contracts_ advanced questions red book question_answer _fidic 87

28
Red Book (Civil Engineering; 4th Ed. 1987) REMEASUREMENT MODIFIED TO LUMP SUM QUESTION The following query is in relation to a situation which has occurred in the context of the execution of a Lump Sum contract, regulated by a standard FIDIC (Red Book) terms and conditions. The Specifications call for "Cast Iron" pipes, while the BOQ calls for "UPVC" pipes. The Contractor and upon the approval of the Engineer, and without having any instructions to do so, executed the Works in UPVC. Does this entitle the Employer to request cost saving on this item? And on what basis? Your response to the above is highly appreciated. ANSWER You say that you have a Lump Sum Contract. The FIDIC Construction Contract Book is a remeasurement contract so the payment provisions must have been changed to provide for the Lump Sum. The answer to your question will depend on the wording of these Lump Sum provisions. I regret that FIDIC can only comment on questions which on the interpretation of the FIDIC General Conditions, so we are unable to answer your question. We fear that this is an indication of what happens if General Conditions are modified by Special Provisions without due care. SUBCONTRCATOR'S EXPERIENCE QUESTION I would like your advice on the definition of a subcontractor, and of the following tender criteria: "subcontractors' experience and resources shall not be taken into account in determining the bidder's compliance with qualifying criteria". In other words, does this mean that if a bidder has worked as a subcontractor, he is not permitted to add that experience as part of his qualification? I would like your clarification. ANSWER The FIDIC definition of a subcontractor is given at SubClause 1.1.2.8 of the 1999 Contract for Construction as: "Subcontractor" means any person named in the Contract as a subcontractor, or any person appointed as a subcontractor, for a part of the Works; and the legal successors in title to each of these persons. Different clients have different criteria when evaluating tenders. FIDIC would certainly expect that any client will want to ensure that the tenderer has adequate experience as a main contractor and has not just worked as a subcontractor. However, in FIDIC's opinion, this would normally be worded as "Experience as a subcontractor ....". FIDIC has also known clients to be concerned that tenderers have relied on a proposed subcontractor's experience and resources when preparing a tender and then the named subcontractor is withdrawn and another, less experienced, company is proposed after the tender has been accepted. However, for an international tender, some clients require that a certain percentage of the Works must be subcontracted to local companies. In this case the experience and resources of the proposed subcontractors will be an important part of the tender. The client's criteria when evaluating tenders depend on a number of different factors, including the past experience of the particular client. In

Upload: aminjoles

Post on 16-Nov-2015

7 views

Category:

Documents


2 download

DESCRIPTION

Contractual matters

TRANSCRIPT

  • 3/28/2015 Contracts:advancedquestionsRedBookQuestion/Answer|InternationalFederationofConsultingEngineers

    data:text/htmlcharset=utf8,%3Cdiv%20class%3D%22field%20fieldnamefieldpagesummary%20fieldtypetextlong%20fieldlabelhidden%22%20style% 1/28

    RedBook(CivilEngineering4thEd.1987)

    REMEASUREMENTMODIFIEDTOLUMPSUMQUESTION

    ThefollowingqueryisinrelationtoasituationwhichhasoccurredinthecontextoftheexecutionofaLumpSumcontract,regulatedbyastandardFIDIC(RedBook)termsandconditions.TheSpecificationscallfor"CastIron"pipes,whiletheBOQcallsfor"UPVC"pipes.TheContractorandupontheapprovaloftheEngineer,andwithouthavinganyinstructionstodoso,executedtheWorksinUPVC.DoesthisentitletheEmployertorequestcostsavingonthisitem?Andonwhatbasis?Yourresponsetotheaboveishighlyappreciated.

    ANSWER

    YousaythatyouhaveaLumpSumContract.TheFIDICConstructionContractBookisaremeasurementcontractsothepaymentprovisionsmusthavebeenchangedtoprovidefortheLumpSum.TheanswertoyourquestionwilldependonthewordingoftheseLumpSumprovisions.IregretthatFIDICcanonlycommentonquestionswhichontheinterpretationoftheFIDICGeneralConditions,soweareunabletoansweryourquestion.WefearthatthisisanindicationofwhathappensifGeneralConditionsaremodifiedbySpecialProvisionswithoutduecare.

    SUBCONTRCATOR'SEXPERIENCEQUESTION

    Iwouldlikeyouradviceonthedefinitionofasubcontractor,andofthefollowingtendercriteria:"subcontractors'experienceandresourcesshallnotbetakenintoaccountindeterminingthebidder'scompliancewithqualifyingcriteria".Inotherwords,doesthismeanthatifabidderhasworkedasasubcontractor,heisnotpermittedtoaddthatexperienceaspartofhisqualification?Iwouldlikeyourclarification.

    ANSWER

    TheFIDICdefinitionofasubcontractorisgivenatSubClause1.1.2.8ofthe1999ContractforConstructionas:"Subcontractor"meansanypersonnamedintheContractasasubcontractor,oranypersonappointedasasubcontractor,forapartoftheWorksandthelegalsuccessorsintitletoeachofthesepersons.Differentclientshavedifferentcriteriawhenevaluatingtenders.FIDICwouldcertainlyexpectthatanyclientwillwanttoensurethatthetendererhasadequateexperienceasamaincontractorandhasnotjustworkedasasubcontractor.However,inFIDIC'sopinion,thiswouldnormallybewordedas"Experienceasasubcontractor....".FIDIChasalsoknownclientstobeconcernedthattenderershavereliedonaproposedsubcontractor'sexperienceandresourceswhenpreparingatenderandthenthenamedsubcontractoriswithdrawnandanother,lessexperienced,companyisproposedafterthetenderhasbeenaccepted.However,foraninternationaltender,someclientsrequirethatacertainpercentageoftheWorksmustbesubcontractedtolocalcompanies.Inthiscasetheexperienceandresourcesoftheproposedsubcontractorswillbeanimportantpartofthetender.Theclient'scriteriawhenevaluatingtendersdependonanumberofdifferentfactors,includingthepastexperienceoftheparticularclient.In

  • 3/28/2015 Contracts:advancedquestionsRedBookQuestion/Answer|InternationalFederationofConsultingEngineers

    data:text/htmlcharset=utf8,%3Cdiv%20class%3D%22field%20fieldnamefieldpagesummary%20fieldtypetextlong%20fieldlabelhidden%22%20style% 2/28

    ordertoascertaintheexactintentionsforevaluatingyourparticulartenderyouwouldneedtoraisethequestionwiththeclient.

    FREEISSUEMATERIALSQUESTION

    IhaveaquestionregardingClause69.1forDefaultofEmployer.WeareexecutingaContractforaProjectinPakistanunderFIDICFourthEdition,1987.TheEmployerhasassignedTheEngineerandalsoanEmployer'sRepresentative.TheEmployer'sRepresentativeisformtimetotimeactinglikeTheEngineerandwouldliketophysicallychecktheworksatsite.TheyarealsoapplyingdeductionsonthecertificatesofTheEngineer,suchasretentionmoneyonescalation,andalsoQuantities,etc.Theamountoftheunauthorizeddeductionsarearound5%ofthetotalamountcertificatesissuedbyTheEngineer.WehaveservedanoticeunderClause69.1and69.4,oftheConditionsofContracttoreducetherateofworkandfurthermore,clarifythattheClause69.1explainsthedefaultoftheEmployer,regardlessofthequantumofamountincaseofEmployer'sfailuretopaytotheContractortotalamountdueunderanycertificateoftheEngineer.DoyouthinkthattheabovestatementistrueanditisacaseofdefaultoftheEmployer?

    ANSWER

    DependingonwhatiswrittenintheContractandtheParticularConditions,generallyspeakingyouhaveacaseagainsttheEmployer.ThedamageswhichtheContractormayclaimwouldincludeinterestand/orfinancingcharges.However,youmustchecktheprovisionsoftheSubclause2.1Engineer'sdutiesandauthority,toseewhatismentionedthere.ItisnotveryclearwhatisthisEmployer'sRepresentativeandwhatarehisdutiesundertheContract,.However,onewouldsuspectthatyouhaveacaseagainsttheEmployer.

    BOGUSCLAIMSQUESTION

    IrequesttogivemeclarificationaboutthecorrectinterpretationofClause60.6FinalstatementintheFIDICConditionsofContract1987revisedin1992.ThisisaboutsubmissionbytheContractoroffinalstatementcontainingthefollowing(a)'thevalueofallworkdoneinaccordancewiththecontract,and(b)anyfurthersumswhichthecontractorconsiderstobeduetohimunderthecontractorotherwise'.Iwantclarificationwithrespectto(b)above.DoesitincludetheClaimswhichtheContractorhasneverraisedduringthecurrencyofcontractaccordingtoprovisionsofthecontract?IamconfrontedwithadisputeInwhichthecontractorforavalueoftotalworkofRs70millionhassubmittedfinalaccountsofRs280millonbyincludingvarioustypeofclaimswhichheneverclaimedduringthecontractperiodandnowclaimsinthefinalstatementandsincetheEngineer/Employerfailedtorespond,theContractorclaimsthatthefinalaccounthasbecomefinal.Iwouldrequestforanearlyresponseastothetrueandintendedpurposeofthesubclause(b)ofClause60.6oftheGeneralConditionsoftheabovementionedFIDICversionforcivilworksconstruction.ShouldIincludeallbogusclaimswhatIintendtoincludeforthepurposethatifIclaimUSD100IwouldatleastgetUSD1.HowIcanrebutthis?

    ANSWER

  • 3/28/2015 Contracts:advancedquestionsRedBookQuestion/Answer|InternationalFederationofConsultingEngineers

    data:text/htmlcharset=utf8,%3Cdiv%20class%3D%22field%20fieldnamefieldpagesummary%20fieldtypetextlong%20fieldlabelhidden%22%20style% 3/28

    TheprovisionsofSubclause60.6havetobereadtogetherwiththeprovisionsofSubclause60.5andofcoursewiththeprovisionsoftheSubclause60.9.InorderfortheContractortomaintainanyclaim,hemustincludeitinhisStatementatCompletion,ifithasarisenbythen,andinhisFinalStatement.ThereareanumberofincidencesunderthecontractwhentheEmployergivestotheContractorindemnitiesorisotherwiseresponsibletotheContractor.ClausesinwhichthisoccursandwheretheContractor'sresultingclaimsagainsttheEmployercouldariseforthefirsttimeaftertheStatementatCompletionorFinalStatementhavebeensubmittedbytheContractorincludethefollowing:Clause19.2(Employer'sresponsibilities)inrelationtosafetyClause21.3(Responsibilityforamountsnotrecovered)Clause22.3(IndemnitybyEmployer)Clause24.1(Accidentorinjurytoworkmen)Clause25.4(Compliancewithpolicyconditions)Clause26.1(Compliancewithstatutes,regulations)Clause70.2(Subsequentlegislation)andClause71.1(Currencyrestrictions).Ineachoftheabovecases,itisconceivablethattheContractorwouldwishtomakeaclaimagainsttheEmployerafterthedateoftheFinalStatement.Further,iftheContractorwasmadeliableundertheapplicablelawtoathirdpartyinrespectofdesignwhichhadbeencarriedoutbytheEngineer,theContractorwouldwishtobringaclaimagainsttheEmployertorecoveranydamagespaidout.Subclause60.9infactbarstheclaimsnotmentionedintheStatementatCompletionandintheFinalStatement.Thepurposeofthesubclauseissensible,namelytoenabletheEmployertoachieveareasonabledegreeofcertaintyastohisultimateliability.

    APPOINTINGANENGINEERQUESTION

    IsitrecommendedtohaveinacontractbasedonFIDIC'sElectricalandMechanicalWorksContractanexternalexpertactingastheEngineer?OristherenoprobleminrecruitingtheEngineerfromamongsttheBeneficiary(inourcasea"public"authority)?Wearesigningacontractshortly.TheEngineerisaccordingtotheRedBook,Clause2.4PartIboundtoactimpartially.ThequestionisifthereisaninternalincompatibilityintherelationshiptohisEmployer.

    ANSWER

    Thebasisuponwhichthe1987YellowBookandRedBookiswrittenisthattheEngineerisappointedbytheEmployer,butthatheisindependentofbothpartiesi.e.,heisanindependentthirdparty.InmanycasesheisrequiredtogiveimpartialdecisionsinfactunderClause2.4oftheYellowBookheisrequiredtoactimpartiallyatalltimeswhenexercisinghisdiscretion.IftheEngineerisanemployeeoftheEmployere.g.,someonefromtheEmployer'sEngineeringDivisionthereisabigriskthathewillnotbeinapositiontoactimpartially.Althoughhemaybeveryexperiencedandcapablefromatechnicalpointofview,andabletohandlealltechnicalmatters,hemaynotbefreetomakedecisionswhichinvolvefinancialarrangements,etc.inafairandimpartialmanner.Itisnotimpossible,norunknown,fortheEmployertonominatehimselforoneofhisownstaffasEngineer,butitisrareandcertainlycausesproblems.ThetextofanyclausesreferringtotheimpartialityoftheEngineerwillprobablyneedrevisingatsomestage,aswilltheprovisionsforhandlingclaimsanddisputes(Clauses2and50).TheprincipleofusinganemployeeoftheEmployerasEngineerwouldbemoreacceptableifaDisputeAdjudicationBoard(DAB)wasintroducedtoreplacetheprincipalprovisionsofClauses2and50.1todealwithclaimsanddisputes.

  • 3/28/2015 Contracts:advancedquestionsRedBookQuestion/Answer|InternationalFederationofConsultingEngineers

    data:text/htmlcharset=utf8,%3Cdiv%20class%3D%22field%20fieldnamefieldpagesummary%20fieldtypetextlong%20fieldlabelhidden%22%20style% 4/28

    STANDARDLETTERSQUESTION

    IamaCivilEngineer,presentlyworkingasContractsManager.Foreign(nonBritishnationality)engineersusuallyhaveanunderstandingofthecontractdocumentandtheassociatedentitlements/obligations,butalwaysexpressdifficultyincomposing(orrespondingto,iftheyareon"theotherside",correctlyworded"standard"letterstotheRE,EngineerorEmployerincompliancewiththerequirementsofthevarioussubclauses.Doyouhavesuchapublication?

    ANSWER

    Theonlybookwhichwecanrecollectis"MusterbriefeinEnglisch"(ISBN3762526079)althoughitsstandardlettersarenotsuchaswewouldprefertoendorse.AlthoughwewillreviewthesituationwithregardtothenewFIDICContractsGuide,FIDIClackenthusiasmfortheveryconceptofstandardletters,whichseemstobetiedupwiththeconceptofavoidingthinkingaboutthesituation.However,wedorecognisethevalidityofconcernsexpressedbythosewhosefirstlanguageisnotEnglish.Thus,"MusterbriefeinEnglisch"hasbeenrepublishedasanelectronicedition(itgoeswiththe1987RedBookcivilworkscontract).AnupdatedversionforusewiththeConstructionContract1stEdition,1999,theRedBooksuccessor,willbepublishedbyFIDICin2009(FIDIChasacquiredthecopyrightofMusterbriefeinEnglisch).ItshouldbenotedthatEdwardCorbett'sbook"FIDIC4th"containssomestandardletters.Thesehavebeenincorporatedwithpermissionintheelectronicversionof"MusterbriefeinEnglisch"publishedbyFIDIC.

    APPENDIXTOTENDERDATAMISSION(CONTINUED)QUESTION

    Ibelievethiscasedoesnotconstituteaquestionofmistakeincontracttobedecidedundertheapplicablelaw.Thescheduleofpricesoflabourandmaterialsisaprovisionforthetenderertoindicatehisprice(costplusprofit)onwhichhehadbasedhisContractPrice,inorderfortheEngineertoascertainthevalueofanitemofworkthathadbeenexecuted(possiblyunderavariationorder)andforwhich,orforasimilaritemofworkofwhich,nopricecouldbefoundintheBillofQuantities(BOQ).ThusthescheduleofpricesofmaterialsandlabouronlyassiststheEngineertodeterminetheoverheadsandprofitsoftheContractor,underthetermsofthecontract,thathastobeaddedtothebasiccostofexecutinganitemofwork,whichtheEngineercanalwaysreadilydetermine.Ifprovisonhadbeenmadeinthecontractforpaymentforpriceescalations,thensuchpaymentshadtobedeterminedbyreferencetopriceescalationindices,publishedbyanacceptedauthority.Astowhichsourceorpublicationistobeusedforthispurpose,dependsonwhatwouldhavebeenreasonablyexpectedtobeinthemindsofthetwopartiesatthetimeofenteringintocontract.

    ANSWER

    WeassumethatthisinquiryisaboutFIDIC1999ConditionsofContractwhereinthe199RedBookSubClause13.8itsays:"13.8(AdjustmentsforChangesinCost)InthisSubClause,"tableofadjustmentdata"meansthecompletedtableofadjustmentdataincludedintheAppendixtoTender.Ifthereisnosuchtableofadjustmentdata,thisSubClauseshallnotapply.IfthisSubClauseapplies,theamountspayable

  • 3/28/2015 Contracts:advancedquestionsRedBookQuestion/Answer|InternationalFederationofConsultingEngineers

    data:text/htmlcharset=utf8,%3Cdiv%20class%3D%22field%20fieldnamefieldpagesummary%20fieldtypetextlong%20fieldlabelhidden%22%20style% 5/28

    totheContractorshallbeadjustedforrisesorfallsinthecostoflabour.GoodsandotherinputstotheWorks,bytheadditionordeductionoftheamountsdeterminedbytheformulaeprescribedinthisSubClause.TotheextentthatfullcompensationforanyriseorfallinCostsisnotcoveredbytheprovisionsofthisorotherClauses,theAcceptedContractAmountshallbedeemedtohaveincludedamountstocoverthecontingencyofotherrisesandfallsincosts.TheadjustmenttobeappliedtotheamountotherwisepayabletotheContractor,asvaluedinaccordancewiththeappropriateScheduleandcertifiedinPaymentCertificates,shallbedeterminedfromformulaeforeachofthecurrenciesinwhichtheContractPriceispayable.NoadjustmentistobeappliedtoworkvaluedonthebasisofCostorcurrentprices.Theformulaeshallbeofthefollowinggeneraltype:Pn=a+bxLn/Lo+cxEn/Eo+dxMn/Mowhere:"Pn"istheadjustmentmultipliertobeappliedtotheestimatedcontractvalueintherelevantcurrencyoftheworkcarriedoutinperiod"n",thisperiodbeingamonthunlessotherwisestatedintheAppendixtoTender"a"isafixedcoefficient,statedintherelevanttableofadjustmentdata,representingthenonadjustableportionincontractualpayments"b","c","d",...arecoefficientsrepresentingtheestimatedproportionofeachcostelementrelatedtotheexecutionoftheWorks,asstatedintherelevanttableofadjustmentdatasuchtabulatedcostelementsmaybeindicativeofresourcessuchaslabour,equipmentandmaterials"Ln","En","Mn",...arethecurrentcostindicesorreferencepricesforperiod"n",expressedintherelevantcurrencyofpayment,eachofwhichisapplicabletotherelevanttabulatedcostelementonthedate49dayspriortothelastdayoftheperiod(towhichtheparticularPaymentCertificaterelates)and"Lo","Eo","Mo",...arethebasecostindicesorreferenceprices,expressedintherelevantcurrencyofpayment,eachofwhichisapplicabletotherelevanttabulatedcostelementontheBaseDate.Thecostindicesorreferencepricesstatedinthetableofadjustmentdatashallbeused.Iftheirsourceisindoubt,itshallbedeterminedbytheEngineer.Forthispurpose,referenceshallbemadetothevaluesoftheindicesatstateddates(quotedinthefourthandfifthcolumnsrespectivelyofthetable)forthepurposesofclarificationofthesourcealthoughthesedates(andthusthesevalues)maynotcorrespondtothebasecostindices.Incaseswherethe"currencyofindex"(statedinthetable)isnottherelevantcurrencyofpayment,eachindexshallbeconvertedintotherelevantcurrencyofpaymentatthesellingrate,establishedbythecentralbankoftheCountry,ofthisrelevantcurrencyontheabovedateforwhichtheindexisrequiredtobeapplicable.Untilsuchtimeaseachcurrentcostindexisavailable,theEngineershalldetermineaprovisionalindexfortheissueofInterimPaymentCertificates.Whenacurrentcostindexisavailable,theadjustmentshallberecalculatedaccordingly.IftheContractorfailstocompletetheWorkswithintheTimeforCompletion,adjustmentofpricesthereaftershallbemadeusingeither(i)eachindexorpriceapplicableonthedate49dayspriortotheexpiryoftheTimeforCompletionoftheWorks,or(ii)thecurrentindexorprice:whicheverismorefavourabletotheEmployer.Theweightings(coefficients)foreachofthefactorsofcoststatedinthetable(s)ofadjustmentdatashallonlybeadjustediftheyhavebeenrenderedunreasonable,unbalancedorinapplicable,asaresultofVariations."TheclauseisveryclearandunfortunatelythequestionraisedisnotrelatedtoaninterpretationofaSubSlause.

    FAIRNESSOFDEDUCTIONSQUESTION

    Asourprojectisalumpsumcontract,theclienthasreducedsomeoftheitemsandisdeductingsuomeofourpaymentamountsfromthemonthlycertificate.Isitfairtodeductanamount?

  • 3/28/2015 Contracts:advancedquestionsRedBookQuestion/Answer|InternationalFederationofConsultingEngineers

    data:text/htmlcharset=utf8,%3Cdiv%20class%3D%22field%20fieldnamefieldpagesummary%20fieldtypetextlong%20fieldlabelhidden%22%20style% 6/28

    ANSWER

    AlthoughitisnotforFIDICtocommentonthe"fairness"ofaparticularcircumstance,itistheFIDICphilosophytopublishConditionsofContractthatadoptanapproachoffairnessandbalancedriskallocationbetweenthepartiesasaprimaryfocus.Further,FIDICcanonlycommentingeneraltermsontheinterpretationofaFIDICclauses,anditshouldbenotedthatfortheapplicationofaclausetoaparticularproblemsituation,oneshouldalwaysconsultaspecialist.Withthatbeingsaid,ingeneral,theSubClauseentitledVariations(SubClause52.1inthe4thEditionor13.1inthe1999EditionoftheConstructionContract)doesprovidetherightfortheEngineertovarytheworkdownwardspecificallytheEngineermaydecreasequantitiesoromitwork,providedofcoursethatthisworkisnotcarriedouttheEmployeroranothercontract.Further,SubClause51.1providesthatsuchvariationswillbevaluedinaccordancewiththeClause52,inthecaseofthe4theditionorClause12inthecaseofthe1999editions.Bothoftheseclausesprovidetherulesforthevaluationofthesevariations,whichincludethepossibilityofreductioninprice.Pleasenotethattheaboverepresentsageneralansweronly,andspecificadvicetotheparticularfactssurroundingyoursituation,werecommendyouconsultaspecialist.

    LIQUIDATEDDAMAGESQUESTION

    IamworkingasaResidentEngineerforHighwayswithconsultants.Abriefdetailofourprojectisasasfollows:Theprojectisarepairprojectandisdividedin3sections.Thesectionsareofvaryinglengthswith150mfortheshortestoneand1.5Kmforthelongestone.Completiondatefortheprojecthasalreadyelapsedearlythisyearandnotimeextensionhasbeengrantedtothecontractorowingtodelayonhisownbehalf.Twosectionshavealreadybeencompleted(openedtotraffic)andthe3rdsectionisnearcompletion.Noseparatetimesforcompletionhavebeenprovidedinthecontractforeithersection.Clause47.2ofFIDICConditionsofContract(4thedition)recommendsthereductioninpenaltysubjecttotakingoverofdifferentsections.Assatedabove,noneofthesectionshavebeenacquiredbytheclientcontractually.Thereferredclausealsostatesthattheprovisionsofthesubclauseshallonlyapplytotherateofliquidateddamagesandshallnotaffectthelimitthereof.WhatIinferfromthispartisthatevenafterthereductionofpenalty,itshallbeapplicablefromtheoriginaldateofexpiryofthecontract.Isthistherightinterpretation?Mysecondqueryisregardingthereductioninliquidateddamages.Undertheabovecircumstanceswherethesectionshavenotbeenacquired,butopenedtotrafficandgeneralpublic,canthepenaltiesbereducedcontractuallysubjecttomutualagreementwiththeclient?Thirdly,duringthecurrencyoftheproject,somesavingshavebeenthere(whichcouldn'tbeestimatedatdesignstageduetorepairingnature).Thesavingsarelessthan15%(consideringClause52.3).Ifpenaltiesareappliedandreducedthereof,aretheytobecalculatedontheoriginalcontractpriceortherevisedone?

    ANSWER

    Ifunderstoodcorrectly,yourfirstquestionrelatestosubclause47.2,specificallythelastsentence,whichreads"TheprovisionsofthisSubClauseshallonlyapplytotherateofliquidateddamagesandshallnotaffectthelimitthereof."Themeaningofthissentenceisthatalthoughthisclauseallowsfortheamountofliquidateddamagestobereducedproportionatelytotheworkbeinghandedover,iftheworkishandedoverinparts,themaximumlimitofliquidateddamages(asspecifiedintheappendixtotender(seeSub

  • 3/28/2015 Contracts:advancedquestionsRedBookQuestion/Answer|InternationalFederationofConsultingEngineers

    data:text/htmlcharset=utf8,%3Cdiv%20class%3D%22field%20fieldnamefieldpagesummary%20fieldtypetextlong%20fieldlabelhidden%22%20style% 7/28

    Clause47.1))isnotaffected.Inregardtoyoursecondquestion,Clause47shouldbereadinconjunctionwithClause48.Inthebackgroundtoyourquestion,youstatedthatnoneofthesectionshavebeen'acquiredbytheClientcontractually',yetearlieryoustatethat'2sectionshavealreadybeencompleted(openedtotraffic)'.Inthislight,wewouldsuggestthatyoumayreviewbothsubclause48.2and48.3,which,dependingontheparticularfactpatternsurroundingyourcontract,maybeapplicable.Inanswertoyourthirdquestion,liquateddamagesarenotpenalties.YouarekindlyreferredtotheverbiagecontainedinSubClause47.1,whichreads,inpart"...andnotasapenalty...".AsexplainedintheGuidetotheRedBook,LiquidateddamagesareanamountdeterminedbytheEmployer,beforetendersareinvited,asareasonableassessmentoftheactualdamageswhichhewouldsufferintheeventofdelayincompletionoftheWorks.Hence,ingeneral,LiquadatedDamagesshouldbecalculatedfromthevantagepointthatwillresultinareasonableassessmentoftheactualdamages.

    VALUEENGINEERINGSUBCLAUSEQUESTION

    IntermsoftheFIDIC1987RedBook,istheContractorentitledtoaportionofthesavingasprovidedforinthetermsofSubClause13.2(ValueEngineering)inthe1999RedBook?

    ANSWER

    TheFIDIC1987eRedBookdoesnothaveasimilarprovisionastheonementionedintheFIDIC1999editionValueEngineering,SubClause13.2Howeveryoumayfindinthe1987RedBookasocalledbonusforearlycompletion.

    ADDITIONALWORKSQUESTION

    Beingaprojectmanagerfromtheclientside,IwouldliketoknowasperFIDICcanIforceacontractortocarryoutadditionalworkspriortoapprovalofhisfinancialclaim?

    ANSWER

    ThebasicanswerisYES,providedyoufollowthecorrectcontractprocedures.ThereareanumberofSubClauseswhicharerelevantincluding,fromthe1999ConstructionContract:a)S/Cl3.1:TheEmployermayhaveimposedconstraintsontheEngineer'sauthorityintheParticularConditions.b)S/Cl3.3:TheContractorshallcomplywithinstructionsgivenbytheEngineer.c)S/Cl13.1:TheContractorshallexecuteandbeboundbyeachVariationinitiatedbytheEngineer.SubjecttoexceptionsasstatedintheSubClause.d)S/Cl13.3:ProceduresfortheEngineertovaluetheVariation.TheEngineermayhaveaskedforandacceptedaproposal,orheproceedsasClause12.

    NEWRATESQUESTION

    InacivilmarineworkcontractofFIDICconditions,disputesquiteoftenoccursonfixingofrevisionofrates.

  • 3/28/2015 Contracts:advancedquestionsRedBookQuestion/Answer|InternationalFederationofConsultingEngineers

    data:text/htmlcharset=utf8,%3Cdiv%20class%3D%22field%20fieldnamefieldpagesummary%20fieldtypetextlong%20fieldlabelhidden%22%20style% 8/28

    thoughclauses51and52ofFourthEditionRedBookclearlyprovidecausesforvariationandvaluationofrates,ambiguitystillpersistswithrespecttoadoptionofrevisedratesforvariedquantitiesonlyorforfullquantityexecutedaslongastherearenomajorchangesindeploymentofworkmen,equipmentandmaterials.LeavingthedecisiontoengineermaynotgiveanappropriatesolutionaspersonsholdingthepostofengineermayhavedifferentviewsandtheirdecisionsmaynotexactlymatchwiththeviewsofFIDICauthors.Pleaseclarifythesituationswhenrevisedratesareapplicablefortheentirequantityorforincreasedquantitiesonly.

    ANSWER

    Thedecisionwhetheranewrateappliestothetotalquantityofanitem,orjusttotheVariationquantity,willdependonthereasonwhyanewrateisnecessary.ThismaydependonthereasonanddetailsofthechangetotheContractor'scost.SometimestheoriginalquantitywillalreadyhavebeenexecutedandpaidattheBQrate,beforetheVariationisordered.However,sometimesthefactofthequantitybeingchangedbytheVariationwillchangethecircumstancesandcostsandmakesitreasonabletopaythetotalquantityatthenewrate.ThenewratemaydifferifitisbeingappliedtothetotalquantityorjusttotheVariationquantity.TheEngineerwill,ofcourse,takeallthesefactorsintoaccountwhencalculatinganewrate.YoushouldalsorefertothecommentaryonClauses51and52intheFIDICGuidetotheFourthEdition.Thecommentaryemphasisestheimportanceofconsultationwithboththeparties.

    APPENDIXTOTENDERDATAMISSINGQUESTION

    AcontractwassignedundertheFIDICConditionsofContractwhichrequirethatindicesfortheskilledandunskilledlabourshouldbefilledbytheContractorintherelevantAppendixwhilesubmittingthetender.ThisrequirementincludingthesourceoftheindiceswashowevernotfulfilledbytheContractor.Thisfactwasnotedbutemployerfailedtogetthisrequirementmetandthecontractwassignedwithoutthisinformation.Thedisputearosewhenthecontractorsubmittedescalationclaimduechangeinpricesofthelabourcomponentaccordingtorelevantprovision.Thecontractorinsiststheusesourceindicesissuedbythelocalgovernmentforcalculationofadjustmentwhichisneartheplaceoftheconstructionandbecausethisconditionismoreprofitabletocontractor.TheClientinsiststhathewillusetheindicesissuesbyagevernmentofficewhicharenormallyusedingovernmentcontracts.IamtheArbitratorinonesuchcaseandneedadviceofFIDICwhatwillbethejudiciouscoarseofactioninthisscenario.IhoweverfeelthatentireresponsibilityofnotprovidingthisinformationcannotbeplacedontheContractorandtheEmployershouldhaveinsuredthatContractorprovidethisinformationbeforesigningofthecontract.omissionwasmadeandthecontractwassignedwithoutthisinformation(sourceofindices).IwillbeanxiouslywaitingforadvicefromyourexpertwhatreasonablecoarseofactionshouldbeadaptedinthisdisputeresolutionastheContractorhasgoneindisputeonthisissue.

    ANSWER

    ItseemsthattheContractormadeamistakebynotaddingtheinformationtotheAppendixtoTender.TheEmployerthenacceptedtheTenderandthePartiessignedaContractwhichincludedthemistake.UnfortunatelyyousaythattheycannotagreeontheinformationwhichshouldbeaddedtotheAppendixto

  • 3/28/2015 Contracts:advancedquestionsRedBookQuestion/Answer|InternationalFederationofConsultingEngineers

    data:text/htmlcharset=utf8,%3Cdiv%20class%3D%22field%20fieldnamefieldpagesummary%20fieldtypetextlong%20fieldlabelhidden%22%20style% 9/28

    Tender.TocorrectthemistakerequiresachangetothesignedContracttoaddthisinformation.CorrectingamistakeinaContractisalegalquestionwhichmustbestudiedundertheapplicablelaw.FIDICcannotcommentonsuchlegalquestions.

    ENGINEER'SDECISIONQUESTION

    OurfirmhasacontractforconsultingserviceswiththeGovernmentofElSalvadorfortheconstructionofmajortransportationinfrastructureinthecountry.TheprojectisdividedintothreepackagesthataregovernedbyFIDICConditionsofContractforWorksofCivilEngineering(Redbook,4thEd.1987).Theconstructionofthefirstpackageofproject,whichincludedtwo400meterbridgesoverthemostimportantriverinElSalvador,wascompletedlastApril.TheContractorisaJointVentureoffirmsthatisnowclaimingadditionalpaymentsbasedonthecontractdocuments.Inordertohaveaclearinterpretationofthedocuments,wewouldliketoclarifythefollowing:Clause67.1Engineer'sDecisionwewouldliketoconfirmifunderthisClausetheContractorcanclaimformattersthathappenedduringtheconstructionperiod,evenaftertheTakeOverCertificatehasbeenissuedandtheStatementatCompletionhasbeencertifiedandpaid.

    ANSWER

    RegardingClause67.1:iftheContractorisdissatisfiedwithanEngineer'sevaluationofaclaimunderClause53,hemayreferthematteratanytime(beforeoraftercompletion)totheEngineerunderClause67.1foran"Engineer'sDecision".HecandothisanytimeuptohisFinalStatementandthereisnotimelimit.TheEngineerthenhas84daystorespond.TheContractorcannotsubmita"new'"claimfornormaldeterminationunderthisclause.TheclaimmustfirstbeprocessedunderClause53,andonlywhenaClause53determinationhasbeengivenwhichtheContractorfindstobeunacceptabledowehavea"dispute"situationwhichcanbehandledunderClause67.1.

    CALCULATIONOFCLAIMSQUESTION

    Iwouldliketoknowifyoucanhelpmefindinformationregardingtheprocedureandcalculationofclaims(ofanykind)arisingoutofaCivilEngineeringConstructioncontract.

    ANSWER

    FIDICpublishesguidestoeachofitsformsofconstructioncontract,whichmayprovidetheguidanceyourequireontheproceduresforclaims.YouwouldneedtoordertheGuidefortheuseofwhateverConditionsyouareusing.IfyourenquiryrelatestoOctober2000.FIDIC'sguidesdonotelaborateonthecalculationofclaims,soyoumightneedtoconsultotherpublications.Personally,Iamonlyawareof"BuildingandCivilEngineeringClaimsinPerspective"byGeoffreyArthurHughes,whichwasfirstpublishedbyLongmanin1983.Itmayhavebeenrepublishedandfulfilyourneeds.

  • 3/28/2015 Contracts:advancedquestionsRedBookQuestion/Answer|InternationalFederationofConsultingEngineers

    data:text/htmlcharset=utf8,%3Cdiv%20class%3D%22field%20fieldnamefieldpagesummary%20fieldtypetextlong%20fieldlabelhidden%22%20style 10/28

    NOTINPREHANDOVERLISTQUESTION

    IhavethefollowingproblemandIcannotfindasolutionintheFIDICRedBookFourthEdition1887.Theproblemisasfollows:wehavemadeacontractwithaprehandoverlistmade,withtheEngineer,inApril2000.Anewcontract,giventoanothercompanyinthesamebuildingwasgiveninMay2000,itwasanobligationformetogivethekeysofthebuilding.AstheEngineerisinZimbabweandtheBuildingisinBurundi,noengineerwasthereforthehandoveroftheinsideofthebuilding.Now,theEngineerasksustorepairsomethingswhichwerenotontheprehandoverlist.CanyoupleasetellmewhatIhavetodo.

    ANSWER

    FIDICdoesnotundertaketoprofferadvicerelatingtoeverysituationwhichmayariseunderaFIDICbasedcontract.However,itappearsthattheanswertoyourquestiondependsuponwhetheraTakingOverCertificatehasbeenissued.Ifso,theprehandoverlistpresumablyadvisedyouoftheworkdescribedinSubClause49.2(a),andtheEngineerhasaskedyoutorepairsomethingsasdescribedinSubClause49.2(b).Ifnot,theEngineermaybe"specifyingalltheworkwhich...isrequiredtobedone...beforetheissueofsuchCertificate"underSubClause48.1.Ineithercase,youhavenotindicatedanyreasonfornotcomplyingwiththeEngineer'sinstructions.

    ADDITIONALPAYMENTSQUESTION

    OurfirmhasacontractforconsultingserviceswiththeGovernmentofElSalvadorfortheconstructionofmajortransportationinfrastructureinthecountry.TheprojectisdividedintothreepackagesthataregovernedbyFIDICConditionsofContractforWorksofCivilEngineering(Redbook,4thEd.1987).Theconstructionofthefirstpackageofproject,whichincludedtwo400meterbridgesoverthemostimportantriverinElSalvador,wascompletedlastApril.TheContractorisaJointVentureoffirmsthatisnowclaimingadditionalpaymentsbasedonthecontractdocuments.Inordertohaveaclearinterpretationofthedocuments,wewouldliketoclarifythefollowing:Clause53.1NoticeofClaimsitisimportanttoconfirmiftheContractorcaninvokethisClausetoclaimforadditionalpaymentowingtoconstructionworksthatwereperformedbeforetheTakeOverCertificate,oncethisCertificatehasbeenissued.Inotherwords,iftheContractorcanclaimformattersthathappenedduringtheconstructionperiodevenaftertheTakeOverCertificatehasbeenissued.

    ANSWER

    RegardingtheapplicationofClause53.1.ThisclauserequirestheContractortogiveNoticeofapotentialclaimwithin28daysoftheeventoccurring.ThisestablisheshisrighttoclaimandheshouldthenproceedtosubstantiatetheclaimaccordingtoClause53.3.HecanclaimatanytimebeforeorafterTakingoverifeventsoccur(beforeoraftertakingover)whichheconsidersentitlehimtoclaim.TheintentionofClause53.1istotrytomakesureclaimsaredealtwithasandwhentheyoccursothateveryoneisfamiliarwiththecircumstances(thusthe28dayprovision)andnottoleavethemtotheendwhenpeoplehaveprobablyforgottenallthedetails.Ifhedidthiswithinthetimelimits,thentheclaimshouldbeevaluatedaccordingtotheContractor'ssubmissions.Ifhedidnotaswouldappeartobethecaseandhascome

  • 3/28/2015 Contracts:advancedquestionsRedBookQuestion/Answer|InternationalFederationofConsultingEngineers

    data:text/htmlcharset=utf8,%3Cdiv%20class%3D%22field%20fieldnamefieldpagesummary%20fieldtypetextlong%20fieldlabelhidden%22%20style 11/28

    inwithaclaimaconsiderabletimeaftertheevent,thenwewouldsuggestthatyouhavetwocoursesofaction.Firstlyyoushouldperhapstrytoestablishwhyhedidnotgivenoticewithinthe28days.Eitheryoucanrejecthisclaimonthegroundthathedidnotsubmititwithin28daysasrequiredbyClause53.1,or,underClause53.4youcanmakeanassessmentbasedonrecordswhichwerekeptatthetime.NormallyIwouldsuggestitdependsonthecircumstances.Iftheclaimappearstobefrivolousandconfusedwithnosubstantiation(possiblyaneventyouknewnothingabout)youmaywelldecidetorejectit.ButifitconcernsaneventofwhichyouwereawarewhichyouknewhaddisruptedtheContractor,thenmaybeyoucouldconsideritunderClause53.4.

    NEWRATESFORREMEASUREMENTQUESTION

    IhaveaquestionregardingadoptionofFIDICRedBookFourthEditionreprinted1992.TheparticularContractcontainsClause51/52"Variations"andalsocontainsClause56"WorkstobeMeasured"andhasBOQ.DesignandConstructServicesforElectricalandMechanicalweretenderedasdiagramaticdesignsandaretobedevelopedtotheApprovalofEngineeraspartofobligationsundertheContractandhavevariousBOQitems.ThisDesignDevelopmentforMechanical/ElectricalservicesishisobligationundertheContract,andinthiswaywouldnotseemtoqualifyasaVariationtotheContract.HowevernewitemstotheoriginalBOQhavebeennecessitatedbyDD.UnderwhichClausecannewratesbeestablishedfortheremeasureoftheseWorks?

    ANSWER

    TheConditionsofContractforWorksofCivilEngineeringConstruction(1992)donotcontainexpressprovisionfornewratesbeingestablishedfortheremeasurementofnonvariedContractordesignworks,wherenewitemstotheoriginalBoQhavebeennecessitatedbyDesignDevelopment.Typically,Contractordesignworksarepricedonalumpsumbasis,andarenotsubjecttoremeasurementafterDesignDevelopment,sosuchexpressprovisionwouldbeinappropriateintheConditionsofContractwhichFIDICintendedtobesuitableforEmployerdesignworks.

    TERMINATIONBEFORECOMPLETIONQUESTION

    HasEmployergotanauthorityaccordingtoFIDICtoterminatethecontractofEngineerbeforecompletionofprojectandappointanotherengineeringcompanyorcontinuewithitsownresources?IknowthatthatEmployercannotdothisaccordingtoRedBookFIDICClause1.1DefinitionsbyreferringtoPartIIofthecontract.Whatshouldwedoasacontractoratthisstage?

    ANSWER

    YouappeartounderstandFIDIC'sprovisions,assummarisedatthetopofpage41oftheRedBookGuide:"Itshouldbenotedthat...theeffectof...[1.1(a)(iv)]istopreventtheEmployerfromchangingtheEngineerwithouttheconsentoftheContractor."Ineffect,providedthelegalpersondefinedas"Engineer"continuestoexist,suchlegalpersoncontinuestobetheEngineerforthepurposesoftheContract,and

  • 3/28/2015 Contracts:advancedquestionsRedBookQuestion/Answer|InternationalFederationofConsultingEngineers

    data:text/htmlcharset=utf8,%3Cdiv%20class%3D%22field%20fieldnamefieldpagesummary%20fieldtypetextlong%20fieldlabelhidden%22%20style 12/28

    theEmployerhasnopowertonamesomeoneelseasEngineer.By"continuestoexist",wemeandoesnot(asanaturalperson)die,orisnot(asacompany)dissolved.FIDICcannotgivespecificadviceinrespecttotheactionsapartyshouldtake,andonlyundertakestoclarifyaspectsofitsownprovisions.Youdonotseemtoneedsuchclarification,butmayneedtoobtainadvicefromalawyerwithexpertknowledgeofconstructionlaw.

    Thereisalwaysapossibilitythatsomeaspectofthesituation(whichyouhavenotmentioned)wouldentitletheEmployertoreplacetheEngineerunderthelawgoverningtheContract.ForFIDIC,itseemsthatyoushouldfirstdecidewhetherthereplacement"Engineer"isacceptableassuchbecause,ifnot,youcouldinformtheEmployeraccordinglyandseektoresolvethematterbeforeitescalatesintoamajordispute.

    EMPLOYERREPLACESTHECONTRACTORQUESTION

    RegardingthecorrectapplicationoftheRedBookContract,theEmployerincompliancewithsubclause63.1,aftergivingwrittennoticetotheContractoruponhiscontraventionofprovisioninsubclause4.1,enetereduponthesiteandtheworks,andterminatedtheemploymentoftheContractor.TheEmployerwantstoemployanotherContractor,whichtooksecondplaceintheinitial,publictender,tocompletetheworks.Thefurtherprocedurewillbeincompliancewithsubclauses63.2,63.3,63.4and64.1.Thequestionsis:isthisprocedureincompliancewiththeGeneralConditionsoftheRedBook4thEdition?

    ANSWER

    WerefertoyourquerywhetheraproposedprocedurecomplieswiththefourtheditionoftheGeneralConditionsofContractforWorksofCivilEngineeringConstruction.FIDICcannotundertaketoprovideadviceonactualcircumstances,andisonlypreparedtoclarifyandexplainthemeaningandpurposeoftheprovisionsitpublishesinitsConditionsofContract.Inthecaseofseriousmatterssuchastermination,legaladviceshouldbesought.However,wewouldmakethefollowingobservations,withoutconcludingwhethertheEmployerisentitledtoproceedasyouhavedescribed.Forthesepurposes,westartbyassumingthattheEmployer'sterminationwasvalidbyreasonoftheContractor'sbreachofsubclause4.1.Suchvaliditymay,ofcourse,bechallengedbytheContractor.Followingavalidtermination,theEmployer'soptionsonemployinganothercontractorwouldnotappeartobeconstrainedbytheGeneralConditions,otherthanunderClause63(withwhichyoustatethefurtherprocedurewillcomply),althoughtheymaybeconstrainedbytheapplicablelaw.Youmentioncompliancewithsubclause63.4,whichrelatestoassignmentofsubcontracts.ApplicablelawmayconstraintheEmployer'srightsinrespectofsubcontractswhichwereassociatedwiththeContractor'sbreachofsubclause4.1.Youmentioncompliancewithsubclause64.1,whichrelatestourgentremedialworkwhichtheContractorisunwillingorunabletodo,priortotermination.Aftertermination,hispreviousunwillingnessorinability

  • 3/28/2015 Contracts:advancedquestionsRedBookQuestion/Answer|InternationalFederationofConsultingEngineers

    data:text/htmlcharset=utf8,%3Cdiv%20class%3D%22field%20fieldnamefieldpagesummary%20fieldtypetextlong%20fieldlabelhidden%22%20style 13/28

    wouldnotseemtoentitletheEmployertoinvokesubclause64.1.Asregardsemployingacontractorwhichtook"secondplace...intheinitialpublictender",thisisnotamattertobedecidedbytheGeneralConditionsoftheContractunderwhichtheterminationwaseffected.Thechoiceofreplacementcontractorisamattertobedecidedbythelawrelevanttotheprocurementproceduresandanyconstraintsimposedbythoseprovidingfundsfortheproject.

    DELAYEDPAYMENTQUESTION

    IamanArchitectregisteredwiththeRIBAintheUKsince1978andtheUAEAuthoritiesinAbuDhabi,UAEsince1981.IhaverecentlybeenEngineerunderaFIDICRedBook4thEditionBuildingContractbetweenaUAEGovernmentAgencyandalocalContractor,andEmployer'sRepresentative/AdviserunderaFIDICDesignandBuildContract,sameEmployerbutdifferentContractor.ClausesofParticularApplicationhavebeenpreparedbyathirdpartyadvisingtheEmployerdirectinbothcases,butlargelyignored,theEmployerpayinglatethroughout,notpayingthefinalInterimCertificatesonTakingOvertheWorksineithercase,threateningtheimpositionofPenaltiesbyignoringand/orrejectingthecasesforExtensionsofTimeinbothcases,andnotpayingatalluntilforcedagreementtoreducedamountshasbeenacceptedbytheContractorsthroughbarter.Asyoumayknow,thereisverylimitedrecoursetothelawhere,especiallyforforeigners.BothContractorsarelikelytoweighthecostsofCourtsandfurtherDelayagainstthebenefitofanypaymentatallonehasalreadygivenin,buttheotherisstillfighting,orperhapsmorerealistically,negotiating.WhatshouldIdo,please:indeed,isthereanythingthatcanbedone?ThisistheworstcaseofabuseofContractIhavecomeacrossinmorethan20yearshere,thoughtheamountsarerelativelysmall.

    ANSWER

    Whilstwecansympathisewiththesituationdescribedinthequestion,thereisnotalotFIDICcanrecommendorthathecandoasEngineerinthiscase.Thesituationdescribedis,unfortunately,notallthatuncommoninsomeMiddleEastcountriesandtheultimatedecisionofwhattodolieswiththeContractor.Ifhefeelsthesituationwarrantsextrememeasures,thenhecanterminateunderClause69.1(unlessofcourse69.1hasbeenchangedasitveryoftenisinthesecountries).Otherwisethereisnotalotyoucando.BeingfairandimpartialtheEngineercould(andperhapsshould)writetotheEmployerremindinghimofthetermsoftheContractbuthewillprobablybringdownthewrathoftheEmployeronhisshoulders,andthatmaynothelpanybody.YoushouldperhapsalsobearinmindthatContractorswhochoosetoworkinthesecountriesareusually

  • 3/28/2015 Contracts:advancedquestionsRedBookQuestion/Answer|InternationalFederationofConsultingEngineers

    data:text/htmlcharset=utf8,%3Cdiv%20class%3D%22field%20fieldnamefieldpagesummary%20fieldtypetextlong%20fieldlabelhidden%22%20style 14/28

    (orshouldbe)ratherfamiliarwiththissituationandmaywellhaveallowedsomethingintheirpricetocoverthissortofthingespecially,asthepersonaskingthequestionsays,theamountisnotverylarge.

    EXPIRYOFDEFECTSLIABILITYPERIODQUESTION

    FortheRedBook,cantheEngineerissueinstructionsunderClause13.1aftertheexpiryoftheDefectsLiabilityPeriod?

    ANSWER

    AftertheDefectsLiabilityPeriodexpires,theEngineermayissueinstructionsunderClause49,andcannotrelyuponClause13asauthoritytoissueotherinstructions.

    PERFORMANCESECURITYQUESTION

    Pleaseinformusaboutthevalidityoftheperformancesecurityifthedurationofthecontractis90days.

    ANSWER

    TheseprincipleswouldprobablyapplywhicheverFIDICdocumentisbeingused.

    PRIORITYOFTENDERDOCUMENTSQUESTION

    ThequestionreferstoFIDICConditionsofContractforWorksofCivilEngineeringConstruction(4thEdition1987,reprinted1988witheditorialamendments,reprinted1992withfurtheramendments).Iamanemployerwhoisnegotiatingwiththecontractornow.IhaveatroubleinusingtheFIDICconditions,andaskforyourhelpurgently.SubClause1.1(b)(v)"Tender"meanstheContractor'spricedoffertotheEmployerfortheexecutionandcompletionoftheWorksandtheremedyingofanydefectsthereininaccordancewiththeprovisionoftheContract,asacceptedbytheLetterofAcceptance."AndSubClause5.2specifiesthepriorityofthecontractdocument,ofwhichtheTenderislistedasthird.Arethosetwo"Tender"havethesamemeaning?CanweexplainthattheTenderonlyrefertothedocumententitledletteroftender(maybe1or2pages,veryshortandsimpleanyway),orallthedocumentssubmittedbytheContractoralongwiththeletteroftenderasresponseupontheBiddingDocument(alotofdocuments,suchasappendixtotender,pricedBOQ,technicalproposal,evidenceforconstructionexperienceandfinancialcapacity)?

    ANSWER

    TheTenderatSubClauses1.1(b)(v)and5.2(3)meanstheformofTenderwhichisgivenattheendofPart1oftheRedBook.TheformofTender,atparagraph2,confirmsthattheAppendixtoTenderformspartoftheTenderandSubClause1.1(b)(iv)confirmsthatthepricedbillofquantitiesformspartofthe

  • 3/28/2015 Contracts:advancedquestionsRedBookQuestion/Answer|InternationalFederationofConsultingEngineers

    data:text/htmlcharset=utf8,%3Cdiv%20class%3D%22field%20fieldnamefieldpagesummary%20fieldtypetextlong%20fieldlabelhidden%22%20style 15/28

    Tender.IftheEmployerrequiresotherdocumentstobeincludedintheContractaspartoftheTenderthenhemuststatethisclearlyintheInstructionstoTenderersandintheformofTender.

    OBTAININGCONTRACTDATAQUESTION

    SubClause11.1tellusthatthehiredcontractingpartyisresponsibleforthedatacontainedinhisproposalbasedonthedatasuppliedbytheContractor.CouldyoupleasetellmehowIcanobtainthedata?

    ANSWER

    TheContractormusthavebasedhistenderoninformation:1)whichwasprovidedtoalltenderersbytheEmployerfromtheinvestigationswhichhadbeencarriedoutbytheEmployer2)whichtheContractorobtainedfromhisowninspectionandexaminationoftheSiteanditssurroundings.WheretheContractorobtainedthisinformationwilldependonthecircumstancesbuthemusthavesatisfiedhimselfthathistenderwascorrectandsufficienttomeethisobligationsundertheContract.

    INTERIMCERTIFICATESQUESTION

    SubClause60.4stipulatesthattheEngineermaycorrectanyerrorinaninterimcertificateinsubsequentcertificates.Arethereanylimitationsintheapplicationofthisprovision?

    ANSWER

    YouarereferringtoSubClause60.4ofthe1987ContractforCivilEngineeringWorks.ThereisasimilarprovisionatSubClause14.6ofthe1999Contracts.TheContractdoesnotputanylimitationonthisprovision.However,underSubClause60.2theEngineerhaspreviouslycertifiedtheamountwhichheconsideredtobedueandpayable.Ifhehasnowfoundanerrorandchangedhismindheshouldexplainthereasonsforthechange.

    REFIXINGOFRATEQUESTION

    IaminterestedinapplicationofClause52.2(PoweroftheEngineertofixRate).Ifcircumstancesallowarefixingofrate,woulditapplytothevariedquantity(increased/decreased)ortotheentirequantity,i.e.,quantitiesinthebidplusincrease/decrease?

    ANSWER

    Youarereferringtothe4thEdition1987oftheContractforWorksofCivilEngineering,SubClause51.1(a)allowstheEngineertoissueaninstructiontoincreaseordecreasethequantityofanyworkincludedintheContract.TheratewhichtheEngineeragreesorfixesunderSubClause52.2wouldonlyapplytothevariedquantity(increasedordecreased).TheoriginalquantityisnotpartoftheVariationandwouldbe

  • 3/28/2015 Contracts:advancedquestionsRedBookQuestion/Answer|InternationalFederationofConsultingEngineers

    data:text/htmlcharset=utf8,%3Cdiv%20class%3D%22field%20fieldnamefieldpagesummary%20fieldtypetextlong%20fieldlabelhidden%22%20style 16/28

    paidattheoriginalrate.

    RECOVERYOFCOSTSQUESTION

    Workingwith1987,4thEdition,reprintedin1992FIDICformofcontractonaprojectwhereClause70,whistbeingmodifieddoespermittherecoveryofchangesinthepricesoflabourandmaterials.Arethereanylegalprecidentswhichreflecttheprovisionreflectedinthe1999formofcontracttoallowtherecoveryofcosts,postthestatedcontractcompletionwherethecontractorhasfailedtocompletetheworksinthespecifiedtime?Orarethereanyprecidentstoreflecttherecoveryofcostspersec,postthecontractcompletiondate?Ifthereareanyprecidents,ifthereareinelectronic,format,couldyouforwardthemor,advisewheretheycouldbeobtained.

    ANSWER

    FIDICisunabletoprovidelegalguidanceorinformationonlegalprecedents.However,tobehelpful,thefederationhasaskedanexperttocommentsothatyourfutureresearchcanguidedintheapproriatedirection.Youarecorrectthatthe19874thEditiondoesnotincludespecificprovisionfortherecoveryofpricechangesafterthecontractcompletiondatewhentheContractorhasfailedtocompletetheworkinthespecifiedtime.AlternativeclausescanbefoundintheFIDICGuidetothe4thEditionandinthe1999Contracts.Theproblemwithlegalprecedentsisthatnotwodisputesituationsareeverexactlythesameandsoneedlegaladvice.Guidanceandsummariesofsomearbitrationawardscanbefoundintheinternationallegaljournals,newslettersfromlawfirmsandthepublicationsoftheinternationalarbitrationcentressuchastheICCParis,theLondonCourtofInternationalArbitrationandothercentresindifferentpartsoftheworld.

    ENGINEER'SINSTRUCTIONSQUESTION

    AFIDICstandardContractforcivilengineering(RedBook4thEdition1987)isbasisofaContractforaWharfandApproachBridgeConstructionandCausewayReclamationproject(TheContrac).TheContractisaLumpsumAgreementandtheBOQrefersasfollows:AllworksinthissectionexceptProvisionalQuantitieswillbepaidforasLumpSums.Quantitiesareestimatesonly.IftheContractorwishes,additionalitemsmaybeaddedtotheBillorquantitiesamended.Ratesnominatedwillbeusedonlytoassessvariations(ifany)totheContractandtoassessprogressclaimsandpayments.ProvisionalQuantitiesandItemswillbepaidforasdescribedintheConditionsofContract.OneoftheBoQitemwaspertainingtoCraneRailstobeprovidedbytheContractor.LatertheCompanyorganizedtheRailsontheirownandtheContractorisnotrequiredtoprovidetheCraneRailsaspertheBoQ.InviewofthistheCraneRailrelatedAmountasstatedintheBoQisproposedtobedeductedoutoftheBoQ.PleaseconfirmthatthisisproperapproachunderArticle51and52oranyotherconditionsofFIDICstandardcontract.

    ANSWER

    UnderaFIDICContract,anychangetoaddoromitworkmustbemadebyaninstructionfromthe

  • 3/28/2015 Contracts:advancedquestionsRedBookQuestion/Answer|InternationalFederationofConsultingEngineers

    data:text/htmlcharset=utf8,%3Cdiv%20class%3D%22field%20fieldnamefieldpagesummary%20fieldtypetextlong%20fieldlabelhidden%22%20style 17/28

    Engineerundertheappropriatesubclause.YoumentionSubClauses51and52,whicharefromthe19874thEditionoftheContractforCivilEngineeringWorks.SubClause51.1,item(b)allowstheEngineertoissueinstructionstoomitwork,butthisisqualifiedbythestatementinbrackets"(butnotiftheomittedworkistobecarriedoutbytheEmployerorbyanothercontractor)".Yourproposalforthecranerailswouldappeartocontravenethisrequirement.HencethechangeandpriceadjustmentmayneedtobenegotiatedbetweenthePartiesandwouldprobablyinvolvelegaladvice.

    VARIATIONSEXCEEDING15PERCENTOFTHEEFFECTIVECONTRACTSUM(CLAUSE52.3)QUESTION

    WeareintheprocessofpreparingaclaimunderClause52.3oftheFIDICConditionsofContractforWorksofCivilEngineeringConstructionandareseekingclarificationontheapplicationoftheclauseespeciallyasregardstowhichamountdoweapplythepercentagewhichisinexcessofthe15%.Doweapplyitto:Theeffectivecontractsumor,Thedifferencebetweentheamountscalculatedusingtheactualpercentagebywhichtheeffectivecontractsumshallhavebeenexceedbyandthe15%.PleasenotethatInthisparticularcontract,themajorityofPreliminaryandGeneralItemswerestatedasprovisionalsums(asstatedintheBillofQuantitiesbytheEngineer)itisnoteasyforustoaccuratelydeterminethecontractor'soncosts.Wehavesinceacquiredacopyofthe"GuidetotheUseofFidlicConditionsofContractforWorksofCivilEngineeringConstruction"andtheexplanationgivendoesnotadequatelycoverus,referpage117oftheguide.Pleaseadviseusonhowthisclauseistobeapplied.

    ANSWER

    ThepreciseproblemisnotclearandwecanonlycommentingeneraltermsontheinterpretationofSubClause52.3.TheSubClauseallowstheContractorandEngineertodiscussandagreealumpsumadditionordeductiontotheContractPricewhentheadditions/deductionsasdescribedat(a)and(b)aremorethan15%ofthe"EffectiveContractPrice".ItwillbeuptotheContractortoprovethechangestohisSiteandgeneraloverheadcosts.ThedetailsandcalculationofthelumpsumwilldependantonthereasonsfortheincreaseordecreasetotheContractPrice.

    UNITRATESQUESTION

    1.ThefollowingadditionhasbeenmadeinClause52.2(FIDIC1987,ContractforWorksofCivilEngineering)inourcontractbytheEmployer:"..ProvidedfurtherthatnochangeintheUnitRatesorpricesquotedshallbeconsideredforanyitemintheSchedulestotheBillofQuantities,unlesssuchitemindividuallyaccountsforanamountofmorethan2percentofthesumnamedintheLetterofAcceptance,andtheoriginalbilledquantitybymorethan30percent.Notwithstandingabove,forvariationexceeding10%inquantityofanyitemofBOQwithrespecttooriginalBOQquantities,thefollowingshallapplytotheunitrateofthatitem:a)ForratesquotedbelowCSR2000rates,nochangeinquotedunitrateshallbeallowed.b)ForratesquotedaboveCSR2000rates,thequantityexceeding10%fromoriginalBOQquantityoftheitemsshallbepaidtothecontractorasperNHACSR2000ratesapplicableintherelevant

  • 3/28/2015 Contracts:advancedquestionsRedBookQuestion/Answer|InternationalFederationofConsultingEngineers

    data:text/htmlcharset=utf8,%3Cdiv%20class%3D%22field%20fieldnamefieldpagesummary%20fieldtypetextlong%20fieldlabelhidden%22%20style 18/28

    district.ProvidedfurtherthatfornonBOQitemsappearinginNHAsCSR2000,CSR2000ratesshallapplywhereastheratesofnonCSR&nonBOQitemsshallbedeterminedbytheEngineerasstipulatedinGeneralConditionsofContract."2.TheSituationBOQItemNo.108b(i)FormationofembankmentfromroadwayexcavationinRockmaterial(HardRock)andBOQItemNo.106d(i)ExcavateSurplusRockmaterial(HardRock)hasincreasedupto453%and77.8%respectivelyfromtheOriginalBilledQuantityandtheseItemsareindividuallyaccountingformorethan2.55%and4.99%respectivelyofthesumnamedintheLetterofAcceptance.Therefore,wedesiretorequesttheEmployer/TheEngineerthattheUnitRatesforthesaiditemsasquotedintheBOQfortheentirequantitybechangedandtillthetimenewratesarefixed,theprovisionalratesorpricesbedeterminedinaccordancewithCSR2005with25%Premiumtoenableonaccountpayment.3.Questionsa)Willtherevisionofratesbebasedoncompositescheduleofrates2005(CSR2005)with25%premiumasrequestedbyus?b)Aresubparagraphsaandboftheadditionmadeinthesaidclause(refertopara1above)applicabletousasweconsiderthatthesaidsubparagraphsarenotrelevanttousbecauseourvariationisover30%.c)WillRevisedRatesbeapplicabletotheentirequantityoronlyonvariedquantity?d)Withsomuchvariation,isitalrighttoaskfordeterminationofProvisionalrates?

    ANSWER

    Asageneralprinciple,FIDICexpresslyprohibitsusersofitscontractstoaddandadjustClausesintheGeneralConditions.AnyadjustmentsandchangesshouldbemadeintheParticularConditions.However,sinceyourOrganizationmaynotberesponsibleformisuseandbreachofcopyrightweshallattempttohelpyou.Buthereagain,FIDICisabletoofferadviceoninterpreationofclauses,butofcourseonlyontheclauseofthecontractsGeneralConditions,notonsomeoneelse'sclauses.Thissaid,onceagain,weshalltrytobehelpfulontheunderstandingthatinfutureyoutrytoimpressonclientsthattheyshouldusetheGCscorrectly,andnotrisklegalactionandcontractinvalidityowingtobreachofcopyright.ThechangestotheGCmeanthattheinterpretationoftheFIDICSubclause52.2maynotberelevanttotheamendedcontract.Howeverthefollowingmaybehelpful.a)ImpossibletoanswerbecauseofthechangestotheGC.b)ImpossibletoanswerbecauseofthechangestotheGC.c)Revisedratesarenormallyonlyapplicabletotheadditionalquantitybutthisdependsonthecircumstancesandthemakeupoftherevisedrates.IndeterminingrevisedratestheEngineershouldtakeallfactorsintoconsideration.d)TheContractorisentitledtobepaidforworkdoneinaccordancewithSubClause60.2.IftherevisedratescannotbeagreedintimeforthenextInterimPaymentCertificatethentheEngineershoulddetermineprovisionalratesasthelastsentenceofthefirstparagraphofSubClause52.2.IfthefinalrateisdifferenttothisprovisionalratethenInterimPaymentCertificatescanbecorrectedasSubClause60.4.

    ADDITIONALSUMFORREPLACEMENTCOSTQUESTION

    WearerequestingaclarificationoftheintentionofClause21.1(b)InsuranceofWorksandContractor'sEquipmentoftheFIDICCivilEngineeringConstruction1987(4thEdition)Part1.ThereappearstobeamixedInsurancemarketviewastowhethertheadditionalsumof"15%ofsuchreplacementcost"forProfessionalFees,DemolitionandRemovalofDebrisappliesto:(1)eachofthesecostsindividually,or(2)asacombinedamount,and(3)whetherthisamountshouldbeappliedasapercentageoflossorapercentageofthesuminsured(contractvalue).OurContractorsarekeentohaveclarification.

  • 3/28/2015 Contracts:advancedquestionsRedBookQuestion/Answer|InternationalFederationofConsultingEngineers

    data:text/htmlcharset=utf8,%3Cdiv%20class%3D%22field%20fieldnamefieldpagesummary%20fieldtypetextlong%20fieldlabelhidden%22%20style 19/28

    ANSWER

    ThewordingofSubClause21.1(b)shouldbeclear.Theinsuranceshallcoverthefullreplacementcostas(a),plusanadditional15%ofthatfigure.Thisadditional15%istocoveranyadditionalandincidentalcosts,INCLUDINGprofessionalfeesetc.ThisfiguremaybechangedintheParticularConditionsandyoushouldalsorefertotheFIDICGuidetothe4thEdition,atpage72.

    EXCESSQUANTITIESOFWORK(SUBCLAUSE52.3)QUESTION

    Iam"TheEngineer"ofProjectandhaverecommendedreratingofcertainitemsofworkundertheprovisionsofClauses52.2oftheContract.Ihavehoweverfailedtounderstandfromthegivenprovisionisthat:a)TheEngineershallevaluateatthetimeofTakingOver,iftheContractCosthasincreasedordecreased()15%oftheoriginalcostofcontract,asaresultof:i)allworkexecuted&measuredisinexcessofBOQqualities.b)ThentheEngineershalldeterminesuchfurther"Sum"thatmaybeaddedordeductedfromthecontractprice,takingintoregardtheContractor'ssiteandgeneraloverheadcostsoftheContractbasedupononlytheamountbywhichsuchadditions/deductionswillbeinexcessof15%oftheEffectiveContractprice.InmyopiniontheExcessquantitiesofworkhavebeentakencareofbyreratingunderClause52.2andnofurtherSummaybeaddedtotheContract.DoestheClause52.3intendtoapplythereratingonquantitiesthataremorethan15%oftheBOQquantitiesthusrerated.Iquoteanexample:letusassumethecostofContractasUSD100000.ABOQitemcostingUSD20000isincreasedtovalueUSD50000atcontractrates.HencereratingunderClause52.2becomesapplicable.Onreratingthevalueof(original+increased)qtyofworkbecomesUSD55000.Nowthetotalvalueofcontract,i.e.,USD55000.Thevalueofworkbeyond15%ofcontractpriceis$40,000.IstheContractorentitledtoadditionalpremiumunderClause52.3forExecutingworkbeyond15%ofContractprice.IsthiswhatismeantbytheprovisionoftheClause52.3?

    ANSWER

    Clause52.2referstothereratingofanindividualvariation.Clause52.3referstothesituationwhenthetotaleffectofallvariations,plustheremeasurementoftheapproximatequantitiesintheBoQresultsinanincreaseordecreaseofmorethan15%.ItispossiblethateachindividualvariationdidnothaveasignificanteffectontheContractor'soverheadsbutthetotaleffectofallvariationsandtheremeasurementwassignificant.ItisnecessarytoconsidertheactualeffectoftheadditionalquantitiesontheContractor'soverheads.Forexample,partoftheallowanceforoverheadsmaybeafixed,orlumpsum,figurewhichisnotrelatedtothequantityofworkwhichhasbeencarriedout.Asubstantialincreaseinthetotalquantityofworkmaynotincreasethispartoftheoverheads.Hence,theoverheadsperunitquantitywoulddecrease.Theallowanceforoverheadsintherateswouldneedtobereconsidered.AnyreratingunderClause52.2wouldbetakenintoaccountwhenconsideringClause52.3.TheGuidetotheFourthEditionpublishedbyFIDICgivesusefulguidanceandexamplesatpages115and117.

    FREEHAULAGEQUESTION

  • 3/28/2015 Contracts:advancedquestionsRedBookQuestion/Answer|InternationalFederationofConsultingEngineers

    data:text/htmlcharset=utf8,%3Cdiv%20class%3D%22field%20fieldnamefieldpagesummary%20fieldtypetextlong%20fieldlabelhidden%22%20style 20/28

    Myinquiryis:aretheiranyguidlinesformaximumFREEHAULAGEdistance...fortheTERMBORROWmaterialstobeengagedinEMBANKMENTCONSTRUCTION....sinilarly....whatfreedistancelimitsareset/providedinFIDICforanytransportationofmaterial....fromBORROW,fromthesiteofe.g.,asphaltmixingorconcretemixingplanttothesiteofaccomodatingthefinishedproductintheroadconstructionprojects.

    ANSWER

    TheFIDICConditionsofContractgivethelegalrightsandobligationsofthePartiestotheContract.Matterssuchasthemaximumfreehaulagedistancewilldependontherequirementsanddetailsoftheproject.Theywillvaryfordifferentprojectsandshouldbegiveninthetechnicalspecificationsand/orbillsofquantities.

    ENFORCINGACLAIMQUESTION

    IamrequestinganinterpretationofClause63.2and63.3oftheFIDICRedBook,4thEdition.a)WhenaContractorhassumsduetoitarisingoutofavaluationunderClause63.2atthetimeoftermination,andtheEmployer/EngineerdelayscertificationofpossibleclaimsunderClause63.3,howdoesFIDICenvisagethattheterminatedContractormayenforceitsclaim/obtainthosesumscertifiedbytheEngineerasbeingduetoit?b)Onceanewcontractorhasbeenengaged,isthedatescheduledforcompletionunderthenewcontractrelevant,andwhenisthenewcontractorliableforfurtherdelaystothecompletiondate?c)IsthereadutyontheEmployerorEngineertoinformthefirstContractorthattheprojecthasbeencompleted?Whenthedefectsliabilityperiodisover?d)IsthereadutyontheEmployer/EngineertoissueacertificateinaccordancewithClause63.3withinareasonabletime?Whatmaybeconsideredareasonableperiodforissuingsuchacertificate?e)WhatarethepossibilitiesforaContractortoobtainthemoniesdueunderClause63.2iftheEngineerfailstoissueacertificateunderClause63.3.?

    ANSWER

    Thisisreallyalegalquestion,butthekeyseemstobethatthefirstsentenceofClause67.1saysthatitcontinuesaftertermination.Afewadditionalcommentsmaybehelpful.OneassumestheenquiryisreferringtotheFourthEdition,amended1992,withoutanysignificantamendments.MattersarisingfromterminationunderClause63.1willdependontheprovisionsoftheapplicablelawaswellasFIDICContractClauses.Mostlegalsystemsincluderequirementsfortheterminationofacontractandalsocontainprovisionsbasedontheconceptof"goodfaith"whichmaybeapplicable.AnycommentsbasedontheFIDICContractmustbereviewedinrelationtotheapplicablelaw,butsomegeneralcommentsmaybehelpful.a)Clause67.1,firstsentence,saysthatitcontinuesaftertermination.b)Clause63.1enablestheEmployerto"terminatetheemploymentoftheContractor".TheClauseisclearthatthisdoesnotreleasetheContractorfromanyofhisobligationsorliabilities.SodoesthelawrequirethattheEmployeralsoisnotreleasedfromhisobligations?IfsothenotherClauseswillalsoberelevant.c)Thenewcontractorispresumablyliablefordelayswhichhecausesandwhicharenotattributabletothepreviouscontractor.d)Clause1.5,finalsentence,requiresthatanyconsent,approval,certificateordeterminationshallnotunreasonablybewithheldordelayed.e)Clauses60.6and60.8givetimeperiodsfortheContractor'sFinal

  • 3/28/2015 Contracts:advancedquestionsRedBookQuestion/Answer|InternationalFederationofConsultingEngineers

    data:text/htmlcharset=utf8,%3Cdiv%20class%3D%22field%20fieldnamefieldpagesummary%20fieldtypetextlong%20fieldlabelhidden%22%20style 21/28

    StatementandtheEngineer'sFinalPaymentCertificate.Clause63.3requirestheEngineertoissueacertificate,withoutstatingatimeperiod.ByreferencetoClause1.5,thismustbeissuedinareasonabletime.ReasonablemightbebasedontheClause60.6and60.8timeperiodsunlesstherearespecialcircumstances.f)ItcertainlyseemsnecessaryfortheContractortobeinformed,orhisquestionstobeanswered,inorderthatheknowswhentheconstructionandDefectsLiabilityPeriodsarecompleted.g)TheContractor'srightsandproceduresforobtainingpaymentarecoveredbyClause67andtheapplicablelaw.

    NEWRATEORPRICEQUESTION

    WeareaconsultingfirmprovidingContractAdministrationServicestoContractorsinPakistan.WhileseekingassistancefromtheFIDICwebsiteFAQSection,wehavecomeacrosstheadviceuponSubClause52.2ofRedBook4thEdtionConditionsofContractPartIIstatingthereinthat:theratewhichtheEngineeragreesorfixesunderSubClause52.2wouldonlyapplytothevariedquantity(increasedordecreased).TheoriginalquantityisnotpartoftheVariationandwouldbepaidattheoriginalrate.TherationalebeingusedinconstruingtheSubClause52.2intermsthattheRevisedRatesunderSubClause52.2willbeappliedtothevariedquantityonlyhascreatedmuchconfusioninsomeoftheongoingprojectswiththeNationalHighwayAuthority,Pakistan.AspertheadviceofFIDICSecretariatFAQSection,ifforinstance,aContractor'soriginalBOQworkincreasesfrom100m3to140m3,thenheshallbepaidfor100m3asperoriginalratesandfortheremaining40m3,revisedratesshallbeapplicable.IfweapplythesamelogicinacasewheretheContractor'soriginalBOQworkdecreasesfrom100m3to60m3,thenheshallbepaidfor100m3asperoriginalquantityofwork.Whereas,forthedecreasedquantity,heshouldbepaidattherevisedrates(althoughheshallbeactuallyexecuting60m3work.).Thesameistrueforthecasewhentotalexecutedquantityexceedsbymorethan30%andthenewrateshallbeapplicabletothetotalexecutedquantity.ThesameClausecannotbeconstrueddifferently.Ifthisdoesnothappen,thenitshallcauseprejudicetotheinterestoftheContractor.

    ANSWER

    UnderSubClause52.2,theEngineeronlyfixesanewrateorpricewhentheBOQrateorpricehasbecomeinappropriateorinapplicableforaparticularVariation.Infixingthenewrateorpricehewillconsiderthereasonswhytheoriginalrateorpriceshouldbechanged.Hewillnotfixanewrateorpriceuntilheknowswhetheritinvolvesanincreaseordecreaseinquantity.Thenewrateorpricewillprobablybedifferentforadecreasetothatforanincrease.Itmaybedifferentforalargeincreasetoasmallincrease.TheanomalieswhichyoumentionshouldnotoccurbecausetheEngineerwillhaveconsideredthesesituationsbeforehefixesthenewrateorprice.

    NEWBOQRATESQUESTION

    Acontractwasdrawnupforaspecificlengthofhighway.Realignmentwasrequiredwhichincreasedthelengthbyafewkilometers.ShouldthisadditionalworkbeincludedinavariationorderasperClause51or

  • 3/28/2015 Contracts:advancedquestionsRedBookQuestion/Answer|InternationalFederationofConsultingEngineers

    data:text/htmlcharset=utf8,%3Cdiv%20class%3D%22field%20fieldnamefieldpagesummary%20fieldtypetextlong%20fieldlabelhidden%22%20style 22/28

    shouldaseperatecontractbefloated.Thecontractorisaskingforsinglevariationorderwithtwodifferentrefixedrates(forthesameitemofBoQ),oneforthevariationintheoriginalworkandsecondfortheadditionalwork.Idifferwithhisviews.Ifeelthatifonevariationorderisconsideredforthewholeworkthenonlyonlyonerefixedrateforvariedquantitycanbegiven.Irequireyouradviceonthisissue.

    ANSWER

    Ifboththechangetotheoriginalworkandtheadditionalworkcamefromthesamechangeofrequirementandinstructionthenitwouldbeusualtoissueasinglevariationorder.However,itisalsoquitenormalforthepricecalculationsforavariationordertoincludedifferentratesforthesameBoQitem.Thecontractor'scostsandthereasonswhytheBoQratesareinappropriatemaybedifferentforthevariedworkandfortheadditionalwork.Itisthenfairerandmoretransparent,tothebenefitofbothparties,tonegotiatedifferentnewrates.

    NEWVARIATIONORDERQUESTION

    Acontractwasdrawnforaspecificlengthofhighway.Realignmentwasrequiredwhichincreasedthelengthbyfewkilometers.shouldthisadditionalworkbeincludedinavariationorderasperClause51orshouldaseperatecontractbefloated.Thecontractorisaskingforsinglevariationorderwithtwodifferentrefixedrates(forsameitemofBoQ),oneforthevariationintheoriginalworkandsecondfortheadditionalwork.Idifferwithhisviews.Ifeelthatifonevariationorderisconsideredforthewholeworkthenonlyonlyonerefixedrateforvariedquantitycanbegiven.irequireyouradviceonthisissue.

    ANSWER

    Ifboththechangetotheoriginalworkandtheadditionalworkcamefromthesamechangeofrequirementandinstructionthenitwouldbeusualtoissueasinglevariationorder.However,itisalsoquitenormalforthepricecalculationsforavariationordertoincludedifferentratesforthesameBoQitem.Thecontractor'scostsandthereasonswhytheBoQratesareinappropriatemaybedifferentforthevariedworkandfortheadditionalwork.Itisthenfairerandmoretransparent,tothebenefitofbothparties,tonegotiatedifferentnewrates.

    INSTRUCTIONSTOVARYTHEWORKSQUESTION

    Weareexecutingaconstructionworksproject(18floortower),nowthereisanadditionoftwomorefloors.Iwouldliketoknow...thisadditionwouldbedealtasavariationorseparatecontractrequired,wherewewillhavethelibertytorevisetheprice,sincethistwofloor'sadditionislessthanthe25percentofthecontractvalue,hencewedonthaverighttoincreasetheprice,inceaseifwedealitbyvariation.pleaseclarify.

    ANSWER

    Clause51.1allowstheEngineertoissueinstructionstovarytheWorks.Yourquestioniswhetherthe

  • 3/28/2015 Contracts:advancedquestionsRedBookQuestion/Answer|InternationalFederationofConsultingEngineers

    data:text/htmlcharset=utf8,%3Cdiv%20class%3D%22field%20fieldnamefieldpagesummary%20fieldtypetextlong%20fieldlabelhidden%22%20style 23/28

    additionaltwofloorsarejustachangetothequantityoftheworkwhichisincludedintheContract,asClause51.1(a),orareoutsidethescopeoftheWorks,whichshouldbedefinedintheContract.TheanswertoyourquestionthereforedependsontheexactwordingoftheContractAgreement,theothercontractdocumentsandperhapsalsotheTenderDocuments.Itwillalsodependontheinterpretationofthiswordinginaccordancewiththeapplicablelaw.ThisisnotsomethingwhichFIDICcananswerandyoushouldobtainspecialistadvice.

    FIXINGOFANEWRATE(RED4:52.2)QUESTION

    WerequestedfortheclarificationregardingrepliestoacoupleofquestionswhichappearattheFAQSectionofFIDICwebsite.ReplytothefirstquestionillustratesthatunderSubClause52.2,EngineermayfixanewrateorapriceiftheBOQratebecomesinappropriateorinapplicableforaparticularvariation,keepinginviewthereasonsforthechange.Inreplytothesecondquestion,FIDICsaysthattheoriginalquantityisnotapartofthevariationandcannotbepaidattherevisedrate.Repliestothequestionsasnotedabovearecontradictorytoeachotherandwethinkthatthemattershouldfurtherbeclarified.Ourelaboratenote,whichwassubmittedtothiseffectconstitutesofourunderstandingoftheClause52.2oftheRedBook4thEdition.ThedefinitionofthevariedworktricklestotheClause52.2fromtheClause51.1,whichgivesthedefinition/scopeofthevariedworkasfollowing:(a)increaseordecreasethequantityofanyworkincludedintheContract,(b)omitanysuchwork(butnotiftheomittedworksistobecarriedoutbytheEmployerorbyanothercontractor),(c)changethecharacterorqualityorkindofanysuchwork,(d)changethelevels,lines,positionanddimensionsofaypartoftheWorks,(e)executeadditionalworkofanykindnecessaryforthecompletionoftheWorks,(f)changeanyspecifiedsequenceortimingofconstructionofanypartoftheWorks.Thegivendefinitionthusholdsthatthevariedworkmaynotessentiallycompriseofonlythechangeinthequantityofcertainitemincludedinthecontract.Variedworkmayalsoariseoutofthevirtueofotherreasonsasnotedabove.Hence,restrictingthedefinitionofvariationonlytothechangeinquantitymaynotbeappropriate.ThereplygivenattheFIDICwebsitetothefirstquestion,ashasbeenreferredabove,seemstoholdthesameviewbythevirtueofwhichthedecisiontothiseffecthasbeenlefttotheEngineer.However,thereplytothesecondquestionforwardsratherarestrictiveinterpretationoftheClause52.2bysayingthatanewratewouldapplyonlytotheincreased/decreasedquantity.SuchaninterpretationfallsincontradictiontothedefinitionofthevariedworkaswellastheopenendedspiritoftheFIDICDocumentingeneralandthatoftheClause52.2,readinconjunctionwiththeClauses51.1,51.2and52.1therebefore,aswellasthatoftheClauses52.3and52.4thereafter......FIDIC'sinitialreply:FIDICcanonlycommentingeneraltermsontheinterpretationofaFIDICclause.Ifyourequireamoredetailedopinionontheapplicationofaclausetoaparticularproblemsituationthenyoushouldconsultaspecialist.TheexamplesinyourletterillustratethewiderangeofsituationswhichmayariseonaprojectandresultintheapplicationofClause52.2.Forthisreason,theclausecannotrestricttheEngineerinthewayhecalculatesanewrate.TheEngineerisawareoftheexactsituationandsocanmaketheappropriatedecisiontosuitthewordingandapplicationoftheVariation.AVariationnormally,butnotalways,onlyappliestoworkwhichhasnotyetbeenexecuted.Ifsomeworkhasalreadybeencarriedoutonthesamebasisaswasenvisagedfortheoriginalbillratethenthatworkwouldnormallybevaluedatthebillrate.HoweveraparticularVariation,suchasadecreaseinquantity,maybewordedinsuchawayastorequireadifferentapproach.........Yourreplyalsonarratesthatour

  • 3/28/2015 Contracts:advancedquestionsRedBookQuestion/Answer|InternationalFederationofConsultingEngineers

    data:text/htmlcharset=utf8,%3Cdiv%20class%3D%22field%20fieldnamefieldpagesummary%20fieldtypetextlong%20fieldlabelhidden%22%20style 24/28

    understandingoftheissuefallscloselytoacertainprojectspecificlegalopinion.Webelievethatsuchaconcurrenceonthematterhasbecomeevidentonlybecauseoftheproperunderstandingoftherationale.Thisparticularlyholdswhenwealsoconsiderthepossibilityofvariationbecauseofthedecreaseinthequantityofcertainitemsofwork.NologicwouldallowthatthedecreasedquantitywhichisnotexecutedmaybepaidatsomerevisedratefixedbytheEngineer.Therevisedratewouldcertainlyapplytothequantityexecuted.TherationalethusdemandsthesametreatmentforfixingoftheratebytheEngineerincaseofvariationinthequantityofcertainitemsoftheworkbecauseofanincrease,givinganobviousreasonofourunderstandingofthematterinlinewiththelegalopinioninthesimilarcontext.Yourreplydated7thJune2007furtherseemstoacknowledgethattheexactsituationundersuchacasemayonlybedeterminedbytheEngineerthroughanappropriatedecision,ashasbeenprovidedunderthespiritoftheFIDICDocument.However,thecommentsthereafter,onceagainseemtorestrictthedefinitionofvariation.So,tocontinue:regardingfixingofanewrate(Red4:52.2)Regardingourqueryregardingreratingofthevariedquantity.WeseektheclarificationregardingtheopinionofFIDIConreratingofthevariedquantity,asshownintheFAQSectionoftheFIDICwebsite.Ourdebate/discussionasappendedwithourqueryisonlymeanttoexpressourunderstandingthattheSubClause52.2onlytalksofthe"variedwork"andnotthe"variedquantity",which,however,remainssubservienttothedefinitionof"variedwork".TheactualintentionofourquerythusremainstoseektheclarificationinlightoftheSubClause52.2ofCivilWorkscontract4thEdition,1987.Tothiseffect,itmaybedeemedappropriatethatthewritersofthisparticularclauseortherelatedbackupmaterialmaybeconsultedsothattheambiguityortheconfusion,ashasarisenregardingthevariedworkthroughtheopinionofFIDICintheFAQsection,mayberemovedandtheprestigeoftheorganizationlikeFIDIC,whichisconsideredasanapexbodyincontractadministration,wouldbemaintained.

    ANSWER

    Thankyouforyourmoredetailedexplanationofyourquery.Ourrepliestopreviousquestionswereinresponsetoparticularquestions,whereasyourquestionisratherdifferent.Youare,ofcourse,correctthatVariationsunderSubClause52.1cancoverawiderangeofsituations,includingchangestothenatureaswellastothequantityofanitemofwork.Forthisreason,SubClause52.2mustbegeneraltocoverthewiderangeofpotentialsituations.ItisthenfortheEngineertoassesstheparticularsituationandtoagreeorfixanappropriaterate.Indecidingthequantum,andalsotheapplication,ofthisratetheEngineerwouldtakeintoaccounttheconsequencesofachangeinnatureaswellasachangeinquantity.YoushouldalsonotetheexplanatoryremarksintheFIDICGuidetotheuseoftheFIDICConditionsofContractforWorksofCivilEngineeringConstruction.SubClauses52.1and52.2arereviewedatpages114and115oftheGuideandincludethestatement:IfthenatureoramountoftheworkinvolveddifferssomuchfromthatincludedintheoriginalContractthattheratesandpricesarerenderedinapplicable,itistheEngineer'stasktoagreeappropriateratesandpriceswiththeContractor,or,ifagreementcannotbereached,tofixtheratesandprices.Wetrustthisfurtherexplanationwillansweryourquery.Anyfurthercommentswouldrequiredetailsofthespecificcontractandproblem,whichFIDICcouldnotconsider.

    UNDUEDELAYFORCLAIMSQUESTION

    Canyoupleaseidentifywhatismeantby"withoutunduedelay"underRedBook4thEditionclause44.3

  • 3/28/2015 Contracts:advancedquestionsRedBookQuestion/Answer|InternationalFederationofConsultingEngineers

    data:text/htmlcharset=utf8,%3Cdiv%20class%3D%22field%20fieldnamefieldpagesummary%20fieldtypetextlong%20fieldlabelhidden%22%20style 25/28

    consideringthattheContractorandtheEngineerhavemutuallyagreed,undercl.44.2(b),tosubmitdetailedparticularseveryfirstweekofthemonthandnotingthateverymonththecontractorissubmittingthesame.Whatisthedurationneededbyengineertoprovidehisinterim/finaldeterminationofextensionoftimeclaimsunderthisclause?

    ANSWER

    YourquestionreferstoSubClause44.3intheRedBook,FourthEdition1987.SubClause44.2hasimposedtimelimitsforthesubmissionofinformationbytheContractor,whichyousayhavebeenagreed.FIDICdoesnotimposeatimelimitontheEngineerbecausetheactualtimeneededforhimtomakehisdeterminationwilldependonthecircumstancesandthedetailsintheinformationprovidedbytheContractor.Howeverthe"withoutunduedelay"emphasisestheneedforthedeterminationtobemadeassoonaspossible.SubClause1.5alsorequiresthatanydetermination"shallnotunreasonablybewithheldordelayed".ThisgivestheContractortheopportunitytoraiseaqueryifheneedsthedeterminationinordertoplanhiswork.

    PAYMENTONACLAUSE63.2VALUATIONQUESTION

    ConcerningClause63.2and63.3oftheFIDICRedBook4thEdition.TheContractwasterminatedbytheEmployerpursuanttoClause63.1(thisisundisputed).ItwasagreedthattheadditionalcoststotheEmployerofexecutingtheworksbyanalternativecontractorhastobedeductedfromthevalueoftheworksexecutedbythefirstContractor.ThewordingofClauses63.2and63.3wasnotchangedoramended.ContractornowrequestsapaymentfromtheEmployercalculatedpursuanttoaClause63.2valuation.InadditionContractorstatesthatthewholeoftheWorkshasnotcompletedand,therefore,theDefectsLiabilityPeriodhasnotexpired,whichisaprecedenttoanycertificationofEmployer'scostsunderClause63.3.Therefore,anEmployer'sapplicationforClause63.3costsispremature,cannotbeconsideredandContractorisentitledtorequestapaymentbasedonthecalculatedClause63.2valuationwithoutanydeductionpursuanttoClause63.3.a)IsacontractorentitledtoaskforapaymentbasedonaClause63.2valuation,sinceanemployerisnotobligedtomakeanyfurtherpaymentuntiltheexpirationoftheDefectsLiabilityPeriod?b)IsitcorrecttointerpretthatContractor'srequestforpaymentbasedonClause63.2isnot(currently)justifiedalsoincases,whereacompletionoftheprojectwasdelayedduetocircumstancescausedbyanalternativecontractorortheemployer,iftheterminatedandrequestingContractoritselfhasformallyandexplicitpleadedthatthewholeprojectisnotcompletedwithoutcomplainingthedelayofcompletingtheprojectcausedbythealternativecontractorortheemployer?c)CantheContractorsimultaneouslyrefertoandrequestaClause63.2calculatedclaimandreject(alleged)unmaturedEmployer'sClause63.3costs,ifbothclauseswereagreed?

    ANSWER

    Thisisacomplextechnical/legalquestionarisingfromaspecificrequestbytheContractoronyourproject.FIDICcanonlyanswergeneralquestionsofinterpretationandcannotcommentonspecificrequestsorclaims.TheFIDICGuidetotheFourthEditionstatesatpage146forSubClause63.3:"IftheEmployerterminatestheContractor'semployment,heisnotliabletopaytheContractoranyfurtheramounts

  • 3/28/2015 Contracts:advancedquestionsRedBookQuestion/Answer|InternationalFederationofConsultingEngineers

    data:text/htmlcharset=utf8,%3Cdiv%20class%3D%22field%20fieldnamefieldpagesummary%20fieldtypetextlong%20fieldlabelhidden%22%20style 26/28

    (includingdamages)untiltheexpirationoftheDefectsLiabilityPeriodandthecertificationbytheEngineerofthecostofexecutionandremedyingofanydefects,damagesfordelayincompletion(ifany)andotherexpensesincurredbytheEmployerasaresultoftheContractor'sdefault."

    WHENISPAYMENTMADEQUESTION

    Weareseekingadefintionastowhenpaymentisactuallymadebytheemployertothecontractor.Isitwhentheemployerissueshispaymentinstructiontohisbank,orispaymentdeemedtobemadeoncethemoniesarereceivedinthecontractor'sbankaccount.ArethereFIDICguidelinesonthismatter?

    ANSWER

    yourqueryisreallyagenerallegalquestionaboutwhenapaymentis"made",ratherthanaquestionofinterpretationofaFIDICcontract.Theanswermaybedifferentunderdifferentjurisdictions.Youshouldconsultalawyerwithexperienceoftheapplicablelaw.

    STATUTORYDECLARATIONQUESTION

    MyfirmisexecutingaContractwithFIDICtermsandconditionsandIrequireaStatutoryDeclarationdocumentforinternationaluse(ProjectlocationisMadagascar).CanyoupleaseadvisewhereIcanfindthisinyourdocumentation,orbetteryetcanyouemailmetheappropriatedocument.

    ANSWER

    YourStatutoryDeclarationwouldseemtoconflictwiththeprinciplesoftheFIDICContracts.Progresspaymentsarereferredtoas'interim',whichsuggeststhattheyareprovisionalandnotfinal.EPCTSubClause14.6allowstheEmployertomakecorrectionsormodificationstopreviousamountsconsidereddue,whichsuggeststhattheContractorcanrequestmodificationstoapreviousvaluation.ItisonlytherequirementfortheApplicationfortheFinalPayment,asSubClause14.11,whichuseswordsindicatingfinality.TheContractorthenconfirmsthefinalitybyhisDischarge,asSubClause14.12.Theequivalentprovisioninthe1987RedBookwasSubClause60.7.TheStandardLetterforthatSubClausemerelyrepeatedthewordingoftheSubClause.However,thiswasacontractualletterandnotaStatutoryDeclaration.AStatutoryDeclarationwillpresumablybeissuedbytheGovernmentandwilldependontherequirementsoftheapplicablelaw,whichwillvaryfordifferentcountries.

    FINALANDBINDINGDABDECISIONQUESTION

    Inthe1992reprintedversionofthe1987FIDICConditionsaswellasinthe1999FIDICConditionsitis,intherelevantDABClauses,statedthattheContractor,EmployerandEngineershallgiveeffectforewithtoeverydecisionoftheBoardunlessanduntilthedecisionisrevisedinanamicablesettlementoranarbitrationalaward.OntheotherhanditisstatedthataBoarddecisionbecomesFINALandBINDING

  • 3/28/2015 Contracts:advancedquestionsRedBookQuestion/Answer|InternationalFederationofConsultingEngineers

    data:text/htmlcharset=utf8,%3Cdiv%20class%3D%22field%20fieldnamefieldpagesummary%20fieldtypetextlong%20fieldlabelhidden%22%20style 27/28

    unlesseitherpartygivesanoticeofdissatisfactionwithin28daysafterreceivingtheBoarddecision.Averybasiclegalprincipleisthatonlyfinalandbindingdecisionsareenforceable.AretheFIDICconditionsreallybasedontheveryunusualprinciplethattheEmployerhas,onbasisofununbindingBoarddecision,topaytotheContractoracompensationwiththeconsequenceofrunningtheriskofneverbeingabletorecoverthepaidamountfromaforeigncontractorwhentherevisedarbitrationawardisissued(long)afterthecompletionoftheworks.PleaseclarifywhethertheEmployerhastopayamonetarycompensationonbasisofaBoarddecision,whichisNOTFINALANDBINDING.

    ANSWER

    SubClause20.4ofthe1999ContractsisclearthatbothpartiesshallpromptlygiveeffecttotheDABDecision.TheEmployermustpayanysumawardedtotheContractoralthoughthesumtobepaidmaybechangedbyalateramicablesettlementorarbitration.IfaNoticeofDissatisfactionhasbeenissuedthenthedispute,nottheDABdecision,maybereopenedandfinallydeterminedbytheArbitralTribunal.Thesumtobepaidmaythenbeincreased,ordecreased,andadditionalmoneymayneedtobepaid,ormoneymayneedtoberepaid.AnArbitralAward,includingsuchfurtherpaymentorrepayment,wouldbeFinalandBindingandwouldbecoveredbyarbitrationlawandtheNewYorkConvention.ItisnormalpracticethataDABorAdjudicator'sDecisionisBindingandsomustbepaid,butisnotFinalandsomaybechangedinthisway.IfnoNoticeofDissatisfactionhasbeenissuedthentheDABDecisionbecomesFinalaswellasBindingandthedisputecannotbereopened.

    LUMPSUMCALCULATIONQUESTION

    Canyoupleaseadvisehowtocalculatethelumpsumtobeaddedordedcutedtothecontractpricewhentheeffectivecontractpriceexecceds15%.Inaddition,pleaseadviseonwhendowededuct,andwhendoweaddsuchamount.

    ANSWER

    Commentaryatpage117oftheFIDICGuidetothe4thEditionisrecommended.TheGuideexplainsthatsomeoftheContractor'soverheadcostsareincludedintheratesforitemsofworkandothersareincludedinseparateitemsintheBillofQuantities.ChangestotheactualquantitiesmaymeanthattheoverheadcontentofitemswhichhavepaidisnotappropriatetotheactualoverheadcostsincurredbytheContractor.InordertocalculateanyadjustmenttheEngineerwillneedtoobtaininformationfromtheContractor,orwouldhavetomakehisownassessment.AnycalculationmusttakeintoaccountanyadjustmentwhichhasalreadybeenmadeunderanotherSubClauseandonlyappliestoanyincreaseordecreaseinexcessof15%oftheEffectiveContractprice.TheSubClausestartswithareferencetothesituation"ontheissueoftheTakingOverCertificateforthewholeoftheWorks".ItisalsonecessaryforthevalueofvariationsandotheradjustmentstohavebeenagreedinordertomaketheSubClause52.3calculations.Anyadditionalpaymentordeductionwouldthenbemadeinthenextpaymentcertificateafterthefigureshavebeenagreedordetermined.

    NEWRATEFORANINCREASEDQUANTITY

  • 3/28/2015 Contracts:advancedquestionsRedBookQuestion/Answer|InternationalFederationofConsultingEngineers

    data:text/htmlcharset=utf8,%3Cdiv%20class%3D%22field%20fieldnamefieldpagesummary%20fieldtypetextlong%20fieldlabelhidden%22%20style 28/28

    QUESTION

    Iam"TheEngineer"foraroadconstructionproject.AdifferenceofopinionhasarisenontheapplicabilityofnewratesfixedbytheEngineeronthequantities,i.ewhetherthenewratewillbeapplicableonlyontheenhancedquantitybeyondtheoriginalBoQquantity,Ooritshallapplyontheentirequantity.Toexplainthisfurther,theBoQquantityforpileswas2000cum.Thedesignerincreasedthenumberofpilessothatthequantitybecame3000cum.TheEngineerfixedanewrateforpileworkfromXtoY.WillYratebeapplicabletoenhancedquantityof1000cum,orshoulditapplyto3000cum?

    ANSWER

    FIDICcanonlycommentingeneraltermsontheinterpretationofaFIDICclauses,anditshouldbenotedthatfortheapplicationofaclausetoaparticularproblemsituation,oneshouldalwaysconsultaspecialist.Withthatbeingsaid,ingeneral,SubClause52.2givesthepowertotheEngineertofixnewratesandstatestheconditionswhensuchnewratesmaybefixed,butSubClause52.2doesnotindicateacalculationmethodortheapplicabilityfornewrates.ThereasonforthisisbecauseSubClause52.2mustallowforcoveringawiderangeofpotentialsituations.So,althoughitistruethatrevisedratesarenormallyonlyapplicabletotheadditionalquantity,itisfortheEngineertoassesstheparticularsituationandcircumstancessurrounding,andtotakeallfactorsintoconsiderationinmakinghisdeterminationregardingthequantumandapplicabilityofthenewratesfixedunderSubClause52.2.Forreference,seepage127128oftheFIDICRedBookGuidetotheuseoftheFIDICConditionsofContractforWorksofCivilEngineeringConstruction,andpleasenotethattheaboverepresentsageneralansweronly,andspecificadvicetotheparticularfactssurroundingyoursituation,werecommendthatyouconsultaspecialist.