coordination of controls of renewable power plants to meet...
TRANSCRIPT
Coordination of Controls of Renewable Power Plants to Meet Steady State and Dynamic Response Requirements for Voltage Control and Reactive Power Supply
Presented by Daniel Feltes, Siemens PTI
Unrestricted
11-Nov-16Page 2
Overview
Discussion of the control strategy developed for a large renewable facility compromised of four wind farms:
• Control Requirements
• Available Controls
• Time Frames
• Controllers
• Example Responses
• Other Points to Consider
11-Nov-16Page 3
The Wind Farm Layout
Utility(POI) 500kV
121kV
4x30MVAR7.8miles
121kV
34.5kV
WindFarm173.5MW
9.7miles 7.0miles
121kV 121kV
WindFarm360MW
34.5kV
WindFarm2150MW
34.5kV9.1miles
WindFarm4100MW
34.5kV 121kV
11-Nov-16Page 4
The Wind Farm Equipment
• Every turbine, padmount transformer and feeder cable section was modeled in the simulations
• Four 121 kV lines – total length of 33.6 miles
• Approximately 171 miles of 34.5 kV collector cables
Wind Farm # Turbines MW Turbine
Manufacturer1 45 73.5 GE2 92 150.0 GE3 37 60.0 GE4 46 100.0 Siemens
Total 220 383.5
11-Nov-16Page 5
Control Requirements
ISO Requirements
• Inject or withdraw reactive power continuously (i.e. dynamically) at the POI point up to 33% of rated active power at all levels of active power output
• Exhibit connection point performance comparable to an equivalent synchronous generation unit with characteristic parameters within typical ranges
11-Nov-16Page 6
Available Controls
The control of voltage and reactive power is accomplished by the following controls:
• On-Load Tap Changer (OLTC) controls to adjust the taps on the 525/121 kV autotransformers
• OLTC controls to adjust the taps on the 121/34.5 kV transformers at each of the four wind farms
• Switching of the four 30 Mvar capacitor banks at the 121 kV bus• The wind farm controllers (i.e., GE WindCONTROL and Siemens Park Pilot)• The wind turbine generator controls
Each of these controls has unique characteristics with respect to its impact and timing. Thus careful coordination of these controls is necessary to ensure the desired accuracy, robustness and speed of response is obtained without undesirable interactions.
11-Nov-16Page 7
Control Time Frames
Transient Timeframe (0 to 5 seconds)
• The voltage and reactive power controls that are active in the transient time frame are the controls of the wind farm controllers and the controls of the wind turbine generators
• The OLTC tap controls and the capacitor bank controls are not active in this time frame
Steady State Timeframe (5 Seconds to Minutes)
• All of the controls are active, but the response is dominated by the OLTC tap controls and the capacitor bank controls
• The goal is to meet the steady state requirements while maintaining as much dynamic reserve capability as possible
11-Nov-16Page 8
Wind Farm Controllers and Turbine Controls
GE Wind Farms
• Doubly-fed induction machines
• Very fast terminal voltage control
• Reactive power setpoint sent to each turbine from the GE WindCONTROL.
One WindCONTROL controls all 3 of the wind farms with GE turbines.
• The WindCONTROL adjusts the WTG setpoints to controls the main 121 kV
bus voltage, using line drop compensation.
• Overall response time of 1 to 2 seconds
11-Nov-16Page 9
Wind Farm Controllers and Turbine Controls
Siemens Wind Farm
• Wind Farm 4 only
• Full inverter machines
• Very fast terminal voltage control
• A voltage reference setpoint is sent to each turbine from the Siemens Park
Pilot controller.
• The Park Pilot adjusts these setpoints to controls the reactive flow at the
121 kV bus of Wind Farm 4.
• Overall response time of 1 to 2 seconds
11-Nov-16Page 10
Wind Farm 4 Reactive Power Boost
Wind Farm 4 controls the reactive power at its 121 kV bus
• To supply a transient reactive power contribution for large voltage changes,
the reactive setpoint is adjusted.
• The steady state contribution is not changed
• The controller is implemented in a PLC located at Wind Farm 4
11-Nov-16Page 11
Outer Loop Controller to Implement Reactive Power Droop at the POI
• The steady state requirements are to supply reactive power to the 500 kV
system with a 4% reactive droop setting
• The controller adjusts the voltage reference of the GE WindCONTROL wind
farm controller
• The controller is implemented in a PLC
D
DIP sT
sKsKK
+++1
S-
-
+
DesiredV500
MeasuredV500
Droop
TotalQ 500
referenceV121Vmax
Vmin
1/QMax
csT+11
11-Nov-16Page 12
121 kV Capacitor Bank Controller
• The objective of the control of the capacitor banks is to supply steady state reactive power when needed
• The capacitors should only be switched in when those system reactive needs are required for a longer period of time
• This “frees up” the reactive capability of the turbines in case it is needed for transient support
• This controller is also implemented in the PLC
11-Nov-16Page 13
500/121 kV Transformer OLTC Control
• Analysis performed to look at the operation of the wind farm over a range of system operating conditions and from low power output to full power output.
• Desired 500/121 kV transformer tap defined as a function of measured 500 kV voltage
• No adverse interaction with droop controller
V500If |D tap| >1.5 * average tap step,move tap one tap position in the desireddirection
Tap Selection Table
Tap# Tap(kV) -16 577.500 -15 574.225
.
.
. -1 528.275 0 525.000 1 521.725
.
.
. 15 475.775 16 472.500
+
+
Offset
asT+11
–
+
Present Tap
Approximate Tap
Average tap step = 3.281 kV = 0.00656 pu
(Time delay between tap change is Td seconds)
Δ tap
“Averaging” filter
11-Nov-16Page 14
121/34.5 kV Transformer OLTC Control
• Conventional OLTC controls at each of the four wind farms
• Each controls the main 34.5 kV collector bus to a selected voltage setpoint(within a voltage band)
11-Nov-16Page 15
Fast Transient Response
• Actual staged test of switching of the 121 kV capacitor banks• Comparison of the measured response to the ISO requirement
Actual Response
ISO Requirement
11-Nov-16Page 16
Slow Controls – Steady State Response
• Simulation of an event that changes the system voltage
• Demonstrates reactive droop control and operation of the taps and capacitor banks to maintain reactive reserve on the turbines
11-Nov-16Page 17
Slow Controls – Steady State Response
• Simulation of an event that changes the system voltage
• Demonstrates reactive droop control and operation of the taps and capacitor banks to maintain reactive reserve on the turbines
11-Nov-16Page 18
Slow Controls – Steady State Response
• Simulation of an event that changes the Wind Farms power output
• Demonstrates reactive droop control and operation of the capacitor banks to maintain reactive reserve on the turbines
11-Nov-16Page 19
Other Points to Consider
When multiple controls are present, it is important to ensure that they are well coordinated:
• Active only in the proper time frame (and these time frames are well separated)
• Not controlling the same quantity as other controllers or quantities that are
highly dependant
• Reach of the controllers does not overlap
The paper gives a few example of problematic strategies.
11-Nov-16Page 20
Example of a Suboptimal Control Strategy
• Simulation of an event that changes the system voltage
• Demonstrates a suboptimal control strategy that leads to an undesirable control action
11-Nov-16Page 21
Conclusions
• The facility may need to demonstrate their capabilities to meet grid codes to be able to interconnect.
• Simulation to develop the control strategy, tune controller response and to test and remedy any interactions is much preferred to debugging control problems in the field
• While the controls and equipment are unique to this facility and may not be directly applicable to other facilities, but the general approach is.
• It is possible to achieve both a fast transient response to system events while coordinating the slower controls
11-Nov-16Page 22
Questions? And Thank You for listening!
11-Nov-16Page 23
Contact Information
Siemens Industry, Inc.Energy Management DivisionDigital Grid Business UnitSiemens Power Technologies International400 State Street, Schenectady, NY 12305 USA
James Feltes, Senior Manager, Consulting+1 (518) [email protected]
Dinemayer Silva, Staff Consultant+1 (518) [email protected]
Daniel Feltes, Consultant+1 (518) [email protected]