Memorandum

CITY OF DALLASDATE

January5, 2012 Trinity River Corridor Project Committee Members: Vonciel Jones Hill (Chair) Linda Koop (Vice Chair), Monica Alonzo, Scott Griggs, Angela Hunt, and Delia Jasso

TO

SUBJECT

Continental Bridge & West Dallas GatewayAt the next Trinity River Corridor Project Council Committee Meeting on Monday, January 9, 2012, the attached briefing will be presented by David Whitley. This briefing will provide an overview and update on the West Dallas Gateway and Continental Bridge Conversion projects. Please contact me if you have questions.

Jill A. Jordan, P.E. Assistant City Manager

TRE TRINITYDALLAS

Attachment cc: Honorable Mayor and Members of the City Council Mary K. Suhm, City Manager A. C. Gonzalez, First Assistant City Manager Ryan S. Evans, Assistant City Manager Forest E. Turner, Assistant City Manager Joey Zapata, Assistant City Manager Kelly High, Director, Trinity Watershed Management Rebecca Rasor, P.E., Managing Director, Trinity River Corridor Project Paul D. Dyer, Director, Park and Recreation Theresa ODonnell, Director, Sustainable Development & Construction Stephanie Cooper, Assistant to the City Manager Council

Dallas. the City that works: diverse, vibrant, and progressive

CONTINENTAL BRIDGE & WEST DALLAS GATEWAY trinity river corridor project committee 01.09.12dallas citydesign studio 1

Provide an overview of all of the projects affiliated with the Continental Bridge conversion Review anticipated schedule and budget Outline additional next steps

purposedallas citydesign studio 2

2006 Bond Program included $1.9 million for Continental Bridge and $1.8 million for the West Dallas Gateway $8 million in additional funds donated for the Continental Bridge Project Planning efforts with the community by the dallas citydesign studio defined the program for the West Dallas Gateway project to connect West Dallas to the Continental Bridge

backgrounddallas citydesign studio 3

ContinentalBridge

WRT

dallas citydesign studio

4

WRT

dallas citydesign studio

5

WRT

dallas citydesign studio

6

FLOWER GATEWAY Trefoil shade structures with vines & seating Vending areas

150.

WRT

dallas citydesign studio

7

WRT

dallas citydesign studio

8

WRT

dallas citydesign studio

9

PLAY AREA Shade Trees Seating Bocce Court Chess Panel Climbing Blocks Sidewalk Games

(POTENTIAL INTERIM,USE)

150

300

WRT

dallas citydesign studio

10

WRT

dallas citydesign studio

11

WRT

dallas citydesign studio

12

WRT

dallas citydesign studio

13

FOUNTAIN/ MIST PLAZA Programmable Mist and Water Jets Seating Area Cooling Fog Poles

150

300

150

WRT

dallas citydesign studio

14

ISLAND GARDENS Shade trees Planters Hanging vines Seating

150

300

150

180

WRT

dallas citydesign studio

15

WRTdallas citydesign studio 16

WRTdallas citydesign studio 17

MEDITATION PLAZA Labyrinth

150

300

150

180

230

WRT

dallas citydesign studio

18

WRT

dallas citydesign studio

19

EVENT PLAZA Shade trees Planters Seating Electrical supply

150

300

150

180

230

640

WRT

dallas citydesign studio

20

WRTdallas citydesign studio 21

WRT example style of light fixturedallas citydesign studio 22

WRT

dallas citydesign studio

23

landscaping to include 9 trees and shrubs area for parallel parking

staircase

limits of construction on eastern end of project removable bollards no change proposed to street configuration

PEDESTRIAN ZONE

SPECIAL EVENT CONTROL POINT

ST

WRT

dallas citydesign studio

RIVERFRONT BLVD 24

NORMAL CONTROL POINT

CO NT INE NT AL

landscaping to include 9 trees and shrubs area available for special event parking

staircase

removable bollards

Section through the eastern end of Continental looking toward Riverfront Blvd

WRT

dallas citydesign studio

25

WesternGateway

dallas citydesign studio

26

levee top

canada drive

continental pedestrian bridge

singleton avenue

margaret hunt hill bridge

TxDOT reconfigured intersectiondallas citydesign studio 27

provide neighborhood access to the park and Continental Bridge

provide much-needed vehicular parking

create a plaza/gathering space

provide a strong bicycle & pedestrian connection from the bridge/plaza to adjacent development opportunities

provide for occasional vehicular access to the Continental Bridge for emergency and service vehicles

utility station/additional median enhancements as a future design opportunity for the gateway

early community planning to define the projects programdallas citydesign studio 28

N. Beckley

FUTURE IMPROVEMENTS

t.

Sin g

Gu lde nS

let on

Blv d.

WRT

current proposed designdallas citydesign studio 29

WRT

dallas citydesign studio

30

WRT

dallas citydesign studio

31

SEAT WALL (SPECIAL FEATURE)

N. Beckley

t.

Sin g

Gu lde nS

let on

Blv d.

WRT

pedestrian connectivitydallas citydesign studio 32

WRT

dallas citydesign studio

33

N. Beckley

Potential future DART bus stop

t.

Sin g

Gu lde nS

let on

Blv d.

WRT

bike connectivitydallas citydesign studio 34

EMERGENCY ACCESS

N. Beckley

t.

Sin g

Gu lde nS

let on

Blv d.

WRT

vehicular connectivitydallas citydesign studio 35

N. Beckley

FUTURE CONCESSIONS & RESTROOM

t.

Sin g

Gu lde nS

let on

Blv d.

WRT

dallas citydesign studio

36

N. Beckley

PICNIC AREA

t.

Sin g

Gu lde nS

let on

Blv d.

WRT

dallas citydesign studio

37

N. Beckley

POTENTAIL AREA FOR FUTURE STREET FAIR/ MARKET TENTS

t.

Sin g

Gu lde nS

let on

Blv d.

WRT

dallas citydesign studio

38

N. Beckley

POTENTIAL AREA FOR FUTURE STAGE / FESTIVAL TENT

t.

Sin g

Gu lde nS

let on

Blv d.

WRT

dallas citydesign studio

39

Project Budget:Continental Bridge: $9.9 million Inclusive of design/ engineering and construction West Dallas Gateway: $1.8 million Inclusive of design/ engineering and construction Total Budget: $11.7 million Available Funding: $11.7 million

Project Schedule:Bid Documents Design underway Bid Advertisement March 2012 Thoroughfare Plan Amendments March 2012 Bid Award April 2012 Construction Duration 16 months Project Opening August 2013

Project Awards for Continental Bridge:2011 Dream Award from the Greater Dallas Planning Council

anticipated schedule and budgetdallas citydesign studio 40

Delete Canada Drive from Singleton to Gulden from the Thoroughfare Plan, if necessary

Delete Continental Avenue from Singleton to Riverfront from the Thoroughfare Plan

N. Beckley

Change BeckleyCanada Connection to North Beckley Avenue

t.

Sin g

Gu lde nS

let on

Blv d.

WRT

thoroughfare plan amendmentsdallas citydesign studio 41

1| CPCTransportationCommittee February2,2012 2| CityPlanCommission February16,2012 3| CityCouncil March28,2012

next steps: thoroughfare plan amendment processdallas citydesign studio 42

WRT