contract change management

50
1 CONTRACT CHANGE MANAGEMENT Mark Adams PE Facility Services Supervisor Nov. 5, 2014

Upload: trinhquynh

Post on 04-Jan-2017

232 views

Category:

Documents


3 download

TRANSCRIPT

1

CONTRACT CHANGE MANAGEMENT

Mark Adams PEFacility Services SupervisorNov. 5, 2014

2

Fight

3

Bigger Fight

4

Paperwork

5

Confusion

6

Stress and Frustration

7

Where to Go

8

What to Do

9

10

Meet the Experts

11

-Jim Dreier – Contract Administrator (CA) Facility [email protected] 303-342-2674

-Annette Kimble – Contract Administrator (CA) Infrastructure [email protected] 303-342-4681

-Neal Swift – Project Controls Estimator – AIM [email protected] 303-342-4550

-David Mashburn – Director of Facility Services – AIM [email protected] 303-342-2610

-Glenn Frieler – Director of Infrastructure Management – AIM [email protected] 303-342-2933

-Jen Stein – Project Controls Scheduler – AIM Development [email protected] 303-342-2324

-Mark H Adams – Manager of Facility Services – AIM [email protected] 303-342-2762

Meet The Experts

12

Alphabet Soup

RFI – Request for Information

CN – Change Notice

CCR – Contractor Change Request

COD – Change Order Directive

TCOD – Task Change Order Directive

CO – Change Order

TCO – Task Change Order

BMS – Business Management Services

Unifier – New DIA Project Management Software produced by

Oracle (Primavera)

13

Common Contract Types

− Unit Cost− Hard Bid− On-Call Task Order− Mainly used with our Civil Infrastructure Projects

− Lump Sum− Hard Bid− On-Call Task Order− Negotiated/Best Value/Design Build− Mainly used with our Building/Facility Projects

14

How does a Change get Started?

− RFI’s− Design Initiated Change (CR)− Owner Initiated Change (CR or CN)− Contractor Initiated Change (CCR)− Deficiency or NCR

How Does a Change Order Get Issued?

− Change Notice (CN)− Change Order Directive (COD)

15

16

CHANGE MANAGEMENT

Annette Kimble & Jim DreierContract AdministratorsNov. 5, 2014

17

18

19

20

21

22

23

24

25

NEGOTIATION REQUIREMENTS

Neal SwiftProject Controls - EstimatorNov. 5, 2014

- Change Order Submission and Pricing Requests– Explain concisely, accurately and with appropriate detail

– Why added scope and / or time is required

– Include pictures to illustrate issues difficult to explain

– How or what caused potential change

– Provide basis for determination of time required and other

constraints that may include additional cost and time

– Understand that reviewer will already have comprehensive

knowledge of your contracted scope of work and be familiar

with project - outline major points26

– Negotiation Meetings

– When level of complexity requires face-to-face meeting

– Come prepared with logs, reports, project docs, photographs

– Receipts and invoices for materials and equipment

– Cost of labor to be fair and reasonable, verified with LMT

– General Info

– Follow contract & general condition before starting added work

– Weather – understand what is considered Adverse Weather

– Mark-up’s, Staff & OH costs and pass-thru costs27

28

What’s the difference between a Change Order Directive (COD) and a Change Order (CO)?

− Change Order Directive (COD)− Directs the contractor to

immediately proceed with the work

− Only used when time does not allow the standard Change Notice (CN) process to be used

− 90% of DIA’s Cost Estimate or T&M with a Not-To-Exceed (NTE)

− A change order (CO) will be issued when final amounts are agreed to

− Change Order (CO)− Proposed work is negotiated

first and then completed− Final amounts to be agreed to

in negotiations− Only mechanism to completely

revise contract terms, dollars or durations

− References Change Notices (CN) and Change Order Directives (COD)

COD vs. CO

29

30

31

32

33

34

35

REDUCING AND AVOIDING CHANGE ORDERS

Glenn FrielerDirector of Infrastructure and QANov. 5, 2014

Change Orders

36

Misinterpretation of the Plans

37

Unclear Plans and Specifications

38

Working at an Airport

39

Things DIA is Doing to Limit Change Orders

40

- Work on improving the quality of our plans

- Involving contractors during the design process

- Limiting additional work that is added to a contract

- Working with the contractor when a change condition occurs

- Using “Common Sense” as we interpret our specifications

- Set realistic timelines for the completion of our projects

Change Condition

41

Plan Error

42

Missing Items

43

Working Together

44

45

REDUCING AND AVOIDING CHANGE ORDERS

David MashburnDirector of Facility ServicesNov. 5, 2014

46

Avoiding Change Orders

The best defense is a good offense

One of our Key Performance Indicators (KPI) is to be below 15% on change orders now. In the future, we want to be below 5%. Currently, on all our projects we are at 4%. Going to BIM and a stronger plan review process will reduce further.

47

Reviewing models with designers leads to stronger coordination. With BIM, the plans are prints of the model, with eSpec, the keynotes in the plans are tied to the specifications.

Plan and Model Review Process

Contractors review models with sub-contractors because it is more cost effective to virtually build first.

48

Reviewing plans with more people in less time.

A 2015 KPI is: turning around plan reviews in under 17 days.

Plan Review Process

49

Improved Planning for projects allows more time for project teams and reviews = reduced changes due to rushing emergency projects

Project Planning Process

50

REDUCING AND AVOIDING CHANGE ORDERS

David MashburnDirector of Facility ServicesNov. 5, 2014