3/21/2012 1 DBIA Presentation on Building 249 Convert and Renovate Company Operations Facility (COF) Building 249 Joint Base Myer-Henderson Hall Contract Number W912DR-09-C-0061 DBIA Presentation on Building 249 Developing the RFP Army Military Construction—Company Operations Facility Planned As New Construction—Standard Design/Site Adapt At Customer’s Request, Changed to Historic Renovation Stimulus Program Funds (ARRA) o Imposed Funding Constraints o Fully Coordinated but Severable Projects RFP Requirements o Validate Basic Concept o Apportion Risk o Execute Within Time and Budget Original Building 2

Upload: others

Post on 26-Jun-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Convert and Renovate Company Operations Facility (COF)DBIA Presentation on Building 249 Partnering & Design Build Approach PARTNERING CHARTER “We are one team dedicated to providing

3/21/2012

1

DBIA Presentation on Building 249

Convert and Renovate Company Operations Facility (COF)Building 249Joint Base Myer-Henderson HallContract Number W912DR-09-C-0061

DBIA Presentation on Building 249

Developing the RFP

Army Military Construction—Company Operations Facility• Planned As New Construction—Standard Design/Site

Adapt• At Customer’s Request, Changed to Historic

Renovation• Stimulus Program Funds (ARRA)

o Imposed Funding Constraintso Fully Coordinated but Severable Projects

• RFP Requirementso Validate Basic Concepto Apportion Risko Execute Within Time and Budget

Original Building

2

Page 2: Convert and Renovate Company Operations Facility (COF)DBIA Presentation on Building 249 Partnering & Design Build Approach PARTNERING CHARTER “We are one team dedicated to providing

3/21/2012

2

DBIA Presentation on Building 249

Design Build Team’s Perspective on RFP• One-Phase

• Limited bridging documents

• Primarily performance-based

• Prescriptive requirements

o Historical Preservation

o Polyurea Wall Reinforcement

o AT/FP

o Prescriptive LEED Credits

3

DBIA Presentation on Building 249

Sample of RFP Drawings

4

Page 3: Convert and Renovate Company Operations Facility (COF)DBIA Presentation on Building 249 Partnering & Design Build Approach PARTNERING CHARTER “We are one team dedicated to providing

3/21/2012

3

DBIA Presentation on Building 249

Our Approach to Design Build

Use the DBIA Model: “Design Build Done Right”

• Fully integrate design and construction

• Clear lines of authority and communication

• Encourage cross-discipline interaction

• Significant involvement by senior staff

• Building Information Modeling (BIM)

5

DBIA Presentation on Building 249

Building the Right Team• What team members did we need?

6

Page 4: Convert and Renovate Company Operations Facility (COF)DBIA Presentation on Building 249 Partnering & Design Build Approach PARTNERING CHARTER “We are one team dedicated to providing

3/21/2012

4

DBIA Presentation on Building 249

Building the Right Team• Who did we select, and why?

7

DBIA Presentation on Building 249

3d U.S. Infantry Regiment (The Old Guard) • Army’s oldest active-duty infantry unit, serving our nation since 1784.

• Official ceremonial unit and escort to the president, providing security for Washington, D.C., in time of national emergency or civil disturbance.

Alpha Company (Commander-in-Chief’s Guard)

• Patterned after General George Washington’s personal guard unit. The unit maintains ceremonial and tactical proficiency in the weaponry and tactics of the 18th century.

• Performs in many Department of Defense ceremonies each year and conducts memorial affairs in Arlington National Cemetery.

Echo Company (Honor Guard Company)

• Executes Joint and Army ceremonies to showcase the traditions of the Army and defend the dignity and honor of our fallen comrades.

8

Page 5: Convert and Renovate Company Operations Facility (COF)DBIA Presentation on Building 249 Partnering & Design Build Approach PARTNERING CHARTER “We are one team dedicated to providing

3/21/2012

5

DBIA Presentation on Building 249

Existing Conditions

9

DBIA Presentation on Building 249

Existing Conditions – Pre-Bid

10

Page 6: Convert and Renovate Company Operations Facility (COF)DBIA Presentation on Building 249 Partnering & Design Build Approach PARTNERING CHARTER “We are one team dedicated to providing

3/21/2012

6

DBIA Presentation on Building 249

Existing Conditions – Pre-Bid

11

DBIA Presentation on Building 249

Advanced Contract for Demolition & Abatement• Owner’s Perspective

• Design-Builder’s Perspective

o Mitigated unforeseen conditions related to environmental issues

o Allowed D/B team to assess structural conditions and existing conditions

o Specialty trades review of existing conditions and input on

potential design & constructability issues

12

Page 7: Convert and Renovate Company Operations Facility (COF)DBIA Presentation on Building 249 Partnering & Design Build Approach PARTNERING CHARTER “We are one team dedicated to providing

3/21/2012

7

DBIA Presentation on Building 249

Existing Conditions – After Demo and Abatement

13

DBIA Presentation on Building 249

Existing Conditions – After Demo and Abatement

14

Page 8: Convert and Renovate Company Operations Facility (COF)DBIA Presentation on Building 249 Partnering & Design Build Approach PARTNERING CHARTER “We are one team dedicated to providing

3/21/2012

8

DBIA Presentation on Building 249

Existing Conditions – After Demo and Abatement

15

DBIA Presentation on Building 249

Existing Conditions – After Demo and Abatement

16

Page 9: Convert and Renovate Company Operations Facility (COF)DBIA Presentation on Building 249 Partnering & Design Build Approach PARTNERING CHARTER “We are one team dedicated to providing

3/21/2012

9

DBIA Presentation on Building 249

Partnering & Design Build Approach

PARTNERING CHARTER

“We are one team dedicated to providing a quality project inaccordance with the project’s parameters using the contractas the framework. We are committed to honest andopen communication, trusting each other,building a strong partnership, resolving problemissues quickly and at the lowest reasonable level possible,a safe work site producing a quality project, timelycompletion, protection of the environment, and minimizinginconvenience to Joint Base Myer-Henderson Hall.”

17

DBIA Presentation on Building 249

Creating the Right Layout: Pre-RFP Layout

18

Page 10: Convert and Renovate Company Operations Facility (COF)DBIA Presentation on Building 249 Partnering & Design Build Approach PARTNERING CHARTER “We are one team dedicated to providing

3/21/2012

10

DBIA Presentation on Building 249

Creating the Right Layout: Proposed Concept Layout

19

DBIA Presentation on Building 249

Creating the Right Layout: Final Approved Concept

Historical preservationOpen lobbyShowcase conference roomsMore traditional finishesExposed columns and wood structure

Room finishes changed from RFPClosetsChanges to locker room

20

Page 11: Convert and Renovate Company Operations Facility (COF)DBIA Presentation on Building 249 Partnering & Design Build Approach PARTNERING CHARTER “We are one team dedicated to providing

3/21/2012

11

DBIA Presentation on Building 249

Basement – Concept Design

21

DBIA Presentation on Building 249

Basement – Approved Concept Design

22

Page 12: Convert and Renovate Company Operations Facility (COF)DBIA Presentation on Building 249 Partnering & Design Build Approach PARTNERING CHARTER “We are one team dedicated to providing

3/21/2012

12

DBIA Presentation on Building 249

Second Floor – Concept Design

23

DBIA Presentation on Building 249

Second Floor – Approved Concept Design

24

Page 13: Convert and Renovate Company Operations Facility (COF)DBIA Presentation on Building 249 Partnering & Design Build Approach PARTNERING CHARTER “We are one team dedicated to providing

3/21/2012

13

DBIA Presentation on Building 249

Discussion on Budget & Schedule Control

• Controlling Costs and Schedule during Design Phaseo Pricing within RFP Requirementso Incorporating Owner Priorities through Innovative Design Solutions

• Subcontactor Procuremento Prospective Bidders with D/B experience

Understanding documents are not 100% “Closing the Gap” based on design intent

o Design/Assist Subcontracts Attending design meetings Incorporating subcontractor drawings

into design

• Controlling Costs During Constructiono Schedule Updates and Reportingo Close Collaboration between D/B Team,

USACE & DPW Alternate methods to reduce costs Wood Flooring example

25

DBIA Presentation on Building 249

Challenge: Maintain Flexibility and Trust on Meeting

RFP Requirements

26

Page 14: Convert and Renovate Company Operations Facility (COF)DBIA Presentation on Building 249 Partnering & Design Build Approach PARTNERING CHARTER “We are one team dedicated to providing

3/21/2012

14

DBIA Presentation on Building 249

AT/FP Reinforcement at Perimeter Walls

AT/FP

• Restrictions on Design

Build

• Coordination of AT/FP &

SHPO requirements

o Mural compromise for

exterior wall

• Innovative Solutions

27

DBIA Presentation on Building 249

AT/FP Reinforcement at Perimeter Walls

28

Page 15: Convert and Renovate Company Operations Facility (COF)DBIA Presentation on Building 249 Partnering & Design Build Approach PARTNERING CHARTER “We are one team dedicated to providing

3/21/2012

15

DBIA Presentation on Building 249

AT/FP Reinforcement at Perimeter Walls

29

DBIA Presentation on Building 249

• Columns

• Ceilings

• Murals

• Floors

• Light Fixtures

• Arms Storage Vault

Challenges - Owner’s & Design Build Team’s Perspectives On Each

Historic Preservation Criteria

30

Page 16: Convert and Renovate Company Operations Facility (COF)DBIA Presentation on Building 249 Partnering & Design Build Approach PARTNERING CHARTER “We are one team dedicated to providing

3/21/2012

16

DBIA Presentation on Building 249

Cast Iron Columns

31

DBIA Presentation on Building 249

Historic Columns as a feature of Conference Room

32

Page 17: Convert and Renovate Company Operations Facility (COF)DBIA Presentation on Building 249 Partnering & Design Build Approach PARTNERING CHARTER “We are one team dedicated to providing

3/21/2012

17

DBIA Presentation on Building 249

Existing Tin Ceilings

33

DBIA Presentation on Building 249

Restored Tin Ceilings

34

Page 18: Convert and Renovate Company Operations Facility (COF)DBIA Presentation on Building 249 Partnering & Design Build Approach PARTNERING CHARTER “We are one team dedicated to providing

3/21/2012

18

DBIA Presentation on Building 249

New Tin Ceilings

35

DBIA Presentation on Building 249

Light fixtures chosen to emulate historic feel

36

Page 19: Convert and Renovate Company Operations Facility (COF)DBIA Presentation on Building 249 Partnering & Design Build Approach PARTNERING CHARTER “We are one team dedicated to providing

3/21/2012

19

DBIA Presentation on Building 249

Historic Mural – Exposed Prior to Building Renovation

37

DBIA Presentation on Building 249

Historic Mural at Pre-bid

38

Page 20: Convert and Renovate Company Operations Facility (COF)DBIA Presentation on Building 249 Partnering & Design Build Approach PARTNERING CHARTER “We are one team dedicated to providing

3/21/2012

20

DBIA Presentation on Building 249

Historic Mural on Display

39

DBIA Presentation on Building 249

Floors Before Renovation

40

Page 21: Convert and Renovate Company Operations Facility (COF)DBIA Presentation on Building 249 Partnering & Design Build Approach PARTNERING CHARTER “We are one team dedicated to providing

3/21/2012

21

DBIA Presentation on Building 249

Flooring Reuse and Replacement Plan

41

DBIA Presentation on Building 249

Floors – Restored and Repaired

42

Page 22: Convert and Renovate Company Operations Facility (COF)DBIA Presentation on Building 249 Partnering & Design Build Approach PARTNERING CHARTER “We are one team dedicated to providing

3/21/2012

22

DBIA Presentation on Building 249

Floors – Restored and Repaired

43

DBIA Presentation on Building 249

Arms Vault Under Construction

44

Page 23: Convert and Renovate Company Operations Facility (COF)DBIA Presentation on Building 249 Partnering & Design Build Approach PARTNERING CHARTER “We are one team dedicated to providing

3/21/2012

23

DBIA Presentation on Building 249

Arms Vault

45

DBIA Presentation on Building 249

Challenges – continued

Restoring and ReinforcingHistoric Windows

46

Page 24: Convert and Renovate Company Operations Facility (COF)DBIA Presentation on Building 249 Partnering & Design Build Approach PARTNERING CHARTER “We are one team dedicated to providing

3/21/2012

24

DBIA Presentation on Building 249

Restored and Reinforced Historic Windows

47

DBIA Presentation on Building 249

Challenges – Owner’s & Design Build Team’s Perspectives On Each

LEED

48

Page 25: Convert and Renovate Company Operations Facility (COF)DBIA Presentation on Building 249 Partnering & Design Build Approach PARTNERING CHARTER “We are one team dedicated to providing

3/21/2012

25

DBIA Presentation on Building 249

Challenges – Owner’s & Design Build Team’s Perspectives On Each

LEED

Challenges, Opportunities, Solutions for an Existing Historic Building

• LEED v. 2.2 Silver Required (Preregistered)

• Partial scorecard in RFP – left some freedom for creative strategy

• Focused on:

• High-Performance envelope elements

• High-efficiency HVAC system and lighting

• Maximized low-emitting materials and recycled content

• Exemplary performance in water use reduction, construction waste diversion

• Sustainable Sites

49

DBIA Presentation on Building 249

Overall Conclusion

50

Page 26: Convert and Renovate Company Operations Facility (COF)DBIA Presentation on Building 249 Partnering & Design Build Approach PARTNERING CHARTER “We are one team dedicated to providing

3/21/2012

26

DBIA Presentation on Building 249

Convert and Renovate Company Operations Facility (COF)Building 249Joint Base Meyer-Henderson HallContract Number W912DR-09-C-0061