construction reportflorida riverwalk–july’20 • ‘b’ building: • rcc work completed for...
TRANSCRIPT
![Page 1: Construction ReportFlorida Riverwalk–July’20 • ‘B’ BUILDING: • RCC work completed for 1st to 8th slab • Brickwork completed for 1st to 4th floor • INFRASTRUCTURE WORK:](https://reader036.vdocuments.net/reader036/viewer/2022071015/5fce73faf17be41b6f4056fb/html5/thumbnails/1.jpg)
Construction Reportas on 28th July 2020
![Page 2: Construction ReportFlorida Riverwalk–July’20 • ‘B’ BUILDING: • RCC work completed for 1st to 8th slab • Brickwork completed for 1st to 4th floor • INFRASTRUCTURE WORK:](https://reader036.vdocuments.net/reader036/viewer/2022071015/5fce73faf17be41b6f4056fb/html5/thumbnails/2.jpg)
Keshav Nagar, Pune
![Page 3: Construction ReportFlorida Riverwalk–July’20 • ‘B’ BUILDING: • RCC work completed for 1st to 8th slab • Brickwork completed for 1st to 4th floor • INFRASTRUCTURE WORK:](https://reader036.vdocuments.net/reader036/viewer/2022071015/5fce73faf17be41b6f4056fb/html5/thumbnails/3.jpg)
Florida Riverwalk– July’20
• ‘A’ BUILDING:
• RCC work completed for all floors slabs
• Block work completed for all floors
• Electrical wall conducting completed for all floors
• Internal plaster work completed
• Gypsum work completed
• Internal toilet concealed plumbing work completed
• External plaster work completed
• Bath Dado tiles, kitchen platform and bath granite frames work completed
• Tile flooring work completed
• Waterproofing work completed
• UPVC window work completed
• 60% work complete of internal painting
• 60% work complete for external painting
• 98% work complete for external duct and terrace plumbing
• 98% work complete for door fixing & 90% work complete for SS railing
• Fire fighting work completed
• 85% Solar work completed
• 60% work complete for wiring and switch plate
![Page 4: Construction ReportFlorida Riverwalk–July’20 • ‘B’ BUILDING: • RCC work completed for 1st to 8th slab • Brickwork completed for 1st to 4th floor • INFRASTRUCTURE WORK:](https://reader036.vdocuments.net/reader036/viewer/2022071015/5fce73faf17be41b6f4056fb/html5/thumbnails/4.jpg)
Florida Riverwalk– July’20
• ‘B’ BUILDING:
• RCC work completed for 1st to 8th slab
• Brickwork completed for 1st to 4th floor
• INFRASTRUCTURE WORK:
• Underground water tank RCC work completed
• Club House: excavation work completed and 80% RCC work complete
• Transformer Room: excavation work, RCC, brickwork, plaster completed, commissioning is pending
• Swimming Pool: excavation work completed and 70% RCC work complete
• Compound Wall and Retaining Wall brickwork completed
• Underground Services Drainage + Storm + Electrical – RCC piping work completed
• Fire Fighting work completed
• Road Trimix work 90% complete for ‘A’ building surrounding area
• Genset work completed
• 90% STP RCC work complete
• 95% work completed for security cabin and gate
![Page 5: Construction ReportFlorida Riverwalk–July’20 • ‘B’ BUILDING: • RCC work completed for 1st to 8th slab • Brickwork completed for 1st to 4th floor • INFRASTRUCTURE WORK:](https://reader036.vdocuments.net/reader036/viewer/2022071015/5fce73faf17be41b6f4056fb/html5/thumbnails/5.jpg)
![Page 6: Construction ReportFlorida Riverwalk–July’20 • ‘B’ BUILDING: • RCC work completed for 1st to 8th slab • Brickwork completed for 1st to 4th floor • INFRASTRUCTURE WORK:](https://reader036.vdocuments.net/reader036/viewer/2022071015/5fce73faf17be41b6f4056fb/html5/thumbnails/6.jpg)
![Page 7: Construction ReportFlorida Riverwalk–July’20 • ‘B’ BUILDING: • RCC work completed for 1st to 8th slab • Brickwork completed for 1st to 4th floor • INFRASTRUCTURE WORK:](https://reader036.vdocuments.net/reader036/viewer/2022071015/5fce73faf17be41b6f4056fb/html5/thumbnails/7.jpg)
![Page 8: Construction ReportFlorida Riverwalk–July’20 • ‘B’ BUILDING: • RCC work completed for 1st to 8th slab • Brickwork completed for 1st to 4th floor • INFRASTRUCTURE WORK:](https://reader036.vdocuments.net/reader036/viewer/2022071015/5fce73faf17be41b6f4056fb/html5/thumbnails/8.jpg)
THANK YOU!
-Team