  • 8/4/2019 Contract Conditions Analysis

    1/20

    Project:- Berth 9,10 & 11, MPSEZ

    CONTRACT CONDITIONS ANALYSIS,REDRAFTING AND COMPARISONS

    EFFORTS BY:NAGENDRA PATEL (UC-1707)ROSHAN PRAJAPATI (UC-2007)

  • 8/4/2019 Contract Conditions Analysis

    2/20

    Project Introduction

    Name of Project: - BERTH 9, 10 & 11, MPSEZ

    Name of Contractors: - SimplexInfrastructure Ltd.

    Type of Project: - Marine Project

    Type of Tender: - Item- Rate Tender

    Civil cost of Project: - 280 Crores Contract Period: - 18 months [471 days]

  • 8/4/2019 Contract Conditions Analysis

    3/20

    Project Introduction

    Maintenance Guarantee Period: - 5 years fromcompletion of Project

    Date of Award of Contract: - 23rd April 2010

    Starting date of construction: - 10th June 2010 Estimated completion date: - 10th December

    2011

    Total length of Berth:-771.2 mtr.

    Total width of Berth:-37.65 mtr.

    Area developed for back up yard: - 86080 sq.m

  • 8/4/2019 Contract Conditions Analysis

    4/20

    CONDITION-IRisk and Responsibility

  • 8/4/2019 Contract Conditions Analysis

    5/20

    CONDITION-I

    ORIGINAL CLAUSEThe subcontractor agrees to indemnify and holdharmless the contractor against loss or threatened loss orexpense by reason of the liability or potential liability of

    the contractor for or arising out of any claims fordamages.

    AMBIGUITY

    An indemnity clause requires that one party indemnifythe other, in the event that certain expenses are incurred.This clause can significantly increase the exposure in theextent of an unexpected event or breach of the contract.

  • 8/4/2019 Contract Conditions Analysis

    6/20

    CONDITION-I

    REDRAFTED CLAUSEThe subcontractorwill not agreeto indemnify and holdharmless the contractor against loss or threatened loss orexpense by reason of the liability or potential liability of

    the contractor for or arising out of any claims fordamages.

    AS PER FIDIC CONDITIONThe Contractor shall not subcontract the whole of theWorks. The Contractor shall be responsible for the actsor defaults of any Subcontractor, his agents oremployees, as if they were the acts or defaults of theContractor. It is not mentioned regarding theindemnification of the sub-contractor.

  • 8/4/2019 Contract Conditions Analysis

    7/20

    CONDITION-IICommunication

  • 8/4/2019 Contract Conditions Analysis

    8/20

    CONDITION-II

    ORIGINAL CLAUSEThe Contractor shall, unless it is legally or physicallyimpossible, execute and complete the works and remedydefects therein in strict accordance with the contract tothe satisfaction of the Engineer. The contractor shall comply

    and adhere to the Engineers instructions on any matter,whether mentioned in the contract or not, concerning theworks. The Contractor shall take instructions only from theEngineer (or his delegates).

    AMBIGUITYThe contractor may suffer a loss, if he has started the worknot specified in the contract only on the basis of oralinstructions of the engineer, and finally does not get approvalby the Employer.

  • 8/4/2019 Contract Conditions Analysis

    9/20

    CONDITION-II

    REDRAFTED CLAUSEThe Contractor shall, unless it is legally or physicallyimpossible, execute and complete the works and remedydefects therein in strict accordance with the contract tothe satisfaction of the Engineer. The contractor shall comply

    and adhere to the Engineers instructions on any matter,whether mentioned in the contract or not, concerning theworks. The Contractor shall take instructions only from theEngineer (or his delegates). In case of execution of anywork commenced only on oral instructions of the

    Engineer which is not specified in the contract, theContractor shall immediately start the work on the basisof the instructions and he shall get approval of theEmployer in written within 7 days.

    AS PER FIDIC CONDITION

    Not mentioned in FIDIC.

  • 8/4/2019 Contract Conditions Analysis

    10/20

    CONDITION-IIIDelegation by the Engineer

  • 8/4/2019 Contract Conditions Analysis

    11/20

    CONDITION-III

    ORIGINAL CLAUSEAll communications from Engineers Representative shallhave the same effect as though given by the Engineer.The Engineer shall however retain the authority to

    disapprove any work, materials or Plant in the event ofthe Engineers Representative failing to do so or revokethe decisions / instructions issued by the EngineersRepresentative.

    AMBIGUITY

    Engineer is not taking responsibility of the decisionstaken by Engineers representative.

  • 8/4/2019 Contract Conditions Analysis

    12/20

    CONDITION-III

    REDRAFTED CLAUSEAll communications from Engineers Representative (Delegated persons),to whom duties have been assigned or authority has been delegated; shallhave the same effect as though given by the Engineer. The Engineer shallhowever retain the authority to disapprove any work, materials or Plant inthe event of the Engineers Representative failing to do so.

    AS PER FIDIC CONDITION

    However also,

    1. Unless otherwise stated in the delegated persons communication relating tosuch act, it shall not relieve the Contractor from any responsibility he has underthe Contract, including responsibility for errors, omissions, discrepancies and

    non-compliances;2. Any failure to disapprove any work, Plant or Materials shall not constitute

    approval, and shall therefore not prejudice the right of the Employer to rejectthe work, Plant or Materials; and

    3. If the Contractor questions any determination or instruction of a delegatedperson, the Contractor may refer the matter to the Employer, who shallpromptly confirm, reverse or vary the determination or instruction.

  • 8/4/2019 Contract Conditions Analysis

    13/20

    CONDITION-IVRight of Access

  • 8/4/2019 Contract Conditions Analysis

    14/20

    CONDITION-IV

    ORIGINAL CLAUSEThe Contractor shall afford every facility for and everyassistance in obtaining the right to access for the Engineer orany of his representative at all reasonable times to the Site

    and to all workshops, places where materials or plant arebeing manufactured, fabricated or prepared.

    AMBIGUITY

    If the contractor is not manufacturing the materials or partsof the work which are being used, and he is using thematerials manufactured by some other manufacturers, it isnot stated that who will arrange for the permission to inspectthe manufacturing facility by the Engineer, if at all it is

    required.

  • 8/4/2019 Contract Conditions Analysis

    15/20

    CONDITION-IV

    REDRAFTED CLAUSEThe Contractor shall afford every facility for and every assistance inobtaining the right to access for the Engineer or any of his representativeat all reasonable times to the Site and to all workshops, places wherematerials or plant are being manufactured, fabricated or prepared. Ifmaterials, plant or parts of works are manufactured, fabricated or

    prepared in places not belonging to the Contractor, the Contractorshall organize necessary permissions from the owners of suchfacilities for the Engineer to inspect such places or plants wherematerials are manufactured, fabricated or prepared.

    AS PER FIDIC CONDITION

    The Contractor shall bear all costs and charges for special and/ortemporary rights-of-way which he may require, including those for accessto the Site. The Contractor shall also obtain, at his risk and cost, anyadditional facilities outside the Site which he may require for the purposesof the Works.

  • 8/4/2019 Contract Conditions Analysis

    16/20

    CONDITION-VInsurance

  • 8/4/2019 Contract Conditions Analysis

    17/20

    CONDITION-V

    ORIGINAL CLAUSEThe Contractor shall provide, in the joint names of theEmployer and the Contractor, insurance cover from theCommencement Date to the end of the Defects LiabilityPeriod, in the amounts and deductibles as stated below and

    the contract data, for the following.(a) Loss of or damage to the Works, Plant and Materials.

    (Minimum full replacement costs and additional 15% costs);(b) Loss of or damage to Contractors Equipment and other

    things at site (minimum full replacement costs).

    (c) Loss of or damage of property and personnel (other than theWorks, Plant, Materials and Equipment in connection withthe Contract); i.e. Third Party Insurance; and

    (d) Personal injury or death. (I.e. Workmen compensationpolicy)

  • 8/4/2019 Contract Conditions Analysis

    18/20

    CONDITION-V

    AMBIGUITYThe insurance cover up to the end of defect liabilityperiod is not required. After completion of the

    project to the defect liability period, no plan,machinery or equipments are involved; there is noneed of increasing the cost unnecessarily.

    There is not clear statement regarding the

    execution of work in the absence of proper insurancecover.

  • 8/4/2019 Contract Conditions Analysis

    19/20

    CONDITION-V

    REDRAFTED CLAUSEThe Contractor shall provide, in the joint names of the Employerand the Contractor, insurance cover from the CommencementDate to the end of the project, in the amounts and deductibles asstated below and the contract data, for the following.Wheneverdefects occur during the defect liability period additionalinsurance shall be taken for the period of repair work.

    (a) Loss of or damage to the Works, Plant and Materials. (Minimumfull replacement costs and additional 15% costs);

    (b) Loss of or damage to Contractors Equipment and other things atsite (minimum full replacement costs).

    (c) Loss of or damage of property and personnel (other than theWorks, Plant, Materials and Equipment in connection with theContract); i.e. Third Party Insurance; and

    (d) Personal injury or death. (i.e. Workmen compensation policy)

    AS PER FIDIC CONDITION

    It is as per the original clause. But, it is not mentioned regarding

  • 8/4/2019 Contract Conditions Analysis

    20/20