BACKGROUND INFORMATION
• Average rainfall in Rawalpindi/Islamabad duringmonsoon season ranges between 400 to600mm.
• Major catchments area of Lai Nullah falls in theFederal capital Islamabad.
• Rainwater of southern side of Margala Hillsflows downstream through various streamswhich enter into Nullah Lai at IJ Principal Road.
• Besides, flow from Islamabad area, 11 maindrains of Rawalpindi City also discharge intoNullah Lai.
CATCHMENT AREA OF NULLAH LAI AND ITS TRIBUTARIES
Nullah Lai
Islamabad Rawal Lake
Korang River
Islamabad Highway
Saidpur kasTenawali kas
Bedarawali
kas
Name of the ProjectLai Nullah Protection and its
Dredging /
desilting Work (Phase-I)
Funds released for 2016-17 Rs.25.00 Million.
Activities of work (i).De-Silting/Cleaning of vulnerable
points of Nullah Lai.
(ii). Cleaning of mouths of
intercepting storm water drains/
Nullahs into Nullah Lai.
(iii). Dredging/De-Silting of Nullah
Lai