control progress
Embed Size (px)
TRANSCRIPT
-
8/13/2019 Control Progress
1/20
University of Western Australia
School of Civil and Resource Engineering
Project Management 362
16. Controlling progress during construction
Control
Project status
Feed-back controlFeed-forward control
General comments
University of Western AustraliaSchool of Civil and Resource Engineering 2003
-
8/13/2019 Control Progress
2/20
CONTROL
Monitoring the project provides the intelligence we need to makecontrol decisions.
Monitoring in itself is not control.
Using the intelligence i.e. the distilled information provided by CV andSV, allows us to decide and to act.
Remember, a decision NOT to act is a decision in itself.
Let us start this examination by considering the
information itself . . .
Consider a particular case of a project in the middle of
construction . . .
-
8/13/2019 Control Progress
3/20
This is the Gannt Chart for a 5 month project, with an estimated totalcost to the Contractor of $1.2M.
The project has been under construction for 2 months.
The Contractor now wishes to estimate the status of the project, i.e.to determine the Schedule Variance, and the Cost Variance.
Note the data date at which time data and cost data are collected andquickly transmitted to the project manager.
The data will be compared, using the S-curve, which is the BCWS. . .
ESTIMATION OF PROJECT STATUS
-
8/13/2019 Control Progress
4/20
=BCWS
Est.Costoutlay
$000
Cum.
cost =S-curve
data date
Now for the intelligence . . .
Estimation of project status
-
8/13/2019 Control Progress
5/20
Estimation of project status
First the Plan Data.
Note that the cost will be linearly distributed over theduration of each task.
Now the data reports, both time and cost . . .
PLANNED ACTUAL ANALYSIS
Totals: $1200k $470k $450k $450k +$5k -$15k
TASK %Complete
BudgetCost
%Complete
ACWP BCWS BCWP SV CV
A 100% $100k 100% $100k $100k $100k $0k $0k
B 75% $200k 75% $140k $150k $150k $0k +$10k
C 16.7% $300k 15% $90k $50k $45k -$5k -$45k
D 37.5% $400k 40% $140k $150k $160k +$10k +$20k
E 0% $200k 0% $0k $0k $0k $0k $0k
-
8/13/2019 Control Progress
6/20
TASK A
TASK B
TASK C
TASK D
TASK E
75%
15%
45%
FIELD OFFICE
TASK A
TASK B
TASK C
TASK D
TASK E
$140k
$90k
$140k
TASK % complete Costs incurred
A 100 $100k B 75 $140k
C 15 $90k
D 45 $140k
E 0 $0k
Processing . . .
-
8/13/2019 Control Progress
7/20
Estimation of project status
The reported data, both % complete
and cost of each task.
Note that the cost data will again bedistributed linearly over the durationof each task.
Lets divert to add
Progress Bars to the
Gannt Chart . . .
PLANNED ACTUAL ANALYSIS
Totals: $1200k $470k $450k $450k +$5k -$15k
TASK %Complete
Budget
Cost
%
Complete
ACWP BCWS BCWP SV CV
A 100% $100k 100% $100k $100k $100k $0k $0k
B 75% $200k 75% $140k $150k $150k $0k +$10k
C 16.7% $300k 15% $90k $50k $45k -$5k -$45k
D 37.5% $400k 40% $140k $150k $160k +$10k +$20k
E 0% $200k 0% $0k $0k $0k $0k $0k
-
8/13/2019 Control Progress
8/20
Estimation of project status
Progress Bars are added to the Gannt Chart, thus:
So Tasks A and B appear to be o.k.
Also Task D appears to be o.k.
But Task C looks a bit suspicious, doesnt it.
Note that Task C is fairly costly, so we are warned.
Finally, weanalyse the
data . . .
-
8/13/2019 Control Progress
9/20
Estimation of project status
Finally, the analysis of the data,using the Plan and reported data.
Conclusions:
Project is slightly ahead of schedule, but
Project is running $15,000 over budget.
PLANNED ACTUAL ANALYSIS
Totals: $1200k $470k $450k $450k +$5k -$15k
TASK %Complete
Budget
Cost
%
Complete
ACWP BCWS BCWP SV CV
A 100% $100k 100% $100k $100k $100k $0k $0k
B 75% $200k 75% $140k $150k $150k $0k +$10k
C 16.7% $300k 15% $90k $50k $45k -$5k -$45k
D 37.5% $400k 40% $140k $150k $160k +$10k +$20k
E 0% $200k 0% $0k $0k $0k $0k $0k
-
8/13/2019 Control Progress
10/20
FEED-BACK CONTROL
An engineering management system can be compared to a physicalsystem, e.g. air-conditioning, chemical processing, electrical, etc.
PLAN
SYSTEM
INPUT OUTPUT
Sensor(monitor)
Comparator
Using similar grahical representation, the management
system looks something like this . . .
-
8/13/2019 Control Progress
11/20
FEED-BACK CONTROL
PROJECT
PLAN
CONSTRUCTION
TEAM
ComparatorRegular Progressand Cost reports
PARTIALLY
COMPLETED
PROJECT
Correctiveaction
Action
By analogy with a physical system, the engineering management systemmy be represented thus:
Some lessons from the physical system:
need for prompt and accurate intelligence
compatibility of progress and cost data
prompt and carefully considered response to variance prompt application of corrective action
-
8/13/2019 Control Progress
12/20
FEED-FORWARD CONTROL
In a physical system, the engineer often employs feed-forward controlprocedures.
e.g. in air-conditioning, where daily or seasonal changes to outside
conditions are anticipated.e.g. in chemical systems, where anticipated changes in feed-stock aresignalled early, and corrective adjustment to reagents, or temperatures,or pressures are effected in advance of feed-back information.
So it is with management systems.
Industrial conditions, weather, road conditions, shortages of supply, etc,when anticipated, can be acted on.
Perhaps that is the artistic side the engineers life.
Now some general matters . . .
-
8/13/2019 Control Progress
13/20
Progressive refinement - rolling programmes
Changes to time and cost schedules occur in most contracts.
An orderly treatment of changes (Variations) is required to minimisedisruption of the contract, and to avoid disputes.
If a Provisional Sum (for contingencies) is included in the contract, thenchanges can be charged against this sum. Note that all parties,including Principal, must be in agreement with this procedure.
If a reasonable amount is entered against the PS, then the contract
does not appear to be exceeding budget if less than this Sum is utilised.
But note that changes may require re-programming of some tasks, andthat the critical path may be altered by this.
-
8/13/2019 Control Progress
14/20
Dealing with multiple contracts on one site
In large projects, two or more major contracts may be workingsimultaneously on site.
The contracts may be mutually dependent.
Therefore clear lines of responsibility must be defined for each contract,and must include time interfaces, technical interfaces, separate andjoint liabilities, etc.
These matters must be properly treated in the design anddocumentation.
Regardless, provisions should clearly define the need for each contractparty to liase and co-operate with all others.
When changes become necessary, all contract parties must be givenclear instructions on their changed position within their contracts.
-
8/13/2019 Control Progress
15/20
Integration of design and construction
When the classical organisational form prevails, the designermust treat construction procedures as vital to the project, anddesign accordingly.
When the design and construct organisational prevails, theresponsibility for such decisions resides with the contractor. Thisis the area in which many failures occur!
Remember that designers are frequently held responsible for site
failures, even though their responsibility does not apparentlyextend to this field of the project.
Documents must be clear on the delegation of responsibilities.
-
8/13/2019 Control Progress
16/20
Resource levelling
Resource levelling is concerned with using labour, materials, and plantcontinuously, and without erratic changes in resource quantities.
For example: 4 dozers for 3 days, then 2 dozers for 3 days, followed by 3dozers for 3 days is inefficient. This amounts to 27 dozer days, so it ismore efficient to use 27/9 = 3 dozers for the entire 9 days, if the schedulepermits.
A resource levelling procedure exists within MS-PROJECT for thispurpose.
-
8/13/2019 Control Progress
17/20
Include schedule refinement and control
The method of project control advocated in this course is basedon the Gannt Chart schedule.
The Chart should be under the control of a single party,responsible for all updating activities associated with theproject, including:
receipt and posting of progress reports from supervisors
and costing officers; changes to the schedule, and refinements as required;
preparation of status reports, for consideration and action bythe project management team.
-
8/13/2019 Control Progress
18/20
Running the Project
Regular meetings
Regular meetings, often on site, are essential for maintainingcontact with the project.
Minutes of such meetings provide an important record of whatwas happening, for future reference.
Appraisal of inspection and testing reports
It is useful for the results of inspections and tests to benoted to all parties, and recorded in the minutes of site
meetings.
-
8/13/2019 Control Progress
19/20
Skilled management of industrial relations
A good working knowledge of the general and site award conditionsrelevant to the project is important.
Remember that confidence of the workers in the skill of the engineer
is central to maintaining good site conditions.
Regular advice from company principals
Keep the Board of Management advised of progress and anyconcerns you have with the project.
Above all, seek advice on important matters. The Board will look
up to you when you show confidence in them.
Good luck with your projects in the future.
Thats enough for today. But next . . .
-
8/13/2019 Control Progress
20/20
NEXT
17. Waiting Line Models -
Queuing Theory!*$*@*!!
10 5 13 7