Construction on the Bing Kong Tong Building. For CCHE Quarterly Report 1/1/2014 – 3/31/2014. Prior to beginning of construction, abatement of hazardous materials took place. Karen Willig of Enercore Services is removing roof materials to test for asbestos. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Construction on the Bing Kong Tong Building](https://reader035.vdocuments.net/reader035/viewer/2022062423/56814376550346895daff713/html5/thumbnails/1.jpg)
Construction on the Bing Kong Tong Building
For CCHE Quarterly Report1/1/2014 – 3/31/2014
![Page 2: Construction on the Bing Kong Tong Building](https://reader035.vdocuments.net/reader035/viewer/2022062423/56814376550346895daff713/html5/thumbnails/2.jpg)
Prior to beginning of construction, abatement of hazardous materials took place.Karen Willig of Enercore Services is removing roof materials to test for asbestos.
![Page 3: Construction on the Bing Kong Tong Building](https://reader035.vdocuments.net/reader035/viewer/2022062423/56814376550346895daff713/html5/thumbnails/3.jpg)
Abatement proceeds with removal of three layers of old roofing.
![Page 4: Construction on the Bing Kong Tong Building](https://reader035.vdocuments.net/reader035/viewer/2022062423/56814376550346895daff713/html5/thumbnails/4.jpg)
Doors and windows are removed from the site to storage.Some went to Sacramento for restoration, these were returned wrapped in protective material. Others were placed directly into storage.
![Page 5: Construction on the Bing Kong Tong Building](https://reader035.vdocuments.net/reader035/viewer/2022062423/56814376550346895daff713/html5/thumbnails/5.jpg)
On March 3rd, a gala start of construction event was held in front of the Tong Building.It began with a traditional Chinese lion dance.
![Page 6: Construction on the Bing Kong Tong Building](https://reader035.vdocuments.net/reader035/viewer/2022062423/56814376550346895daff713/html5/thumbnails/6.jpg)
The celebration featured speakers who represented agencies key to the successful launching of Phase 1.The speaker at the podium is Don Nottoli, Sacramento District 5 County Supervisor. On the right is Mimi Morris, Executive Officer of the CCHE. On the left is Mark Bettencourt, Mayor of Isleton.
![Page 7: Construction on the Bing Kong Tong Building](https://reader035.vdocuments.net/reader035/viewer/2022062423/56814376550346895daff713/html5/thumbnails/7.jpg)
A temporary center wall was constructed to help stabilize the building during construction. Tilt-up jacks used to erect concrete tilt-up buildings were employed to bring the structure back to vertical.
![Page 8: Construction on the Bing Kong Tong Building](https://reader035.vdocuments.net/reader035/viewer/2022062423/56814376550346895daff713/html5/thumbnails/8.jpg)
Existing concrete was broken up and removed to make way for footings for restoration of the façade.
![Page 9: Construction on the Bing Kong Tong Building](https://reader035.vdocuments.net/reader035/viewer/2022062423/56814376550346895daff713/html5/thumbnails/9.jpg)
The metal siding as well as the shiplap siding that was under it were removed.These will be replaced by 1/2 inch plywood sheets and new metal siding.
![Page 10: Construction on the Bing Kong Tong Building](https://reader035.vdocuments.net/reader035/viewer/2022062423/56814376550346895daff713/html5/thumbnails/10.jpg)
Forms are completed and ready for concrete to be poured