CONSTRUCTION UPDATE – February 2015Dr. Prem Reddy Health & Science
![Page 2: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/2.jpg)
Perimeter wall framing in SIM Labs
![Page 3: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/3.jpg)
Metal Framing of west wall of cadaver room / cat storage
![Page 4: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/4.jpg)
Looking at wall framing for cadaver room/cat storage rooms from anatomy lab
![Page 5: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/5.jpg)
Student restroom area, overhead fire sprinkler piping, perimeter wall framing
![Page 6: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/6.jpg)
Overhead ductwork in beds/equipment room
![Page 7: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/7.jpg)
Templates for medical headwalls in Nursing
Fundamentals
![Page 8: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/8.jpg)
Front entry, shot of overhead work
![Page 9: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/9.jpg)
Perimeter wall framing in nursing fundamentals and
corridor 127. Fire sprinkler piping and duct
overhead
![Page 10: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/10.jpg)
Install of columns for shade structures has started in courtyard
![Page 11: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/11.jpg)
South west side exterior.
Metal deck installed at sloped roof
![Page 12: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/12.jpg)
Wall Framing of observation, control, and
SIM labs
![Page 13: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/13.jpg)
Posts for shade structure, outside deans office
![Page 14: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/14.jpg)
Framing at faculty offices area.
Looking in from exterior door on west
side
![Page 15: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/15.jpg)
Looking up at rotunda framing
![Page 16: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/16.jpg)
Rotunda steel being welded.
![Page 17: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/17.jpg)
CMU block being installed for main covered walkway
to existing bldg
![Page 18: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/18.jpg)
Looking down upon covered walkway columns
in progress.
![Page 19: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/19.jpg)
Mechanical unit set on mezzanine level
![Page 20: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/20.jpg)
South side flat metal decking, sloped roof
metal decking
![Page 21: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/21.jpg)
Penetrations in deck for solatubes (skylights)
![Page 22: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/22.jpg)
Air handler unit on mezzanine (AHU 2)
![Page 23: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/23.jpg)
Emergency eyewash installed at chemistry lab
![Page 24: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/24.jpg)
Wall framing at chemical balance room, exit foyer
![Page 25: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/25.jpg)
Overhead duct & walls framed in nursing
fundamental
![Page 26: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/26.jpg)
Installing overhead duct in corridor 127.
![Page 27: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/27.jpg)
Medical supplies and utility rooms framed up. Overhead duct installed
![Page 28: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/28.jpg)
Deans office, and meeting room to the right.
![Page 29: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/29.jpg)
Bottom side of metal deck, with cut outs for solatube. Anatomy lab.
![Page 30: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/30.jpg)
Concrete just poured at north covered walkway
![Page 31: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/31.jpg)
Emergency eyewash installed at anatomy lab
![Page 32: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/32.jpg)
SIM lab, control room, observation room wall
framing. Overhead duct.
![Page 33: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/33.jpg)
In wall plumbing at patient toilet rm 150
![Page 34: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/34.jpg)
Aluminum frames for glass along corridor 127
![Page 35: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/35.jpg)
Window in digital nurse proctor room, looking into
digital nurse test lab
![Page 36: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/36.jpg)
Piping ran to medical headwall template,
nursing fundamentals lab
![Page 37: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/37.jpg)
Overhead ducts in nursing fundamentals
![Page 38: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/38.jpg)
Looking at south covered walkway, from roof.
![Page 39: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/39.jpg)
North side roofing install
![Page 40: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/40.jpg)
South roof
![Page 41: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/41.jpg)
Mezzanine level. Mechanical unit & piping
![Page 42: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/42.jpg)
Looking from south, to north.
Rotunda and mechanical attic to the right
![Page 43: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/43.jpg)
Mock up of medical headwall in nursing
fundamentals
![Page 44: Construction Update - February 2015 - VVCCD Dr. Prem Reddy Health Sciences Building Project](https://reader034.vdocuments.net/reader034/viewer/2022042518/55a5ee171a28ab086b8b46ff/html5/thumbnails/44.jpg)
Plumbing for washer & dryer in utility room