contract closeout, reporting and documentation system

Upload: maro

Post on 17-Feb-2018

235 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/23/2019 Contract Closeout, Reporting and Documentation system

    1/29

    CONTRACT CLOSEOUT/

    REPORTING/DOCUMENTATIONSYSTEM

    Construction Method and Management

  • 7/23/2019 Contract Closeout, Reporting and Documentation system

    2/29

    ...Construction Phase CM tasks

    ProjectdocumentationRequirements

    ProjectDocumentation

    System

    Prepare anAgenda

    and Meeting

    Transfer ofOwner-purchased

    material

    MonitorContrator'sprogress

    Communicationand

    Exchange ofinformation

    Daily reportingsystem#4. Slide

    4Administer QA

    Review safetyplan

    Resolve Changes

    Issue *CO reportMonitor Cost

    recordEstablish Cash

    Flow report

    Establish a systemTo control Contractor's

    paymentEstablish report

    PrepareSummary

    To the Owner

    Receive andEvaluate notices

    Review drawingsBefore approving

    Final payment

    Reporting System

  • 7/23/2019 Contract Closeout, Reporting and Documentation system

    3/29

    ...Post Construction Phase CM tasks

    compilation,organization andturnover of thesematerials

    Final Inspectionswith the ownerand designer

    expeditecompletion of the

    Contractorssubmittals

    should providethe owner with alist of contacts forremaining work

    , summarizing theproject history

    at the ownersrequest, the CMshould assist inmove-in/start up.

    the acquisition ofand compliance

    of all permitrequirements

    requirements forspare parts and

    warranties.

    Contract closeout

  • 7/23/2019 Contract Closeout, Reporting and Documentation system

    4/29

    ...reporting systemDaily Construction Report

    Report numberDate and day reportProject name and numberWeather conditionsName of contractor whose workwas specifically involvedWorkforceDescribe all works in progressProblems and difficulties

    encounteredCompleted form should be signed

    and dated.

    PMArea superintendentProject engineersinspectors

    Identify the number and classification of allcraft labor at the site for each contractor

    Identify the number and type of major constructionequipment on the job. Specifically note if equipmentwas idle or active.

    Items requiring supervisory attentionshould be attended to promptlyandsonoted on the original inspectionreportModifications to original reportshould be notedand initiated bysupervisor at a time of reviewOne copy of each report should besent off site for safe storage.Information contained in the dailyreports should be summarized as

    appropriate to form the basis of anyweekly or monthly reporting that isrequired.

  • 7/23/2019 Contract Closeout, Reporting and Documentation system

    5/29

    Monthly Change Order report

    Date of discovery, notification of the problem

    Brief description of the issue

    Potential changes should be assigned areference number

    Construction managers evaluation of theissue

    Construction manager estimate of time, cost,or both requires for equitable compensation.

    Any time cost adjustments requested orproposed by the contractor.

    Agreed upon compensation Date of resolution

    Change order reference number.

  • 7/23/2019 Contract Closeout, Reporting and Documentation system

    6/29

    . Monitor and maintain cost records

    establishing a system for segregating and documenting

    forced account work resources.

  • 7/23/2019 Contract Closeout, Reporting and Documentation system

    7/29

    establish cash flow reporting system

    develop a cash flow monitoring system and integrateit into the progress payments tracking system.

    The ff. methods are commonly utilized: Unit price schedule Schedule of values Cost- loaded CPM schedule Cost reimbursible

    Based upon the actual amount of work performedthrough the period of payment request.

  • 7/23/2019 Contract Closeout, Reporting and Documentation system

    8/29

    establish report formats for submissions to the owner ona weekly, monthly or quarterly basis, depending upon theindividual project requirements.

    Typical report includes:construction schedulesummary project costcash flowchange order (pending and approved)

  • 7/23/2019 Contract Closeout, Reporting and Documentation system

    9/29

    Prepare narrative to the owner

    pointing out impacts, exceptions and revisions to the management plan.

    including:monthly report incl. problemimpactchangesdelaysplan approach in solving the effect of ff. mentioned above.

  • 7/23/2019 Contract Closeout, Reporting and Documentation system

    10/29

    ...Documentation System

    Capable of:

    RecordingStoringRetrieving information

    TechnicalFinancialadministrative

  • 7/23/2019 Contract Closeout, Reporting and Documentation system

    11/29

    Required Project Documentation

    - is imperative for the following reasons:

    - integral part of all construction managementactivities. Project records should be:

    Project- subject of LENGTHY claims and LITIGATION.

    Actual record- can beinvaluable when negotiating and Evaluating

    Contractors request for compensation.

    Written recordcan be valuable.

    made CONTEMPORANEOUSLYwith the event

    Based upon direct knowledge of the event.

    Keep as a regular practice of the firm.

    Contain adequate detail to allow reconstruction of the situation from therecords at a later date.

  • 7/23/2019 Contract Closeout, Reporting and Documentation system

    12/29

    Recording Construction Activities Use still photographic images and narrated video camera recording to enhance all written documentationfrom preexisting site conditions to final inspections. The Construction Field Inspection Log (see Figure 4.21) or other line management approvedform should provide a documented factual record of the work performed each day, as well asAll changesthat might affect cost and schedule.Major project status changes.All directions or clarifications.Personnel accidents or injuries, safety infractions, and corrections.Safety meetings held on site.Names of visitors to the site.Conditions and actions in response to Subcontractor violations.Potentially reportable occurrences in accordance with the occurrence reporting process.Significant events, such as unexpected power outages, severe weather occurrences, or spills ofhazardous materials (residual radioactive material, hazardous waste, hazardous substance).Construction inspections and quality control tests performed. Include time of tests and inspectionsand results.Implementation of the applicable emergency plan.Security incidents.Applicable equipment parameters, including out-of-tolerance readings.Non-conformance reports.Signatures that acknowledge notifications or changes in construction activities.Positive actions that resulted in significant savings, quality improvements, lessons learned, etc.Hours worked.Equipment on-site and used.Weather.

    http://localhost/var/www/apps/conversion/tmp/scratch_2/construction_documentation.pdfhttp://localhost/var/www/apps/conversion/tmp/scratch_2/construction_documentation.pdfhttp://localhost/var/www/apps/conversion/tmp/scratch_2/construction_documentation.pdfhttp://localhost/var/www/apps/conversion/tmp/scratch_2/construction_documentation.pdfhttp://localhost/var/www/apps/conversion/tmp/scratch_2/construction_documentation.pdfhttp://localhost/var/www/apps/conversion/tmp/scratch_2/construction_documentation.pdf
  • 7/23/2019 Contract Closeout, Reporting and Documentation system

    13/29

    Typical information that must be handled by a project documentation system:

    Pre- Contract Documents Contract Documents Technical Contemporaneous Correspondence Scheduling Cost

    1. Bid package drawings and specifications2. Pre-bid Meeting minutes3. Pre-bid schedules4. cost estimate and takeoffs (designPhase)5. contractor's bid proposal6. bidder prequalification information7. technical proposal8. bid analysis

    1. original contract2. bonds and assurance certificates3. pre-contract negotiation4. plans and specifications issued for contruction5. notice to proceed.

    6. any notices or changed conditions, request for *CO,or *CO proposals7.directives8. log of all requested, proposed and executed *CO.9. formal contract.10. request for final inspection.11. punch lists.12. certificate of final inspection.

    *change order

  • 7/23/2019 Contract Closeout, Reporting and Documentation system

    14/29

    Typical information that must be handled by a project documentation system:

    Pre- Contract Documents Contract Documents Technical Contemporaneous Correspondence Scheduling Cost

    1. log and file of all design and fieldrevisions

    2. log and file of all request for information.3. log and file of all shop drawings4. inspection/ testing/ QC report.5. record drawings.6. operation and maintenance manuals7.warranties and guarantees.

    1. daily reports2. daily diaries3. daily labour reports4. accident reports5. progress photos6.material deliveryreports

    1. directives2. meeting minutes

    3. generalcorrespondence

  • 7/23/2019 Contract Closeout, Reporting and Documentation system

    15/29

    Typical information that must be handled by a project documentation system:

    Pre- Contract Documents Contract Documents Technical Contemporaneous Correspondence Scheduling Cost

    1. Project/ program master schedule2. preliminary contractor schedule3. approved contractor baseline schedule

    4. periodic updates5. scheduling meeting minutes.

    1. approved schedule of values2. applicable labour rates3. work order time sheets4. bid analysis5. periodic labour distribution6. control budget.7. payment request and actual disbursementWith explanation of discrepancies.

  • 7/23/2019 Contract Closeout, Reporting and Documentation system

    16/29

    Contract Closeout

    By definition, projects have an end point. Closing out is a very importantphase in the project life cycle, which should follow particular disciplines and

    procedures with the objective of: Effectively bringing the project to closure according to agreed-on contractualrequirements Preparing for the transition of the projectinto the next operational phase,such as from production to field installation, field operation, or trainingAnalysing overall project performancewith regard to financial data,schedules, and technical efforts.

  • 7/23/2019 Contract Closeout, Reporting and Documentation system

    17/29

    Although most project managers are completely cognizant of thenecessity for proper planning for project start-up, many project managers

    neglect planning for project termination. Planning for project terminationincludes:

    Transferring responsibilityCompletion of project records

    Historic reports Post project analysis

  • 7/23/2019 Contract Closeout, Reporting and Documentation system

    18/29

    Documenting results to reflect "as built" product or

    installationAcceptanceby sponsor/user Satisfying contractual requirements Disposition of materials Closing out work orders (financial closeout) Preparing for financial payments

  • 7/23/2019 Contract Closeout, Reporting and Documentation system

    19/29

    Closeout Document:warranties/guaranteesCertifications

    maintenance manualscontractors' statements (tax forms)Targeted Small Business Reporting forms (if applicable), etc.

  • 7/23/2019 Contract Closeout, Reporting and Documentation system

    20/29

    the completion of the project identifying the sales taxand/or use tax paid on all supplies and materialsincorporated into the Work.

  • 7/23/2019 Contract Closeout, Reporting and Documentation system

    21/29

    coordinate the compilation, organization andturnover of these materials

    Post Construction Phase CM tasks

  • 7/23/2019 Contract Closeout, Reporting and Documentation system

    22/29

    coordinate the requirements for spareparts and warranties.

    Post Construction Phase CM tasks

  • 7/23/2019 Contract Closeout, Reporting and Documentation system

    23/29

    coordinate the acquisition of allrequirements permits and compliance of allpermit requirements

    Post Construction Phase CM tasks

  • 7/23/2019 Contract Closeout, Reporting and Documentation system

    24/29

    at the owners request, the CM shouldassist in move-in/start up.

    Post Construction Phase CM tasks

  • 7/23/2019 Contract Closeout, Reporting and Documentation system

    25/29

    conduct Final Inspections with the ownerand designer when the final punch list iscomplete. When the parties are satisfied that allwork is complete, the CM should recommendthat the final payment be made.

    Post Construction Phase CM tasks

  • 7/23/2019 Contract Closeout, Reporting and Documentation system

    26/29

    should expedite completion of theContractors submittals including certificate ofsubstantial completion, punch list completion,final lien viewers, guarantees/warranties andfinal payment application.

    Post Construction Phase CM tasks

  • 7/23/2019 Contract Closeout, Reporting and Documentation system

    27/29

    the CM may stay on to complete warranty

    work, but it is usually not cost effective.Therefore, the CM should provide the ownerwith a list of contacts for remaining work.

    Post Construction Phase CM tasks

  • 7/23/2019 Contract Closeout, Reporting and Documentation system

    28/29

    all reports that have been issued during thedesign and construction phase should be

    prepared in final form, summarizing the projecthistory including costs reports. The reportshould note the date of substantial completionand commencement of warranties.

    Post Construction Phase CM tasks

  • 7/23/2019 Contract Closeout, Reporting and Documentation system

    29/29

    CloseoutProcess

    It is important to note that the closeout of the construction contract or contracts onthe project is only one step in the closeout of the project.

    http://localhost/var/www/apps/conversion/tmp/scratch_2/Map%20-%20Contractor%20Closeout.pdfhttp://localhost/var/www/apps/conversion/tmp/scratch_2/Map%20-%20Contractor%20Closeout.pdfhttp://localhost/var/www/apps/conversion/tmp/scratch_2/Map%20-%20Contractor%20Closeout.pdf