Mopac Mobility Bridges Construction Update JANUARY 2016 FEBRUARY 2016 MARCH 2016 PHASE 1 BARTON CREEK SEGMENT PAGE 1 ABOUT THE PROJECT Barton Creek Segment (Phase 1) Loop 360 Segment (Phase 2) MOPAC LOOP 360 N Connect to Existing 8 Foot Sidewalk Construction of the 14-foot-wide, 1,045-foot-long MoPac Mobility Bridges (formerly called Mopac Bicycle & Pedestrian Bridge) began in Feb. 2014. One bridge is being built adjacent to MoPac and spans the Barton Creek Greenbelt at MoPac, and two additional bridges will be built which span Loop 360. spring 2016 Completed all substructure work. Completed beam erection. Placement of bridge deck forms. Began construction of retaining walls along trail. Completed work along northbound frontage road cycle track. Completed concrete painting. Continued with grading and retaining walls along the trail. The Barton Creek Segment is taking shape. Over the past three months we have completed major milestones including finalizing the construction of the columns and the erection of the bridge beams. Retaining walls along the trail portion are also taking shape. For the next several months the public will experience nightly lane closures on Mopac so that we are able to place the concrete for the bridge deck and railings.

Upload: others

Post on 10-Jul-2020

13 views

Category:

Documents


0 download

TRANSCRIPT

Mopac Mobility BridgesConstruction Update

JANUARY 2016 FEBRUARY 2016 MARCH 2016

PHASE 1 BARTON CREEK SEGMENT

PAGE 1

ABOUT THEPROJECT

Barton Creek Segment(Phase 1)

Loop 360 Segment(Phase 2)

MOPAC

LOO

P 36

0N

Connect to Existing8 Foot Sidewalk

Construction of the 14-foot-wide, 1,045-foot-long MoPac Mobility Bridges (formerly called Mopac Bicycle & Pedestrian Bridge) began in Feb. 2014. One bridge is being built adjacent to MoPac and spans the Barton Creek Greenbelt at MoPac, and two additional bridges will be built which span Loop 360.

spring 2016

Completed all substructure work. Completed beam erection.

Placement of bridge deck forms. Began construction of retaining walls along trail. Completed work along northbound frontage road cycle track.

Completed concrete painting. Continued with grading and retaining walls along the trail.

The Barton Creek Segment is taking shape. Over the past three months we have completed major milestones including finalizing the construction of the columns and the erection of the bridge beams. Retaining walls along the trail portion are also taking shape. For the next several months the public will experience nightly lane closures on Mopac so that we are able to place the concrete for the bridge deck and railings.

Installation of bridge rail and illumination to begin along with

concrete for the Shared Use Path.

Retaining walls and

bridge slab in progress.

Construction substantially completed.

FOR MORE INFO:[email protected] Phone (512) 974-3570austintexas.gov/urbantrails

Mopac Mobility Bridges Construction Update Spring 2016

THE MOPAC MOBILITY BRIDGES ARE A JOINT PROJECT OF THE CITY OF AUSTIN, THE TEXAS DEPARTMENT OF TRANSPORTATION AND THE CAPITAL AREA METROPOLITAN PLANNING ORGANIZATION (CAMPO).

PAGE 2

FUNFACT

JANUARY 2016 FEBRUARY 2016 MARCH 2016

Grading of bike path in Barton Creek

Switch back trail Bridge nearing completion

Elevation on recently placed bridge beams

Bridge column

Concrete path was completed. Pathway lighting was installed. Began wiring of pathway lighting, installed landscaping and trees north of Loop 360. Completed pathway south of Loop 360. Began installation of railings along pathway.

PHASE 2 360 SEGMENT

During the last three months the majority of the path was completed. The last of the concrete pathway is being placed and pathway lighting is being installed.

Did you know that Austin joins other

Texas cities, Houston and Dallas, that have a dedicated bike bridge.

Construction activities to begin with installation of bridge

foundations.

PROJECTTIMELINE

DEC ‘14

Construction on Micropile foundations

to begin.

Micropile foundation completed.

Bridge columns

in progress.

Bridge columns

and beams completed

and in place.

Installation of bridge rail and illumination.Bulk of Shared Use

Path completed.

WE AREHERE

MAR ‘15 JUNE ‘15

Bridgefoundations completed.

Installation of bridge beams

to begin.

Bridge columns

completed.

Installation of bridge beams

to begin. Installation of bridge rail and illumination to

begin along with concrete for

the Shared Use Path.

NOV ‘15

DEC ‘15OCT ‘15

PHASE 1

PHASE 2

APR ‘15

MAR ‘16

Construction substantially completed.

JUL ‘16

MAY ‘16

APR ‘16FEB ‘16