construction of dlf mall of india
DESCRIPTION
Training report of 4 weeks summer internship at DLF mall of India.TRANSCRIPT
1
Construction of DLF Mall of India
On-Site Training Report
And
Summer Internship Project
On
“Safety and Quality Management System”
Submitted by
Bhoomika Mansharamani (1009740028)
Galgotias College of Engineering and Technology
Greater Noida
2
CERTIFICATE
This is to certify that this project report entitled “IN PLANT TRAINING REPORT WITH SAFETY
AND QUALITY MANAGEMENT SYSTEM” by BHOOMIKA MANSHARAMANI, submitted in
partial fulfillment of the requirements for the degree of Bachelor of Technology in Mechanical
Engineering from GALGOTIAS COLLEGE OF ENGINEERING AND TECHNOLOGY, during the
academic year 2013-14, is a bonafide record of work carried out under my guidance and supervision
during 19th June 2013-19th July 2013.
Tarun Chandra
Quality Manager, MEP Department,
L & T Constructions
3
Acknowledgement
One cannot achieve worthwhile in the field of technical education until or unless theoretical education
acquired in the classroom is effectively wedded to its practical approach.
I take this opportunity to express my profound gratitude and deep regards to my project guide and mentor
Mr. Tarun Chandra (Quality Manager, QA/QC department, Mall of India) for his exemplary
guidance, monitoring and constant encouragement throughout the course of this project. The blessing,
help and guidance given by him from time to time shall carry me a long way in the journey of life on
which I am about to embark.
I also take this opportunity to express a deep sense of gratitude to Mr. Vikas Saini (MEP head), Mr.
Manoranjan Raheja (MEP Coordinator), Mr. Deepak Mittal (Assistant Manager MEP), Mr.
VarinderPal Singh (Assistant Manager, FF), Sudhir Kumar (Assistant Manager, FF), Mustafa
Raza (Assistant Manager, HVAC) & Mr. Bhoopendra Rathore (Senior Engineer), for their cordial
support, valuable information provided by them in their respective fields and guidance, without which I
couldn’t have achieved knowledge about HVAC, Quality Management and would not have got any lead
to approach the methodology to be followed. I am grateful for their cooperation during the period of my
internship.
Last but not the least, I thank almighty, my parents, and friends for their constant encouragement without
which this internship would not be possible.
Bhoomika Mansharamani
4
Index S.NO Topic Page No
2 Abstract………………………………………………………………………………... 5
3 History of Larsen and Toubro…………………………………………………………. 6
4 Project Brief…………………………………………………………………………… 7
5 Basic Layout of the Mall of India Project……………………………………………... 8
6 Major Quantities of Work……………………………………………………………… 9
7 Major item of project value……………………………………………………………. 10
8 Scope of MEP………………………………………………………………………….. 11
9 MEP Department………………………………………………………………………. 12
10 HVAC…………………………………………………………………………………. 13
11 Diesel Generator………………………………………………………………………. 18
12 Quality Management System………………………………………………………….. 19
13 Test And Commissioning At Mall Of India…………………………………………… 25
5
2. Abstract
Quality Management is the act of overseeing all activities and tasks needed to maintain a desired level of
excellence. This includes creating and implementing quality planning and assurance, as well as quality
control and quality improvement. For this, a full fledge system is installed which defines several
guidelines for the industries to ensure full satisfaction of the customer and how we can enhance it.
Material Inspection and Work Inspection Report are prepared before installing any system or device at
the construction site. On spot training of the workers and periodic safety checks are done at the site.
At L&T, Environment, Health & Safety (EHS) is given the highest priority. The EHS policy enunciated
by the Corporate Management lays emphasis on Environment, Health and Safety through a structured
approach and well defined practices. Systems and procedures have been established for implementing the
requisites at all stages of construction and they are accredited to the International standards of ISO
9001:2008, ISO 14001:2004 and OHSAS 18001:2007. L&T continues to maintain the trail blazing
tradition of meeting the stringent quality standards and adherence to time schedules in all the projects.
In this project, several processes used by L&T constructions at Mall Of India site, to ensure and control
quality of the product as well as safety of the manpower are outlined.
6
3. History of Larsen & Toubro Larsen & Toubro (L&T) is India’s largest technology, engineering,
manufacturing and construction organization with a record of over 70 years. L&T
is also adjudged India’s best managed and most respected company on various
attributes of customer delight and shareholder value. L&T Construction’s cutting
edge capabilities cover every discipline of construction – civil, mechanical, and
electrical and instrumentation engineering and services extend to large industrial
and infrastructure projects from concept to commissioning.
L&T Construction has played a prominent role in India’s industrial and infrastructure development by
executing several projects across length and breadth of the country and abroad. For ease of operations and
better project management, in-depth technology and business development as well as to focus attention
on domestic and international project execution, entire operations of L&T Construction is structured into
four Independent Companies.
ECC – The Engineering Construction and Contracts Division of L&T is India’s largest construction
organization with over 60 years of experience and expertise in the field. ECC figures among the World’s
Top Contractors and ranks 29th among top global contractors and 77th among international contractors
as per the survey conducted by Engineering News Record magazine, USA (August 2011).
Larsen & Toubro Limited is the biggest legacy of two Danish Engineers, who built a world-class
organization that is professionally managed and a leader in India's engineering and construction industry.
It was the business of cement that brought the young Mr. Henning Holck-Larsen and Mr. S.K. Toubro
into India. They arrived on Indian shores as representatives of the Danish engineering firm F L Smidth &
Co in connection with the merger of cement companies that later grouped into the Associated Cement
Companies.
Together, Mr. Holck-Larsen and Mr. Toubro founded the partnership firm of L&T in 1938, which was
converted into a limited company on February 7, 1946. Today, this has metamorphosed into one of India's
biggest success stories. The company has grown from humble origins to a large conglomerate spanning
engineering and construction.
7
4. Project Brief
• CLIENT DLF LIMITED
• NAME CONSTRUCTION OF MALL OF INDIA AT NOIDA.
• LOCATION SECTOR - 18, NOIDA
• TOTAL AREA OF LAND 13.42 ACRE (APPROX.)
• BUILT-UP AREA 27,49,180 SQFT
• NO. OF FLOORS 3 BASEMENTS + GR. FLOOR LEVEL + FIVE FLOORS
• MAIN CONTRACTOR LARSEN & TOUBRO LIMITED
• ARCHITECTURE DESIGN PLUS
• PROJECT VALUE Rs. 447 CRORE (EXCLUDING SERVICE TAX)
8
5. Basic Layout of the Mall of India Project
Fig 5.1 Layout
9
6. Major Quantities of Work
S. No. ITEM DESCRIPTION UOM QTY
1 Excavation & Backfilling Cum 76133
2 PCC Cum 14475
3 RCC Cum 72300
4 Formwork Sqm 281860
5 Reinforcement MT 11960
6 Reinforcement Coupler Nos 134383
7 Str. Steel MT 850
8 VDF Flooring Sqm 94283
9 Block Masonry – 100mm Sqm 13635
10 Block Masonry – 200mm Cum 14262
11 Internal Plastering Sqm 173025
12 External Plastering Sqm 19780
10
7. Major Item of Project Value
Fig 7.1
0%1% 8%4%
12%
2%3%1%
7%
33%
24%
3% 2%Excavation/ Backfilling
PCC
RCC
Formwork
Reinforcement
Str. Steel
Block Masonry
Plastering & VDF
Mis Works
MEP Works
Finishing Works
Waterproofing
External Development
11
8. Scope of MEP
Service Subcontractor Cost Main items of Work
HVAC Blue Star 41.08 Cr. Chiller- 5 x1000 TR & 2 x350 TR AHU’s & FCU’s- 512 Nos. FAN – (Cent-190 Nos., Axial- 181 Nos.) Jet Fan- 327 Nos. Ducting – 35000 Sqm Piping – 35 KM
Electrical Trimoorti 24 Cr. DG Sets- 11 Nos. (2000KVA- 9 Nos. 1010 KVA- 2 Nos.) Transformer- 8 Nos. HT Panel- 1 Set LT Panels- 85 Nos. Conduit- 249 KM Cable Tray – 13 KM Wire- 256 KM
PHE & FPS
Scenario 18.91 Cr. Piping- 123 KM Fire Pump- 6 Nos. PHE pumps- 7 Nos. Toilet – 32 Nos.
Lift & Escalator
Thyssen Krupp 26.5 Cr. Lift – 22 Nos. Escalator- 80 Nos.
12
9. MEP Department
MEP Activities
HVAC
FIRE FIGHTING(FPS)
PLUMBING
ELECTRICAL WORKS/LIFT & ESCALATORS/BMS
PANELS & TRANSFORMERS
PLANNING AND DOCUMENTATION
QUALITY
Packages Sub-Contractors
HVAC Blue Star Ltd.
Fire Fighting and Plumbing Scenario India
BGMS Bose
BMS Johnson Control (I) Ltd.
Electricals Trimoorti
STP(Sewage Treatment Plant) Watcon Water
Lift and Escalator Thyssenkrupp
FTTH Radius Infratel
Gen Set Sudhir D.G.
13
10. HVAC HVAC (heating, ventilation, and air conditioning) is the technology of indoor and vehicular environmental
comfort. HVAC system design is a sub discipline of mechanical engineering, based on the principles
of thermodynamics, fluid mechanics, and heat transfer. Refrigeration is sometimes added to the field's
abbreviation as HVAC&R or HVACR, or ventilating is dropped as in HACR (such as the designation of
HACR-rated circuit breakers).
HVAC is important in the design of medium to large industrial and office buildings such
as skyscrapers and in marine environments such as aquariums, where safe and healthy building conditions
are regulated with respect to temperature and humidity, using fresh air from outdoors.
10.1 DETAILS OF HVAC AT DLF MALL OF INDIA
Main Contractor Larsen & Toubro
Sub-Contractor Blue Star LTD
HVAC Consultant Dew Point Consultants Pvt Ltd
Architect Design Plus
Amount Of Work Rs. 41,08,00,000
Date of LOI issued 8th February 2012
10.2 Introduction
All air conditioning systems require a means for generating the cooling effect that offsets building heat
gain due to external loads (sun, wind, outdoor temperature) and internal loads (heat and moisture from
people, lights, and equipment). In smaller buildings and residential applications, this is usually
accomplished with an air-based system that ducts cold air from the point of generation (usually on the
roof) to each space in the building that requires cooling.
Larger buildings and multiple building campuses usually use a chiller plant to provide cooling. In such
systems, chilled water is centrally generated and then piped throughout the building to air handling units
serving individual tenant spaces, single floors, or several floors. Ductwork then runs from each air handler
to the zones that are served.
Heat transfer loops in refrigeration system
14
10.2.1 Types of Air Conditioning System
Depending upon the type of fluid used either for heating or cooling, air-conditioning methods can be
classified as:
a) Direct Expansion system (also referred as unitary system)
In this system, a self-contained air conditioned unit is located in or next to the space to be air
conditioned. It consists of minimum essential components producing cooling effect generally using
direct expansion system. Heating is also included with the unit itself. In this system if heater is added,
or it is adopted to heat pump arrangement by transfer valve, it can be used as year-round air
conditioning system
Advantages:
1) Individual room control is inexpensive and simple
2) Installation is simple and takes less time
3) Initial cost is normally low compared to central system.
Disadvantages:
1) As the components are selected and matched by the manufacturer, the system is less flexible in terms
of airflow rate, condenser and evaporator sizes.
2) Power consumption per TR can be higher compared to central systems.
3) Close control of space humidity is generally difficult.
These systems are used for air conditioning of individual rooms of large office buildings, classrooms,
hotels, shopping centers etc.
b) All Air System
In this system, air conditioned plant is remotely located in the central pace and the conditioned air is
sent through the ducts and distributed into the air conditioned spaces through inlets.
15
Advantages:
1) It is possible to provide good room air distribution and ventilation under all conditions of load.
2) Since the air-conditioning plant is located at remote place, low noise level is achieved in the room.
3) Building pressurization can be achieved easily.
Disadvantages:
1) Occupy more space.
2) Balancing of airflow quantity is time consuming and sometimes could be difficult to achieve.
3) Installation of these systems is time consuming.
They are especially suited to buildings that require individual control of multiple zones, such as office
buildings, classrooms, laboratories, hospitals, hotels, ships etc.
They are also extensively used in applications that require very close control of the conditions in
conditioned spaces such as cleanrooms, operation theatres, research facilities etc.
c) All water system
In this system, water is used to pick up/give the heat in the conditioned space (or room).
Advantages
1) Since specific heat of water is more than air, all water systems require less space compared to all
air systems.
16
2) Individual room control is possible and at the same time the system offers all benefits of a large
central system.
Disadvantages
1) Requires higher maintenance compared to all air system.
2) Draining of condensate can be messy and may also create health problems.
3) Noise level in the room is more compared to all air system.
All water systems using Fan Coil Unit (FCU) are most suitable in buildings requiring individual room
control such as hotels, apartment buildings, and office buildings.
Larger buildings and multiple building campuses usually use a chiller plant to provide cooling. In such
systems, chilled water is centrally generated and then piped throughout the building to air handling units
serving individual tenant spaces, single floors, or several floors. Ductwork then runs from each air handler
to the zones that are served. Chilled water-based systems result in far less ductwork than all-air systems
because chilled water piping is used to convey thermal energy from the point of generation to each point
of use.
Though more costly to install and more complicated to operate, a chiller plant offers a number of benefits
over simple packaged cooling units, including greater energy efficiency, better controllability, and longer
life. Additionally, a chiller-based system can be much more efficient in terms of space utilization within
the building because components need not be located within the same space. One reason that less space
is needed is that the size of pipes that convey chilled water throughout the building is much smaller than
the size of air ducts that would deliver cold air to provide the same cooling effect. One pound of water
can store about four times as much thermal energy as the same mass of air, and—because water is much
denser than air—a pound of water has a much smaller volume than the pound of air. The combination of
increased thermal capacity and higher density makes water an ideal medium for space-efficient heat
transfer.
17
10.3 DUCTS
Ducts are used in heating, ventilation, and air conditioning (HVAC) to deliver and remove air. These
needed airflows include, for example, supply air, return air, and exhaust air. Ducts also deliver, most
commonly as part of the supply air, ventilation air. As such, air ducts are one method of ensuring
acceptable indoor air quality as well as thermal comfort.
A duct system is often called ductwork. Planning ('laying out'), sizing, optimizing, detailing, and finding
the pressure losses through a duct system is called duct design.
Ducts can be made out of the following materials:
Galvanized mild steel is the standard and most common material used in fabricating ductwork.
10.3.1 Duct System Components
Besides the ducts themselves, complete ducting systems contain many other components.
(a) Vibration isolators: A duct system often begins at an air handler. The blowers in the air handlers
can create substantial vibration and the large area of the duct system would transmit this noise and
vibration to the inhabitants of the building. To avoid this, vibration isolators (flexible sections)
are normally inserted into the duct immediately before and after the air handler. The rubberized
canvas-like material of these sections allow the air handler to vibrate without transmitting much
vibration to the attached ducts. The same flexible section can reduce the "bang" that can occur
when the blower engages and positive air pressure is introduced to the ductwork.
(b) Take-off: Downstream of the air handler, the supply air trunk duct will commonly fork, providing
air to many individual air outlets such as diffusers, grilles, and registers. When the system is
designed with a main duct branching into many subsidiary branch ducts, fittings called take-
offs allow a small portion of the flow in the main duct to be diverted into each branch duct. Take-
offs may be fitted into round or rectangular openings cut into the wall of the main duct. The take-
off commonly has many small metal tabs that are then bent to retain the take-off on the main duct;
round versions are called spin-in fittings. Other take-off designs use a snap-in attachment method,
sometimes coupled with an adhesive foam gasket to provide improved sealing. The outlet of the
take-off then connects to the rectangular, oval, or round branch duct.
(c) Stacks, boots, and heads: Ducts, especially in homes, must often allow air to travel vertically
within relatively thin walls. These vertical ducts are called stacks and are formed with either very
wide and relatively thin rectangular sections or oval sections. At the bottom of the stack, a stack
boot provides a transition from an ordinary large round or rectangular duct to the thin wall-
mounted duct. At the top, astack head can provide a transition back to ordinary ducting while
a register head allows the transition to a wall-mounted air register.
(d) Volume Control Damper: Ducting systems must often provide a method of adjusting the volume
of air flow to various parts of the system. VCDs (Volume Control Dampers - Not to Be confused
with Smoke/Fire Dampers) provide this function. Besides the regulation provided at the registers
or diffusers that spread air into individual rooms, dampers can be fitted within the ducts
themselves. These dampers may be manual or automatic. Zone dampers provide automatic control
in simple systems while VAVs allow control in sophisticated systems.
(e) Smoke/Fire Dampers: Smoke dampers are automated with the use of a mechanical motor often
referred to as an Actuator. A probe connected to the motor is installed in the run of duct, and
detects smoke within the duct system which has been extracted from a room, or which is being
supplied from the AHU (Air Handling Unit) or elsewhere within the run. Once smoke is detected
within the duct, the Actuator triggers the motor release and Smoke and Fire dampers are found in
ductwork, where the duct passes through a firewall or fire curtain. The smoke damper will
18
automatically close until manually re-opened. You will also find Fire dampers in the same places
as smoke dampers, depending on the application of the area after the firewall. Unlike smoke
dampers, they are not triggered by any electrical system, which is perfect in the event of an
electrical failure where the Smoke dampers would fail to close. Fire dampers may be mounted in
either horizontal or vertical configurations. Vertically mounted fire dampers are gravity operated
while horizontal fire dampers are spring powered. In either case, a fire damper's most important
feature is known as a fusible link. A fusible link is a piece of metal that will fail at a specified
temperature allowing the damper to open under gravity or spring power, effectively sealing the
duct, containing the fire, and denying it the necessary air to burn.
(f) Plenums: Plenums are the central distribution and collection units for an HVAC system. The return
plenum carries the air from several large return grills (vents) or bell mouths to a central air handler.
The supply plenum directs air from the central unit to the rooms which the system is designed to
heat or cool.
(g) Terminal units: While single-zone constant air volume systems typically don't have them, other
types of air distribution systems often have terminal units in the branch ducts. Usually there is one
terminal unit per thermal zone. Some types of terminal units are VAV 'boxes' of either single or
dual duct, fan-powered mixing boxes of either parallel or series arrangement, and induction
terminal units. Terminal units may also include either, or both, a heating or cooling coil.
(h) Air terminals: Common, but grille ‘Air terminals' are the supply air outlets and 'return' or 'exhaust
air inlets'. For supply, diffusers are most s, and for very small HVAC systems such as in residences,
'registers' are also used widely. Return or 'exhaust grilles' are used primarily for appearance
reasons, but some also incorporate an air filter and are known as 'filter returns'.
11. Diesel Generators A diesel generator is the combination of a diesel engine with an electric generator (often an alternator)
to generate electrical energy. Diesel generating sets are used in places without connection to the power
grid, as emergency power-supply if the grid fails, as well as for more complex applications such as peak-
lopping, grid support and export to the power grid. Sizing of diesel generators is critical to avoid low-load
or a shortage of power and is complicated by modern electronics, specifically non-linear loads.
Generating sets are selected based on the Electrical load they are intended to supply, the electrical loads
total characteristics (kwe, kVA, and Harmonic Content including starting currents (normally from motors)
and non-linear loads. The expected duty, for example, emergency, prime or continuous power as well as
environmental conditions such as altitude, temperature and emissions regulations must be taken into
account as well.
Most of the larger generator set manufacturers offer software that will perform the complicated sizing
calculations by simply inputting site conditions and connected electrical load characteristics
Only Diesel generator required the less time to operate so most commonly for power back up diesel
generators are preferred though it generates electricity at high cost. Total 11 DG’s are installed in this site
on B03 floor. Among them nine are of capacity 2000KVA i.e. approximately 1600KW at 415 volts. The
alternator used in DG is Stamford brushless AC alternator. It is separately excited and self-regulated. It
has class H insulation, salient pole revolving field, single/double bearing, and automatic voltage regulator.
The DG has a silencer suitably optimized to reduce noise also have a 990 liters free standing fuel tank.
The special features of Cummins engines like STC(step timings controls) injectors, low temperature after-
cooler, square combustion chamber, optimized turbo charging and precision heavy duty cam-shaft make
these engines the ultimate in exceptional fuel efficiency all across the operating ranges.
19
12. Quality Management System
Quality management system is a comprehensive and fundamental rule/belief, for leading and operating
an organization, aimed at continually improving performance over the long term by focusing on customers
while addressing the needs of all other stake holders. QMS is becoming increasingly important to the
leadership and management of all organizations.
There are eight basic principles of Quality Management System-
Principle 1:
Customer-Focused Organization: "Organizations depend on their customers and therefore should
understand current and future customer needs, meet customer requirements and strive to exceed customer
expectations".
Principle 2:
Leadership: "Leaders establish unity of purpose and direction of the organization. They should create and
maintain the internal environment in which people can become fully involved in achieving the
organization's objectives."
Principle 3:
Involvement of People: "People at all levels are the essence of an organization and their full involvement
enables their abilities to be used for the organization's benefit".
Principle 4:
Process Approach: "A desired result is achieved more efficiently when related resources and activities
are managed as a process."
Principle 5:
System Approach to Management: "Identifying, understanding and managing a system of interrelated
processes for a given objective improves the organization's effectiveness and efficiency."
Principle 6:
Continual Improvement: "Continual improvement should be a permanent objective of the organization."
Principle 7:
Factual Approach to Decision Making: "Effective decisions are based on the analysis of data and
information."
Principle 8:
Mutually Beneficial Supplier Relationships: "An organization and its suppliers are interdependent, and a
mutually beneficial relationship enhances the ability of both to create value.
12.1 Elements of Quality Management System (a) Quality Assurance: Quality Assurance is a set of activities intended to establish confidence that
quality requirement will be met. Two principles included in QA are:
Fit for purpose: The product should be suitable for the intended purpose.
Right first time: Mistakes should be eliminated.
QA includes management of the quality of raw materials, assemblies, products and components, services
related to production, and management, production and inspection processes.
20
(b) Quality Control: Quality Control is a process by which entities review the quality of all factors
involved in production. This approach places an emphasis on three aspects:
Elements such as controls, job management, defined and well managed processes, performance
and integrity criteria, and identification of records
Competence, such as knowledge, skills, experience, and qualifications
Soft elements, such as personnel, integrity, confidence, organizational culture, motivation, team
spirit, and quality relationships.
The quality of the outputs is at risk if any of these three aspects is deficient in any way. Quality control
emphasizes testing of products to uncover defects and reporting to management who make the decision
to allow or deny product release.
12.2 Ways of Ensuring Quality at Mall Of India Project (a) Method Statement:
• The document used in a tender process which sets out questions for the suppliers to answer
which help us understand how you intend to provide the goods or services.
• Method statement is issued by the sub-contractor and is finally approved by the consultant of the
Client. And after the approval the method statement is ready to be implemented.
(b) Technical Submittal:
Submittals are required to verify that the correct products and quantities will be installed on the
project. This is of 2 types:
• Product data submittal: The product data submittal usually consists of the manufacturer’s
product information. The general information included in the product data submittal are
a) Manufacturer, trade name, model or type number and quantities
b) Size and physical characteristics
c) Description of use and performance characteristics
• Shop drawing: A shop drawing is a drawing or set of drawings produced by
the contractor, supplier, manufacturer, subcontractor, or fabricator. Information included in shop
drawing:
a) Notes of changes or alterations from the construction documents.
b) Information needed to fabricate the product.
c) Installation information
21
(c) Drawing approvals:
It’s a multistage process.
Stage 1: Client prepare a GFC (Good for Construction) Drawing
(Sends it to)
Contractor
Stage 2: Contractor prepares a SHOP DRAWING based on GFC.
(Sends it to)
Client (for approval)
Stage 3: If satisfied, client approves the drawing and the structure is ready for construction as per the
drawing.
If not, he sends it back to the contractor for revision.
Stage 4: The contractor, in last, prepares an “As Build Drawing” which includes the final drawing and
any changes made in the shop drawing during construction due to site condition.
(d) Checklist: It is a list proposed by the contractor to check the implemented work on the
construction site and is approved by the client.
12.3 Ways of controlling quality at Mall of India Project
a) Material Inspection Request (MIR):
The material inspection request is used by a consultant that is inspecting a piece of a material to issue
comments and record the findings of the inspection in a standard report.As soon as the materials
delivered to site, it is inspected for
Physical damages
Manufacturer Test report
Invoice/ Chalan
Compiling with approved technical specification
After the quality check of the material, there are three levels of assessment:
a. Level A: Approved
The material is OK and ready to use.
b. Level B: Approved as Noted
Material is approved with comments. Those comments are to be rectified by the sub-contractor.
c. Level C: Rejected
The material is not fulfilling the requirement of the approved technical data of the material to
be used and is rejected.
After internal inspection, Clients/Consultants are called for final inspection & the same shall be
recorded in the inspection report.
22
If there is any dilemma with the material’s test certificate issued by the manufacturer, a THIRD
PARTY TEST comes in action. Following are the steps of a third party test.
To Ensure the Manufacturer test certificate’s genuineness, Piece of the material is sent to
authorize third party laboratory for testing (National accreditation board for testing and
calibration Lab - NABL).
Test report from laboratory is compared with manufacturer’s test report.
In case of major deviation, the material shall be rejected.
23
Sample of MIR to be used at mall of India project
24
(b) Work Inspection Report:
The work inspection request is used by a consultant that is inspecting work done by the sub-contractor
to issue comments and record the findings of the inspection in a standard report.
Work done at any particular location of the project is inspected and tested by the sub-contractor,
contractor and PMC. If approved by all 3 of them, the work done is O.K. and is as per the requirement
of the client.There are three levels of assessment:
1. Level A: Approved
The work done is perfectly O.K. and need no changes.
2. Level B: Approved as Noted
The work done is approved with comments and need some changes. Those comments are to
be rectified by the sub-contractor.
3. Level C: Rejected
The work is inappropriate as per the requirement and is rejected.
Sample of WIR to be used at Mall of India
25
(c) Non-conformance report:
A report issued when a product, process or procedure does not comply with the set standards for a
particular belonging to the product, process or procedure under inspection.
There are two types of NCR:
1. Internal NCR: It’s a NCR issued by a department within an organization for same or
another department within the same organization.
2. External NCR: It’s a NCR issued by an organization for another organization that are in
any kind of contract.
• NCR issued by the PMC to the contractor.
• NCR issued by the contractor to the sub-contractor.
12.4 Non Conformance Report Closure
To close the issued NCR, there is a definite procedure. It includes of following 4 steps.
a) Root Cause: First of all, the root cause of the NCR is to be determined. The reason because of
which the NCR was issued.
b) Corrective action proposed: After determining the root cause, a corrective action is to be
proposed to close the NCR.
c) Corrective action taken: If the corrective action proposed is acceptable by the issuing
organization, the proposed corrective action is implemented.
d) Preventive action: NCR receiving organization should propose some preventive measures for non-
occurrence of same NCRs in future.
26
13. Test and Commissioning At Mall Of
India
These are done to check the material as soon as it reaches the site.
Some of the examples are:
(a) MS/GI Pipe- Site Test
Following parameters are to be checked-
Diameter of the pipe.
Thickness of the pipe –Screw gauge / venire caliper is used to find the thickness.
Length of the pipe.
Check ovality of pipes.
Apart from site test, the sample is sent to THIRD PARTY laboratory for testing:
Mechanical Test Standard Chemical Test Standard %
(max)
Yield Stress 235N/mm2 Carbon (C) 0.02
Tensile Stress 320 N/mm2 Manganese (Mg) 0.04
% of Elongation 5.65 Phosphorus (P) 0.005
Bend Test Should pass Sulphur 0.005
1. ‘V’ Groove check
Template made at site is used to check the ‘V’ groove between the two pipe ends.
2. Die-Penetrate Test (DP Test)
DP test conducted for 25% of welded joints.
Penetrant is applied on cleaned welded joint
Developer is applied after 5 min. red color spot indicates the pin hole.
27
3. Pressure Test
Pressure test is done to ensure the entire welding quality.
Water is pumped till it reaches double the working pressure & maintained for 24hrs.
If any leak, the same shall be rectified and redo the test.
It is less expensive.
4. Holiday Test
It is for underground pipes, where pipes are wrapped with antirust protection to avoid cathodic
reaction.
Test is conducted to identify air holes in wrapping, which if left buried may lead to rusting of pipe.
Operate on the principle - High Voltage Units with necessary safety arrangements.
5. Radiography Test
As per TAC 10% of total weld has to be radio graphically tested.
Defective welds are rectified & tested again.
Expensive & Time consuming.
(b) FIRE FIGHTING PUMPS
1. Head in meters
Head is derived from Discharges pressure measured from pressure gauge.
28
2. Fire Pump Testing
This test is done to ensure that the pump will operate without any mechanical difficulty and
protect the facility if a fire should occur.
Test Procedure
Start the pump with a drop in system pressure. Record the starting pressure.
Check the pump packing glands to verify that a slight discharge of water is visible.
Check for excessive vibrations, unusual noise, or other sign of malfunction. Make corrections as
needed.
Record the systems suction and discharge pressure.
Periodically verify that the pump and driver are not over heating during the test.
Shut down the pump manually.
3. Current Consumption
Starting & running current is measured with the help of tong tester. Horse Power (HP) is
derived from running current of motor.
(c) HVAC (Heating, Ventilation and Air Conditioning)
1. G.I. Duct test - Light Test and pressure test
It is to ensure no hole in duct & duct joints for air leakage
High intensity halogen lamp is lighted from one side of the duct and other side closed with
dummy.
This test is done only during evening time.
Holes in the duct identified by leakage of light and redo the test after closing the hole with
sealant.
2. AHU– Commissioning Test
2.1 Rotation of Motor
Direction of the motor rotation is very important and Proper output shall not be obtained unless
otherwise the motor rotates in right direction.
29
2.2 Noise test and performance test
Noise test is very important, as these equipment are installed very near to working environment
Human feels uncomfortable when the noise level increases beyond 70dba
With the help of sound level meter, noise of AHU is measured 2mtrs from the AHU
The unit shall be replaced incases the noise level found more than the specified value.
Discharge ( CFM ) has to be verified with anemometer
3. Pump–Commissioning Test
3.1 Flow rate in lpm
Pitot tube is used to find out velocity of water from pump.
Area of the pipe is measured.
3.2 Discharge pressure
Discharge pressure is calculated with the help of pressure gauge fixed in discharge side.
3.3 Efficiency
Eff-1 pumps used for HVAC chiller water pumping as the operation of these pumps are
continuous. Pump efficiency is calculated by finding ratio of output to input power.
4. Chiller – Commissioning Test
4.1 Performance Test
Chiller Capacity (TR) = 500 x Qw x (T2-T1)
12000
Where,
TR = Capacity in TR (Tons of Refrigerant)
Qw = Water Flow rate through chiller (usgpm)
T1 = Water temperature at chiller outlet (Deg F)
T2 = Water temperature at chiller inlet (Deg F)
Qw to be obtained from the collar characteristic curves based on the pressure difference.
4.2 Refrigerant gas Pressure Test (R134)
4.3 Suction & Discharge pressure Test
4.4 Temperature Test For Evaporator & Condenser
4.5 Flow Rate Test For Evaporator & Condenser
4.6 Noise Level Distance @ 1 mtr & 2 mtr
4.7 Vibration Test