1 Contents 1.0 EXECUTIVE SUMMARY .................................................................................................... 3 2.0 INTRODUCTION OF THE PROJECT ............................................................................. 4 2.1 Identification of project & Project Proponent .................................................................. 4 2.2 Nature of Project ..................................................................................................................... 4 2.3 Need of Project...................................................................................................................... 5 2.4 Demand Supply Gap............................................................................................................. 5 2.5 Employment generation ....................................................................................................... 6 3.0 PROJECT DESCRIPTION ................................................................................................. 6 3.1 Type of Project ...................................................................................................................... 6 3.2 Location................................................................................................................................... 6 3.3 Size or Magnitude of Operations........................................................................................ 6 3.4 Project Description ............................................................................................................... 9 3.5 Water, Energy/Power requirement ................................................................................. 18 3.6 Schematic Representative of feasibility drawing which give information of EIA Purpose............................................................................................................................................... 18 4.0 SITE ANALYSIS................................................................................................................... 20 4.1 Connectivity........................................................................................................................... 20 4.2 Land Form, Land Use & Land ownership ..................................................................... 20 4.3 Topography: ......................................................................................................................... 20 4.4 Existing Land Use Pattern ................................................................................................. 20 4.5 Existing Infrastructure ......................................................................................................... 21 4.6 Soil Classification................................................................................................................. 21 4.7 Climatic Conditions:............................................................................................................. 21 4.8 Social infrastructure Available. ......................................................................................... 22 5.0 PLANNING BRIEF ............................................................................................................ 23

Upload: hanhan

Post on 20-May-2018

242 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: Contentsenvironmentclearance.nic.in/writereaddata/Online/TOR/19_Jun_2017... · Contents 1.0 EXECUTIVE ... IOCL is having about 129 POL Depot/Terminals, ... The latest version of OISD

1

Contents

1.0 EXECUTIVE SUMMARY .................................................................................................... 3

2.0 INTRODUCTION OF THE PROJECT ............................................................................. 4

2.1 Identification of project & Project Proponent .................................................................. 4

2.2 Nature of Project ..................................................................................................................... 4

2.3 Need of Project...................................................................................................................... 5

2.4 Demand Supply Gap ............................................................................................................. 5

2.5 Employment generation ....................................................................................................... 6

3.0 PROJECT DESCRIPTION ................................................................................................. 6

3.1 Type of Project ...................................................................................................................... 6

3.2 Location................................................................................................................................... 6

3.3 Size or Magnitude of Operations........................................................................................ 6

3.4 Project Description ............................................................................................................... 9

3.5 Water, Energy/Power requirement ................................................................................. 18

3.6 Schematic Representative of feasibility drawing which give information of EIA

Purpose ............................................................................................................................................... 18

4.0 SITE ANALYSIS ................................................................................................................... 20

4.1 Connectivity ........................................................................................................................... 20

4.2 Land Form, Land Use & Land ownership ..................................................................... 20

4.3 Topography: ......................................................................................................................... 20

4.4 Existing Land Use Pattern ................................................................................................. 20

4.5 Existing Infrastructure ......................................................................................................... 21

4.6 Soil Classification ................................................................................................................. 21

4.7 Climatic Conditions: ............................................................................................................. 21

4.8 Social infrastructure Available. ......................................................................................... 22

5.0 PLANNING BRIEF ............................................................................................................ 23

Page 2: Contentsenvironmentclearance.nic.in/writereaddata/Online/TOR/19_Jun_2017... · Contents 1.0 EXECUTIVE ... IOCL is having about 129 POL Depot/Terminals, ... The latest version of OISD

2

5.1 Planning concept ................................................................................................................. 23

5.2 Population projection........................................................................................................... 23

5.3 Land Use Planning ............................................................................................................. 23

5.4 Assessment of infra structure Demand ........................................................................... 23

6.0 PROPOSE INFRASTRUCTURE ................................................................................... 23

6.1 Industrial Area (Processing Area) ................................................................................... 23

6.2 Residential Area (Non Processing Area) ...................................................................... 23

6.3 Green Belt.............................................................................................................................. 23

6.4 Social Infrastructure ........................................................................................................... 24

6.5 Connectivity .......................................................................................................................... 24

6.6 Drinking Water ..................................................................................................................... 24

6.7 Sewage ................................................................................................................................. 24

6.8 Industrial Waste Management ......................................................................................... 24

6.9 Power requirement ............................................................................................................. 24

7.0 REHABITATION AND RESETTLEMENT (R & R) PLAN ...................................... 24

8.0 PROJECT SCHEDULED AND PROJECT COST....................................................... 25

9.0 ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS)…………………….25

Page 3: Contentsenvironmentclearance.nic.in/writereaddata/Online/TOR/19_Jun_2017... · Contents 1.0 EXECUTIVE ... IOCL is having about 129 POL Depot/Terminals, ... The latest version of OISD

3

1.0 EXECUTIVE SUMMARY Indian Oil Corporation Ltd (IOCL) is a premier public sector company in the Oil & Gas

sector and is engaged in the business of refining and retailing of petroleum products

including LPG in the country. It is the leading Indian corporate in the Fortune “Global

500’ listing ranked at the 119th position in the year 2015. IOCL is having about 129 POL

Depot/Terminals, 91 LPG Bottling Plants which serve every nook and corner of the

country. Indane (the trade name of LPG of IOCL) is supplied to the consumers through a

network of about 5,456 distributors (51.8% of the industry).The growth in demand of LPG

for domestic purpose is increasing at a rapid pace. To improve safety standards in

Petroleum Industry, Ministry constituted OISD which establishes standards/practices to be

followed in petroleum sector from time to time.

The latest version of OISD standard for LPG Plant is OISD 144. The OISD 144 has given

stipulation on safety distance to be maintained between different facilities in LPG Plant

and also it gives the minimum safety measures to be taken for LPG Plants. Also OISD 150

will be followed for mounded vessel. The OISD 144/150 is accepted by Industry and

safety council and Govt. of India has advised to implement the same in all LPG Plants

across the country.

The proposed project is expansion one and target time frame for construction and

commissioning of the proposed project is 24 months from the date of granting

Environmental Clearance (EC) and allied approvals.

Page 4: Contentsenvironmentclearance.nic.in/writereaddata/Online/TOR/19_Jun_2017... · Contents 1.0 EXECUTIVE ... IOCL is having about 129 POL Depot/Terminals, ... The latest version of OISD

4

SALIENT FEATURES OF THE PROJECT

Sr. No. Points Description 1. Title of the project M/S. INDIAN OIL CORPORATION LIMITED

Construction of additional storage of LPG, Indian Oil Corporation Ltd (M.D.), at Farrukhabad.

2 Site Location Khasra nos: 704,705,706,707,708,709/1,710/1,714,715,818,822,832 Gaisinghpur Village, Farrukhabad Tehsil & District Uttarpradesh

3 Land Acquired Land Area – 32.9Acres Existing Built up area – 9.5Acres Proposed Builtup area – 0.5Acres Open area – 11.0 Acres Greenbelt area – 12.0Acres

4 Cost of the Project Rs.26.43 crores (Approximately) 5 Proposed facilities 2 x 900 MT MSVs

60 TMTPA bottling capacity 6 Existing Capacities 2 × 150 MT & 1 × 660 MT

250 TPD bottling capacity 7 Proposed Air pollution

Control measures D.G. Sets of 2× 500 KVA & 1x250 KVA will be provided with appropriated stack height as per PPCB guidelines

8 Water Requirement Domestic : 9.0KLD Source of Waster: 3nos of Tube wells

9 Waste Water Treatment Waste water generated will be send to Septic Tank followed by soak pit

10 Recycle & Reuse Treated Water from STP will be used for Green Belt Development in the plant premises.

11 Solid & Hazardous Waste Management and Disposal

Used Lubricating oil: 8 MT

12 Green Belt Around 12.0 acres land is for Green Belt 13 No. of employee Existing: 32 nos (Officers – 09nos, Staffs – 23nos)

Proposed: 10nos

Page 5: Contentsenvironmentclearance.nic.in/writereaddata/Online/TOR/19_Jun_2017... · Contents 1.0 EXECUTIVE ... IOCL is having about 129 POL Depot/Terminals, ... The latest version of OISD

5

2.0 INTRODUCTION OF THE PROJECT

2.1 Brief Description of Project

Indian Oil Corporation Limited (IOCL) proposes for additional storage of 2 x 900

MT capacity Mounded Storage Vessels and bottling capacity of 60TMTPA at

existing facility situated in Gaisinghpur (V), Farrukhabad (D), Uttar Pradesh to

meet the increasing demand in the state.

2.2 Nature of Project

Oil marketing companies have projected an increase in demand of Liquefied

Petroleum Gas (LPG) due to increase in its domestic use. The demand is likely to

increase substantially over the years to come. Oil PSUs have planned enrollment of

new customers to saturate the demand potential as per directive of the Ministry of

Petroleum and Natural Gas, Government of India.

As per vision 2015 Document of MOP & NG, Govt. of India, the LPG Penetration

has to be increased so as to achieve 75% penetration of LPG.

2.3 Need of Project

Oil marketing companies have projected an increase in demand of Liquefied

Petroleum Gas (LPG) in future due to increase in its domestic use. The demand is

likely to increase substantially over the years to come. Oil PSUs have planned

enrollment of new customers to saturate the demand potential as per directive of

the Ministry of Petroleum and Natural Gas, Government of India.

In line with the requirement envisaged and to ensure fulfillment of demand,

Ministry of Petroleum & Natural Gas has planned that different oil companies

should increase their storage and bottling capacity of LPG. Accordingly Indian Oil

Page 6: Contentsenvironmentclearance.nic.in/writereaddata/Online/TOR/19_Jun_2017... · Contents 1.0 EXECUTIVE ... IOCL is having about 129 POL Depot/Terminals, ... The latest version of OISD

6

Corporation Limited (IOCL) proposes to establish the LPG bottling plant and

construction of 2 Nos. of 900 MT Mounded storage vessels each.

2.4 Demand Supply Gap

This LPG bottling plant at Gaisinshpur & Nissai Village, Farrukhabad Tehsil &

District, Uttar Pradesh, is being established to meet the increasing demand in Uttar

Pradesh state, is being established with the purpose of supplying commercial and

domestic LPG to surrounding districts. As per Government of India, MOP &NG’s

vision 2015 to cover 75% population, mainly in rural areas with domestic LPG

connections from current 59%, about 350 TMTPA additional bottling capacity

needs to be added by 2020-21 by IOCL in UP.

2.5 Employment generation

There will be a positive impact in creation of direct and indirect employment

opportunities due to LPG Bottling Plant on local socioeconomic profile.

Construction phase: Employment generation as contractual basis and

involvement of unskilled labor will be more.

Operation phase: Indirect Employment generation in handling of cylinder,

transportation of cylinder etc for skilled / semi-skilled labors and drivers.

Existing Employees: 32 Nos (Officers = 09 nos and Staffs = 23nos)

Proposed Employees: 10Nos

Page 7: Contentsenvironmentclearance.nic.in/writereaddata/Online/TOR/19_Jun_2017... · Contents 1.0 EXECUTIVE ... IOCL is having about 129 POL Depot/Terminals, ... The latest version of OISD

7

3.0 Project Description

3.1 Type of Project

As per EIA Notification dated 14 Sep 2006 this projects falls under 6B category

i.e. for Isolated storage & handling of hazardous chemicals.

This is expansion of LPG Bottling Plant and will have 2 x 900 MT Mounded

Storage Vessels.

As per the EIA Notification, in the absence of duly constituted SEIAA & SEAC,

category –B project shall be cleared at MoEF&CC, New Delhi.

In this regard, we bring to your kind notice that, SEAC committee of Uttar Pradesh

has been expired; project is filed at MoEF&CC, New Delhi.

3.2 Location

The proposed project will be carried out at Gaisinghpur (V), Farrukhabad (Dt),

Uttar Pradesh which is about 13.4Km form Fatehgarh Railway station.

3.3 Size or Magnitude of Operations.

The total area of LPG Bottling Plant is 32.9 acres at Gaisinghpur (V), Farrukhabad

(D), Uttar Pradesh proposed for additional storage of LPG in 2x900 MT Mounded

Storage Vessel.

There will be no chemical process involved and the operation carried out will be

receipt of LPG in Bulk form in road tankers, storage in mounded bullets and filling

of LPG into cylinders using carousel and associated systems. The cylinders filled

will be checked for quality and then dispatched.

In the Proposed LPG Bottling Plant the storage will be pressurized form in

mounded storage. The mounded storage will be in 2 bullets of 900 MT each with a

total capacity of 1800 MT. The system of mounded storage has been recognized as

one of the safest form of storage of LPG.

Page 8: Contentsenvironmentclearance.nic.in/writereaddata/Online/TOR/19_Jun_2017... · Contents 1.0 EXECUTIVE ... IOCL is having about 129 POL Depot/Terminals, ... The latest version of OISD

8

Details on current proposal

LPG Storage Facility (Existing) LPG Bottling capacity (Existing)

2 x 150 MT (Above ground bullets), 1 x

680 MT (Horton Spheres)

250 MTPD

LPG Storage Facility (Expansion) LPG Bottling capacity (Expansion)

2 x 900 MT (Mounded storage vessels) 60 TMTPA

Location Map

Page 9: Contentsenvironmentclearance.nic.in/writereaddata/Online/TOR/19_Jun_2017... · Contents 1.0 EXECUTIVE ... IOCL is having about 129 POL Depot/Terminals, ... The latest version of OISD

9

Google Image of 10 Km Radius

Page 10: Contentsenvironmentclearance.nic.in/writereaddata/Online/TOR/19_Jun_2017... · Contents 1.0 EXECUTIVE ... IOCL is having about 129 POL Depot/Terminals, ... The latest version of OISD

10

Site Layout

Page 11: Contentsenvironmentclearance.nic.in/writereaddata/Online/TOR/19_Jun_2017... · Contents 1.0 EXECUTIVE ... IOCL is having about 129 POL Depot/Terminals, ... The latest version of OISD

11

3.4 Project Description

M/s. Indian Oil Corporation Ltd is operating a LPG cylinder bottling plant at

Khasra nos. 704, 705, 706, 707, 708, 709/1, 710/1, 714, 715, 818, 822, 832,

Gaisinghpur and Nissai, Farrukhabad Tehsil and District.

There will be no chemical process involved and the operation carried out will be

receipt of LPG in Bulk form in road tankers, storage in mounded bullets from

Vadodara, Bina Refineries & Kandla Import Terminal and filling of LPG into

cylinders using carousel and associated systems. The cylinders filled will be

checked for quality and then dispatched by Cylinder stake Trucks.

The process involved can be divided into 4 Stages

Receipt of finished LPG products through bullet trucks.

Storage of LPG products in storage tanks as per OISD norms. Packaging of the LPG into cylinders.

Dispatch of LPG products through Stake Trucks

Fig: Process Description

Page 12: Contentsenvironmentclearance.nic.in/writereaddata/Online/TOR/19_Jun_2017... · Contents 1.0 EXECUTIVE ... IOCL is having about 129 POL Depot/Terminals, ... The latest version of OISD

12

LPG BULK STORAGE

It is now proposed to expand the existing LPG Bottling plant by constructing two

No’s of 900MT capacity Mounded Storage Vessel and bottling capacity of which

will be constructed/fabricated to the stringent Oil Industry Safety Directorate’s

OISD norms and BS standards. There will be only one LPG liquid nozzle through

which LPG shall be received and discharged from each bullet.

The following provisions will be provided for proposed expansion project:

No Description Dimensions Area Remarks 1 LPG Bullets 2Nos

3.80mǾ x 28.70M long

150 MT each Existing

1A Horton Spheres 1 no 14mǾ, 660 MT each Existing 1B LPG Mounded

Bullets 2 Nos 7.0m Ǿx54.172m long

900 MT each Proposed

2 Fire water tanks 2 Nos 3700KL each Existing 3 Service water tank 50 KL capacity Existing A Plant sheds 4 LPG pump/Comp.

house 25m x 8m 200Sq.m Existing

5 Cold Repairs shed 11.2m x 16.8m 188.16Sq.m Existing 6 Filled cyls.

Storage shed 14m x 22.4m 345 Sq.m Existing

7 Filling cum empty cyls shed

56m x 30.8m 2217.6Sq.m Existing

8 Truck loading/unloading shed

22.4mx5.6m 180Sq.m Existing

9 TLD shed 8 bays 42m x 16.8m 705.60Sq.m Existing B Non Plant

Building

10 Fire water/Air comp. house

35m x 10m 350Sq.m Existing

11 Elec. Sub station 36m x 8m 304Sq.m Existing 12 Security Kiosk 3.23m x 3.23m 10.433 sq.m Existing 13 Weigh bridge pit 50 MT capacity Existing 14 Car/Scooter shed 30m x 6m 180sq.m Existing 15 Safety

eqpt/general store 10m x 27m 270 sq.m Existing

Page 13: Contentsenvironmentclearance.nic.in/writereaddata/Online/TOR/19_Jun_2017... · Contents 1.0 EXECUTIVE ... IOCL is having about 129 POL Depot/Terminals, ... The latest version of OISD

13

16 Workers amenity block/canteen

Double storey 300sq.m Existing

17 Office Building Double storey 360 sq.m Existing 18 S&D block & Ralf

control room Existing

19 Security kiosk at main gate

4.77m x 4.77m 22.752 sq.m Existing

20 Drivers rest room 7 m x 9m 63sq.m Existing C Drive ways Existing 21 Truck parking For 50 truck 7720 sq.m Existing 22 Internal roads -- 10700 sq.m Existing 23 External roads -- 5100 Sq.m Existing 24 Emergency control

center (ECC room) -- -- Existing

25 Assembly point -01 (TT crew)

-- -- Existing

26 Assembly point -02 (Contract labour)

-- -- Existing

27 Assembly point -03 (First aid & External aid)

-- -- Existing

28 STP shed 22m x 12m 264sq.m Proposed

FIRE FIGHTING FACILITIES

Fire fighting system is consisting of Automatic sprinkler system provided in all

LPG handling areas/sheds covered with network of hydrants & monitors as per

requirement of OISD 144.

All LPG storage Vessels, Cylinder Storage/ Filling/ Repair Sheds, LPG Pump

House, TLD are fully covered by medium velocity water spray system.

The main components of the fire water system are:

Fire Water Storage

Fire Water Pumps

Water Sprinkler/ Deluge system.

Fire water distribution piping network inclusive of Hydrant/ Monitor

Page 14: Contentsenvironmentclearance.nic.in/writereaddata/Online/TOR/19_Jun_2017... · Contents 1.0 EXECUTIVE ... IOCL is having about 129 POL Depot/Terminals, ... The latest version of OISD

14

Safety data No of monitors Monitors & Hydrant points (alternate) in hydrant ring

@30m. Numbers as per requirement Hydrant points Monitors & hydrant points (alternate) in hydrant ring

@30mtr. Numbers as per requirement Fire Extinguishers

10kg DCP, 75kg DCP & CO2 fire extinguishers as per requirement given in OISD -144

Hand siren As per requirement mentioned in OISD -144 ETB As per requirement mentioned in OISD -144 MCP As per requirement mentioned in OISD -144 Inter Distance for LPG Facilities: Required as per OISD/proposed

LPG Storage vessels

LPG storage vessels (mounded)

Boundary/Property line

Shed LPG

TLD LPG pump House

Fire water pump house

LPG Storage Vessels

As per OISD

-- 30m 15m 30m 30m 15m 60m

Actual -- 102.47m 78.71m 206.2m 91.70m 38m 373.68m LPG Storage Vessels (mounded)

As per OISD

30m -- 15m 30m 30m 15m 60m

Actual 102.47 -- 54.4m 294.75m 206.07m

153.07m

488.75m

Boundary/Property Line

As per OISD

15m 15m -- 30m 30m 30m 60m

Actual 78.71m 54.4m -- 46.96m 69.14m 77.61m

38.82m

Shed LPG As per OISD

30m 30m 30m -- 30m 15m 60m

Actual 206.2m 294.75m 46.96m -- 46.68m 158.4m

134.43m

TLD As per OISD

30m 30m 30m 30m -- 30m 60m

Actual 91.70m 208.07m 69.14m 46.68m -- 44.23m

243.02m

LPG pump House

As per OISD

15m 15m 30m 15m 30m -- 60m

Actual 38m 153.07m 77.61m 158.4m 44.23m -- 327.69m Fire water pump house (Planned)

As per OISD

60m 15m 60m 60m 60m 60m --

Actual 373.68m 488.75m 38.82m 134.43m 243.02m

327.69m

--

Page 15: Contentsenvironmentclearance.nic.in/writereaddata/Online/TOR/19_Jun_2017... · Contents 1.0 EXECUTIVE ... IOCL is having about 129 POL Depot/Terminals, ... The latest version of OISD

15

Flow Rate Design:

Medium Velocity sprinkler system with automatic heat detection having remote/

local operated Deluge valve with spray density of Minimum 10.2 LPM/ Sq.M are

provided at all facilities excluding LPG Pump house (i.e., storage Vessels,

Cylinder Storage/ Filling/ Repair Sheds, TLD) where as LPG Pump house is

provided with 20.4 LPM/ Sq.M.

The fire water system in the plant designed to meet the highest fire water flow

requirement of a single largest risk i.e., Filling Shed water requirement plus 288

KL/Hr

Fire Water Storage:

Total2 numbers of fire water tanks with capacity of 3700KL each.

Total fire water storage = 7400 KL

PROPERTIES OF LPG

1. LPG has been identified as 'hazardous chemical' as per Manufacture, Storage

and Import of Hazardous Chemicals Rules, 1989/1994.

2. LPG marketed in India is governed by IS 4576 and test methods by is 1448. IS

4576 defines LPG as a mixture of light hydrocarbons derived from petroleum

which are gaseous at ambient temperature and atmospheric pressure but

may be condensed to the liquid state at normal ambient temperature by the

application of moderate pressure.

3. LPG to be handled at the facility under study will be Propane - Butane mixture,

with small quantities of unsaturated hydrocarbons. LPG is highly flammable,

capable of producing fire and explosion hazards under certain conditions.

4. LPG at atmospheric pressure and temperature is a gas which is 1.5 to 2.0 times

heavier than air. It is easily liquefied under moderate pressure, Since LPG

vapour is heavier than air, it normally settles down at ground level/low lying

areas. This accumulation of LPG vapour gives rise to potential fire and

explosion.

Page 16: Contentsenvironmentclearance.nic.in/writereaddata/Online/TOR/19_Jun_2017... · Contents 1.0 EXECUTIVE ... IOCL is having about 129 POL Depot/Terminals, ... The latest version of OISD

16

5. LPG has an explosive limit range of 1.8% to 9.5% by volume of the gas in air.

This is considerably narrower than other common gaseous fuel. Combustion of

LPG increases the volume of products in addition to generation of heat. LPG

requires about 24 to 30 times its own volume of air for complete combustion

and yields 3-4 times its own volume of CO2. The heat of combustion is about

10,500 Kcal/kg.

6. LPG is colorless both in liquid and vapor phase. During leakage, vaporization

of LPG cools the atmosphere and condenses the water vapor contained in it

forming a white fog. This makes possible to see an escape of LPG.

7. LPG has a low viscosity (around 0.3 C.S. at 45°C) and can leak when other

petroleum products cannot. This property demands a high degree of integrity in

the pressurized systems handling LPG to avoid leakage.

8. LPG has a very faint smell and as such for detecting leakage of LPG, ethyl

mercaptan is generally added in the ratio approx 20 part mercaptan per million

liquid LPG (20 ppm).

9. Although it is not poisonous in vapor phase, it suffocates when present in large

concentrations due to displacement of oxygen. Immediately Dangerous to Life

& Health (IDLH) value of LPG is generally taken as 115000 ppm.

HAZARDS OF LPG

LPG is approximately twice as heavy as air when in gas form and will tend to sink

to the lowest possible level and may accumulate in cellars, pits, drains etc.

LPG in liquid form can cause severe cold burns to the skin owing to its rapid

vaporization.

Vaporization can cool equipment so that it may be cold enough to cause cold

burns.

LPG forms a flammable mixture with air in concentrations of between 2% and

10%.

It can, therefore, be a fire and explosion hazard if stored or used incorrectly.

Vapor/air mixtures arising from leakages may be ignited some distance from the

point of escape and the flame can travel back to the source of the leak.

Page 17: Contentsenvironmentclearance.nic.in/writereaddata/Online/TOR/19_Jun_2017... · Contents 1.0 EXECUTIVE ... IOCL is having about 129 POL Depot/Terminals, ... The latest version of OISD

17

At very high concentrations when mixed with air, vapor is an anesthetic and

subsequently an asphyxiant by diluting the available oxygen.

A vessel that has contained LPG is nominally empty but may still contain LPG

vapor and be potentially dangerous. Therefore treat all LPG vessels as if they were

full.

However, in case of non existence of any source of fire there will be no occurrence

of hazardous event and the cloud may get diluted to such a level that the mixture is

no longer explosive.

IMPORTANT PROPERTIES OF LIQUIFIED PETROLEUM GAS (LPG)

Sr. No. Property Remark

1. Appearance and Odour Colorless and odorless gas when

pure. Normally marketed with

mercaptan odouring agent.

2. Composition Mixture of commercial propane,

butane and unsaturated

hydrocarbons.

3. Liquid Density 500 to 580 kg/m3 at 15 deg. C

depending on composition.

4. Vapor Density 1.5 To 2.0 times heavier than air.

5. Boiling Point - 50 to -0.5 deg. C.

6. Flammability Limits in Air LFL - 1.9% V/V.

UFL - 9.5% V/V.

7. Permissible Exposure Limit-

OSHA Standard

1000 ppm (1800 mg/m3 )

Different types of combustion reactions associated in case of release of LPG from

the containment are listed in the following sections.

Page 18: Contentsenvironmentclearance.nic.in/writereaddata/Online/TOR/19_Jun_2017... · Contents 1.0 EXECUTIVE ... IOCL is having about 129 POL Depot/Terminals, ... The latest version of OISD

18

Escaping jet of LPG from pressure vessels / piping, if ignited, causes a Jet flame.

The jet flame direction and tilt depend on prevailing leakage direction and

velocity. Damage, in case of such type of jet fires, is restricted within plant

boundary. However in case of mounded vessel there will be no question of such

occasion.

There are two more situations of LPG fire. One is Boiling Liquid Expanding

vapour explosion (BLEVE) and unconfined Vapor cloud explosion (UVCE).

BLEVE is not possible in mounded bullet. However, in second case, plants having

a layout as per OISD recommendation, maintaining of safe operating Practice and

other precautionary measures, the above event can be avoided.

SAFETY PHILOSOPHY

LPG is a common material used extensively in households as well as industry. If

its characteristics are understood well and proper precautions as stipulated in

various codes and standards are followed, it is an easy and safe material to handle.

Accordingly, in most of the developed / developing countries, where LPG is

consumed in million tons / year, specific codes and standards are available for

storing and handling of LPG.

LPG INSTALLATIONS - CODES & STANDARDS

Codes and standards which are generally followed for LPG installations are as

follows:

1. NFPA (National Fire Protection Association of USA) Standards

- NFPA-58: Standard for the Storage and Handling of Liquefied

Petroleum Gases

- NFPA-59: LP-Gases at Utility Gas Plants

2. API (American Petroleum Institute) Standards

- API-2510: Design & Construction of LPG installations

3. IP (Institute of Petroleum) Standards.

- IP-9: Liquefied Petroleum Gas - Large Bulk Storage of Pressurized

and Refrigerated LPG

Page 19: Contentsenvironmentclearance.nic.in/writereaddata/Online/TOR/19_Jun_2017... · Contents 1.0 EXECUTIVE ... IOCL is having about 129 POL Depot/Terminals, ... The latest version of OISD

19

4. The Static and Mobile Pressure Vessels (Unfired) Rules, 1981 of India

(SMPV Rules)

5. OISD (Oil Industry Safety Directorate) Guidelines

- OISD RP-158: Recommended Practices on Storage and Handling of Bulk

Liquefied Petroleum Gas (LPG), 1997. (This is being followed by Public

Sector Refineries and Oil Industry in India. It is currently a guide and not a

mandatory code or standard).

LPG storage tanks like any other pressurized vessels may be designed as per any

of the following well known international or local codes / standards:

- ASME, Section VIII, Division I

- ASME, Section VIII, Division II

PROCESS FLOW CHART OF LPG BOTTLING PLANT AT FARUKHABAD

Page 20: Contentsenvironmentclearance.nic.in/writereaddata/Online/TOR/19_Jun_2017... · Contents 1.0 EXECUTIVE ... IOCL is having about 129 POL Depot/Terminals, ... The latest version of OISD

20

3.5 Water, Energy/Power requirement

The water requirement is fulfill by existing 3nos of tube well of capacity 25m3/hr

within plant premises. Water is to be used during construction and operation

phases. During operation water consumption will be 9.0 KLD for domestic.

Water Requirement & Wastewater Generation

S.No Domestic

water

Industrial Water requirement(KLD)

Domestic sewage

generation

Waste water from

process/ cylinder washing

1 6.0 3.0 4.8 1.6 Total 9.0 6.4

Note: Mock Drills -15KL/6Months

Power Requirement:

The total contracted demand 270 KW connected load is 410 KW and will be

supplied by Uttar pradesh State Electricity board. 1x 500 KVA DG for operation

and 2 x 250 KVA DG for lighting purpose will be maintained as power back up.

3.6 Schematic Representative of feasibility drawing which give

information of EIA Purpose

The EIA study covered an area of 10km radius from proposed project site for

assessing the baseline Environmental conditions. The details of Baseline Data

collection is given below:

Primary Baseline Data

S.No Environmental Attributes

Duration and frequency of sampling and other remarks

1 Meteorology Data Meteorology data was collected on an hourly/3hourly

basis for 1 / 3 months.

2 Ambient Air Quality Twice in a week for 24 hours; for 3 months

3 Ambient Noise Levels Once in the study period

4 Surface Water Quality Monthly Once

5 Ground Water Quality Monthly Once

Page 21: Contentsenvironmentclearance.nic.in/writereaddata/Online/TOR/19_Jun_2017... · Contents 1.0 EXECUTIVE ... IOCL is having about 129 POL Depot/Terminals, ... The latest version of OISD

21

6 Soil Quality Once during the study period

7 Terrestrial Ecology Once during the study period

8 Socio-economic Studies Primary and secondary data were collected from the

villagers living within 10 km radius during the study

period.

The number of sampling locations will be finalized based on TOR issued by SEIAA.

Secondary Baseline Data

S.No Environmental Attributes Source of Data Collection

1 One season meteorological data Indian Meteorological Department

2 Cyclone data IMD

3 Geology, geomorphology and

hydrogeology

Geology – Geological Survey of India

(GSI), Government of India (GoI)

4 Land use Through Satellite imageries from NRSA

5 Forest area Department of Forest

6 Physical features Survey of India topo sheets

7 Socio-economic Census of India.

There will be no impact on the environment due to proposed activity as the

proposed activity is bottling of LPG only.

Page 22: Contentsenvironmentclearance.nic.in/writereaddata/Online/TOR/19_Jun_2017... · Contents 1.0 EXECUTIVE ... IOCL is having about 129 POL Depot/Terminals, ... The latest version of OISD

22

4.0 Site Analysis

4.1 Connectivity

Plant is well connected by black top road. The nearest railway station is Fatehgarh

Railway station at a distance of 13.0 km from plant.

4.2 Land Form, Land Use& Land ownership

The proposed expansion project will be within the existing premises of 32.9Acrs of

land and acquired vide Ref No- 12A/92-93/DLRC 12th June.1993

4.3 Topography:

The district lies on a plain, varied only by a few gentle undulations and slopes,

sometimes abrupt, which lead down to the river valleys. The highest recorded

elevation is 167 m above sea level at Mohammadabad and the lowest 145.69 m at

Mau Rasulpur in the Trans Ganges flats of Tehsil Farrukhabad.

4.4 Existing Land Use Pattern

Present land use based on remote sensing satellite imageries were collected from

NRSA Bhuvan and interpreted for the district. However, in preparation EIA 10

KM radius of the project site LU/LC will be made using latest satellite imaginary.

S.no Land use Area (Ha)

Built-up land

1 Rural 101.17

2 Urban 26.92

Forest

3 Deciduous 0.62

Agricultural Land

4 Fallow 97.84

5 Crop land 1731.53

6 Plantation 35.74

Page 23: Contentsenvironmentclearance.nic.in/writereaddata/Online/TOR/19_Jun_2017... · Contents 1.0 EXECUTIVE ... IOCL is having about 129 POL Depot/Terminals, ... The latest version of OISD

23

Waste Land

7 Salt affected land 48.71

8 Scrub land 30.39

Water Body

10 Inland wetland 7.11

11 River/stream/canals 93.10

12 Water bodies 1.47

Total 2174.6

4.5 Existing Infrastructure Open area. 4.6 Soil Classification

Saline and alkaline soils occur in the district. Soils with salt content exceeding

0.2% are considered to be high salt soils and this concentration is injurious for

plant growth.

4.7 Climatic Conditions:

The summer is hot and dry with maximum daily temperature ranging between

38°C to 43°C. The humidity during this season is lowest ranging between 30% to

53% at 08.30 hrs and 18% to 42% at 17.30 hrs. Summer seasons ends by May and

transition period starts. The rainy season commences by late June when south

western monsoon sets in over the State. The humidity gradually increases and

reaches above 80%. August is the peak rainy season. The bulk of annual rainfall

about 85% occurs during monsoon period (June to September). The monsoon

starts retreating from the State in late September or early October. Then

commences another transitional period followed by winter from late November till

February. January is the coldest month of the period. Another transitional period

follows between winter and summer.

Page 24: Contentsenvironmentclearance.nic.in/writereaddata/Online/TOR/19_Jun_2017... · Contents 1.0 EXECUTIVE ... IOCL is having about 129 POL Depot/Terminals, ... The latest version of OISD

24

4.8 Social infrastructure Available:

Some of the prominent ones:

1. Mount Litera Zee School -4.92km

2. Central Jail at 10.15kms

3. Radha Soami Stasang Beas -5.0Km

5.0 Planning brief

5.1 Planning concept

IOCL Plan for the following:

Brief Description of facilities No of Bullets 2 x 900 MT Bottling capacity 60TMTPA

5.2 Population projection

The proposed project does not envisage any displacement or population and no

resettlement of population as proposed facility as the plot is within industrial focal

point. Hence there is no impact on this account.

5.3 Land Use Planning

The total area of the plant is 32.9 Ac.

5.4 Assessment of infrastructure Demand

Infrastructure required for the proposed storage will be constructed. The

development shall only lead to positive impact on infrastructure and services.

6.0 Proposed infrastructures

6.1 Industrial Area (Processing Area)

Proposed infrastructure will construct at Gaisinghpur, Farrukhabad, Uttar pradesh.

6.2 Residential Area (Non Processing Area)

IOCL is not proposing to construct any residential facility for proposed project at

the site

Page 25: Contentsenvironmentclearance.nic.in/writereaddata/Online/TOR/19_Jun_2017... · Contents 1.0 EXECUTIVE ... IOCL is having about 129 POL Depot/Terminals, ... The latest version of OISD

25

6.3 Green Belt

Around 12.0acres will be developed for green belt

6.4 Social Infrastructure

The proposed site is well connected with road network to village and Mandal

head quarters.

6.5 Connectivity

The proposed site is well connected with black top roads.

6.6 Drinking Water

Drinking water will be met from existing tube wells

6.7 Sewage

The maximum water consumption will be 9.0 KLD of which 6.4KLD will be

waste water generated and is treated using septic tank followed by soak pit.

6.8 Industrial Waste Management

In the proposed LPG Bottling plant, there is no generation of Solid/Liquid waste.

LPG will be stored in mounded vessel. Only waste like paper which can be

recycled, terminal sweepings & viz. and hazardous waste, used batteries and used

lubricating oil & STP sludge in minute quantities which can be disposed to

authorized agencies.

6.9 Power requirement

It will met through Uttar Pradesh state.

Page 26: Contentsenvironmentclearance.nic.in/writereaddata/Online/TOR/19_Jun_2017... · Contents 1.0 EXECUTIVE ... IOCL is having about 129 POL Depot/Terminals, ... The latest version of OISD

26

7.0 Rehabilitation and Resettlement (R & R) Plan

The proposed facility does not envisage any displacement of population and no

resettlement of population as the plot is within industrial focal point. Hence there

is no impact on this account.

8.0 Project Scheduled and Project Cost.

The total cost of the Project is Rs.26.43 crores which is scheduled to be completed

in twenty four months from the date of EC from UPSCB and other allied

clearance.

9.0 Analysis of Proposal (Final Recommendations)

There will be creation of indirect employment opportunities to the local people due

to construction of LPG Bottling Plant. There are no tribal people in the proposed

area.

Page 27: Contentsenvironmentclearance.nic.in/writereaddata/Online/TOR/19_Jun_2017... · Contents 1.0 EXECUTIVE ... IOCL is having about 129 POL Depot/Terminals, ... The latest version of OISD

27

PRE-FEASIBILITY REPORT

FOR

INDIAN OIL CORPORATION LTD (ADDITIONAL STORAGE OF LPG)

AT KHASARA NOS: 704, 705, 706, 707, 708, 709/1, 710/1, 714, 715, 818, 822, 832

GAISINGH PUR (V),

FARRUKHABAD TEHSIL, FARRUKHABAD (D),

UTTAR PRADESH STATE

Submitted by

M/s. SV ENVIRO LABS & CONSULTANTS ENVIRO HOUSE, BLOCK-B, B-1, IDA, AUTONAGAR,

VISAKHAPATNAM (Dt), ANDHRA PRADESH QCI No: 140, MoEF& NABL Recognized Laboratory