contract costing

16
CONTRACT COSTING

Upload: shubham-verma

Post on 15-Apr-2017

48 views

Category:

Education


0 download

TRANSCRIPT

Page 1: Contract costing

CONTRACT

COSTING

Page 2: Contract costing

COSTING

“The technique

and process of ascertaining costs.”

Contract

Costing

Batch Costin

g

Single Costin

g

Process

Costing

Job Costin

g

Operating

Costing

Multiple

Costing

Page 3: Contract costing

Contract Costing is defined by the ICMA Terminology as

CONTRACT COSTING

that form of costing

which applies where work is undertaken to customer’s special requirements

and each order is of long duration.

The work is usually of constructional nature.

Page 4: Contract costing

Each contract is treated as a cost unit. A separate account for each contract. Work is done at site, away from contractor’s own

premises. The contract has a long duration usually extending more

than one accounting year. All items of cost which are directly related to the contract

are chargeable to respective contract accounts. Payment is made by contractee on the basis of work

certified by surveyor or architect. Penalties or extra money may be imposed. Though contract costing is a part of Cost Accounting, but

it is purely based on the principles of Financial Accounting. Such as Dual Aspect, Prudence and Conservatism. And AS9 (Revenue Recognition)

FEATURES OF CONTRACT COSTING

Page 5: Contract costing

• Fixed Price is agreed• Deductions are made for Defectives and Penalties• Extra money for additional work

Fixed Price Contract

• compensates for costs actually incurred by contractor.• a percentage of cost or any lump sum amount.

Cost Plus Contract

• Mixture of both of the above.• A fixed price will increase with increase in cost of material,

labour.

Contract with Escalation Cost

TYPES OF CONTRACT (IN COSTING)

Page 6: Contract costing

Land Cost Site labour Cost Cost of material Depreciation on plant and equipments used at site Sub Contract Cost Cost of moving plant Cost of hiring Plant & Machinery Cost of design Maintenance Cost Guarantee & Warrantee Cost Penalties, etc.

COST ATTRIBUTABLE TO CONTRACT A/C

Page 7: Contract costing

× General Administrative Cost× Selling Cost× Research & Development Cost× Depreciation on ideal plant & equipment× Cost of unconsumed material× Advance payment to sub contractor× Cost of material which is delivered to site for

future× Profit/Loss on sale of any material/plant

COST NOT ATTRIBUTABLE TO CONTRACT A/C

Page 8: Contract costing

Can you Say how much work has been completed ???

Can you Say how much work has been completed ???

This is why an architect or surveyor is needed & invited and his certificate is obtained about how

much work has been completed.

New Building of Central Bank, Europe

Page 9: Contract costing

“Work Certified is that proportion of the work completed which has been certified or and valued by the architect or surveyor.”

Payment is made on the basis of Work Certified.

“Work Uncertified is that part of the work completed which has not been certified/approved by the contractee’s architect or surveyor.”

There is no role of Work Uncertified in payment.

WORK CERTIFIED

WORK UNCERTIFIED

Accounting Treatment is same for both:Work-in-Progress A/c Dr.

To Contract A/c

Page 10: Contract costing

01/04/2015 – 31/03/2016(ONE FINANCIAL YEAR)

01/04/20151.Starting of year 2. Starting

/continuation of contract

31/10/2015Assessment done by Architect or Surveyor and certified the

work done, i.e. work certified

31/03/20151.Ending of year2. Date of payment 3. Closing of

account of incomplete contract

Work Done and certifiedWork Done but not certified

WORKCERTIFIED

WORK UNCERTIFIE

D

Page 11: Contract costing

A Contractor does not receive full payment of the Work Certified by the surveyor.

Contractee retains some amount to be paid, after sometime, when it is ensured that there is no fault in the work carried out by contractor.

This retained money is called as Retention Money.

RETENTION MONEY

Retention Money= Value of work Certified (-) Payment actually made

Page 12: Contract costing

Particulars Amount

Particulars Amount

To Material Purchased XXX By Work-in-progress:Work CertifiedWork Uncertified

XXXXXX

To Material received from stores XXX

By Material Return to Stores XXX

To Material from other contract XXX

By Material sent to other contract XXX

To Wages XXX By COST of Material Sold

XXX

To Indirect Expenses XXX By Material on Hand XXXTo Plant & Machinery XXX By Plant on Hand XXXTo Accrued Wages XXXTo Accrued Expenses XXXTo Notional Profit c/d XXX

XXX XXX

SAMPLE OF CONTRACT A/C

Page 13: Contract costing

Profit Distribution

(Contract Costing)

Completed Contract

If Profit,Transferred to Credit side of P&L Account

If Loss,Transferred to Debit side of P&L Account

Incomplete Contract

If Profit, 1 Part Transferred to

Credit side of P&L Account as per the work Completed

Another to WIP A/c

If Loss,Transferred to Debit side of P&L Account

Page 14: Contract costing

As per the % of Work Completion, 3 stages of work completed is made which helps in transferring the amount to P&L Account.

PROFIT DISTRIBUTION IN INCOMPLETE CONTRACT

Stage Name % of Work Completion Formulae

Initial Stage 0% to 24% No Profit will be transferred to P&L

Work done but not Substantial 25% to 49%

Substantial Work Done 50% to 100%

Page 15: Contract costing

LIABILITIES Amount

ASSETS Amount

Work in Progress:

XXX

Work Certified XXXCosting P&L Account

XXX(+)Work Uncertified XXX

Contractee A/cXXX

(-) Cash Received (XXX)

Unpaid ExpensesXXX

(-) WIP Reserve (XXX)

Unpaid WagesXXX

Plant in Hand(Less Depreciation) XXXMaterial on Hand XXXCash XXX

SAMPLE OF BALANCE SHEET (EXTRACT)

DON’T TRY TO TALLY …. !!!

Page 16: Contract costing

Shubham [email protected]

Thanking You…