................................................................45 4.1 FLORA, FAUNA & INVASIVE SPECIES .........................................................................52 4.2 TRAINING (TOOLBOX TALKS) ......................................................................................53 4.3 WASTE MANAGEMENT ................................................................................................45 4.4 CONSTRUCTION WASTE ASSESSMENT .......................................................................53 4.5 QUALITY MANAGEMENT PROCEDURES ....................................................................55 4.6 CONTROL MEASURES ..................................................................................................55 5 QUALITY ................................................................................................................. 60 5.0 BREEAM AND CONSIDERATE CONSTRUCTORS SCHEME .........................................60 6 APPENDICES (STANDARD FORMS) ........................................................................... 62 6.0 RISK ASSESSMENT REGISTER ........................................................................................62 6.1 TEMPORARY WORKS REGISTER ..................................................................................62 6.2 INDUCTION FORM .......................................................................................................62 6.3 METHOD STATEMENT TEMPLATE .................................................................................62 6.4 TOOL-BOX TALKS REGISTER ........................................................................................62 6.5 TOOL-BOX TALKS FORM ..............................................................................................62 6.6 SITE INSPECTION TEMPLATE.........................................................................................62 6.7 H&S EMERGENCY RESOURCE PLAN ..........................................................................62 6.8 ENVIRONMENTAL EMERGENCY RESPONSE PLAN ....................................................62

Page 3: CONSTRUCTION LOGISTIC PLAN - LBBD

ii

6.9 ENVIRONMENTAL CHECK LIST ....................................................................................62 6.10 UTILITY MONITORING ...................................................................................................62 6.11 CONSTRUCTION PHASE PLAN (CDM 2015) ..............................................................62

Page 4: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 3 of 62

Summary This proposal seeks to combine Corporate Governance and best practise in Construction, especially within the design and build environment; and to confirm our strength in depth with over 150 years of experience as a major contracting entity. For every project we manage we implement a Construction Logistic Plan, which enables us to manage Environmental, Quality and Occupational Safety & Health at project level. The plan outlines the specific Environmental, Quality and Occupational Safety & Health management practices, resources and sequence of activities relevant to a contract or project. This Project Management Plan demonstrates our proposed methods and planning for the project, it specifically highlights the resources, programming, recording, risk management and consultation processes, coordination and cooperation, including the responsibilities, practices and procedures that will be employed on a single individual project. This document offers a focus on the delivery of the project with attention to the Employers Requirements, and the resultant Contractors Proposal’s namely:- compliance with the Employers deliverables, the CDM Regulations, engagement with all Stakeholders and the critical construction deliverables of the programme , cost, , quality and the Employers stated performance objectives. Our aim is to engage with all and to continually demonstrate through-out the delivery process that we are fully committed deliver the Employers expectations by delivering the Project to the combined expectation of all The main aim of this proposal is also to convey our approach to managing the various project activities and to ensure full compliance with all statutory provisions through-out the life cycle of the Project. Document Control Sheet: Construction Logistic Plan

Project Name: Axe Street Barking Document Reference:

Version: Details: Date: Prepared

By: Checked

By: Notes:

0 Construction 14th May 2020

Karen Muldowney

ROL To ensure compliance with Planning

1 Construction update

22nd June 2020

Karen Muldowney

ROL H&S details updated

Page 5: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 4 of 62

Project Name: AXE Street Barking Project Particulars:

Description Axe Street

Site Address Axe Street, Barking, London

Client Contact Sherhill (Barking) Limited (Company No. 9461882). Solar House 282 Chase Road London

N14 6NZ Principal Contractor Shapoorji Pallonji UK Limited 5 New Street Square London EC4A 3TW

Principal Designer Peardon Health and Safety 1st Floor, 14 North Road, South Ockendon Essexm, RM15 6QL

Architect SADA Architects 6 Spicer St, St Albans AL3 4PQ

Structural Engineer Malcolm Brady Partnership 72-78 Fleet Street, London EC4Y 1HY

Building Services Engineer

Energy Engineering Ltd 156 Shirehall Rd, Hawley, Sutton at Hone, Dartford DA2 7SN, United Kingdom

EHS Manager Peardon Head Office: 14 North Road, South Ockendon, Essex, RM15 6QL

Project Duration

24 months

Page 6: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 5 of 62

1 PROJECT MANAGEMENT DETAILS 1.0 SUMMARY OF PROJECT INFORMATION Demolition of existing buildings and the redevelopment of the site, including the erection of buildings ranging in height from 1 to 13 storeys to provide 170 residential units together with flexible commercial floorspace (Classes A1, A2, A3, A4, B1, D1 and D2), and office accommodation (class B1) with associated landscaping & public realm improvements.

1.1 SITE LAYOUT

1.2 MANAGEMENT 1.2.1.1.1 Management Team Function Our delivery team will consist of a core team of existing experienced and trusted Shapoorji staff who will be supported by locally engaged managers who, in the main, will be existing contacts of our senior management team within the UK and Europe All of the team will be experienced in successfully delivering Design and Build projects. The teams’ function will be to: -

• At all times to engage with the Employer and all Stakeholders to continually ensure through open communications that the needs and concerns of all are addressed

• As the Principle Contractor to ensure full Compliance with the CDM Regulations (2015)

• To engage with the Principal Designer, the Design Team and external consultants to deliver the best solution for the project.

• Work as one with the Professional Team and the Client’s Management Team to achieve the objectives and goals embraced by the client and published within this document

• Develop a team philosophy with Contractors so that there is a mutual understanding as to what must be achieved to meet the Client’s expectations.

Page 7: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 6 of 62

• Employ our depth of management knowledge and previous experience of undertaking similar projects to achieve the best outcome for the Client

• Bring the Project in on time, and budget, to meet the Client’s aspirations. • Provide the relevant handover documentation and certification for the

project • That the mantra of “No-Surprises” is successfully applied from ‘cradle to

grave’ across the life cycle of the Project 1.2.1.1.2 Organogram

1.2.1.1.3 Management & Coordination of Subcontractors & Suppliers The Employer and all Stakeholders are engaged with to discuss and investigate all potential supply chain preferences and options in an attempt to offer best value in terms of performance and cost. This exercise is undertaken to support and supplement our existing supply chain contacts Once the various vendors have been identified Pre-contract Tender Meetings are held with the identified vendors to confirm their suitability and to confirm their interest. Once the proposed vendor list has been agreed formal Invitations to Tender are issued so the that supply chain can be brought to the table to: -

1. As required to work with the Principal Designer

2. To assist as requested with Design Reviews to validate best practise and to try and offer Value Engineering and programme savings

Prior to the award of any supply chain order and prior to commencement on site all sub-contractors are informed of the sites Quality, Health, Safety and Environmental requirements and their own plans are fully interrogated. Full compliance with CDM 2015 is mandatory.

Page 8: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 7 of 62

As the Principal Contractor we, and our supply chain, need to work with the appointed Principal Designer during the pre-construction phase (design and planning stage) to ensure

that significant and foreseeable risks are managed throughout the design process. The Plan details the risks involved in this project and the control measures to eliminate/reduce those risks. We ensure that all vendors implement the required hazard identification, risk assessment and risk control procedures: compliance is mandatory, and a zero-tolerance policy is applied for any failures. All sub-contractors must nominate an individual who will co-ordinate their company quality and health and safety matters, and report to our Site Management team on all Quality, Health, Safety and Environmental matters. Sub-Contractors must comply with any directions given to them by the Project Supervisor for Construction. In addition, they must also comply with the provisions of all of the mandated EHS obligations set out in the Law and at all times be fully compliant with our requirements , regulations and the notified site rules: they must ensure that all their employees have received the appropriate level of health and safety training and information for the work’s on which they are engaged and for general site compliance. All sub-contractors must have their own Safety Statement available on site. Detailed duties and responsibilities should be outlined in their Safety Statement. Safety Statements must be signed by company director/owner and they must also;

• Set out arrangements for managing safety • Name the person(s) who has been appointed as a supervisor/foreman with

responsibility for safety on site. • Detail training such as safe pass and CSCS • Detail First aid arrangements • Identify all Manual Handling requirements and their controls • List PPE supplied by subcontractor • Agree accident reporting to the main contractor and to the HSA

Sub-contractors will have to sign a form (part of the Contractor’s Assessment Form) stating that they will comply with the provisions of this Plan prior to that sub-contractor commencing on site. Sub-contractors may, at any time, inspect this plan, which is kept in the Site Office. Subcontractors Performance We undertake regular performance reviews, site inspections and audits. These assessments are performed to evaluate each supply chain partners performance in relation to their: • Level of Workmanship • Quality Control • Teamwork • Adherence to Site Rules • Communication • Co-operation • Ability to work without close supervision/constant management • Flexibility and reliability

Page 9: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 8 of 62

We also conduct a further assessment at the end of each project to determine whether the sub- contractor has performed well enough to remain on our ‘approved’ list. As part of this assessment, we look at what lessons have been learnt from our perspective but also in relation to the sub-contractor/supply chain partner. At Shapoorji Pallonji we have built a considerable reputation amongst our sub-contractors for demanding, and only accepting, the highest standards of workmanship. If, at any time, a sub-contractor fails to meet our required standard they are issued with an improvement notice. Where a sub-contractor is guilty of a serious non- conformance they are immediately taken of site and their ‘approved’ status is removed.

1.3 KEY DOCUMENTS Typical Documents listed below will be used to formulate the Integrated Construction Logistic Plan: -

No. Document Title Held By: Date Received.

1 Construction Phase Plan Project Manager & Site Manager

2 Designer Risk Assessments Project Manager & Site Manager

3 Health and Safety Plan Project Manager & H&S Officer

4 Construction issue information, Drawings & Specifications

Doc Control

5 Existing Service Drawings Issued By PSDP

Contracts Manager & Site Manager

6 Master Program Contracts Manager & Site Manager

7 Site Establishment Layout Site Manager

8 Local Authority Service Drawings Site team

9 Bill of Quantities QS

10 Traffic Management Plan Displayed on site

11 Planning Conditions Contracts Manager

12 Asbestos Survey N/A

13 Form of Contract Head Office

14 Environmental Impact Statement Head Office

15 Client Specific Conditions Site Team

16 Archaeology survey Site team

1.4 MEETING SCHEDULE Subject Frequency Attendees Day / Time Location

Client Meeting Monthly Director in charge

T.B.C Head Office

Design Team Meeting Fortnightly All site Management

T.B.C Site Meeting Room

Subcontractor Meeting Weekly Site Team T.B.C Site Meeting Room

Page 10: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 9 of 62

Site Safety Meeting Weekly Site Team T.B.C Site Meeting Room

SP Site Progress Meeting

Weekly Site Team T.B.C Site Meeting Room

Construction Management Meeting

Monthly Contracts Manager, Site QS and Site PM

T.B.C Head Office

Site M & E Meetings Fortnightly Site Team T.B.C Site Meeting Room

1.5 LEGAL & OTHER REQUIREMENTS SP has drafted this plan in line with various national and regional policies in mind. The Traffic Management Act (2004) The act makes ‘provision in relation to the management of road networks; to make new provision for regulating the carrying out of works and other activities in the street’. It acknowledges that highways may be occupied due to construction activities and identifies appropriate changes levied for any extended occupation. Designing for Deliveries, Freight Transport Association (2006) Published in 2006, Designing for Deliveries, provides specifications for the size of delivery vehicles, turning radii and clearance requirements and should be used to ensure that delivery vehicles can safely and efficiently access the construction site. Delivering a Road Freight Legacy (2013) This document details how stakeholders can work together to deliver a freight management legacy for London and outlines a longer-term freight plan for the capital. Seven key elements are covered: Better planning; Improving safety; Re-timing deliveries and collections; Kerbside access; Increasing efficiency; Effective communications; and journey planning. The London Plan (2011) Addressing the key trends and challenges that London will face, this Mayor’s document pays particular attention to encouraging sustainable modes of travel. Policy 6.3 states that CLPs should be secured in line with the London Freight Plan and should be co-ordinated with Travel Plans. In addition, Policy 6.14 stresses the need to promote movement of freight by rail and waterway. Development proposals promoting the uptake of the Fleet Operators Recognition Scheme (FORS), CLPs and Delivery and Servicing Plans (DSP) to consolidate freight will be encouraged. The Mayor’s Transport Strategy (2010) Freight and servicing is frequently mentioned throughout this document which contains a strategy considering all methods of freight delivery including road, rail, pipeline, water, bicycles and air. The document especially highlights the importance of the London Freight Plan, DSPs, CLPs and FORS to encourage improved efficiency and provide a framework for incentivisation and regulation. In particular, Proposal 99 states that “the Mayor, through Transport for London (TfL) and working with the London Boroughs, road freight operators and other stakeholders, will:

• Aim for 50% of HGVs and vans serving London to be members of FORS by 2016;

Page 11: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 10 of 62

• Encourage, and where appropriate specify, improved freight movement efficiency through, for example, greater consolidation, more off-peak freight movement and greater use of water and rail-based transport;

• Support freight industry land requirements for locally focussed consolidation and/or breakbulk facilities and access to waterways and railways”.

Proposal 117 acknowledges the incorporation of DSPs, CLPs and the FORS; “the Mayor, through TfL, and working with the London boroughs, and other stakeholders in the public and private sectors, will improve the efficiency and effectiveness of freight operations through the promotion of ‘delivery and servicing plans’, ‘construction logistics plans’, the Fleet Operator Recognition Scheme and other efficiency measures, across London”. The London Freight Plan (2007) The vision for sustainable freight distribution in London over the next five to ten years is for: “…the safe, reliable and efficient movement of freight and servicing trips to, from, within, and, where appropriate, through London to support London’s economy, in balance with the needs of other transport users, the environment and Londoners’ quality of life”. The Plan identifies FORS, DSPs, CLPs and the Freight Information Panel (FIP) as key projects for delivering freight more sustainably in London. Fleet Operator Recognition Scheme (FORS) FORS is a unique, industry-led, membership (bronze, silver, gold) scheme to help van and lorry operators become safer, more efficient and more environmentally friendly. It’s relevance to the CLP is via its mention in the Mayor’s Transport Strategy and requirements will be relayed to all operators engaged during the development.

1.6 ROLES AND RESPONSIBILITIES The Principal Contractors responsibilities include, but are not limited to:

• Co-ordinate the implementation of the Construction Regulations by contractors

• Co-ordinate the identification of hazards, the elimination of the hazards or the reduction of risks during construction

• Organise co-operation and the provision of information between contractors • Co-ordinate the reporting of accidents to the Health and Safety Authority • Notify the Health and Safety Authority before construction commences

where construction is likely to take more than 500-person days or 30 working days

• Co-ordinate the checking of safe working procedures • Co-ordinate measures to restrict entry to the site • Co-ordinate the provision and maintenance of welfare facilities • Co-ordinate arrangements to ensure that craft, general construction and

security workers have a safety awareness card, e.g. Safe Pass, and Construction Skills Certification Scheme (CSCS) card where required

• Co-ordinate the appointment of a site safety representative where there are more than 20 persons on site

• Provide information to the site safety representative • Appoint a safety adviser where there are more than 100 persons on site • Provide all necessary safety file information to the PSDP • Monitor the compliance of contractors and others and take corrective action

where necessary

Page 12: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 11 of 62

• Notify the Health and Safety Authority and the Client of non-compliance with any written directions issued.

• Work with the Principal Designer, the design team and the supply chain to ensure all legal compliances are fulfilled.

The Employer’s responsibilities include to:

• Manage and conduct work activities to ensure the safety and health of employees and others affected

• Prevent improper conduct likely to put an employee’s safety or health at risk • Provide a safe place of work that is adequately designed and maintained • Provide safe means of access and egress • Provide safe plant, equipment and machinery • Provide safe systems of work, e.g. operating procedures • Prevent risk to health from any article or substance (including plant, tools,

machinery, chemical substances and equipment) • Provide appropriate information, instruction, training and supervision –

considering the employee’s capabilities – when an employee begins work or is transferred to new tasks, and when new technology is introduced

• Provide suitable protective clothing and equipment where hazards cannot be eliminated

• Prepare and review emergency plans • Designate staff to take on emergency duties • Provide and maintain welfare facilities • Provide, where necessary, a competent person to advise and assist in

securing the safety, health and welfare of employees. (A competent person must have the necessary qualifications as well as sufficient training, experience and knowledge appropriate to the nature of the work to be undertaken)

• Comply with the relevant health and safety legislation, e.g. co-operating with the employer, reporting unsafe procedures or equipment

• Comply with safety policies and procedures to ensure his/her personal safety and that of others

• Co-operate with the employer in relation to safety, health and welfare at the place of work

• Report all hazards, injuries, incidents, dangerous occurrences and near misses as soon as possible to the employer

• Report any defects in equipment, unsafe activities or deficiencies in safety procedures to the employer

• Use any protective clothing and equipment that has been provided for his/her safety

• Attend any training as required by the employer • Co-operate with the employer to enable the employer to comply with

relevant health and safety legislation • Not engage in improper conduct or behaviour that is likely to endanger

his/her or others’ safety, health and welfare while at work • Not be under the influence of intoxicants as they may endanger his/her or

others’ safety, health and welfare • Not interfere with, misuse or damage anything provided for securing safety,

health and welfare. Other Contractor’s responsibilities include to:

Page 13: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 12 of 62

• Co-operate with the Principle Designer and promptly provide to them any site-specific information, including any relevant extract from their safety statement that (i) is likely to affect the safety, health or welfare of any person at work on the construction site, or (ii) might justify a review of the safety and health plan

• Provide information to the Principle Designer on any accident or dangerous occurrence on site

• Provide relevant information to the Principle Designer to develop the safety file and to comply with directions from the Principle Designer Comply with the safety and health plan and any rules in the plan that are applicable to the contractor or to the contractor’s employees

• Apply, where appropriate, the general principles of prevention in a consistent ma

Facilitate the performance and functions of the safety representative.

Task Person Responsible

Site Inductions Project Manager

Arrangements to ensure Statutory Inspections take place

Project Manager

Site Safety Audits TBA

Arrangements to ensure RAMs are completed Project Manager

Emergency Procedures, First Aid Project Manager

Environmental Inspections TBA

Fire Evacuation Drills Project Manager

1.7 EMERGENCY PLAN to be confirmed

Service Contact Phone No.

Emergency

Fire Brigade

Hospital

Local Doctor

Garda Station

Local Authority

ESB Services

GAS- Services

Local Health & Safety Authority Office

Site First Aider

Project Manager

Contracts Manager

Environmental; Officer

Commercial Manager

Out of Hours Contact

Security

1.6.1.1.1 Emergency Evacuation Procedures

Page 14: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 13 of 62

• In the event of an accident or emergency, the assembly point for all personal is in the compound.

• On Hearing the Horn/ Klaxon sound for three long blasts please proceed to this point and give your name to your foreman / Supervisor

• Remain at the assembly point until you are instructed by SP Construction site management to return to work

• Each Contractor Foreman will be responsible for check off procedures at the assembly point and must always know his full team on site

1.6.1.1.2 Emergency Procedures (Specific responsibilities) Site Manager/Engineers To Contact

• Outside Emergency Services • Foremen/Site Clerk/First Aider/Safety Officer as applicable • To control situation by instructing foremen to keep area clear and secured. • To notify all site management that Emergency Services are on the way • To stand down Emergency as required & to deal with any media • To ensure the area is preserved for incident investigation follow up • To liaise with all relevant services & HSA as appropriate

Safety Officer/Safety Rep

• To assist in controlling the situation • To monitor the situation, ensure all personnel involved in the emergency is

safe & commence Accident Investigation as soon as possible. Foremen/Engineers/Supervisors

• To assist in controlling the situation by following all instructions. • To ensure an adequate route is available for emergency services. • To ensure any plant, machinery or equipment does not obstruct access. • Organise men on road to direct Emergency Services to the Location. • To ensure no unauthorised persons enter the incident areas.

First Aiders

• To deliver emergency First Aid until the Emergency Services arrive. • First Aider on this site is: Site Manager

Site Workers/Contractors

• Not to put themselves or others in danger if assisting • To assemble at the site compound in a safe manner if not required • To assist site management as directed throughout the incident

A planned Emergency evacuation will be conducted on a periodic basis, typically twice over the duration of this project.

Page 15: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 14 of 62

2 CONSTRUCTION METHODOLOGY 2.0 PROJECT OUTLINE The site is located Axe Street Barking London. Demolition of existing buildings and the redevelopment of the site, including the erection of buildings ranging in height from 1 to 13 storeys to provide 170 residential units together with flexible commercial floorspace (Classes A1, A2, A3, A4, B1, D1 and D2), and office accommodation (class B1) with associated landscaping & public realm improvements Consideration is being given to the development of this site address: Axe Street, Barking IG117LX. Through the demolition and redevelopment of this site through the construction of one new building, the building comprises of stepped levels ranging from 2 to 13 stories. The 1st to 12th floor consists of accommodation and the ground floor will be commercial space. The development will house a total of 170 apartments Existing Site The Site is comprised of the former Abbey Sports Centre, a two storey brick building with a corrugated iron roof. The building has a large footprint that occupies the majority of the Site. The size of the current building provides limited public realm with a small area of vegetation provided where the building fronts the roundabout. The Site is bounded by Axe Street to the north, St Anne’s Road to the east, St Pauls Road to the south and the roundabout to the south west. The road network to the west and the south of the Site form the natural boundaries of Barking Town Centre with the wider town centre located to the north and east of the Site

2.1 IMPACT ON SURROUNDINGS There are some established constraints to accessing the Site, notably the following:

• Due to the nature of each site, parking will be an issue of concern. For reasons of Health and Safety, parking of contractors’ vehicles will not be permitted on the approach roads to the sites.

• The site has potential for active frontages on all sides, however, pedestrian footfall is likely to be less adjacent to primary roads (A123) compared to Axe Street and St Ann’s Road that are nearer to the town centre retail areas

• The surrounding land uses will continue to operate during the planned construction period, therefore the Applicant is committed to carrying out the works in the most practicably sustainable manner.

2.2 SITE ESTABLISHMENT 2.2.A.1.1 Welfare We will provide fully functional and compliant temporary site accommodation arrangements as part of our site set‐up. We will provide sufficient facilities for all parties including all Employer’s staff as required. These will include separate male/female and disabled toilets, drying rooms including lockers, fully resourced changing facilities and canteen etc., in accordance with current regulations. 2.2.A.1.2 Compound We will provide temporary hoardings/netting/screens around all work areas and maintain these to the highest standards for the duration of our work. This will ensure that construction works are always secure from unauthorized access and segregated from the public. We will agree the type, finish, extent, layout and decoration of all hoardings, nettings screens, with the Client prior to commencement on site.

Page 16: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 15 of 62

Hoardings will be 2.4m high and comply with the HSE booklet HS (G) 151 “Protecting the Public” to the satisfaction of the Employer and the Local Authority. The hoarding design and erecting works will be carried out by a qualified hoarding contractor. Weekly inspections of the hoarding will be carried out by our Site Managers as part of the checks to all on site temporary works. 2.2.A.1.3 Wheel Wash All truck wheels will be washed on exit from site. Water from wheel washing areas can contain oil and diesel, as well as high levels of silt. The Site Foreman / Gateman will ensure that water from wheel washing and wash down areas is contained and not allowed to soak into surrounding ground. The wheel wash will have a self-contained water recirculation system. A tank will store water for washing purposes, a pump will re-circulate the water back into the tank during washing. Solids that settle at the base of the tank will be removed by a vacuum tanker. Water will only be discharged to the foul water system during the periodic replenishment of the used process water with fresh water.

2.3 SITE ACCESS Access/egress to the site will be via Axe Street for both pedestrians and via and Vehicular access. The main site entrance will be controlled by a Gateman at the main gate. A pedestrian gate with turnstile will be included in the hoarding for operatives/visitors arriving by foot. All visitors including site operatives will require a pass to enter the site. All roads and footpaths in the vicinity of the Site will be meticulously maintained and on completion of the works they will all be reinstated to the condition they were found in at the start of the works. All vehicles leaving the site will have the tyres and under carriage power hosed by the gateman to ensure no debris or dirt are brought outside of site and sullying the surrounding area. Road sweeps will be used on a regular basis to aid in the cleaning of the area around the site 2.3.A.1.1 Car parking Car parking for site workers will not be provided on site and all site staff will be encouraged to travel using sustainable transport means. Limited short stay waiting capacity will be available for those construction staff with site-specific needs (e.g. transporting significant apparatus etc.). The available area will be reviewed throughout the construction periods to ensure the potential overspill to surrounding streets is adequately controlled. All construction staff will be kept informed about acceptable travel and parking arrangements during the works. 2.3.A.1.2 Access/Egress to the Site Access and egress to the site will be via Axe Street for both pedestrians and Vehicular access. The main site entrance will be controlled by a Gateman at the main gate. A pedestrian gate with turnstile will be included in the hoarding for operatives/visitors arriving by foot. All visitors including site operatives will require a pass to enter the site. All roads and footpaths in the vicinity of the Site will be meticulously maintained and on completion of the works they will all be reinstated to the condition they were found in at the start of the works. All vehicles leaving the site will have the tyres and under carriage power hosed by the gateman

Page 17: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 16 of 62

to ensure no debris or dirt are brought outside of site and sullying the surrounding area. Road sweeps will be used on a regular basis to aid in the cleaning of the area around the site The Site will at all-time be adequately protected by barriers to prevent unauthorised access (either accidental or deliberate). SP intent to install a 2.4 meter high solid hoarding to the entire site boundary. When the work has stopped for the day, the Site must be secured, all ladders and access must be removed, the plant must be immobilised, and all hazardous materials must be safely stored. 2.3.A.1.3 Local Roads The site is located along Axe Street, adjacent to the leisure centre. The site is surrounded on all four sides by roads. The A123 is the primary road to south east (St Pauls Road) and south west (Broadway). The secondary roads are Axe Street (1 way system & Site Access), to north west and St Ann’s Road to north east. To construct the proposed development some parking bay and footpath suspensions will be required at various times. These will be pre-arranged with TFL, the highways authority, and the local authorities. Currently it is envisaged that the following Traffic Regulation Orders will be required during the construction phase Footpath closure or partial thereof, along Axe Street to undertake the RC Frame and façade due to proximity to the footpath and public realm works Parking bay suspension to facilitate the public realm works. A road closure, timing and location to be confirmed, to allow for a tower cranes to be assembled and dismantled. At all times access to neighbouring properties will be maintained via redirecting traffic via various routes. 2.3.A.1.4 Nearby Railway Barking Railway Station is the nearest station located appox 900m from the development, however not within close proximity to cause any effect to the operations of these services. 2.3.A.1.5 Bus Routes Nearby bus routes include the 62, 287, 368 and 687 serving London and the surrounding area. As no bus routes pass along Axe Street no interference is envisaged, however should this alter SP will liaise with TFL to ensure minimal disruption to any service. 2.3.A.1.6 Cycle The local highway network has a network of footways which are wide and street lighting. The site is located adjacent to an existing signed cycle route which follows the alignment of Broadway heading north. A further quieter cycle route also passes the site along St Paul’s Road, providing access to the surrounding areas to the south and west of the site. Cyclist activity on the surrounding highway network and private access roads will be unhindered. We plan will note this route and make our supply chain aware of cycle safety. A Banksman will be available to ensure cyclist safety in conjunction with other vehicles.

Page 18: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 17 of 62

2.4 SITE CONSTRAINTS There’re some established constraints to accessing the Site, notably the following The site has potential for active frontages on all sides, however, pedestrian footfall is likely to be less adjacent to primary roads (A123) compared to Axe Street and St Ann’s Road that are nearer to the town centre retail areas The surrounding land uses will continue to operate during the planned construction period; therefore the Applicant is committed to carrying out the works in the most practicably sustainable manner. It must be noted the surrounding land uses will continue to operate during the planned construction period, therefore SP is committed to carrying out the works in the most practicably sustainable manner. There is significant height, weight or width restrictions in the immediate vicinity of the Site as shown above, therefore forward planning with the local council on anticipated construction vehicles is a necessity. Furthermore, the Site lies within the boundary of the London Lorry Control Scheme (LLCS) which restricts the movement of HGVs in London at night and weekends. Enforced by London Councils, it applies to vehicles weighing more than 18 tonnes. It aims to limit noise pollution in residential areas. Restrictions apply between: 21:00 to 07:00, Monday to Friday; 13:00 to 07:00 Saturday. It is possible to operate a vehicle over 18 tonnes within the restricted area during restricted times, however prior approval must be sought. 2.4.A.1.1 Schools There is a primary school situated to the south west of the site along St Pauls Road. While the school is not in the immediate vicinity, it is likely pupils will be using adjacent footpaths to walk to nearby tube stations and transport links. The Community Engagement Officer will regularly contact the school to share information in order to maximise child and pedestrian safety. 2.4.A.1.2 Neighbouring Construction Sites Axe street development has no neighbouring construction sites. When the works schedule is known, trip generation analysis will be cross-referenced to ensure precautions are taken to lower any compounding peak vehicle movements. The same procedure will be performed for any other construction sites in the area. In addition to vehicle analysis, an SP will collaborate on shared services such as marshalling areas, vehicle holding areas and stakeholder engagement. 2.4.A.1.3 Neighbour Relations We acknowledge that many parties will have an interest in this project throughout the duration of the contract. Our presence during the construction phase will have a direct impact on the local environment, particularly the following: • Planning Authority • Building Control • Environmental Health • Utilities providers • Adjacent properties

Page 19: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 18 of 62

• Residents committee • Local law enforcement • Fire service Our Project Manager will be responsible for project strategic liaison whilst the site Managers will be responsible for day to day liaison and logistics for all of the construction related activities. Both will be permanently based on site with the site Managers as the first point of contact for all concerns, issues and complaints. Any complaints received will be logged, assessed and appropriate action taken as soon as is practical. We will actively seek liaison with all parties throughout the pre-construction and construction periods. It will be critical to the success of the project that key issues are properly addressed from the outset to create a good working relationship and an integrated team approach to resolving potential issues before they arise. Workshops and forums will be held on a regular basis to maintain open relationships and keep stakeholders up to date on construction progress and its impact on all third parties. Newsletters, liaison meetings, progress photos, organised site visits are all methods we will use to communicate how we intend to carry out the works and keep people informed. This process is part of the Considerate Constructors scheme that we automatically register with, and by which we are independently monitored and assessed.

2.5 SECURITY PROVISIONS We will adequately safeguard the site, the works, products, materials, plant, and any existing buildings affected by the Works from damage and theft. Issues such as noise, pollution and nuisance will be kept to an absolute minimum so as not to infringe on the rights of neighboring owners/tenants. Site entry will be restricted to personnel solely involved in the construction process during working hours and also to prevent unauthorised access out of hours. Site access for all personnel and visitors will be strictly controlled and all visitors will report to the site offices prior to entering the construction area. CCTV cameras covering the entrance and boundaries will be installed, linking back to the security office. The site will be monitored through 24‐ hrs CCTV security. All personnel and visitors entering the site will be required to sign‐in and made aware of safety issues associated with the construction process and emergency procedures to evacuate the site as part of the site‐specific induction. All visitors will be issued with safety helmets and any other appropriate protective clothing will be escorted by a responsible member of the site team.

2.6 MATERIALS AND STORAGE Store materials in a planned and orderly manner that does not endanger employee safety. Ensure stacks, tiers, and piles are stable and stacked to aid safe handling and loading. Store hazardous materials in accordance with the individual requirements. Unloading of Plant and Materials Each delivery driver involved in deliveries to construction sites should clearly define and allocate responsibility for this role. All materials should be correctly loaded and secured in accordance with the Code of Practice on Safe Loading of Goods Vehicles. All drivers

Page 20: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 19 of 62

delivering to site should always wear PPE when out of the vehicle and descending from the cab. The following guidance will be adhered to for each delivery

• Report to site office before entry

• Undertake Driver induction / briefing

• Enter Site

• Vehicle routes on sites will be clearly marked.

• Reversing should be kept to a minimum a

• Overhead hazards will be clearly identified

• The driver will be guided to the location of loading / unloading and storage areas by the site manager

Note there is little on-site storage space Store materials in a planned and orderly manner that does not endanger employee safety. Ensure stacks, tiers, and piles are stable and stacked to aid safe handling and loading. Store hazardous materials in accordance with the individual requirements. Store all materials on pallets to discourage rodent infestation. Immediately clean up spills and leaks that create such rodent habitat. Use slings to hoist bagged material, lumber, bricks, masonry blocks, and similar loosely stacked materials only if the slings are fully secured against falling by straps, sideboards, nets, or other suitable devices. Storing Materials in an Open Yard Storing materials in an open yard requires attention to combustible materials, access, powerlines, and fire protection. Combustible Materials. Stack combustible materials securely. Stacks or piles must be no more than 16 feet high. Store combustible material at least 10 feet away from a building or structure. Access. Driveways between and around combustible storage piles must be at least 15 feet wide. Keep them free from accumulations of material or rubbish. Use a map grid system of 50 by 150 feet when planning driveways in open-yard combustible material storage areas. Powerlines. Do not store materials under power lines or where materials may block egress or emergency equipment. Fire Protection. Provide portable fire extinguishing equipment rated 2-A:40-B:C at accessible marked locations in the yard so that the nearest extinguisher is no more than 50 feet away for a Class B hazard or 75 feet away for a Class A hazard. Requirements for Storing Materials Indoors Storing materials indoors requires attention to access, fire prevention and protection, floor loading, and overhead hazards. Buildings under construction require special precautions. Access. Place or store materials so they do not interfere with access ways, doorways, electrical panels, fire extinguishers, or hoistways. Do not obstruct access ways or exits with accumulations of scrap or materials. Aisles must be wide enough to accommodate forklifts or firefighting equipment. Fire Prevention. When storing, handling, and piling materials, consider the fire characteristics. Store noncompatible materials that may create a fire hazard at least 25 feet apart or separate them with a barrier having at least a 1-hour fire rating. Pile

Page 21: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 20 of 62

material to minimize internal fire spread and to provide convenient access for firefighting. Fire Doors. Maintain a 24-inch clearance around the travel path of fire doors. Sprinklers. Maintain at least an 18-inch clearance between stored materials and sprinkler heads. Heating Appliances. Maintain at least a 3-foot clearance between stored materials and unit heaters, radiant space heaters, duct furnaces, and flues or the clearances shown on the approval agency label. Fire Protection. Emergency fire equipment must be readily accessible and in good working order. Floor Loading. Conspicuously post load limits in all storage areas, except for floors or slabs on grade. Buildings Under Construction. Store materials inside buildings under construction at least 6 feet away from any hoistway or inside floor openings, and 10 feet away from an exterior wall that does not extend above the top of the material stored. Requirements for Stacking Bagged Material Stack bagged materials by stepping back the layers and cross-keying the bags at least every 10 bags high, except when restrained by walls or partitions of adequate strength. Requirements for Storing Material in Bulk Ensure entry to bulk storage locations, such as silos, hoppers, tanks, or bins (which are also classified as confined spaces) complies with OSHA requirements and local operating procedures. Requirements for Storing Bricks and Masonry Blocks Stack bricks and masonry blocks on level and solid surfaces. Bricks. Stack bricks no more than 7 feet high. Step back a loose brick stack at least 2 inches for every foot of height above 4 feet. Stack packaged brick no more than three units high. Masonry Blocks. Step back masonry blocks one-half block per tier above the 6-foot level. Requirements for Handling and Storing Cement and Lime Handling or storing cement or lime requires a job hazard analysis (JHA). Lime requires careful storage and handling procedures. Cement and Lime. Employees must wear appropriate personal protective equipment, as specified in the “Personal Protective Equipment” section and as identified in the JHA. Provide washing facilities, hand cream, chemical barrier cream, or similar preparations for protection from dermatitis. Lime. Store unslaked lime in a dry area and, because it presents a fire hazard, separate it from other materials. Requirements for Handling and Storing Reinforcing, Sheet, and Structural Steel Stack steel to prevent sliding, rolling, spreading, or falling. Use lagging (sleeve) when steel is handled by a crane or forklift to aid safe rigging. Requirements for Handling and Storing Pipe, Conduit, and Cylindrical Material Make sure cylindrical materials are stable when storing or handling. Stacking. Place pipe, conduit bar stock, and other cylindrical materials in racks or stack and block them on a firm, level surface to prevent spreading, rolling, or falling. Use either

Page 22: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 21 of 62

a pyramided or battened stack. Step back battened stacks at least one unit per tier and securely chock them on both sides of the stack. Removal. Remove round stock (e.g., wood poles, pipe, and conduit) from a stack from the ends of the stock. Unloading. Unload carriers so that employees are not exposed to the unsecured load. Taglines. Use taglines when working with round stock. Requirements for Storing Sand, Gravel, and Crushed Stone Locate stockpiles to provide safe access for withdrawing material. Material or vertical faces must not overhang. Store material against walls or partitions only in an amount that will not endanger the stability of the wall or partition. Requirements for Handling Flammable and Combustible Liquids Unless defined otherwise, terms used in this subsection are the same as those in the flammable and combustible liquids code, NFPA 30, or 29 CFR 1910.106. Classification of Flammable and Combustible Liquids. Flammable and combustible liquids are classified as follows: Flammable Liquids (Class I Liquids):

1. Class I—Flashpoint below 100 °F (38 °C)

2. Class IA—Flashpoint below 73 °F (23 °C) and boiling point below 100 °F (38 °C)

3. Class IB—Flashpoint below 73 °F (23 °C) and boiling point at or above 100 °F (38 °C)

4. Class IC—Flashpoint at or above 73 °F (23 °C) but below 100 °F (38 °C)

Combustible Liquids (Class II and III Liquids):

5. Class II—Flashpoint at or above 100 °F (38 °C) and below 140 °F (60 °C)

6. Class III—Flashpoint at or above 140 °F (60 °C) Class IA Flammable Liquids Restricted Use. Because of the extreme explosion hazard of Class IA liquids, purchase them only after you have reviewed the MSDS and the storage, dispensing, and use procedures have been approved. Submittals for approval must provide the name and description of the liquid, its characteristics, a detailed description of its intended use, the MSDS, and the safety and health precautions. This requirement does not apply to small quantities of aerosol starter fluid used for engines. Substitute Product. Wherever practical, use a less hazardous product. Controlled Use. A competent person must supervise storage, dispensing, and use of Class IA liquids, including design of the storage and dispensing system. Toxicity of Flammable and Combustible Liquids. Most flammable and combustible liquids are highly toxic. Use them only after determining their toxic characteristics. In handling toxic liquids, follow the appropriate safety and health requirements in the “Occupational Health” section. Closed Tanks and Containers Approved Types. Use only the following approved and labeled closed tanks and containers to store, handle, and dispense flammable and combustible liquids. Original Container. Store and use flammable and combustible liquids in the original Department of Transportation (DOT) shipping containers, as shown in table 11-1.

Page 23: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 22 of 62

However, store only up to 1-day’s use in the work area, up to a maximum of 25 gallons of a Class 1A liquid or a maximum of 120 gallons of any other class of liquid. When dispensing and using smaller quantities of flammable and combustible liquids, dispense them into properly labeled, approved safety containers. Exception: You may store and handle highly viscous (extremely hard to pour) liquids in any size original container. Liquids that are transferred from labeled containers to portable containers for immediate use are exempt from labeling. Safety Can. An approved container holding no more than 5 gallons with a spring-closing lid, spout cover, and designed to safely relieve internal pressure when subjected to fire or heat exposure. Drum/Barrel. An approved container holding more than 5 gallons but no more than 60 gallons. Portable Tanks. An approved, closed storage vessel holding more than 60 but no more than 660 gallons and not intended to be a fixed installation. Tanks. Any vessel holding more than 60 gallons, intended for fixed installation, is not used for processing.

Table 11-1.—Maximum allowable size of containers and portable tanks, combustible

Flammable liquids Liquids

Container type Class IA Class IB Class IB Class II Class III Glass

Metal (other than approved DOT drums) or approved plastic

Safety cans

Metal drums (DOT specifications)

Approved portable tanks

Polyethylene DOT specification 34,or as authorized by DOT exemption

1 pint 1 gallon 2 gallon 60 gallons 660 gallons 1 gallon

1 quart 5 gallons 5 gallons 60 gallons 660 gallons 5 gallons

1 gallon 5 gallons 5 gallons 60 gallons 660 gallons 5 gallons

1 gallon 5 gallons 5 gallons 60 gallons 660 gallons 60 gallons

5 gallons 5 gallons 5 gallons 60 gallons 660 gallons 60 gallons

Approved Storage Cabinets General Design and Construction. The design, construction, and approval of storage cabinets must comply with NFPA 30. Requirements for Storing Flammable or Combustible Liquids Indoor Storage. Do not store flammable and combustible liquids indoors, except as follows:

• Store no more than 25 gallons in a room or single fire area.

• Store no more than 60 gallons of Class I or II liquids, or more than 120 gallons of Class III liquids, in an approved cabinet. Locate no more than three such cabinets in a single fire area.

• You may store larger quantities in separated indoor storage areas when such storage meets the requirements of NFPA 30, Section 4-4, “Design, Construction, and Operation of Inside Storage Areas.”

Page 24: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 23 of 62

• Place at least one 2-A:40-B:C fire extinguisher 10 feet to 30 feet away from the stored material or cabinet.

• Place at least one 2-A:40-B:C fire extinguisher outside of, but not more than 10 feet from, the door opening into an inside liquid storage area.

Outdoor Storage. Do not store flammable and combustible liquids outdoors, except as follows:

Above ground in approved containers with no more than 60-gallon capacity, subject to the following restrictions:

(a) The total capacity of any one group of containers stored together must not exceed 1,100 gallons. Each group of containers must be at least 5 feet apart, and each group must be at least 20 feet away from any building or other combustibles.

(b) Each group of containers must be adjacent to an access way at least 12 feet wide to facilitate the use of firefighting equipment.

Above ground in approved portable tanks with no more than 660-gallon capacity, providing that you:

(a) Keep a 5-foot clear area around groups of two or more tanks with a combined capacity of more than 2,200 gallons.

(b) Keep portable tanks at least 20 feet away from any building or other combustibles.

(c) Equip portable storage tanks with emergency venting and other devices, as required in NFPA 30.

(d) Locate each tank adjacent to an access way at least 12 feet wide to facilitate use of firefighting equipment.

Above ground in approved tanks installed in accordance with NFPA 30, Section 2-3, “Installation of Outside Above Ground Tanks.” Dike storage areas at least 12 inches high or grade and slope them, and seal them with a 50-mil plastic compatible sheeting or equivalent liner to contain leaks and spills equal to the capacity of all tanks or containers in each area. Keep the area free from vegetation or combustible material within 10 feet of the storage area perimeter. Place at least one portable fire extinguisher unit rated not less than 2-A:40-B:C 25 feet to 75 feet away from each portable tank or group of tanks or containers.

Handling and Dispensing Flammable or Combustible Liquids Dispensing Area. Separate areas where you transfer more than 5 gallons of flammable or combustible liquids at a time from other operations by at least 25 feet or by a partition with a minimum 1-hour fire rating. Use drainage or an equally effective method to contain spills. Ventilation. Provide adequate natural or mechanical ventilation to maintain the concentrations of flammable vapor below 10 percent of the lower explosive limit (LEL). Grounding. Transferring Class I flammable liquids from one container to another requires bonding of the containers and the transfer system. Electrically ground and bond all dispensing systems. Dispensing. Withdraw or transfer flammable and combustible liquids into vessels, containers, or tanks only through a closed piping system, from safety cans, by means of a device drawing through the top, from containers or tanks by gravity or pump through a listed self- closing valve. Do not transfer by injecting pressurized air into a tank or

Page 25: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 24 of 62

container. Use approved dispensing devises and nozzles. The dispensing units must be protected against collision damage. Lighting and Electrical Equipment. Use only electrical lighting to illuminate areas where Class I flammable liquids are handled or dispensed or where flammable vapor may be present. Wiring and all electrical equipment must meet the requirements of NFPA designation: Class I, Division 2, of the National Electrical Code. Covered Containers. Keep Class I and II liquids in covered containers when not in use. Flame and Ignition. Do not permit open flame, smoking, or other sources of ignition within at least 50 feet of areas where Class I flammable liquids are dispensed or used. Post approved “No Smoking” signs in such areas. Leakage or Spillage. Clean up leaking or spilled flammable or combustible liquids promptly and dispose of them safely. Refuse Containers. Provide self-closing metal refuse containers in all areas where employees use or dispense flammable or combustible liquids. Requirements for Refueling Equipment. Ensure that the design and installation of tanks and equipment used to refuel vehicles or equipment (fueled with flammable or combustible liquids) comply with the applicable provisions of the NFPA standards or nationally recognized testing laboratories or have the approval of the Government agency having jurisdiction. Tank Truck. Ensure that tank trucks comply with the requirements published in NFPA 385, “Standard for Flammable and Combustible Liquid Tank Vehicles.” Dispensing Stations. Mount dispensing devices, except those attached to containers, on a concrete platform elevated at least 5 inches above grade. Use guardrails or posts to protect them from collision with a motor vehicle. Dispensing Hose. To dispense flammable and combustible liquids, use an approved-type hose with an automatic self-closing valve or nozzle without a latch-open device. Ensure that a hanger or hose retracting system is in place to protect the hose from traffic abuse. Electrical Equipment. Ensure that electrical wiring, pumps, and equipment meet the appropriate requirements of NFPA designation, Class I of the National Electrical Code. Provide clearly marked and accessible switches at a location remote from dispensing devices to shut off all power to devices in an emergency. Refueling Equipment. During refueling, shut down vehicles or equipment that use gasoline, liquified petroleum gas (LPG), or other flammable or combustible liquid fuels. An exception is diesel equipment when fueled in accordance with the manufacturer’s recommendations. Use guardrails or posts to protect refueling tanks or dispensing islands from vehicular damage. Smoking. Post a “No Smoking Within 50 Feet” sign on all mobile refueling equipment and in established refueling areas. Emergency Shut-Off Switch. Ensure that an emergency shut-off switch is within 50 shall be located within 50 feet of the fuel dispensing equipment. Post a conspicuous sign to identify the switch location. Fire Protection. Provide each refueling area with one or more listed fire extinguishers with a minimum classification of 40B:C. Locate a fire extinguisher within 100 feet of each pump, dispenser, underground fill pipe opening, and lubrication or service room. Requirements for Handling Asphalt and Tar Products Employees who handle or work with these materials must complete a JHA, including exposure determinations. Make available and ensure employees follow the MSDS for storing, handling, and applying these materials.

Page 26: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 25 of 62

Protective Clothing and Equipment. Give full consideration to protective clothing, respiratory protection, and skin protection, as specified in the “Personal Protective Equipment” section, to protect employees handling or applying these materials. Confined Spaces. In enclosed or confined areas where hot tar, asphalt, enamel, or similar materials are heated or applied, the operation must conform fully with the “Confined Spaces” section. Heating Kettles. Do not leave asphalt or tar kettles unattended, when in use. Place them on a firm, level base and protect them from overturning. Kettles must have an effective lid or hood. They must have an operable temperature indicator and limiting device ensuring the asphalt or tarremains at no less than 50 EF below the flashpoint. Do not use kettles in confined or unventilated spaces, underground, in conduits, or in or on enclosed buildings or structures. Fire Protection. Provide a fire extinguisher, rated not less than 2-A:40-B:C, where heating devices or heating kettles are in use. Handling. Provide adequate unobstructed runways or access ways for employees handling hot materials. Employees must not carry hot materials up or down ladders. Instead, provide adequate hoisting devices. Thinners. Do not use gasoline or similar volatile liquids as thinners. Hand Spraying. The nozzle person applying hot tar asphalt must not work under the hoses supplying the material to the spray nozzle. Use flexible metallic hoses fitted with insulated handles in hand spraying operations. Housekeeping. Keep distributors, retorts, hoses, and related equipment reasonably free of asphalt and tar accumulations. Requirements for Handling Liquified Petroleum Gas (LPG) Store, handle, install, and use LPG and systems in accordance with NFPA 58, 29 CFR 1910.110(f), and 29 CFR 1926.153. Cylinders must meet DOT specifications published in 49 CFR, Part 178, “Shipping Container Specifications.” Hazardous Locations. Do not use LPG containers and equipment in unventilated spaces, below grade in pits or trenches, below deck, or in confined areas. Tubing. Use only tubing or piping approved for use in LPG systems. Do not use aluminum or polyvinyl piping or tubing. Hose. Use only hoses labeled “LP-gas or LPG.” Hose must have a minimum working pressure of 250 pounds per square inch. Valves and Accessories. Valves, fittings, and accessories connected directly to the container, including primary shutoff valves, must have a minimum working gauge pressure of 250 pounds per square inch and be designed for LPG service. Shutoff Valves. Connections to containers, except safety relief connections, liquid level gauging devices, and plugged openings, must have a shutoff valve located as close to the container as possible. Shutoff valves must not be located between the safety relief device and the container, except when the location of the shutoff valve allows the fully required capacity flow through the safety relief device. Safety Relief Valves. Equip each container with one or more approved safety relief valves. These valves must allow free venting to the outer air. The discharge must be 5 feet away from any building opening. Place container safety relief devices and regulator relief vents at least 5 feet from air openings into sealed combustion system appliances or mechanical ventilation air intakes. Dispensing Portable Containers. Fill portable containers from storage containers outside and at least 50 feet away from the nearest building.

Page 27: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 26 of 62

Motor Vehicles. Fill fuel containers on motor vehicles from bulk storage containers at least 10 feet away from a masonry-walled building and at least 25 feet away from any other building or structure. Refueling. Shut down equipment using LPG during refueling. Storage of Cylinders and Containers. Store LPG containers and cylinders not in use outside of buildings or structures, at not less than the following distances away from the nearest building or combustible material storage.

Quantity of LP-gas stored (pounds)

Minimum distance

(a) and (b) (feet)

(c) and (d) (feet)

(e) (feet)

720 or less 0 0 5 721 to 2,500 0 10 10 2,501 to 6,000 10 10 10 6,001 to 10,000 20 20 20 Over 10,000 25 25 25

(a) nearest building or storage area; (b) line of adjoining property; (c) thoroughfares or sidewalks; (d) line of adjoining property used for public gathering; (e) dispensing station.

Fire Protection. Provide storage locations with at least one accessible portable fire extinguisher rated not less than 2-A:40-B:C, between 25 feet and 75 feet away from the container. Requirements for Storing and Handling Paints, Varnishes, and Thinners Storing and handling paints, varnishes, or thinners requires special attention to flammability characteristics. Storage. Store and dispense paints, varnishes, lacquers, thinners, and other volatile paints or coatings according to their flammability characteristics. Tightly close containers when not in use; store no more than a 1-day supply in buildings under construction. Ventilation. Provide sufficient ventilation to prevent hazardous concentrations of flammable vapors from accumulating where employees dispense or apply paints or coatings. Spray Painting. Do not allow smoking, open flame, exposed heating elements, or other sources of ignition where employees spray flammable or combustible paints or coating. Spray painting booths and equipment must be in accordance with NFPA 33, “Standard for Spray Application Using Flammable and Combustible Materials.” Personal Protective Equipment. Make exposure determinations for employees who have been exposed to paints or coatings potentially hazardous to their health to document exposure and, when appropriate, provide appropriate protective equipment and hazard training. Electrostatic Paint Spraying Electrical. Locate transformers, power packs, control apparatus, and other electrical portions of the equipment, with exception of the gun and its connection to the power supply, outside the spraying area. Grounding. Ground the handle of the spray gun with a conductive device to ensure the gun and the operator are at the same ground potential.

Page 28: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 27 of 62

2.7 CONSTRUCTION METHODOLOGIES AND PROGRAMMING To be finalized after a full design review and site inspection, engagement with all Stakeholders, insurance reports and an internal legal review of all relevant facts 2.7.A.1.1 Demolition and Groundworks Following the early appointment of the demolition contractor, in order to facilitate site clearance. Demolition is relatively minor on this scheme and mainly consists of breaking up of the current RC Slab beneath the west Building. This material will be crushed on site and reused on site to prevent material been delivered in its absence. On completion of the above phase construction shall swiftly move onto The Piling works followed by the ground beams and GF floor slab. The below ground drainage shall also be incorporated within this timeline. Prior to the construction of the Ground Floor slab the remediation strategy as carried out by GEA for Planning Condition 35 will have been sign off and approved by the relevant inspector. A Demo and Waste management plan will be prepared to ensure that waste arisings during the construction and demolition phases of the project will be managed and disposed of in a way that ensures the provisions of the CDM Regulation 2015 and Health and Safety in Construction (HSG150) and The Environmental Protection Act 1990 It will also ensure that optimum levels of waste reduction, reuse and recycling are achieved. This plan aims to ensure waste prevention, maximum recycling and recovery of waste with diversion from landfill, wherever possible. It also seeks to provide guidance on the appropriate collection and transport of waste to prevent issues associated with litter or more serious environmental pollution (e.g. contamination of soil or water resources). Demolition Methodology will include the systematic demolition by mechanical excavator (approx. 15 tonne). Removal off site by a second similar sized mechanical excavator loading highways complaint (FORS) haulage Lorries for processing off site and reuse. Plant Machinery • 2No. 30 tonne mechanical excavators • 1No. Compressor (Diesel) • 1No. Jack Hammer • 4No. Haulage Lorries Pollution Controls • Dust mitigation by means of dampening down works interfaces with water sprays • Plant Machinery compliant with Stage V NRMM • Material Transfer to highways mitigated by 24/7 entry & exit wheel wash • Covered haulage 2.7.A.1.2 RC Frame Upon completion of the relevant floor plate the RC Frame shall commence. The RC frame will be undertaken in sequential manner floor by floor until the roof is topped out. Scaffold

Page 29: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 28 of 62

or mast climbers and Goods hoists shall be erected around each building once the RC Frame has had the back props removed. 2.7.A.1.3 Façade Works The SFS framing will start on the ground floor once the RC Frame is sufficiently elevated and will work up the building floor by floor until works are complete. Windows will be installed following the installation of the SFS. Once the ground floor framing is complete the windows will follow. This sequence will follow up the façade. The SFS will be follow by the external brickwork leaf on a level by level basis. 2.7.A.1.4 Internal works The internal finished will commence as soon as the windows have been installed and the building is adequately watertight on each floor. 2.7.A.1.5 Landscaping works The Landscaping works will be undertaken following the completion of the façade and subsequent striking out the mast climbers. The landscaping works will be in progress whilst the internal fit out is ongoing. 2.7.A.1.6 Commissioning Programme: A detailed Commissioning Programme will be developed in line with our M&E design and works schedule. 2.7.A.1.7 Labour/Resource Programme: Furthermore, SP during pre-commencement stage, will compile a detailed labour and resource programme which is in line in the main programme where resources are uploaded to each task bar in the programme. Labour Histograms for the project have been can then extracted from the Resource Programme. 2.7.A.1.8 Quality Control: SP has a Quality Management System in place fully compliant to ISO 9001:2015. This ensures that our quality system, checking, documentation control and record keeping are in line with the highest standards within the industry. We are also registered with the International Certification Network. Measures for ensuring quality are met through our Quality and Procedures Manual which detail all our organisation systems responsibilities, inspection and test plan procedures, which are fully described to ensure that all essential inspection requirements are determined and satisfied throughout all phases of the works. We will use priority software to track all quality checks and inspections. The software used will be BIM 360 Field which is linked to the Revit model of the project. 2.7.A.1.9 Check Sheets, Witnessing Sign Off SP has a full suite of check sheets to ensure that each element of the works is checked, signed off and is fully compliant with the Works Requirements, Specifications Drawings and all contract documents. For each and every activity there is a proforma quality control sheet that will be signed off by both our own personnel and those of the Subcontractors / Specialists. Each element of the works will be signed off and witnessed every step of the way by all relevant parties. This will safeguard and ensure that all works is fully compliant and fit for its intended purpose. In terms of MEP, the Services Coordinator and Commissioning Manager will be responsible for inspecting, witnessing, testing and signing off all stages of the Building Services

Page 30: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 29 of 62

installation prior to following trades closing up or advancing their works. They will ensure that all installations are in accordance with the design and governing standards and regulations. SP will keep and maintain a copy of all relevant check certificates for inspection on a web-based portal with full access provided to the Client Design Team. The Client Design Team will be provided with no less than 5 working days’ notice prior to the performance of a test to allow them to witness the testing. 2.7.A.1.10 Samples Mock-Ups SP will provide a range of Samples and Mock-Ups that have been identified in order to allow the Client Design Team to review the design, quality of proposals and establish compliance and quality control criteria and benchmarks for elements of the works. We will produce these items in good time for proper review and comments to be returned prior to manufacture / order / installation dates. All approved samples / mock-ups will be retained on site in a controlled environment for comparison with the products and materials used in the work throughout the entire contract.

2.8 DESIGN ISSUE, REVIEW PRE-START PLANNING During the pre-construction phased we will work with the Principal Designer , the Design Team , the supply chain and all stakeholders to complete the Health and Safety Plan and the Construction Phase Plan. This process will consist of, but is not limited to the following reviews:

• Agreement of GA arrangements to the agreed RIBA Stage • Agreement on fabrication submission and approval process including

schedule of Amendments • Meetings, as required, between the Principal Designer, the Employers Team,

Stakeholders, and the supply chain SP and the client’s representative to avoid unnecessary delay in this process.

• Carry out dilapidation surveys on the surrounding area. The final report will set out in detail our strategy in respect of managing the construction of the typical package work elements of :-

1. Demolition and Site Clearance 2. Basement 3. Superstructure Frame 4. External Walls & Finishes 5. Internal Walls 6. Roof Finishes 7. External Walls Completion/Facade 8. Internal Walls Completion 9. Roof Completions 10. Balustrades and Handrails 11. Floor Finishes 12. Internal Wall Finishes 13. Ceiling Finishes 14. Sanitary Fittings 15. Mechanical Services Installations 16. Electrical Services Installations 17. Sprinkler 18. Lift Installation

Page 31: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 30 of 62

Impact on Surroundings • Works will take place very close to Public area along with being near public

roads. • Introduction of additional traffic during construction • Introduction of heavy plant throughout the development • Dust and dirt

2.9 PROGRAMME AND PROGRESS REPORTS Construction Programme Formulated by the Project Manager, the programme will be issued to the team upon agreement on start date. Sub Programmes to be formulated by the Project Manager as the project progresses. The programme of construction for Axe Street has been developed with input our supply chain. Construction is expected to last for 104 weeks and is scheduled to begin March 2020. The building will be completed and ready for occupancy in February 2022 We have prepared a robust and detailed set of Programmes, Schedules, Site set-up and Traffic Management Drawings for the Axe Street Project as follows.

Overview SP has prepared a robust and detailed set of programmes, schedules, site set-up and traffic management drawings for the Axe Street project as follows.

• Our sequence of working will generally follow that shown on our master programme, along with our programme, this document provides a detailed explanation of our approach and methodology to demonstrate the phasing of the works from pre-commencement activities, construction, testing, commissioning and handover of the completed project.

• Furthermore, the following narrative demonstrates that our tender programme is very specific and fully integrates the management of preconstruction, design development, procurement and construction delivery. The detailed and specific programme outlines all activities and milestones and are broken down as per the key specialists / trades.

• The programme also identifies key links between the separate specialists / trades on the project. In addition, the programme also demonstrates that SP fully understands the key issues associated with the project and identifies those materials which are long lead items and the estimated duration from ordering to delivery.

Pre-Commencement

Page 32: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 31 of 62

SP during pre-commencement will immediately commence with appointment of the relevant consultant required to meet the projects demands. In conjunction with this all relevant pre-construction and mobilisation works as outlined in the tender programme will be undertaken. Works include site set up, hoarding installation, and statutory notices that requiring to be served. Additionally, a UXO survey will be commissioned to commence on site.

Page 33: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 32 of 62

3 HEALTH & SAFETY 3.0 SITE RULES

An example of a site policy is set out below

Page 34: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 33 of 62

3.1 HAZARD IDENTIFICATION, RISK ASSESSMENTS & CONTROL MEASURES The final document will be developed after a full site inspection, engagement with all Stakeholders, insurance reports and an internal legal review of all relevant facts

Activity Hazards Likelihood / Consequences

Control Measures Residual Risk Level

Responsible

Access to site Through Residential Area

Injury/Fatality High Traffic Management Plan Warning signs 100m and 50m prior to site entrance. All delivery drivers will be sent map prior to delivery and warned that it is a residential Area. Communications between site management and delivery drivers to avoid any unnecessary disruption.

Low SP Project Team

Formal Access Point required into the site

New access Point can cause disruption to public traffic.

High Site Hoardings Traffic Management Plan to be prepared Warning signs shall be posted on the public Road at either side of the access to warn the presence of Construction site and the movement of construction traffic.

Low SP Project Team

Overhead Power lines

Contractors hitting them with plant Electrocution

High Site survey to be carried out Overhead power lines area cordoned off from main site if possible. Bunting as per codes of practice) Avoidance of dangers of Overhead electricity Lines Part of Induction

Low SP Project Team

Page 35: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 34 of 62

Site Location Inadequate planning can cause disruption on main roads leading to site

High Prepare site logistics proposal document TMP will be prepared

Low SP Project Team

Security a temporary works design for the site hoarding

Members of the public/trespasser entering the site Falls and at a risk of encountering potentially dangerous substances. Injury/ fatality/Collision

High Hoardings and Safety security Fencing. The PSCS must put into action a security system that prevents access by anyone other than authorised persons, always throughout the construction project All plant and equipment stored Overnight will be immobilised. Dangerous materials/ substances will be removed off site or secured in a locked storage area. Method statement from contractors

Low SP Project Team

Managing Traffic access and Egress to site

Injury/ fatality/Collision

High Traffic Management Plan for site. The PSCS shall provide a flagman to safely direct vehicles onto, and off, the site. Roads & Footpaths – the PSCS shall ensure that existing roads & footpaths in are always kept in a safe condition and shall undertake cleaning of same as required to maintain them in a safe condition Access off public Roads defined And controlled and sign posted.

Low SP Project Team

Page 36: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 35 of 62

Site Welfare Facilities First Aid and Emergency Planning

Contractors/Operators Injury and or the need to call Emergency services

High Temporary site accommodation / welfare facilities as required during the construction phase of the works. All details for Emergencies shall be displayed on Notice board. These will be pointed out to workers during induction. First Aider shall be on site

Low SP Project Team

Connection to existing site services

Contractors/Operators Injury /Fatality Electric shock, electrocution risk of gas explosion, damage to drainage systems

High Any proposed temporary connections to sewers, services, water supply for welfare facilities will be the responsibility of the PSCS / Contractor. Prior to excavation all pit locations to be CAT scanned by trained operatives with suitable equipment for buried services Method statement from contractor and a Permit to dig shall be drawn up for all digging. All record /drawings shall be obtained. Hand excavation to be used on site. Standard Safe working procedures “Avoiding danger from underground services”

Low Contracts Manager / Project Manager / Sub- contractors

Page 37: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 36 of 62

Working at heights

Falling from heights Falling objects

High Site Manager should be a competent trained person A specialist company will be sub- contracted to erect dismantle and alter access scaffolding. Proof of training certification will be verified by the Site Manager prior to commencement of works. Restricted Access

Low Contracts Manager / Project Manager / Sub- contractors

Installation of Plant and Machinery on Ground level

Falls from heights High Competent person Certified equipment

Low Project Manager / Sub- contractors

Installation of new mechanical services at High level.

Hot works – risk office Working at height Heavy lifting

High Contractor to adopt safe Working practices etc. And make necessary provisions. Contractor to use appropriate access equipment/ temporary platforms during works Hot works – minimal risk of fire following adoption of safe working practices etc. Working at height and heavy lifting using appropriate access to the working area

Low Project Manager / Sub- contractors

Working with gas services

Gas explosion High Only Competent persons contracted to carry out work Method statement shall be available with all Risk Assessments All controls put in place prior to any

Low Contracts Manager / Project Manager / Sub- contractors

Page 38: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 37 of 62

work being carried out

Hot works Risk of fire Burns

High Contractor to adopt safe working practices etc. Comply with hot works permit procedures. Competent person sub-contracted to carry out work. Signed Method statements and Risk assessments for the job.

Low Contracts Manager / Project Manager / Sub- contractors

Accidental contact with Live electrical services.

Electrical shock

High Identification of services during works and insist contractor clearly label any possible hazards before commencing works Identification of services during works. Permit to work required for each work period on or near live services

Low Contracts Manager / Project Manager / Sub- contractors

Electricity Electrical power tools have the potential to cause electric shock, which can result in serious injury. Fire

High All portable electric tools only used at a voltage of 110v Method Statement from the contractor

Low Contracts Manager / Project Manager / Sub- contractors

Housekeeping Slips, trips and falls Rats, weils disease Site not in control

High PSCS must ensure Roadways and Site are kept clean and tidy at all times Good housekeeping procedures in place at all times Site Manager to do site walk around daily

Low Contracts Manager / Project Manager / Sub- contractors

Page 39: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 38 of 62

Noise Prolonged exposure to noise can result in hearing damage. Disruption and irritation to Neighbors.

High Hours of Work 8.00am to 1800 mon to Fri & 8.00am -1600 Sat No construction Operations on Sundays All plant and machinery will be fitted with silencers. All employees will wear hearing protection when operating plant and machinery Method statement from contractor use of noisy equipment will be restricted to suitable times to minimise disruption.

Low Contracts Manager / Project Manager / Sub- contractors

Environmental Health

Risk of injury from discarded hypodermic needles, broken glass, metal shards, nails and splinters Site being contaminated by rats which can result in infection Weil’s Disease

High All employees shall have up to date tetanus vaccinations. Wear suitable protective clothing and be provided with suitable washing facilities. Good housekeeping

Low Contracts Manager / Project Manager / Sub- contractors

Manual Lifting While carrying out manual lifting there is a risk of back strain, trips and slips causing injury

High All employees shall receive manual handling training

Low Contracts Manager / Project Manager / Sub- contractors

Storage of Oils and Chemicals

Risk of leaks High The smallest amount of chemicals possible to be used on site. Bunded storage for all oils and chemicals Spill Kits will be available on site.

Low Contracts Manager / Project Manager / Sub- contractors

Page 40: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 39 of 62

Control of Dust & Emissions during construction

Dust in atmosphere Dust in eyes Difficulty breathing

High An Air Quality & dust Risk Assessment will be carried out. Emissions controls shall be implemented as part of the scheme if deemed necessary. The PSCS shall ensure that adequate measures are in place to prevent any nuisance during the works PPE to be worn at all times

Low Contracts Manager / Project Manager / Sub- contractors

Root Protection Area

Damage to existing tress

High Details of Protective fencing and signage

Low

3.2 CONSTRUCTION METHOD STATEMENTS Method statements will be generated throughout the project by SP and our sub- contractors. A register of method statements required on the project will be formulated at commencement stage and updated as the project evolves. Method statements will be available for review by the design team on request.

3.3 TRAFFIC MANAGEMENT & DELIVERY PLANS The Traffic Management Plan minimises the impact of construction on the free flow of traffic on the local highway network and in the interests of highway safety, and in accordance with policy BR10 of the Borough Wide Development Policies Development Plan Document and policy 6.3 of the London Plan Objectives of this Plan This traffic management plan is designed to control the movement of traffic, both public & site related and to safely co-ordinate the delivery and loading/offloading of materials and products. The plans main objectives will be to: • To warn all personnel of any hazards that may exist. • To protect all site workers, members of the public & drivers alike, from any injury

involving site vehicles. • To eliminate any risks to the public by segregating pedestrians and local traffic from

vehicles. • To reduce the need for vehicles to reverse wherever possible and provide traffic

control measures. • To limit crossing of pedestrians and vehicles as much as is possible. • To control all site vehicles during movement, reversing and turning, so that no injury

or damage may occur.

Page 41: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 40 of 62

• To minimise the impact of the construction works on local traffic to the existing building.

A traffic management plan will be implemented on the site. The plan will outline timings of deliveries and routes to be taken by hauliers to minimise disruption to local residents and businesses. This includes the potential risk for noise disturbance as well as minimising additional traffic during peak periods. In an attempt to reduce vehicles attending site the Principal Contractor will target the following items: Procurement of local sub-contractors and labour. • Procurement of local suppliers. • Combined deliveries. • Cycle parking on-site for staff. • Encourage and reward car sharing. • Encourage the use of public transport, time tables and routes available in the site off

notice boards. • Any site meetings to commence outside peak hours. • Any meeting that does not have to be on site will not. • Adopt any learning from the other local surrounding projects • Where practicable coordinate major construction operations so as not to conflict

with other projects It is intended for deliveries to take place within the Site utilising the one-way access road along Axe Street. Should kerbside deliveries be necessary, by exception, the Principal Contractor will plan for traffic management measures. Vulnerable Road Users The operation of the construction site will comply with the Construction Logistics and Cyclist Safety (CLOCS) initiative. This will extend beyond the Site boundary to include, where possible, supply chain vehicles etc. we will ensure all deliveries made through our supply chain for the Axe Street project are Fleet Cyclists Cyclist activity on the surrounding highway network and private access roads will be unhindered, but traffic management measures will need to be adhered to as with any other highway user. During normal deliveries Banksmen will be able to ensure cyclist safety in conjunction with other vehicles. It is not anticipated that cycle movements will be disrupted as all necessary storage and works are expected to take place within the Site boundary. Pedestrians At this stage it is proposed that a hoarding would be provided at the Site boundary leaving footways open during the initial stages of construction. There will be a requirement to carry out a footpath closure during parts of construction for pedestrian safety.

Page 42: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 41 of 62

We will arrange the necessary footpath and scaffold licences required throughout the process with the local authorities and will ensure all pedestrians will be directed to alternative routes using a signage layout compliant with Chapter 8 of the Traffic Sign Deliveries will be restricted to the period between 08:00 and 18:00. Pedestrian routes will not be blocked during deliveries and collections, unless a temporary road or footway closure is in operation. In such circumstances appropriate alternative routes and signage will be provided. Site management will conduct routine daily and weekly checks to ensure the safety and security of pedestrians around the Site are maintained. This will form part of the overall monitoring strategy, reporting to the Council and local parties as necessary. The contractor's procedure for governing the interaction of pedestrians and deliveries will be presented in more detail in this section. Traffic Routing Access Location: It is proposed to direct delivery and collection vehicles to the site via the existing access point along Axe street. The existing access point is accessible from St Pauls Rd which in turn is only a short distance from the North Circular. It is envisaged both drop kerbs will be utilised to facilitate additional unloading areas should needs must. During normal construction operations there will be no need for temporary traffic management controls or alterations to waiting restrictions. If such measures are needed for specific exceptional construction operations, the Principal Contractor will secure the necessary approvals or permits in advance Deliveries It should be noted that shared access roads along the site boundaries will remain open to general traffic in order to maintain access to existing commercial premises adjoining the site during the works. If deliveries etc. arrive without a pre-booked slot, they will be refused and will exit the area via the agreed lorry routes back to the TLRN, if required. SP will later demonstrate that site can accommodate he peak flow at all times. The use of any other residential streets in the area by construction lorries will not be permitted. All movements will accord with the Councils guidance and will ensure the carriageway remains open at all times (unless subject to a Temporary Road Closure). Notifications and applications to the Council, if additional traffic management measures are required, will take place in good time. All deliveries to site will be carefully controlled and managed by the Site Manager, and the procurement team. Use of online booking coordination systems will be considered to improve reliability. Operations will also consider other construction activities in the area.

Page 43: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 42 of 62

Deliveries will be coordinated to avoid multiple vehicle arrivals at any one time. In the event of delivery vehicles arriving to Site simultaneously, the unscheduled vehicle will be asked to leave, park up in permissible areas, and return to Site after an agreed period. It is noted previously there is some limited on-street capacity available along the Axe Street. All traffic management proposals will be regularly reviewed with the Council's highway engineers and the appropriate orders, licenses sought in good time.

3.4 TEMPORARY WORKS SP will ensure that all temporary works required for the works are to be timely approved by a qualified structural engineer who holds appropriate professional indemnity insurance cover and appointed by the subcontractor. Approval by the subcontractors’ engineer must be made / received prior to the subcontract works or phase of the subcontract works commencing on site. The subcontractor must ensure that all risks of job specific PPE have been undertaken & provided for (e.g. hard hats, safety boots, hi – viz clothing). The list is not exhaustive & it is the subcontractor’s responsibility to carry out a full risk assessment and COSHH assessment of the exposure to the employee / visitors & what PPE is required.

3.5 CORONAVIRUS / COVID 19 OR SIMILAR OUTBREAK These are exceptional circumstances and the industry must comply with the latest Government advice on Coronavirus at all times. The health and safety requirements of the site activity must also not be compromised at this time. If an activity cannot be undertaken safely due to a lack of suitably qualified personnel being available or social distancing being implemented, it should not take place. If a site is not consistently implementing the measures set out below, it may be required to shut down. Self-Isolation Anyone who meets one of the following criteria should not come to site: • Has a high temperature or a new persistent cough • Is a vulnerable person (by virtue of their age, underlying health condition, clinical

condition or are pregnant)? • Is living with someone in self-isolation or a vulnerable person. Procedure if Someone Falls Ill • If a worker develops a high temperature or a persistent cough while at work, they

should: • Return home immediately • Avoid touching anything • Cough or sneeze into a tissue and put it in a bin, or if they do not have tissues, cough

and sneeze into the crook of their elbow. They must then follow the guidance on self-isolation and not return to work until their period of self-isolation has been completed. Travel to Site Wherever possible workers should travel to site alone using their own transport and sites need to consider: • Other means of transport to avoid public transport (eg cycling) • How someone taken ill would get home

Page 44: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 43 of 62

Hand Washing • Ensure soap and fresh water is readily available and kept topped up, where possible. • Provide hand sanitizer where hand washing facilities are unavailable, where possible. • Regularly clean the hand washing facilities and check soap and sanitizer levels. Toilet Facilities • Restrict the number of people using toilet facilities at any one time. • Wash hands before and after using the facilities. Canteens and Eating Arrangements Whilst there is a requirement for working sites to provide a means of heating food and making hot drinks, these are exceptional circumstances and where it is not possible to introduce a means of keeping equipment clean between use, kettles, microwaves etc. must be removed from use. The workforce should also be advised to stay on site once they have entered it and not use local shops: • Dedicated eating areas should be identified on site to reduce food waste and

contamination • Break times should be staggered to reduce congestion and contact at all times. • The workforce should be asked to bring pre-prepared meals and refillable drinking

bottles from home • Workers should sit 2 metres apart from each other whilst eating and avoid all

contact • Drinking water should be provided with enhanced cleaning measures of the tap

mechanism introduced • Tables should be cleaned between each use • All rubbish should be put straight in the bin and not left for someone else to clear up • All areas used for eating must be thoroughly cleaned at the end of each break and

shift. Avoid Close Working There will be situations where it is not possible or safe for workers to distance themselves from each other by 2 metres. General Principles • Non-essential physical work that requires close contact between workers should not be carried out. • Work requiring skin to skin contact should not be carried out. • Plan all other work to minimise contact between workers. • Re-usable PPE should be cleaned after use and not shared between workers. • Single use PPE should be disposed of so that it cannot be reused. • Increase ventilation in enclosed spaces. • Regularly clean the inside of vehicle cabs between use by different operators. Site Meetings during COVID19 • Only absolutely necessary meeting participants should attend. • Attendees should be 2 metres apart from each other. • Rooms should be well ventilated / windows opened to allow fresh air circulation. • Consider holding meetings in open areas where possible.

Page 45: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 44 of 62

Cleaning Enhanced cleaning procedures should be in place across the site, particularly in communal area and at touch points including: • Taps and washing facilities • Toilet flush and seats • Door handles • Food preparation and eating surfaces • Telephone equipment • Keyboards, printers and other office equipment

Page 46: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 45 of 62

4 ENVIRONMENTAL & WATE MANAGEMENT PLAN Good planning of site welfare facilities will be an essential part of the works to ensure mitigation of both dust and odour emissions. The location of site skips or waste bins will be located away from areas close to public interface. Skips should be sealed and regularly exchanged to ensure that excessive odour is not released. Measures shall be taken to prevent the occurrence of any nuisance arising as a result of any activities on the Project. The ISO9001 complaints procedure shall be utilised on the project and contact numbers communicated to all personnel and displayed on office notice boards

4.0 WASTE MANAGEMENT This waste management plan (WMP), details the actions that SP will carry out to minimise waste on construction projects. This WMP is a live document and will be periodically reviewed for its continual suitability and effectiveness. This plan complies with the requirements of: • Control of Pollution Act 1974 • Environmental Protection Act 1990 • The Site Waste Management Plans Regulations 2008 • Control of Waste (England & Wales) Regulations 2012 • Waste Management Framework Directive - 2008/98/EC • EWC – Decision 200/532/EC This Waste Management Plan is an important tool that allows SP to monitor and improve environmental performance, meet regulatory commitments and help to reduce waste disposal costs. Hence, the aim of this WMP is to determine the waste types and amounts to be produced during design and construction and to identify appropriate waste management controls and solutions. The role of Waste Manager will be assumed by the Quality & Environmental Manager who acts as the overall Environmental Co-ordinator. The Waste Manager will: • advise and instruct construction teams on how to meet legal and contractual requirements • develop and implement the Site Waste Management Plan as part of the Environmental Management Plan for the Project • identify and implement ways to reduce, reuse and recycle waste with a preference given to reusing and recycling of waste within the Project • classify waste categories and characterisation prior to removal from site • work with the Health & Safety Manager to provide training and information on waste • provide reports on progress and any problems with waste issues • work closely with construction teams • liaise with external parties as necessary • Ensure all Waste Management Licensing / Environmental Permits and Exemptions are current and sufficient for the Project requirements • Demonstrate a good knowledge and practical experience of developing and implementing Site Waste Management Plans. The Waste Manager will be assisted by the Project Manager, who will: • support the development and implementation of the Site Waste Management Plans

Page 47: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 46 of 62

• identifying ways to reduce, reuse and recycle waste with a preference given to reusing and recycling of waste within the Project ensuring waste categories and segregation has been carried out prior to the waste being removed from site • Work with the project team to provide information on waste; and • Provide reports on progress and any problems with waste issues SP Waste Management Plan centres around the fundamental waste management prioritisation principles of prevent/reduce, reuse, recycle & dispose. SP Waste Management Plan Priority 1 Waste Prevention / Avoidance / Reduction Either avoid or reduce the production of waste. Eliminate or minimise the production of hazardous entering the waste stream Priority 2 Re-Use Putting materials back into construction processes or re-purpose them to avoid re-entry to the waste stream Priority 3 Recovery This includes recycling a material or composting or similar. Recycling is the preferred option. Use best practice environmental option available. Priority 4 Disposal To be avoided where ever possible Options involve landfill, incineration or permanent destruction (specialist) The Project Delivery Team will ensure that each WMP component, where applicable, is adequately addressed. To ensure all aspects of this WMP are complied with, regular audits will be made by the Waste Manager during bi/weekly site waste inspections. The Project Delivery Team will also ensure that all SP employees and subcontractors’ staff are provided with appropriate training (e.g., tool box talks) so that everyone understands the requirements of this WMP and the site Waste Management approach. The site team will apply the above principles throughout the project process. This will mean that rather than just dealing with waste management at site level “on the ground”, waste management will be part of the whole project process – during design, procurement and construction. Materials of specific environmental and hazardous natures such as asbestos or heavy metals that are encountered during the construction phase will be handled, removed and disposed of by a specialist licensed environmental carrier. 4.0.1.1.1 Procurement Throughout the construction phase the Project Delivery Team should ensure that: • Only the correct amount of materials required are ordered • 'Just in time' deliveries are arranged to reduce storage and material losses • The amount of packaging used for materials delivered to the site is reduced or recycled as much as possible • Deliveries are rejected if materials are damage

Page 48: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 47 of 62

4.0.1.1.2 Monitoring SP will monitor and measure the waste involved on the project. The Project Delivery Team will record the quantity of waste categorised into the following criteria: Reduction & Prevention of Waste In line with good modern industry practice, all efforts will be made by the Project Delivery Team to minimize the creation of waste throughout the job. There are several keyways in which this can be dealt with. In order of preference, these are: • Re-use of a material on site • Re-use of a material off site • Recycling of a material for use on-site • Recycling of a material for use off-site • Sending of material to a recycling facility • Sending of a material to WML facility as ‘exempt’ under terms of EWC • Disposal of material to landfill or other processing facility under terms of EWC Some practical applications of the above are: • Cutting back on the amount of wastage for trimming of material etc. for example cutting of plywood, built into the amount ordered. • Educating foremen and others to cut/use materials such as ply wisely for shutters etc • To re-use shutters, formwork and temporary works materials as much as possible by careful planning throughout the job. • Recycling of paper generated on site. • Increasing the use of electronic transmittal of documents and drawings, as opposed to paper. • Sending an item of formwork to another SP site, where that item could be used (assuming no further use is possible without generating costly waste at this site In addition, there are a number of steps that can be taken in order to prevent the creation of waste in the first instance, thus negating the need to deal with the waste product. These are as follows: 4.0.1.1.3 Material Recycling Options Recycling Wherever possible, materials shall be recycled. There will be a skip located in the site compound for the recovery of paper/cardboard and plastic containers. It is the responsibility of the SP Safety & Health Manager to ensure safe egress and control access to these skips at all times. Once full a recycling company will collect the contents of this bin. Modern recycling techniques mean that many construction materials can be recycled. Taking cognisance of this, SP will ensure that, where reasonably practicable and economically acceptable, recycling will be carried out with as many materials as possible. The following is a guide: Timber: The recycling of timber is a three-stage process. The process includes shredding, screening and metal segregation to produce a woodchip. The low moisture content from recycled timber provides an advantage over virgin wood stock, reducing utility costs prior to manufacturing wood chip board or as a secondary fuel source in an organic ‘waste to energy’

Page 49: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 48 of 62

process. The use of recycled wood also preserves virgin wood stock. SP will actively re-use timber on this or other SP sites, with recycling to be used for large volumes. Glass: Glass cullet can be processed at a rate of 10 tonnes per hour, to produce screened fractions of glass to recycle into a variety of industrial uses, (providing colour is not an issue). Markets such as water filtration, shot blasting with abrasive characteristics, paint additives with light reflecting properties and acoustic attenuators and insulation are able to utilise recycled glass. However, it is not though that sufficiently large volumes of glass will be generated on site to warrant recycling, although this will be constantly reviewed. Fluorescent tubes: The mercury powder contained within these is a valuable resource and can be re-cycled where sufficient amounts of tubes are available. Paper: Paper will be put into the paper re-cycling bin on site. The full bags are put in the wheelie bin and collected regularly for transportation to the nearest processing facility. The sorted and baled paper is then sent to paper mills for recycling. Plastics: The availability of recycling of plastics generated on site will depend on the type and amount of plastics generated. Whilst low-density polyethylene (LDPE) used for plastic film - shrink wrap, stretch wrap etc, can be recycled, as can HDPE, PET and PVC used for bottles and Polystyrene (PS) used for drinks cups and packaging, consideration needs to be given to quality, quantity and the cost of getting it out of waste and to the processor. With this project, as nearly all plastic would need to be baled for transport and storage and this would generally demand an 'on site' baler, this approach would not be practicable or economically viable given the amount of plastics of the above types likely to be generated. Storage of Waste on Site Waste stored on site, whether from construction activity or general consumer waste from the site facilities etc., shall be stored in a safe manner to minimise the likelihood of cross-contamination, further pollution, vandalism or vermin infestation. This will involve using various storage mechanisms and ensuring the proper segregation of waste. Segregation of waste shall include provision of appropriately signed and classified storage areas/skips, using various signs to assist the site team and operatives with the process of storing and sorting waste. Typical signs are shown overleaf.

4.1 ENVIRONMENTAL CONTROL MEASURES 4.1.1.1.1 Environmental Plan This plan is prepared in accordance with the requirements of EN ISO14001:2015 This Construction Phase Environmental Management Plan has been prepared to detail and outline how SP will manage and control the environmental aspects of this project.

Page 50: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 49 of 62

SP seek to achieve the highest standard of environmental performance for this project. The application of this plan is fundamental to achieving this aim. The Objectives of the Construction Phase Environmental Management Plan are: To set out the responsibilities, key actions required for the successful implementation of best practice environmental management on the project • To maximise potential benefits of the proposed works • To identify potential negative impacts • To set out specific mitigation measures for these impacts • To provide guidance on compliance with accepted best practice standards • To inform all parties of environmental sensitivities of the site • To guide works toward best environmental practice at all times • To provide protection of the site and environs during and after works • To ensure compliance with accepted best practice standards Summary of the Environmental Management Process The SP Environmental Management System (EMS) (forms part of the Integrated Management System IMS), encompasses various documents, procedures, forms and policies. These elements form the overall Management Systems for project environmental management: These main project control documents include: 1. Construction Phase Environmental Management Plan 2. Construction Phase Waste Management Plan (In conjunction with SmartWaste) 3. Construction Phase Quality Plan 4.0.1.1.1 Environmental Records In order to demonstrate compliance with legal, other stakeholder requirements and this management plan, site records will be controlled, maintained and archived appropriately to facilitate retrieval at a later date, if required. All records demonstrating environmental compliance shall be retained until all legal requirements have subsided The SP Environmental Policy statement is relevant to the works and project undertaken by SP and is fully endorsed by the Directors and Senior Management Team. This policy, together with the application of the Environmental Management System is the means in which SP seek to achieve the highest standard of environmental performance. SP expect both the personnel and subcontractors representing SP do so in-line with the ethos of this policy. 4.0.1.1.2 Project Specific Environmental Aspects & Issues SP recognise the importance of the earliest identification of site characteristics, stakeholder receptors and construction process & method related environmental risk(s) “aspects”. Our Quality & Environmental Manager in conjunction with the Health & Safety Manager and Project Manager will identify project aspects and detail their impacts on the project Aspects & Impacts Register, The Aspects & Impacts Register shall be populated and maintained by the Project Manager, detailing the mitigation measures required to minimise the impact to the environment. The register should highlight the risk indicators and assign responsibilities for their monitoring. Risk indicators are events that “may” provide indication that an identified risk is about to mature in to an issue. A typical example would be uncontrolled concrete run off “may” cause pollution of a watercourse.

Page 51: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 50 of 62

4.0.1.1.3 Project Specific Environmental Controls Prevention of Pollution Good planning of site welfare facilities will be an essential part of the works to ensure mitigation of both dust and odour emissions. Temporary portable toilets will be regularly cleaned and maintained, and the location of site skips or waste bins will be located away from areas close to public interface. Skips should be sealed and regularly exchanged to ensure that excessive odour is not realised. Similarly, regular checking of portable toilet facilities will be effected so as to ensure prompt cleaning and removal by licenced tanker from the portable units, thus prevents the generation of unacceptable odour. SP will adopt a best practice approach to the management of site operations so as to ensure the best possible pollution prevention and control mechanisms on the project. Avoiding Public Nuisance Measures shall be taken to prevent the occurrence of any nuisance arising as a result of any activities on the Project. The ISO9001 complaints procedure shall be utilised on the project and contact numbers communicated to all personnel and displayed on office notice boards. In the event of an environmental nuisance complaint being received, these must be logged on Emergency Incident Report SP will endeavour to minimise nuisance, however when construction operations require out of hours working we will carry out the following procedures: • Consult and gain agreement from the relevant planning authority prior to any operation likely to cause out of hours noise or light nuisance • Carry out letter drops to local residents and businesses at least 48 hours prior to any operations where we may cause a nuisance • Inform the emergency services and local press Lighting Management • All lighting will be directional and will be directed towards the activity or secured area • All task lighting will be sufficient for the job, not over lit Whilst working adjacent to live traffic, • task lighting will be positioned to avoid any glare to road users • If complaints are received we will stop the operation (if possible) and investigate the working method and endeavour to stop the light nuisance • Lights will never be left on if no work is being carried out • Existing street lighting will be utilised where possible • If existing street lights are removed temporarily for construction, these will always be replaced with a similar standard of lighting coverage where required. Vehicles and Traffic Management As well as the provision of a Traffic Management Designer as detailed elsewhere, we will employ a TSCO (Traffic Safety Control Officer) for the implementation of Traffic Management. The TSCO shall ensure all TM is approved and placed in accordance with the required legislation. The Highways Agency and Police must agree all traffic diversions and closures prior to installation.

Page 52: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 51 of 62

Emergency services and bus companies will always be consulted prior to any formal approaches for traffic closures and diversions. All traffic management systems will be placed by trained, experience and authorised operatives. It is an offence for untrained staff or operatives to change or adapt traffic management. Anybody caught doing so, will be disciplined. Parking on Site There will be on-site parking provided for subcontractors. To minimise the amount of onsite parking, SP will inform subcontractors that access to the site most be achieved through shared transport (Minibus). Formal arrangements for additional parking will be made with the hotel development opposite the site for rental of additional parking spaces. Car usage and parking will be actively discouraged at SP projects. Operatives and staff, parking cars elsewhere, will be informed at induction to follow these procedures: • Where possible always park in recognised parking places • Never park in private property • Never obstruct private accesses • Never leave mud on the road • Never park on pavements • Act in a courteous manner to all other public road users. Unloading of Plant and Materials Each delivery driver involved in deliveries to construction sites should clearly define and allocate responsibility for this role. All materials should be correctly loaded and secured in accordance with the Code of Practice on Safe Loading of Goods Vehicles. All drivers delivering to site should always wear PPE when out of the vehicle and descending from the cab. The following guidance will be adhered to for each delivery

• Report to site office before entry

• Undertake Driver induction / briefing

• Enter Site

• Vehicle routes on sites will be clearly marked.

• Reversing should be kept to a minimum a

• Overhead hazards will be clearly identified

• The driver will be guided to the location of loading / unloading and storage areas by the site manager

Note there is little on-site storage space Access Locations Agreed access locations will be defined in consultation with the Employers Representative. These will be clearly marked and signed. Signage All temporary traffic signage will be placed as per Chapter 8 guidelines and placed with Local Authority traffic and police approval. Temporary traffic signage will be inspected daily and after inclement weather and a Traffic Management Team will be on site during all major traffic management set ups to ensure compliance. Businesses that may be obscured or indirectly impacted by the construction works will be clearly signed.

Page 53: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 52 of 62

Road Sweeping Road sweepers will be directed by the construction programme to target high volume traffic movements. Wherever possible, road sweeping will be utilised outside peak traffic flows to minimise traffic disruption. Dust Control & Monitoring Dust levels will be continuously monitored throughout the course of the project. Monitors will be positioned at points along the perimeter hoarding – monthly reports will be produced based on the data collected by these monitors. Dust suppression will be carried out as and when required using water/power hoses, particularly during the groundwork’s stages and during times of dry weather. Concrete Washout Bays A designated concrete washout bay will be located away from existing drainage infrastructure in order to avoid contamination. Wheel Washing Facilities Effective wheel/body washing facilities to be provided and used as necessary; all vehicles entering/leaving site will be routinely inspected by SP gatemen for contaminants/debris.

4.2 FLORA, FAUNA & INVASIVE SPECIES 4.2.1.1.1 Flora The key deliverable is to minimise any impact on native trees and shrubs. All trees, hedges and shrubs within or adjacent to the site, except those that have been approved for removal shall be protected from damage during construction work by the erection of ‘Heras’ Fencing. Wherever possible the removal of any flora will be limited and removal will only be carried out with the prior approval of the Client and Quality & Environmental Manager. Removal of tress and saplings will only be carried out where absolutely required, and replacement of trees, post works, will be carried out wherever possible. 4.0.1.1.1 Fauna Wherever possible the project will avoid disturbing any fauna within/near to the project works. Any fauna observed will be monitored and avoidance techniques utilised. To minimise marine habitat species loss or disturbance, efforts will be made to keep the area of shore disturbed by any pipeline trenches to a minimum. To protect the aquatic environment, chemicals and oils used shall be those approved for use in, or with the least potential for causing damage to, the marine environment. 4.0.1.1.2 Invasive Species Invasive non-native plant and animal species are the second greatest threat to biodiversity worldwide after habitat destruction. They can negatively impact on native species, can transform habitats and threaten whole ecosystems causing serious problems to the environment and the economy. The transport or introduction of Invasive species can result in deterioration in water quality and significant fish mortality, dramatically alter the ecology of receiving watercourses and render them unavailable for recreational and other water-based pursuits. On commencement of the project, the Quality & Environmental Manager will prepare a risk assessment on invasive species. This risk assessment will be informed by discussions with the client team, the project ecologist, Local Authority and other stakeholders and will form the

Page 54: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 53 of 62

basis of actions taken during the construction period. This EMP will be updated to reflect these actions.

4.3 TRAINING (TOOLBOX TALKS) 4.0.1.1.1 Training SP will provide training at various levels and to varying degrees to ensure adequate understanding and competence when managing environmental issues. Senior and Project Management shall be trained to competently manage day-to-day environmental issues under HSQE guidance. All SP personnel will be trained to understand environmental issues, the policies encompassed in the SP Environmental Management System and its objectives. Supply chain subcontractors and suppliers shall be inducted into the approach to environmental management SP expect and where relevant the objectives of the Construction Phase Environmental Management Plan and the Company Environmental Management System policies and objectives. 4.0.1.1.1 Toolbox Talks Toolbox talks are the means to which SP shall communicate specific environmental issues, management and control measures to personnel and supply chain subcontractors. The content of environmental toolbox talks necessary to ensure adequate management shall be detailed in all RAMS documentation and derived from Environmental Aspects & Impacts Register specific to the project. The Project Manager is responsible for ensuring RAMS are suitable and thorough, communicated and understood by any and all personnel whose actions may lead to environmental damage. The Project Manager will ensure environmental risks identified on Environmental Aspects & Impacts Register are communicated to all supply chain subcontractors prior to their submission of RAMS for approval. 4.3.1.1.1 Auditing All SP projects are subject to regular audit by the HSQE Department. Audits are conducted by either the Health & Safety Manager for OHSAS18001 and by the Quality & Environmental Manager for ISO9001 & ISO14001 issues. The Directors of SP UK also undertake audits and inspections. The requirements of this plan shall be evaluated by the Project Manager and Quality & Environmental Manager. The audit regime to be adopted shall be based on the complexity of the project and the number of environmental risks. The audit schedule shall be encompassed on the Company Audit Programme. 4.3.1.1.2 Evaluation The environmental performance of SP Project Teams and the degree of success of project objectives shall be reviewed on a project level and against other projects during Management Review. Environmental performance forms part of the SP Management Review agenda. Projects shall be continuously reviewed and adjusted in-line with the finding of the Quality & Environmental Manager during site visits and audits. Supply chain compliance and performance shall be reviewed at weekly team meetings and shall be encompassed in the agenda for Post Contract Review.

4.4 CONSTRUCTION WASTE ASSESSMENT The nature of wastes arising from the development and their treatment will vary throughout the different stages of construction. A detailed construction programme is not available at this stage, however the key stages will include:

Page 55: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 54 of 62

4.4.1.1.1 Preliminaries This stage of development will comprise: • The establishment of a site compound and installation of security fencing; • Establishment of vehicle access arrangements; • Import and storage of materials in preparation for the commencement of development. Waste arisings during this stage will be small and likely to result in very low numbers of vehicle movements for off-site disposal of surplus waste. 4.4.1.1.2 Site Preparation and Earthworks During this stage, the following activities will be undertaken: • Removal of existing hard-standings and existing buildings; • Removal of topsoil and regrading of site ground levels of Excavation for basements and foundation construction Foundation and groundworks construction is likely to generate a significant volume of surplus excavated material to be removed from Site. This will be removed by road using covered tipper trucks or skip lorries. This surplus material will be segregated at the point of disposal (waste transfer station) and re-used as fill for other construction projects where possible. 4.4.1.1.3 Construction and Fabrication During this main construction phase the following operations will take place: • Below ground construction including reinforced concrete piled foundations • Reinforced concrete basement floor slabs and walls • Below ground drainage and services • Erection of steel frame and construction of walls, floors and glazing; • Installation and commissioning of mechanical & electrical plant • Installation of building services • Roofing • Access and parking areas; • Hard and soft landscaping; • Fit-out of buildings Again, the absence of a completed design or Bill of Quantities means that precise quantities cannot be evaluated at this stage. However, as an initial guide, reference has been drawn from current standards, including BRE's Smart waste benchmarking data (2012). 4.4.1.1.4 Anticipated Demolition Materials Pre-demolition audit and asbestos audit will be required prior to demolition works being undertaken. Due to the low volume of demolition materials and restricted nature of the site it is anticipated there will be no secondary processing of demolition materials on site. This removes the likelihood of post demolition crushing activities. Demolition Methodology will include the systematic demolition by mechanical excavator (approx. 15 tonne). Removal off site by a second similar sized mechanical excavator loading highways complaint (FORS) haulage Lorries for processing off site and reuse.

Page 56: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 55 of 62

Plant Machinery 2No. 30 tonne mechanical excavators 1No. Compressor (Diesel) 1No. Jack Hammer 4No. Haulage Lorries Furthermore there are no landscaping requirements, the scope of the earthworks element will not require the storage of topsoil’s or subsoils for re-use and the extent of the earthworks will be confined to excavation to formation level and preparation of the formation level.

4.5 QUALITY MANAGEMENT PROCEDURES SP ISO9001:2015 Quality Management Procedures Required By This Plan Encompass: • Planning, Programming & Reporting • Subcontractor Procurement • Quality Plans • Training, Competency & CPD • Risk Management • Statutory & Regulatory Compliance • Control of Nonconforming Product • Client & Stakeholder Management • Construction Methodology • Control of Monitoring & Measuring Devices • Materials Control • Post Contract Review All Regulatory Requirements (Legal, Planning, Standards, etc): Air Pollution Acts etc shall be complied with.

4.6 CONTROL MEASURES All control measures will be in line with The Control Of Dust And Emissions During Construction And Demolition From The Mayor Of London (July 204) Dust & Dirt Control Measures • On existing (or adjacent) operational facilities close to the works the site team must

check for existing air intake points and discuss with the client additional measures to prevent dust or fumes entering the building or area of concern or to determine if any equipment shutdown needs to be organised.

• Any areas of the site where dust may generate are to be dampened down at regular intervals to eliminate the potential for dust to blow. If possible, generation of dust should be prevented at source.

• If required dust monitoring will be carried out. • Regarding the heavy sulphur content of fuels and diesels all engines must be shut off

when any available opportunity arises, e.g. Lunch breaks. • All paints, solvents and fuels to be always lidded or caped to prevent unnecessary

evaporation. • Neighbour can contact the Project Manager to discuss any concerns and regular

meetings will be held with the residents and the City Council to review site issues. • Ensure good housekeeping is maintained and that all on site operate a ‘clean as you

go’ policy.

Page 57: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 56 of 62

GEM Air Quality Ltd undertook a detailed air quality assessment based on the potential impacts of existing and future traffic levels on a proposed mixed-use development location along Axe Street in Barking, London. Habitat ControL It is an offence to intentionally kill or injure a protected species or to wilfully interfere with or destroy the breeding site or resting place of a protected wild animal unless such activities are carried out in accordance with an appropriate licence. Control Measures • No issues of habitat or species protection is envisaged but with on-going close

supervision of the site if such issues arise they will be acted upon in an appropriate manner at that stage.

Housekeeping Control Measures • Maintain company policy signage, access roadways, entrance & around

accommodation lay down areas to the highest standard. • Ensure hoarding is always erected / secured correctly in good order. • Ensure good housekeeping is maintained and that all on site operate a ‘clean as you

go’ policy. • Traffic management cones & signs to be positioned correctly and well maintained. • Skip areas to be in an orderly state with correct signage and skips not to get to an

overflow state. • Storage areas to have appropriate access and egress and all items to stacked /

stored neatly and in an orderly fashion. • The site agent is to ensure that there are adequate resources such as wheelie bins,

mini skips, etc. in place whether provided by SP or sub-contractors. • Neighbour can contact the Contract Manager to discuss any concerns and regular

meetings will be held with the residents and the Local County Council to review site issues.

• The site agent must monitor housekeeping outside the site such as keeping the public roads clean and checks on hoarding quality.

Noise Control Measure All Regulatory Requirements (Legal, Planning, Standards, etc): Air Pollution Acts etc shall be complied with. Control Measures

o A background noise survey will be carried out at the nearest noise sensitive locations prior to works commencing on site and if noise monitoring is required during the works it will be carried out at the required locations, downloaded, checked, reported on and filed on at least a daily basis.

o Planning the hours of work o Movement of noise generating activities to fewer sensitive areas of the site. o The use of quiet working methods o Controlling noise at source o Enclosures for plant & equipment o Erection of hoarding o Maintenance of equipment

Resource Usage Control Measure

Page 58: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 57 of 62

Control Measures • Energy: Power will primarily be mains. Where generators are required they

will be suited to demand. Timers will be in place for all office heaters and all lighting both internal and external will be through PIR.

• Materials: Items required will be ‘Just in Time’. Storage on site will be organised with the aid of signage and in an orderly state.

• Water: Toilet Areas and Water Consumption: Signs to be placed in all toilets on site stating, ‘please turn off taps after use’. Ideally all toilet taps should be push button type. All hose pipes to have end stop taps fitted and turned off when not required.

Vibration Measure Control Measures

• Specification to be sought from the design engineer on the project on the extent of any required monitoring and the criteria for monitoring.

• Project team to get guidance from the insurance company on extent of vibration monitoring that should be carried out.

• If noise monitoring is required during the works it will be carried out at the required locations, downloaded, checked, reported on and filed on at least a daily basis.

Spillage As soon as practicable after the occurrence of an accidental discharge, spillage or deposit of any polluting matter which enters or is likely to enter any waters or a sewer, the person responsible shall notify the local authority in whose functional area the discharge, spillage or deposit occurs or, in the case of a sewer, the sanitary authority in which the sewer is vested or by which it is controlled Control Measures

• All plastic and single skinned metal fuel tanks to be in a concrete bund substantially enclosed structure with a built-in sump for pumping out miscellaneous spills and rain ingress. This will be known as the central storage / refuelling station.

• All mobile bowsers to be inspected weekly for leaks and a log of the inspection to be retained with the bowser.

• Only metal gerry / fuel cans to be used on site. Plastic drums are banned. • Gerry cans to be stored on weathe- proof grated poly spill pallets or tray or

else within the bund. • Refuelling trucks and mobile bowsers to have correct nozzle with auto cut

off. • Refuelling of small plant to be carried out on a weather-proof grated poly

spill pallets or tray or else within the bund. • There must be a hard-standing concrete slab provided at the central

refuelling station with a built-in sump for miscellaneous spills. • All generators and portable plant must be double bunded units or be placed

on a grated drip tray. • All generator hoses must be hydraulic wire reinforced. • Crimped connections must be used, not jubilee clips. • A designated concrete wash-out area to be in use throughout the works.

Unidentified Contamination Control Measure

Page 59: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 58 of 62

A person shall not hold, transport, recover or dispose of waste in a manner that causes or is likely to cause environmental pollution. A person shall not transfer the control of waste to any person other than an appropriate person. If waste is transferred to an inappropriate person, responsibility for waste remains with original waste generator. Control Measures Where there is concern of there being any form of contamination the works in that area must cease, senior site staff informed and expert advices, sampling, analysis, reports, etc. to be sought before proceeding to deal with the contaminant. Excavations: Soil, Sub Soil:Before any soil is removed from site the Waste Collection Permit (WCP) of the haulier to be used will be checked thoroughly including the appendices for validity. This WCP will be cross checked with the Waste Permit (WP) of the Tip Site to be used. Tests will be carried out before removal of soil off site. And the Tip Site must be a site that is permitted to allow waste of that particular criteria in.

Construction Phase: General Waste, Timber, Metal, Plasterboard, Cardboard, Plastic, Paper and wastes of a hazardous nature such as aerosols, mastic tubes, oily rags, oils, oily water, oil-based paint containers, etc. All these waste fractions will be separated out on site into individual skips / bins. A certified Environmental Services company will be employed to remove this off site to their facility. Demolition: All strip out material, rubble. Before any demolition waste is removed off-site the Waste Collection Permit (WCP) of the haulier to be used will be checked thoroughly including the appendices for validity. This WCP will be cross checked with the Waste Permit (WP) or Waste Licence (WL) of the receiving facility. It is anticipated that the bulk of waste streams form demolition will be sent for recycling.

Water Discharges A person shall not discharge or cause or permit the discharge of any trade effluent or sewage effluent to any waters except under and in accordance with a licence). A person other than a sanitary authority shall not discharge or cause or permit the discharge of any trade effluent or other matter (other than domestic sewage or storm water) to a sewer, except under and in accordance with a licence under this section granted by the sanitary authority in which the sewer is vested or by which it is controlled All truck wheels will be washed on exit from site. Water from wheel washing areas can contain oil and diesel, as well as high levels of silt. Effective wheel/body washing facilities to be provided and used as necessary; all vehicles entering/leaving site will be routinely inspected by SP gatemen for contaminants/debris. Control Measures

• Ground to ground pumping of uncontaminated water is generally deemed acceptable.

• Under no circumstances is pumping onto hard standing such as concrete or tarmac to be allowed.

• Permission or a discharge permit to be sought from the Local Authority before any water is pumped into a storm or sewer line.

Page 60: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 59 of 62

• If water is to be pumped off site it must be sampled and analysed prior to discharge.

• Settlement Pond / Tanks to be set up on site to aid in settlement of solids prior to discharge. These tanks must be of enough size to allow ample retention time for the solids to settle.

Neighbours and Local Residence Our Project Manager will be responsible for project strategic liaison whilst the site Managers will be responsible for day to day liaison and logistics for all of the construction related activities. Both will be permanently based on site with the site Managers as the first point of contact for all concerns, issues and complaints. The plan will outline timings of deliveries and routes to be taken by hauliers to minimise disruption to local residents and businesses. This includes the potential risk for noise disturbance as well as minimising additional traffic during peak periods.

Page 61: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 60 of 62

5 QUALITY SP will implement our EHS&Q plan on the project which complies with the requirements of ISO 9001:2008. The implementation of this plan by all our sub-contractors contributes to us achieving our goal of delivering a snag free building on handover. All retained sub-contractors will be given a quality induction before commencing on site and samples will be used extensively to set and maintain the standard of work required.

A site-specific Preliminary Inspection Plan (PIP) for the project will be developed with the design team. The plan will include hold points for inspections to be carried out before work progresses or is closed in. A detailed programme for inspections will be developed and issued to the design team to ensure adequate notice is given prior to each inspection. All materials used on site will be in accordance with the designer’s specifications. Where applicable, only materials with a current CE marking will be used on the project. All material data sheets and CE certification will be held on site by the Site Manager and will be available at any time for inspection. Concrete, stone and concrete blocks will be supplied by a reputable supplier and will be free from pyrites. Test certs for quarries will be issued to the design team prior to any of these materials arriving on site. Concrete cube and slump testing will be carried out on all wet concrete delivered to site as per the Engineers specification. SP will carry out its duty as the registered builder on the project. SP will collect and issue Ancillary certs from all relevant subcontractors. In addition to our own Test & Inspection Plan, we will work closely with the Design team to give adequate notice for inspections required under the design teams Inspection Plans.

5.0 BREEAM AND CONSIDERATE CONSTRUCTORS SCHEME SP in an attempt to reduce workflows utilise the bre Green Guide to Specifications. To demonstrate our commitment to the reduction of CO2e and the objective to provide sustainable & responsible procurement, our design & procurement departments endeavour to attain A+ ratings for all construction materials where possible.

Develop the site specific Quality Plan

Provide samples

Intergrate the design team checks with our quality

checks

Inpections, records, hold

points and sign off sheets

Manage defect so

snag free -Quliaty sign

off

Page 62: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 61 of 62

SP are committed to lowering the impact of construction materials on the environment across the total lifecycle of the material from cradle to grave. Materials listed in the bre Green Guide to Specifications rated at A+ offer the lowest embodied C02 (CO2e) options.SP seek to deliver to our clients and by extension satisfy planning objectives of local authorities and stakeholders the highest BREEAM rating the project is capable of obtaining. The aims of the Considerate Constructors Scheme shall be adopted for this project with the ultimate objective of being considerate to local communities and stakeholders. To achieve this aim SP Senior Management Team engage at project level to provide authority to the Project Delivery Team to plan best practice actions. The Contracts Manager (Senior Management) shall liaise directly with the Project Manager and Quality & Environmental Manager to ensure authority for indirect project procurements and actions.

Page 63: CONSTRUCTION LOGISTIC PLAN - LBBD

Page 62 of 62

6 APPENDICES (STANDARD FORMS) Project Specific pro-forma’s shall be developed for use in London after due diligence to confirm compliance with all Site Specific and UK 6.0 RISK ASSESSMENT REGISTER 6.1 TEMPORARY WORKS REGISTER 6.2 INDUCTION FORM 6.3 METHOD STATEMENT TEMPLATE 6.4 TOOL-BOX TALKS REGISTER 6.5 TOOL-BOX TALKS FORM 6.6 SITE INSPECTION TEMPLATE 6.7 H&S EMERGENCY RESOURCE PLAN 6.8 ENVIRONMENTAL EMERGENCY RESPONSE PLAN 6.9 ENVIRONMENTAL CHECK LIST 6.10 UTILITY MONITORING 6.11 CONSTRUCTION PHASE PLAN (CDM 2015)