Mopac Mobility BridgesConstruction Update
JANUARY 2016 FEBRUARY 2016 MARCH 2016
PHASE 1 BARTON CREEK SEGMENT
PAGE 1
ABOUT THEPROJECT
Barton Creek Segment(Phase 1)
Loop 360 Segment(Phase 2)
MOPAC
LOO
P 36
0N
Connect to Existing8 Foot Sidewalk
Construction of the 14-foot-wide, 1,045-foot-long MoPac Mobility Bridges (formerly called Mopac Bicycle & Pedestrian Bridge) began in Feb. 2014. One bridge is being built adjacent to MoPac and spans the Barton Creek Greenbelt at MoPac, and two additional bridges will be built which span Loop 360.
spring 2016
Completed all substructure work. Completed beam erection.
Placement of bridge deck forms. Began construction of retaining walls along trail. Completed work along northbound frontage road cycle track.
Completed concrete painting. Continued with grading and retaining walls along the trail.
The Barton Creek Segment is taking shape. Over the past three months we have completed major milestones including finalizing the construction of the columns and the erection of the bridge beams. Retaining walls along the trail portion are also taking shape. For the next several months the public will experience nightly lane closures on Mopac so that we are able to place the concrete for the bridge deck and railings.
Installation of bridge rail and illumination to begin along with
concrete for the Shared Use Path.
Retaining walls and
bridge slab in progress.
Construction substantially completed.
FOR MORE INFO:[email protected] Phone (512) 974-3570austintexas.gov/urbantrails
Mopac Mobility Bridges Construction Update Spring 2016
THE MOPAC MOBILITY BRIDGES ARE A JOINT PROJECT OF THE CITY OF AUSTIN, THE TEXAS DEPARTMENT OF TRANSPORTATION AND THE CAPITAL AREA METROPOLITAN PLANNING ORGANIZATION (CAMPO).
PAGE 2
FUNFACT
JANUARY 2016 FEBRUARY 2016 MARCH 2016
Grading of bike path in Barton Creek
Switch back trail Bridge nearing completion
Elevation on recently placed bridge beams
Bridge column
Concrete path was completed. Pathway lighting was installed. Began wiring of pathway lighting, installed landscaping and trees north of Loop 360. Completed pathway south of Loop 360. Began installation of railings along pathway.
PHASE 2 360 SEGMENT
During the last three months the majority of the path was completed. The last of the concrete pathway is being placed and pathway lighting is being installed.
Did you know that Austin joins other
Texas cities, Houston and Dallas, that have a dedicated bike bridge.
Construction activities to begin with installation of bridge
foundations.
PROJECTTIMELINE
DEC ‘14
Construction on Micropile foundations
to begin.
Micropile foundation completed.
Bridge columns
in progress.
Bridge columns
and beams completed
and in place.
Installation of bridge rail and illumination.Bulk of Shared Use
Path completed.
WE AREHERE
MAR ‘15 JUNE ‘15
Bridgefoundations completed.
Installation of bridge beams
to begin.
Bridge columns
completed.
Installation of bridge beams
to begin. Installation of bridge rail and illumination to
begin along with concrete for
the Shared Use Path.
NOV ‘15
DEC ‘15OCT ‘15
PHASE 1
PHASE 2
APR ‘15
MAR ‘16
Construction substantially completed.
JUL ‘16
MAY ‘16
APR ‘16FEB ‘16