copy of cost
TRANSCRIPT
From, Dated :- 31st Jan 2012 M/s. Real Gem Buildtech Private Limited R.A.Bill No :- 23
Bill Period :- 1st Jan'12 to 31st Jan'12
Contract Doc No :- RGBPL / OC / LTL / 22 / 10 (Rev-03) Dated 26/12/2011. To, Name Of Project / Work :- ORCHID CROWN RESIDENTIAL PROJECT (3 Buildings)
M/s. Larsen & Toubro Limited, ECC Division Location :- Dadar, Mumbai.
Andheri (E),Mumabi. Scope Of Work :- Civil Works.
SUMMARY OF CERTIFIED WORK ABSTRACT
ITEM DESCRIPTION BOQ Amount BILL AMOUNT (RS)
Previous Present Total1 Raftwork. (Annexure A) 998,506,926.00 778168323.06 - 778,168,323.06 2 Basement work. (Annexure B) 940,828,020.31 600812916.07 #REF! #REF!3 Podium work. (Annexure C) 1,278,412,930.00 #REF! - #REF!4 Tower A typical floor work. (Annexure D) 1,387,471,556.00 - - - 5 Tower B typical floor work. (Annexure E) 1,251,174,381.00 #REF! - #REF!6 Tower C typical floor work. (Annexure F) 969,430,796.00 #REF! #REF! #REF!7 Sales Pavillion work. (Annexure G) #REF! #REF! #REF! #REF!8 Preliminaries (Annexure H) 418,292,362.00 #REF! #REF! #REF!9 Chawl Repairing work 826,742.00 #REF! - #REF!10 SUB TOTAL AMOUNT. #REF! #REF! #REF! #REF!11 Less rebate @ 1.806%. #REF! #REF! #REF! #REF!
12 Rebar Basic Rate Variation - 67768708.59 #REF! #REF!
13 Cement Basic Rate Variation - - 3461585.00 3,461,585.00
14 TOTAL AMOUNT INCLUDING VAT/LAB CESS #REF! #REF! #REF! #REF!15 MVAT (Actual) - 40,351,105.73 #REF! #REF!16 TOTAL AMOUNT EXCLUDING VAT. - #REF! #REF! #REF!17 Add Service Tax @4.12% #REF! #REF! #REF! #REF!18 GRAND TOTAL INCLUDING ALL TAXES. #REF! #REF! #REF! #REF!
D B House, Yashodham, Gen.A.K.Vaidya Marg, Goregaon (E), Mumbai - 400 063
BOQ Code
From, Dated :- 31st Jan 2012 M/s. Real Gem Buildetech Private Limited R.A.Bill No :- 23 D B House,Yashodham, Gen.A.K.Vaidya Marg, Goregaon (E), Mumbai - 400 063 Bill Period :- 1st Jan'12 to 31st Jan'12
Contract Doc No :- RGBPL / OC / LTL / 22 / 10 (Rev-03) Dated 26/12/2011. To, Name Of Project / Work :- ORCHID CROWN RESIDENTIAL PROJECT (3 Buildings)M/s. Larsen & Toubro Limited, ECC Division Location :- Dadar, Mumbai.
Andheri (E), Mumabi. Scope of Work :- Civil Works.
C E R T I F I E D W O R K A B S T R A C T
BOQ Code ITEM DESCRIPTION UNIT RATE BOQ
Page Nos BILL QUANTITY BILL AMOUNT (RS)
Quantity Amount Previous Present Total Previous Present Total
Main Works ANNEXURE A- RAFT WORK
1 M15 grade PCC below Raft Level Cum 4900.00 2,271.00 11,127,900.00 2028.86 2,028.86 9,941,410.08 - 9,941,410.08
2 M50 grade Concrete at Raft Level Cum 7200.00 33,018.00 237,729,600.00 24983.55 24,983.55 179,881,567.20 - 179,881,567.20
2.1 M60 grade Concrete at Raft Level Cum 1197.00 32,903.00 39,384,891.00 24869.07 24,869.07 29,768,277.99 - 29,768,277.99
2.2 M70 grade Concrete at Raft Level Cum 3227.00 QRO - - - - - -
2.3 M80 grade Concrete at Raft Level Cum 4813.00 QRO - - - - - -
2.4 M45 grade Concrete at Raft Level Cum 7000.00 4,200.00 29,400,000.00 366.00 366.00 2,562,000.00 - 2,562,000.00
3 Sqm 519.00 38,784.81 20,129,316.39 1180.76 1,180.76 612,811.85 - 612,811.85
4 Reinforcement Steel - upto Raft Level MT 51171.00 10,150.00 519,385,650.00 9253.86 9,253.86 473,529,065.38 - 473,529,065.38
5 Sqm 717.00 22,710.00 16,283,070.00 12287.41 12,287.41 8,810,074.40 - 8,810,074.40
6 Cum 6825.00 2,271.00 15,499,575.00 - 0.00 - - -
7 Sqm 1058.00 22,710.00 24,027,180.00 - 0.00 - - -
8 SCC Concrete M30 Cum 8097.00 64.00 518,208.00 63.17 63.17 511,479.39 - 511,479.39
9 Vertical Rock Anchors 212MT Nos 123144.00 475.00 58,493,400.00 456.00 456.00 56,153,664.00 - 56,153,664.00
Formwork - Conventional upto Raft Level
Chemical Waterproofing upto Raft Level
M15 grade Trimix Floor Finish upto Raft Level
Rubberised paint on flooring upto Raft Level
From, Dated :- 31st Jan 2012 M/s. Real Gem Buildetech Private Limited R.A.Bill No :- 23 D B House,Yashodham, Gen.A.K.Vaidya Marg, Goregaon (E), Mumbai - 400 063 Bill Period :- 1st Jan'12 to 31st Jan'12
Contract Doc No :- RGBPL / OC / LTL / 22 / 10 (Rev-03) Dated 26/12/2011. To, Name Of Project / Work :- ORCHID CROWN RESIDENTIAL PROJECT (3 Buildings)M/s. Larsen & Toubro Limited, ECC Division Location :- Dadar, Mumbai.
Andheri (E), Mumabi. Scope of Work :- Civil Works.
C E R T I F I E D W O R K A B S T R A C T
BOQ Code ITEM DESCRIPTION UNIT RATE BOQ
Page Nos BILL QUANTITY BILL AMOUNT (RS)
Quantity Amount Previous Present Total Previous Present Total
10 Dowel Anchors - 80mm Dia Nos 7003.00 2,500.00 17,507,500.00 1126.00 1,126.00 7,885,378.00 - 7,885,378.00
11 Dowel Anchor Pullout Test Nos 30395.00 25.00 759,875.00 6.00 6.00 182,370.00 - 182,370.00
12 M15 grade Plum Concrete Cum 3736.00 324.00 1,210,464.00 323.65 323.65 1,209,137.72 - 1,209,137.72
13 Concrete Breaking Cum 3136.00 2,236.00 7,012,096.00 774.27 774.27 2,428,118.56 - 2,428,118.56
13 Concrete Breaking Cum 3166.00 2,000.00 1495.39 1,495.39 4,734,392.08 - 4,734,392.08
13.2 Cum -30.00 2,000.00 1495.39 1,495.39 (44,861.58) - (44,861.58)
14 P & F of weldmesh Sqm 191.00 200.00 38,200.00 18.00 18.00 3,438.00 - 3,438.00
SUB-TOTAL 998,506,926.00 778,168,323.06 - 778,168,323.06
Concrete Breaking - Deduction in above 13.1 Item which is paid at extra rate at 30Rs
From, Dated :- 31st Jan 2012 M/s. Real Gem Buildetech Private Limited R.A.Bill No :- 23 D B House,Yashodham, Gen.A.K.Vaidya Marg, Goregaon (E), Mumbai - 400 063 Bill Period :- 1st Jan'12 to 31st Jan'12
Contract Doc No :- RGBPL / OC / LTL / 22 / 10 (Rev-03) Dated 26/12/2011. To, Name Of Project / Work :- ORCHID CROWN RESIDENTIAL PROJECT (3 Buildings)M/s. Larsen & Toubro Limited, ECC Division Location :- Dadar, Mumbai.
Andheri (E), Mumabi. Scope of Work :- Civil Works.
C E R T I F I E D W O R K A B S T R A C T
ITEM DESCRIPTION UNIT RATE BOQ
Page Nos BILL QUANTITY BILL AMOUNT (RS)
Quantity Amount Previous Present Total Previous Present Total
ANNEXURE B : BASEMENT WORK
1 Excavation in Soil -Basement Cum 460.00 261,335.00 120,214,100.00 220,975.03 220,975.03 101,648,515.81 - 101,648,515.81
2 Excavation in Rock -Basement Cum 874.00 136,260.00 119,091,240.00 83,903.35 83,903.35 73,331,529.65 - 73,331,529.65
3 Cum 7200.00 14,057.29 101,212,488.00 9,087.95 #REF! #REF! 65,433,229.81 #REF! #REF!
3.1 M25 Grade Concrete for Caping Beam Cum 6445.00 413.00 2,661,785.00 412.56 412.56 2,658,949.20 - 2,658,949.20
3.2 Cum 1197.00 3,322.00 3,976,434.00 2,607.08 #REF! #REF! 3,120,675.08 #REF! #REF!
3.3 Cum 3227.00 1,460.00 4,711,420.00 29.262 29.26 94,428.47 - 94,428.47
3.4 Cum 4813.00 9,663.00 46,508,019.00 6,300.63 #REF! #REF! 30,324,943.34 #REF! #REF!
3.5 M45 Grade Concrete Cum 7000.00 3,528.00 24,696,000.00 2,568.66 2,568.66 17,980,606.00 - 17,980,606.00
3.6 Cum 7200.00 - - -150.97 (150.97) (1,086,984.00) - (1,086,984.00)
4 Formwork upto Basement Lvl Sqm 519.00 126,525.00 65,666,475.00 36,531.40 #REF! #REF! 18,959,796.40 #REF! #REF!
5 MT 51171.00 6,043.00 309,226,353.00 4,934.39 #REF! #REF! 252,497,677.59 #REF! #REF!
6 PT Work -upto Basement Lvl Sqm 1060.00 68,130.00 72,217,800.00 - - - - -
BOQ Code
M50 Grade Concrete -upto Basement Lvl
Over and above item no 3 above for using M60 grade design ready mix concrete in place of M50.
Over and above item no 3 above for using M70 grade design ready mix concrete in place of M50.
M80 Grade Concrete -upto Basement Lvl
Deduct M50 qty which is paid for Retaning wall - Same Qty added in M45
Reinforcement Steel upto Basement Lvl
From, Dated :- 31st Jan 2012 M/s. Real Gem Buildetech Private Limited R.A.Bill No :- 23 D B House,Yashodham, Gen.A.K.Vaidya Marg, Goregaon (E), Mumbai - 400 063 Bill Period :- 1st Jan'12 to 31st Jan'12
Contract Doc No :- RGBPL / OC / LTL / 22 / 10 (Rev-03) Dated 26/12/2011. To, Name Of Project / Work :- ORCHID CROWN RESIDENTIAL PROJECT (3 Buildings)M/s. Larsen & Toubro Limited, ECC Division Location :- Dadar, Mumbai.
Andheri (E), Mumabi. Scope of Work :- Civil Works.
C E R T I F I E D W O R K A B S T R A C T
ITEM DESCRIPTION UNIT RATE BOQ
Page Nos BILL QUANTITY BILL AMOUNT (RS)
Quantity Amount Previous Present Total Previous Present TotalBOQ Code
7 Sqm 836.00 16,839.00 14,077,404.00 6,709.03 6,709.03 5,608,749.08 - 5,608,749.08
8 Sqm 1010.00 3,370.42 3,404,121.68 - - - - -
9 Internal Plaster Sqm 234.00 15,665.55 3,665,739.64 - - - - -
10 Guniting Works Sqm 1955.00 10,248.00 20,034,840.00 6,709.00 6,709.00 13,116,102.82 - 13,116,102.82
11 Cum 5296.00 2,000.00 10,592,000.00 653.02 653.02 3,458,409.81 - 3,458,409.81
12 Sqm 717.00 3,800.00 2,724,600.00 - - - - -
13 Supply of Excavator Hour 1615.00 100.00 161,500.00 7.00 7.00 11,305.00 - 11,305.00
14 Couplers -32mm Dia Nos 337.00 19,463.00 6,559,031.00 15,322.00 15,322.00 5,163,514.00 - 5,163,514.00
15 Couplers -25mm Dia Nos 239.00 11,700.00 2,796,300.00 9,150.00 9,150.00 2,186,850.00 - 2,186,850.00
16 Couplers -20mm Dia Nos 168.00 8,192.00 1,376,256.00 6,253.00 6,253.00 1,050,504.00 - 1,050,504.00
17
L.S. 5254114.00 1.00 5,254,114.00 1.00 1.00 5,254,114.00 - 5,254,114.00
`
SUB-TOTAL 940,828,020.31 600,812,916.07 #REF! #REF!
Waterproofing on Retaining wall-upto Basement Lvl
150mm thk brickwork - upto Basement Lvl
Braking the RCC piles Using Rock Braker
65mm thick and 25mm thick waterproofing treatment by INJECTION GROUTING AND TOPSTOP METHOD on UGWT & OHWT
Carrying out shifting, re-shifting, rehandling & multiple handling serval times of excavated earth
Larsen & Toubro Ltd.
Orchid Crown Project, Dadar.
Retaining wall, BeamFormwork
S.N. Perticulars Quantity Unit
1 R.A. Bill - 05 39.900 Sqm
2 R.A. Bill - 06 82.278 Sqm
3 R.A. Bill - 07 12.000 Sqm
4 R.A. Bill - 08 - Sqm
5 R.A. Bill - 11 - Sqm
6 R.A. Bill - 12 - Sqm
7 R.A. Bill - 13 - Sqm
8 R.A. Bill - 14 - Sqm
9 R.A. Bill - 15 - Sqm
10 R.A. Bill - 16 88.704 Sqm
11 R.A. Bill - 17 45.587 Sqm
TOTAL QUANTITY = 268.469 Sqm
LARSEN & TOUBRO LTD ECC DIVISION RA - 23
ORCHID CROWN PROJECT - DADAR
Description No. L B H Qty. Total Qty Unit
1 Formwork for Columns & Shear Walls
-
C1,C2,C3,C4,C5,C6,C7,C8,C9,C10,C11 2 7.587 2.850 43.246
2 1.925 2.850 10.973
2 6.950 2.850 39.615
2 3.675 2.850 20.9472 2.050 2.850 11.685
2 7.277 2.850 41.479
2 1.000 2.850 5.700
2 1.048 2.850 5.974
2 2.050 2.850 11.685
2 1.221 2.850 6.960
2 1.000 2.850 5.700
2 1.200 2.850 6.840
2 1.741 2.850 9.924
2 1.150 2.850 6.555
2 1.895 2.850 10.802
2 1.160 2.850 6.612
2 6.495 2.850 37.022
2 0.450 2.850 2.565
2 8.501 2.850 48.456
2 0.450 2.850 2.565
2 0.450 2.850 2.565
2 1.718 2.850 9.793
2 0.300 2.850 1.710
2 1.055 2.850 6.014
2 1.000 2.850 5.700
2 8.380 2.850 47.766
2 7.800 2.850 44.460
2 1.125 2.850 6.413
2 1.550 2.850 8.835
2 2.175 2.850 12.397
2 0.700 2.850 3.990
TOWER 'A' - Measurement Sheet - Formwork for Columns & Shear Walls
SL. No.
From 2nd basement to 1st basement floor level
C31, C32, C33, C34, C35, C36, C37, C38, C39, C40, C41
Description No. L B H Qty. Total Qty UnitSL. No.
2 2.975 2.850 16.958
2 2.950 2.850 16.815
2 2.275 2.850 12.967
2 1.850 2.850 10.545
2 4.725 2.850 26.932
2 3.900 2.850 22.230
2 5.45 2.850 31.065
2 0.7 2.850 3.990
2 4.55 2.850 25.935
2 3.200 2.850 18.240
2 4.400 2.850 25.080
2 2.321 2.850 13.230
2 7.314 2.850 41.690
2 2.252 2.850 12.836
2 0.700 2.850 3.990
2 2.158 2.850 12.301
2 4.072 2.850 23.210
2 5.191 2.850 29.591
2 0.173 2.850 0.986
2 0.854 2.850 4.868
2 0.173 2.850 0.986
2 5.097 2.850 29.053
1 111.624 0.250 27.906
C3 & C38 4 2.150 3.100 26.660
4 0.800 3.100 9.920
Add cutout formwork
Cutout no. 31 2 1.000 0.700 1.400
2 0.700 0.400 0.560
-2 1.000 0.400 -0.800
Cutout no. 32 2 0.300 0.700 0.420
2 0.700 0.300 0.420
-2 0.300 0.300 -0.180
Cutout no. 33 2 0.600 0.700 0.840
2 0.700 0.300 0.420
-2 0.600 0.300 -0.360
Cutout no. 28 2 2.000 0.700 2.800
2 0.700 2.100 2.940
-2 2.000 2.100 -8.400
Description No. L B H Qty. Total Qty UnitSL. No.
Cutout no. 30 2 1.000 0.900 1.800
2 0.900 0.350 0.630
-2 1.000 0.350 -0.700
Cutout no. 29 2 1.000 0.700 1.400
2 0.700 0.350 0.490
-2 1.000 0.350 -0.700
Cutout no. 27 2 0.300 0.700 0.420
2 0.700 0.300 0.420
-2 0.300 0.300 -0.180
Cutout no. 44 2 1.850 0.700 2.590
2 0.700 0.550 0.770
-2 1.850 0.550 -2.035
Retaining wall - near C8 & C11 2 3.000 3.100 18.600
2 3.027 3.100 18.767
Retaining wall - near C3 2 1.777 3.100 11.017
2 3.650 3.100 22.630
C17, C21 2 =3.141x2.70x3.1 52.580
C20, C24 4 6.550 2.850 74.670
4 1.000 2.850 11.400
Lift 2 8.500 2.850 48.450
4 2.600 2.975 30.940
4 2.450 2.975 29.155
Add cutout formwork
Cutout no. 9 2 1.000 0.900 1.800
2 0.900 0.350 0.630
-2 1.000 0.350 -0.700
Cutout no. 8 2 2.000 0.700 2.800
2 0.700 2.100 2.940
-2 2.000 2.100 -8.400
Cutout no. 10 2 1.000 0.700 1.400
2 0.700 0.350 0.490
-2 1.000 0.350 -0.700
Cutout no. 11 2 1.300 0.900 2.340
2 0.900 0.640 1.152
-2 1.300 0.640 -1.664
Cutout no. 1 2 2.300 0.700 3.220
2 0.700 2.100 2.940
-2 2.300 2.100 -9.660
Cutout no. 2 2 2.300 0.700 3.220
2 0.700 2.100 2.940
Description No. L B H Qty. Total Qty UnitSL. No.
-2 2.300 2.100 -9.660
Cutout no. 3 2 2.500 0.700 3.500
2 0.700 2.100 2.940
-2 2.500 2.100 -10.500
Cutout no. 5 2 2.500 0.700 3.500
2 0.700 2.100 2.940
-2 2.500 2.100 -10.500
Cutout no. 6 2 2.500 0.700 3.500
2 0.700 2.100 2.940
-2 2.500 2.100 -10.500
Cutout no. 7 2 2.500 0.700 3.500
2 0.700 2.100 2.940
-2 2.500 2.100 -10.500
Retaining wall - near C31 &C38 2 2.275 3.100 14.105
37 2 3.638 3.100 22.556
38 2 7.604 2.975 45.244
39 2 7.950 2.975 47.303
SW19 1 4.804 2.700 12.971
1 3.002 2.850 8.556
2 2.700 2.850 15.390
3 2.450 2.850 20.948
1 0.300 2.850 0.855
1 0.500 2.850 1.425
1 2.900 2.850 8.265
1 1.200 2.850 3.420
1 2.700 2.850 7.695
2 2.850 2.850 16.245
2 3.000 2.850 17.100
2 0.600 2.850 3.420
1 7.700 2.850 21.945
1 0.900 2.850 2.565
2 3.350 2.850 19.095
1 3.000 2.850 8.550
1 1.400 2.850 3.990
2 0.300 2.850 1.710
1 0.950 2.850 2.708
2 0.600 2.850 3.420
1 2.450 2.850 6.983
1 3.141 2.850 8.952
Add Opening Side 1 41.750 0.250 10.438
Description No. L B H Qty. Total Qty UnitSL. No.
at LB 19 Side 1 1.635 2.300 3.760
Add cutout formwork
Cutout no. 38&40 4 0.450 0.300 0.540
4 0.300 0.450 0.540
-4 0.450 0.450 -0.810
Cutout no. 39 2 0.450 0.600 0.540
2 0.450 0.600 0.540
-2 0.450 0.450 -0.405
SW23 1 4.804 2.700 12.971
1 3.002 2.850 8.556
2 2.700 2.850 15.390
1 0.300 2.850 0.855
3 2.450 2.850 20.948
1 0.500 2.850 1.425
1 2.900 2.850 8.265
2 0.600 2.850 3.420
2 0.950 2.850 5.415
2 3.000 2.850 17.100
1 2.700 2.850 7.695
1 6.800 2.850 19.380
1 0.900 2.850 2.565
2 4.350 2.850 24.795
1 2.900 2.850 8.265
1 4.041 2.850 11.517
Add Opening Side 1 41.880 0.250 10.470
at LB 20 Side 1 1.635 2.300 3.760
Cutout no. 41&42 2 0.450 0.300 0.270
2 0.300 0.450 0.270
-2 0.450 0.450 -0.405
Cutout no. 39 2 0.450 0.600 0.540
2 0.450 0.600 0.540
-2 0.450 0.450 -0.405
SW18, SW22 2 7.300 2.850 41.610
2 1.935 2.850 11.030
2 0.600 2.850 3.420
2 1.035 2.850 5.900
2 5.600 2.850 31.920
2 1.035 2.850 5.900
2 5.000 2.850 28.500
Description No. L B H Qty. Total Qty UnitSL. No.
2 2.900 2.850 16.530
2 0.500 2.850 2.850
6 2.450 2.850 41.895
4 2.700 2.850 30.780
2 3.002 2.850 17.111
2 1.203 2.850 6.857
2 0.515 2.850 2.936
2 0.600 2.850 3.420
2 3.650 2.850 20.805
2 1.000 2.850 5.700
2 0.600 2.850 3.420
2 0.500 2.850 2.850
2 0.900 2.850 5.130
Add Opening Side 1 35.870 0.250 8.968
Add Opening Side 1 22.825 0.250 5.706
at Beam 1 Side 2 2.400 2.500 12.000
at 400 thick Slab Side -2 4.800 0.150 -1.440
Add Cutout formwork
Cutout no. 22 & 15 4 1.000 0.600 2.400
4 0.600 0.500 1.200
-4 1.000 0.500 -2.000
Cutout no. 34&37 4 0.450 0.600 1.080
4 0.600 0.450 1.080
-4 0.450 0.450 -0.810
Cutout no. 35&36 4 0.450 0.300 0.540
4 0.300 0.450 0.540
-4 0.450 0.450 -0.810
2 1.207 2.850 6.880
2 10.664 2.850 60.785
2 10.538 2.850 60.067
2 1.200 2.850 6.840
2 2.537 2.850 14.461
2 18.778 2.850 107.035
2 2.505 2.850 14.279
4 2.450 2.850 27.930
2 3.375 2.850 19.238
1 3.221 2.850 9.180
SW13A,SW12,SW13,SW14,SW15,SW16 &SW25,SW26,SW27,SW28,SW29,SW30
Description No. L B H Qty. Total Qty UnitSL. No.
1 1.741 2.850 4.962
2 6.550 2.850 37.335
2 6.860 2.850 39.102
2 2.468 2.850 14.068
2 1.572 2.850 8.960
2 0.816 2.850 4.651
2 1.694 2.850 9.656
2 9.199 2.850 52.434
2 1.513 2.850 8.624
Add cutout formwork
Cutout no. 24 & 12 4 1.000 0.900 3.600
4 0.900 0.400 1.440
-4 1.000 0.400 -1.600
Cutout no. 25 & 13 4 1.200 0.900 4.320
4 0.900 0.350 1.260
-4 1.200 0.350 -1.680
Cutout no. 26 & 14 4 1.000 0.900 3.600
4 0.900 0.250 0.900
-4 1.000 0.250 -1.000
Podium Columns - PC2, PC18, PC18A 3 =3.141x0.60x2.85 16.113
TOTAL QUANTITY = 2609.564 Sq.m
LARSEN & TOUBRO LTD ECC DIVISION RA - 23
ORCHID CROWN PROJECT - DADAR
Description No. L B H Qty. Unit
1 Formwork for Slab & Slab Beams
1 1722.790 1722.790
1 81.886 0.000 0.000
Deduction of Cutouts -
1 -1 12.514 -12.514
2 -1 6.200 -6.200
3 -1 6.614 -6.614
4 -1 6.614 -6.614
5 -1 6.614 -6.614
6 -1 6.614 -6.614
7 -1 1.460 -1.460
8 -1 6.614 -6.614
9 -1 6.614 -6.614
10 -1 6.614 -6.614
11 -1 6.614 -6.614
12 -1 9.590 -9.590
13 -1 2.250 -2.250
14 -1 2.840 -2.840
15 -1 12.590 -12.590
16 -1 5.635 -5.635
17 -1 5.635 -5.635
18 -1 5.635 -5.635
19 -1 22.800 -22.800
20 -1 28.715 -28.715
Add formwork around cutouts Perimeter Slab thk.
1 1 15.660 0.250 3.915
2 1 10.019 0.250 2.505
3 1 10.300 0.250 2.575
4 1 10.300 0.250 2.575
5 1 10.300 0.250 2.575
Tower A - Measurement Sheet - Formwork for B1 Floor Slab & Slab Beams
SL. No.
Total Quantity
Area of 1st basement floor slab
Add offset of 400 mm thk. Slab - Perimeter x thk. of slab
Description No. L B H Qty. UnitSL. No.
Total Quantity
6 1 10.300 0.250 2.575
7 1 6.100 0.250 1.525
8 1 10.300 0.250 2.575
9 1 10.300 0.250 2.575
10 1 10.300 0.250 2.575
11 1 10.300 0.250 2.575
12 1 12.400 0.250 3.100
13 1 7.500 0.250 1.875
14 1 7.900 0.250 1.975
15 1 14.400 0.250 3.600
16 1 9.500 0.250 2.375
17 1 9.500 0.250 2.375
18 1 9.500 0.250 2.375
19 1 26.838 0.250 6.710
20 1 23.342 0.250 5.836
Deduction of Columns & Shear walls-
C1, C2,C4, C5, C6, C7, C8, C9, C10, C11 -1 =198.147-141.25 -56.897
Add 1 2.090 2.090
C3 -1 2.150 0.800 -1.720
-1 48.530 -48.530
RW near C3 -1 1.748 0.300 -0.524
RW near C3 -1 3.650 0.300 -1.095
C20, C24 -2 6.550 1.000 -13.100
C17, C21 -2 5.725 -11.450
Lift wall -1 7.880 -7.880
SW25, SW26, SW27, SW28, SW29, SW30, SW23 -1 45.290 -45.290
RW near C31 -1 2.275 -2.275
RW C36 -1 3.638 0.150 -0.546
RW near C38 -1 7.604 0.150 -1.141
RW near C38 -1 7.950 0.150 -1.193
SW18, SW22 -2 15.662 -31.324
-1 =198.147-137.77 -60.377
Add 1 2.090 2.090
C38 -1 2.150 0.800 -1.720
SW13A, SW12, SW13, SW14, SW15,SW16, SW19
C31, C32, C33, C34, C35, C36, C37, C38, C39, C40, C41
Description No. L B H Qty. UnitSL. No.
Total Quantity
Podium columns -1 3.141/4*0.6*0.6 -0.283
Slab Beams -
LB3 2 2.050 0.350 1.435
-2 0.900 0.350 -0.630
LB9 2 3.875 0.650 5.038
-2 0.900 0.650 -1.170
2 1.088 0.650 1.414
-2 0.900 0.650 -1.170
2 3.514 0.650 4.568
-2 0.900 0.650 -1.170
LB12 2 3.875 0.650 5.038
-2 0.900 0.650 -1.170
2 1.088 0.650 1.414
-2 0.900 0.650 -1.170
2 4.414 0.650 5.738
-2 0.900 0.650 -1.170
LB11 2 2.050 0.500 2.050
-2 0.900 0.650 -1.170
LB13 1 1.770 0.600 1.062
1 1.676 0.600 1.006
LB19 2 1.203 0.600 1.443
-2 0.825 0.600 -0.990
LB20 2 1.203 0.600 1.443
-2 0.825 0.600 -0.990
LB21 0 2.000 0.600 0.000
LB22 0 2.300 0.600 0.000
LB23 0 2.300 0.600 0.000
LB24 0 2.500 0.600 0.000
LB25 0 2.500 0.600 0.000
LB26 0 2.500 0.600 0.000
LB27 0 2.500 0.600 0.000
LB28 0 2.000 0.600 0.000
1 8 1.200 0.150 1.440
-2 0.600 0.150 -0.180
1A 2 2.235 0.350 1.564
Description No. L B H Qty. UnitSL. No.
Total Quantity
-2 0.230 0.350 -0.161
2 3.000 0.350 2.100
-2 0.230 0.350 -0.161
3 4 3.553 0.350 4.974
-4 0.515 0.350 -0.721
4 4 6.192 0.200 4.954
-4 0.450 0.200 -0.360
8 4 7.187 0.200 5.750
-4 0.450 0.200 -0.360
9 4 5.403 0.200 4.322
-4 0.450 0.200 -0.360
13 2 5.383 0.200 2.153
-2 0.450 0.200 -0.180
10, 11, 12 6 2.300 0.300 4.140
6 0.150 0.300 0.270
10X 4 0.150 0.300 0.180
-2 0.350 0.300 -0.210
14 2 4.650 0.200 1.860
-2 0.450 0.200 -0.180
17 2 4.775 0.200 1.910
-2 0.450 0.200 -0.180
15 2 6.778 0.200 2.711
-2 0.450 0.200 -0.180
18 4 4.500 0.350 6.300
-2 0.300 0.350 -0.210
21 2 2.701 0.150 0.810
22 2 2.701 0.150 0.810
23 2 2.701 0.150 0.810
24 2 2.701 0.150 0.810
25 2 2.701 0.150 0.810
26 2 2.701 0.150 0.810
27 2 2.701 0.150 0.810
28 2 2.701 0.350 1.891
21X 2 0.462 0.150 0.138
24X 2 0.462 0.150 0.138
Description No. L B H Qty. UnitSL. No.
Total Quantity
25X 2 0.462 0.150 0.138
28X 2 0.462 0.150 0.138
-4 0.300 0.150 -0.180
22X 2 0.342 0.150 0.102
23X 2 0.342 0.150 0.102
26X 2 0.342 0.150 0.102
27X 2 0.342 0.150 0.102
-4 0.400 0.150 -0.240
35 2 2.450 0.200 0.980
-2 0.300 0.200 -0.120
36 2 2.450 0.200 0.980
-2 0.300 0.200 -0.120
37 2 5.075 0.350 3.552
-2 0.300 0.350 -0.210
38 2 7.604 0.350 5.323
-2 0.300 0.350 -0.210
39 2 7.950 0.350 5.565
-2 0.300 0.350 -0.210
38A 2 1.287 0.350 0.901
-2 0.300 0.350 -0.210
39B 2 1.625 0.350 1.138
-2 0.300 0.350 -0.210
29 2 1.600 0.200 0.640
-2 0.150 0.200 -0.060
30 2 1.600 0.200 0.640
-2 0.150 0.200 -0.060
1B 2 2.235 0.350 1.564
16 2 6.778 0.200 2.711
-2 0.450 0.200 -0.180
26A 2 2.450 0.350 1.715
27A 2 2.450 0.350 1.715
1 205.053 0.250 51.263
Less - Stair Case Area
TOTAL QUANTITY = 1478.853 Sq.m
Add pheriphery of slab thk. - Pheriphery of outer side of slab x thk. of slab
LARSEN & TOUBRO LTD ECC DIVISION RA - 23
ORCHID CROWN PROJECT - DADAR
Description No. L B H Qty. Unit
1 Formwork for Columns & Shear Walls
- From 1st basment lvl to Ground floor.
C1, C2,C3, C4, C5, C17 2 1.714 4.500 15.426
C11, C12, C13, C14, C15, C18 2 1.764 4.500 15.876
4 0.650 4.500 11.700
2 0.750 4.500 6.750
4 10.837 4.500 195.066
4 0.650 4.500 11.700
2 0.750 4.500 6.750
2 1.725 4.500 15.525
2 1.675 4.500 15.075
2 8.350 4.500 75.150
2 3.350 4.500 30.150
4 2.325 4.500 41.850
2 0.800 4.500 7.200
2 2.450 4.500 22.050
2 3.025 4.500 27.225
2 1.625 4.500 14.625
2 1.645 4.500 14.805
2 1.945 4.500 17.505
2 7.450 4.500 67.050
2 8.850 4.500 79.650
4 1.945 4.500 35.010
2 5.250 4.500 47.250
2 3.400 4.500 30.600
2 1.300 4.500 11.700
2 0.450 4.500 4.050
2 5.600 4.500 50.400
2 8.350 4.500 75.150
Less @ 350 mm Slab , Slab Top - 3.55 -2 26.995 0.350 -18.896
Less @ 200 mm Slab , Slab top 4.6 (Left Wing) -1 30.564 0.200 -6.113
C3 3 2.000 4.300 25.800
3 2.000 4.500 27.000
4 0.800 4.300 13.760
Add Cutout
Cutout No. 01 2 1.200 0.750 1.800
TOWER 'C' - Measurement Sheet - Formwork for Columns & Shear Walls
SL. No.
Total Quantity
2 0.750 2.100 3.150
-2 1.200 2.100 -5.040
Cutout No. 02 2 1.300 0.700 1.820
2 0.700 0.650 0.910
-2 1.300 0.600 -1.560
Cutout No. 03 2 2.500 0.700 3.500
2 0.700 2.100 2.940
-2 2.500 2.100 -10.500
Cutout No. 04 2 2.500 0.700 3.500
2 0.700 2.100 2.940
-2 2.400 2.100 -10.080
Cutout No. 05 2 0.350 0.700 0.490
2 0.700 0.350 0.490
-2 2.400 2.100 -10.080
Cutout No. 06 2 0.350 0.700 0.490
2 0.700 0.350 0.490
Cutout No. 07 2 2.500 0.700 3.500
2 0.700 2.100 2.940
-2 2.500 2.100 -10.500
Cut out No. 41 2 0.150 0.700 0.210
2 0.700 0.150 0.210
Cut out No. 42 2 0.150 0.700 0.210
2 0.700 0.150 0.210
Add Cutout
Cutout No. 31 2 0.600 0.700 0.840
2 0.700 0.300 0.420
Cutout No. 32 2 2.000 0.750 3.000
2 0.750 2.100 3.150
-2 2.000 2.100 -8.400
Cutout No. 30 2 2.000 0.750 3.000
2 0.750 0.300 0.450
-2 2.000 0.300 -1.200
Cutout No. 29 1 =3.141*0.3 0.750 0.053
Cutout No. 28 2 1.000 0.700 1.400
2 0.700 0.400 0.560
Cutout No. 47 2 2.000 0.750 3.000
2 0.750 2.100 3.150
-2 2.000 2.100 -8.400
Cutout No. 43 2 0.150 0.700 0.210
2 0.700 0.150 0.210
Cutout No. 44 2 0.150 0.700 0.210
2 0.700 0.150 0.210
4 4.700 4.300 80.840C6, C10 - 2 Nos.
4 0.800 4.300 13.760
SW4, SW5 & SW9, SW10 2 0.800 4.500 7.300 1.6
2 1.725 4.500 15.525 3.45
2 7.400 4.500 66.600 14.8
2 0.550 4.500 4.950 1.1
2 1.050 4.500 9.450 2.1
4 6.875 4.500 123.750 27.5
2 0.500 4.500 4.500 1
4 3.000 4.500 54.000 12
2 4.600 4.500 41.400 9.2
4 0.250 4.500 4.500 1
2 1.050 4.500 9.450 2.1
2 1.600 4.500 14.400 3.2
4 7.425 4.500 133.650 29.7
2 3.450 4.500 31.050 6.9
2 2.900 4.500 26.100 5.8
Less @ 350 mm Slab , Slab Top - 3.55 -2 9.000 1.400 -25.200
at 200 mm thick slab -2 50.200 0.200 -20.080
Add Cutout
Cutout No. 10 2 0.600 0.550 0.660
2 0.550 0.300 0.330
Cutout No. 11 2 1.000 0.500 1.000
2 0.500 0.600 0.600
-2 1.000 0.600 -1.200
Cutout No. 45 2 0.150 0.500 0.150
2 0.500 0.150 0.150
Add Cutout No. 26 2 1.000 0.550 1.100
2 0.550 0.300 0.330
Cutout No. 27 2 1.000 0.500 1.000
2 0.500 0.600 0.600
-2 1.000 0.600 -1.200
Cutout No. 46 2 0.150 0.500 0.150
2 0.500 0.150 0.150
2 =3.141x2.5x4.25 66.746
8 =3.141x0.60x3.1 57.292
Column Capitals - RC12, RC16 2 2.500 0.100 0.500
C7, C8 - Circular column - 2500 mm dia. - Perimeter x height of column
Podium Columns - RC14, 13, 11, 12, 18, 17, 15, 16 - 600 mm dia. - Perimeter x height of column
Retaining walls 2 2.855 4.300 24.553
2 1.950 4.300 16.770
1 1.900 4.300 8.170
1 1.700 4.250 7.225
1 1.750 4.250 7.438
1 1.550 4.250 6.588
1 1.600 4.250 6.800
1 1.700 4.300 7.310
1 1.450 4.300 6.235
1 1.550 4.300 6.665
4 4.250 4.300 73.100
4 3.050 4.300 52.460 0.95
4 2.225 4.300 38.270 1.9
4 1.500 4.300 25.800
4 1.700 4.300 29.240
2 6.650 4.300 57.190
2 6.650 4.300 57.190
4 0.375 4.300 6.450
2 2.950 4.300 25.370
2 2.950 4.300 25.370
4 2.650 4.300 45.580
2 3.650 4.300 31.390
4 2.275 4.300 39.130
SW1, SW2, SW3 2 1.587 4.500 14.283 3.174
SW7,SW8,SW9 2 1.007 4.500 9.063 2.014
2 1.810 4.500 16.290 3.62
4 4.610 4.500 82.980 18.44
2 0.300 4.500 2.700 0.6
4 8.075 4.500 145.350 32.3
4 6.725 4.500 121.050 26.9
4 7.425 4.500 133.650 29.7
4 1.000 4.500 18.000 4
4 1.000 4.500 18.000 4
4 11.600 4.500 208.800 46.4
12 2.600 4.500 140.400 31.2
8 2.450 4.500 88.200 19.6
Less @ 350 mm Slab , Slab Top - 3.55 -2 11.972 0.350 -8.380
at 250 mm thick slab -2 16.274 0.250 -8.137
Add Cutout
Cutout No. 8a,24a 4 1.000 0.700 2.800
4 0.700 0.400 1.120
Cutout No. 08,24 4 1.000 0.700 2.800
4 0.700 0.400 1.120
Cutout No. 09,25 4 1.000 0.700 2.800
4 0.700 0.400 1.120
Cutout No. 35,36 4 0.800 0.500 1.600
4 0.500 0.400 0.800
Cutout No. 12,20 4 1.000 0.500 2.000
4 0.500 0.400 0.800
Cutout No. 13,19 4 1.000 0.500 2.000
4 0.500 0.400 0.800
Cutout No. 15,23 4 1.000 0.450 1.800
4 0.450 0.350 0.630
Cutout No. 48,49 4 0.250 0.250 0.250
4 0.250 1.800 1.800
-4 0.250 1.800 -1.800
Cutout No.42,43 4 0.250 0.250 0.250
4 0.250 1.800 1.800
-4 0.250 1.800 -1.800
Cutout No. 40,41 4 0.250 0.250 0.250
4 0.250 1.800 1.800
-4 0.250 1.800 -1.800
Cutout No. 44,45 4 0.250 0.250 0.250
4 0.250 1.800 1.800
-4 0.250 1.800 -1.800
TOTAL QUANTITY = 3304.776 Sq.m
3.428 210.06
3.528
2.6
1.5
43.348
2.6
1.5
3.45
3.35
16.7
6.7
9.3
1.6
4.9
6.05
3.25
3.29
3.89
14.9
17.7
7.78
10.5
6.8
2.6
0.9
11.2
16.7
210.064 3.1
121.45
164.896
3.8
0.7
3.1
0.6
2.45
1.9
3.1
0.6
6.138
6.381
LARSEN & TOUBRO LTD ECC DIVISION RA - 23
ORCHID CROWN PROJECT - DADAR
SL. No. Description No. L B H Qty. Total Quantity Unit
#
- 1 1672.36 1672.36
350 mm thick area 0 326.50 0.00
250 mm thick slab 0 223.75 0.00 1672.36
Deduction of Cutouts - Area
1 -1 33.68 -33.68
2 & 3 -2 2.71 -5.42
4 & 5 -2 14.14 -28.27
6 &13 -2 1.89 -3.78
7 &12 -2 1.28 -2.55
8 & 11 -2 0.72 -1.44
9 & 10 -2 0.66 -1.32
14 & 17 -2 14.14 -28.27
15,16,18,19,29 &21 -6 4.86 -29.16
22 & 23 -2 2.45 -4.90
24 & 27 -2 3.89 -7.78
25 & 26 -2 10.18 -20.36
28 & 29 -2 1.25 -2.50
30 -1 2.00 1.73 -3.45 -172.88
Add formwork around Cutouts:- Perimeter
1 1 35.15 0.20 7.03
2 & 3 2 6.60 0.20 2.64
4 & 5 2 17.45 0.20 6.98
6 &13 2 6.15 0.20 2.46
7 &12 2 4.70 0.20 1.88
8 & 11 2 3.60 0.20 1.44
9 & 10 2 3.40 0.20 1.36
14 & 17 2 10.35 0.20 4.14
15,16,18,19,20 &21 6 8.85 0.20 10.62
Tower C - Measurement Sheet - Formwork for G.F Slab & Slab Beams
Formwork for Ground floor Slab & Slab Beams
Area of Ground floor slab
Slab thickness
SL. No. Description No. L B H Qty. Total Quantity Unit
22 & 23 2 7.18 0.20 2.87
24 & 27 2 7.89 0.20 3.16
25 & 26 2 12.94 0.20 5.18
28 & 29 2 5.65 0.20 2.26
30 1 7.46 0.20 1.49 53.51
C1,C2,C4,C5,C17 and-2 39.09 -78.18
C11,C12,C14,C15,C18
C3 & C13 -2 2.00 0.80 -3.20
C7 & C8 -2 3.93 -7.85
SW1 & SW6 -2 6.47 -12.94
SW2, SW3 & SW7 , SW8 -2 21.45 -42.91
C6 & C10 -2 4.70 0.80 -7.52
SW4 & SW9 -2 10.34 -20.68
SW5& SW10 -2 6.88 0.55 -7.56
-2 1.60 0.55 -1.76
-2 1.60 0.50 -1.60
Podium columns 8 Nos. -8 =3.141/4x0.60x0.60x.2 -0.45
Retaining walls near 3 -1 2.855 0.300 -0.856
-1 1.950 0.300 -0.585
-1 1.900 0.150 -0.285
-1 1.550 0.150 -0.232
-1 1.600 0.150 -0.240
-1 1.550 0.150 -0.232
-2 8.600 0.150 -2.580
-2 3.050 0.150 -0.915
-2 2.225 0.150 -0.668
-2 1.500 0.150 -0.450
-2 1.700 0.150 -0.510
-2 6.650 0.150 -1.995
-2 0.375 0.150 -0.112
-2 2.950 0.150 -0.885
-2 2.650 0.150 -0.795
-1 3.650 0.150 -0.548 -196.54
Deductions of shear walls and columns:-
SL. No. Description No. L B H Qty. Total Quantity Unit
Slab Beams:-
LB2 2 3.65 0.70 5.11
LB3,LB5 4 2.65 0.40 4.24
LB7A,LB8A 4 2.10 0.40 3.36
LB7,LB8 4 2.10 1.55 13.02
LB10,LB11 4 1.30 0.40 2.08
LB12 2 2.00 0.65 2.60
LB13 2 2.50 0.65 3.25
LB14 2 2.50 0.65 3.25
LB15 2 2.50 0.65 3.25
LB16 2 1.20 0.65 1.56
LB17 2 2.00 0.65 2.60
1,2 4 3.05 0.25 3.05
-4 0.23 0.25 -0.23
9,14 4 1.00 0.25 1.00
-4 0.23 0.25 -0.23
10,15 4 0.60 0.25 0.60
-4 0.23 0.25 -0.23
11,16 4 2.15 0.25 2.15
-4 0.23 0.25 -0.23
1X, 2X 8 0.53 1.20 5.04
-4 0.30 1.20 -1.44
3,4 4 2.28 0.35 3.19
-4 0.15 0.35 -0.21
5,6 4 2.28 0.35 3.19
-4 0.23 0.35 -0.32
7,17 4 1.95 1.20 9.36
-4 0.30 1.20 -1.44
7A,17A 4 4.17 1.20 20.02
-4 0.30 1.20 -1.44
7B,17B 4 4.15 1.20 19.92
-4 0.30 1.20 -1.44
9A,9B,10A,14A,14B,15A 12 2.70 0.25 8.10
SL. No. Description No. L B H Qty. Total Quantity Unit
-6 0.23 0.25 -0.35
9AX,9BX,14AX,14BX 8 0.25 0.25 0.50
-4 0.23 0.25 -0.23
11X 4 1.90 0.25 1.90
-2 0.23 0.25 -0.12
11X 4 1.47 0.25 1.47
-2 0.23 0.25 -0.12
18 2 7.59 0.55 8.34
-2 0.45 0.55 -0.50
18 2 7.41 0.55 8.15
-2 0.45 0.55 -0.50
18A 2 7.71 0.55 8.48
-2 0.45 0.55 -0.50
18A 2 7.93 0.55 8.72
-2 0.45 0.55 -0.50
18B 2 3.62 0.25 1.81
18B 2 3.32 0.25 1.66
-2 0.45 0.25 -0.23
18C 2 10.20 0.25 5.10
-2 0.45 0.25 -0.23
19A,22A 4 5.46 0.55 12.01
-4 0.45 0.55 -0.99
19,22 4 11.42 0.55 25.11
-4 0.45 0.55 -0.99
20,21 4 8.09 0.55 17.80
-4 0.45 0.55 -0.99
23,24 2 5.71 0.40 4.57
-2 0.45 0.40 -0.36
24 2 6.61 0.40 5.29
-2 0.30 0.40 -0.24
25,26 4 7.45 0.54 16.09
-4 0.60 0.54 -1.30
27 2 4.00 0.25 2.00
SL. No. Description No. L B H Qty. Total Quantity Unit
-2 0.30 0.25 -0.15
28 2 0.25 0.50
-2 0.30 0.25 -0.15
29 2 3.65 0.25 1.83
-2 0.55 0.25 -0.28
1A,2A 4 2.15 0.25 2.15
-4 0.23 0.25 -0.23
1B,2B 4 1.50 0.25 1.50
-4 0.23 0.25 -0.23 238.55
1 82.511 0.350 28.88 28.88
1 18.048 0.250 4.51 4.51
TOTAL QUANTITY = = 1628.39 Sq.m
Add pheriphery of slab thk. - Pheriphery of outer side of slab x thk. of slab
Add pheriphery of slab thk. - Pheriphery of outer side of slab x thk. of slab
LARSEN & TOUBRO LTD ECC DIVISION
ORCHID CROWN PROJECT - DADAR
Particulars No. L B H
1 R.C.C. Concrete M60
- From (-)6.1 m to (-) 3 m level :- From 3rd basement floor to Mid Landing lvl
Sloping slab 2 2.945 1.500 0.250
Steps 18/2 1.500 0.250 0.155- From Mid Landing lvl to
Mid-Landing 2 4.200 2.000 0.250
Sloping slab 2 2.945 2.000 0.250
Steps 18/2 1.500 0.250 0.155
Top-Landing 2 4.200 2.025 0.050TOTAL =
2.586 0.6 1.8 2.792882.586 1.05 1.8 2.44377
5.23665
Tower C - Measurement Sheet - Staircase - R.C.C. Concrete (M60)
SL. No.
RAB22
Qty. Unit
2.208
0.523
4.200
2.945
0.523
0.85111.250 Cu.m
LARSEN & TOUBRO LTD ECC DIVISION
ORCHID CROWN PROJECT - DADAR
Particulars No. L B H
1 R.C.C. Concrete M60
- From (-) 3 m to (+) .1m level :- From 2nd basement floor to Mid Landing lvl
Bottom Landing 2 4.200 2.025 0.250
Sloping slab 2 2.945 1.500 0.250
Steps 18/2 1.500 0.250 0.155- From Mid Landing lvl
Mid-Landing 2 4.200 2.000 0.250
Sloping slab 2 2.945 2.000 0.250
Steps 18/2 1.500 0.250 0.155
Top-Landing 2 4.200 2.025 0.050TOTAL =
Tower C - Measurement Sheet - Staircase - R.C.C. Concrete (M60)
SL. No.
RAB22
Qty. Unit
4.253
2.208
0.523
4.200
2.945
0.523
0.85115.503 Cum
LARSEN & TOUBRO LTD ECC DIVISION
ORCHID CROWN PROJECT - DADAR
Description No. L B H Qty.
1 R.C.C. Concrete for Slab & Slab Beams
1 1722.790 0.250 430.698
400 mm thick area 1 115.18 0.150 17.277
Deduction of Cutouts -
1 -1 65.082 0.250 -16.271
2 -1 69.382 0.250 -17.346
3 -1 12.514 0.250 -3.129
4 -1 6.614 0.250 -1.654
5 -1 6.614 0.250 -1.654
6 -1 0.712 0.250 -0.178
7 -1 0.67 0.250 -0.168
8 -1 6.201 0.250 -1.550
9 -1 6.614 0.250 -1.654
10 -1 6.614 0.250 -1.654
11 -1 1.47 0.250 -0.368
12 -1 6.614 0.250 -1.654
13 -1 6.615 0.250 -1.654
14 -1 9.6 0.250 -2.400
15 -1 2.25 0.250 -0.563
-1 0.63 0.250 -0.158
16 -1 6.615 0.250 -1.654
17 -1 6.614 0.250 -1.654
18 -1 1.168 0.250 -0.292
19 -1 2.85 0.250 -0.713
20 -1 12.6 0.250 -3.150
21 -1 5.635 0.250 -1.409
22 -1 5.635 0.250 -1.409
Tower A - Measurement Sheet - R.C.C. Concrete for Slab & Slab Beams
SL. No.
area of 2nd basement floor slab
23 -1 5.635 0.250 -1.409
24 -1 25.565 0.250 -6.391
25 -1 28.715 0.250 -7.179
Deduction of Columns & Shear walls-
C1, C2, C3, C4, C5, C6, C7, C8, C9, C10, C11 -1 =197.610-137.946 0.250 -14.916
add 1 1.979 0.250 0.495
-1 69.408 0.250 -17.352
RW -1 2.953 0.250 -0.738
RW -1 0.450 0.250 -0.113
C20, C24 -2 6.550 0.250 -3.275
C17, C21 -2 5.725 0.250 -2.863
Lift -1 7.880 0.250 -1.970
SW25, SW26, SW27, SW28, SW29, SW30, SW23 -1 67.924 0.250 -16.981
RW -1 2.589 0.250 -0.647
RW -1 0.450 0.250 -0.113
SW18, SW22 -2 15.662 0.250 -7.831
Curve walls -2 2.601 0.250 -1.301
-1 2.593 0.250 -0.648
-1 2.589 0.250 -0.647
-1 =201.377-137.946 0.250 -15.858
Add 1 1.979 0.250 0.495
Podium columns -1 3.141/4*0.6*0.6 0.250 -0.071
Slab Beams -
LB3 1 2.050 0.900 0.350 0.646
LB9 1 3.875 0.900 0.650 2.267
1 1.088 0.900 0.650 0.636
1 3.514 0.900 0.650 2.056
LB12 1 3.875 0.900 0.650 2.267
1 1.088 0.900 0.650 0.636
1 4.414 0.900 0.650 2.582
LB11 1 2.05 0.900 0.500 0.923
LB19 1 1.203 0.821 0.450 0.444
SW13A, SW12, SW13, SW14, SW15,SW16, SW19
C31, C32, C33, C34, C35, C36, C37, C38, C39, C40, C41
LB20 1 1.203 0.785 0.450 0.425
LB21 1 2.000 0.700 0.250 0.350
LB22 1 2.300 0.700 0.250 0.402
LB23 1 2.300 0.700 0.250 0.402
LB24 1 2.500 0.700 0.250 0.438
LB25 1 2.500 0.700 0.250 0.438
LB26 1 2.500 0.700 0.250 0.438
LB27 1 2.500 0.700 0.250 0.438
LB28 1 2.000 0.700 0.250 0.350
LB13 1 1.723 0.700 0.600 0.724
1 4 1.200 0.600 0.150 0.432
1A 1 2.235 0.230 0.350 0.180
1 3.000 0.230 0.350 0.242
1B 1 2.235 0.230 0.350 0.180
3 2 3.547 0.515 0.350 1.279
5 1 5.075 0.300 0.350 0.533
6 1 7.604 0.300 0.350 0.798
1 7.950 0.300 0.350 0.835
4 2 6.192 0.450 0.200 1.115
8 2 7.187 0.450 0.200 1.294
9 2 5.403 0.450 0.200 0.972
13 1 5.383 0.450 0.200 0.484
10, 11, 12 3 2.300 0.150 0.300 0.310
10X 2 0.15 0.350 0.300 0.032
14 1 4.65 0.450 0.200 0.419
17 1 4.775 0.450 0.200 0.430
15 1 6.778 0.450 0.200 0.610
16 1 6.778 0.450 0.200 0.610
18 2 4.500 0.300 0.350 0.945
26, 27 2 2.450 0.450 0.350 0.772
28 2 2.450 0.300 0.200 0.294
TOTAL QUANTITY =
1679.333 7001.00290915
697.9695
BOQ Code:
RA Bill - 22
Unit
447.975
2.00215
Total Quantity
-77.307
-84.333
0.6
0.9
Already Considered in the Wall Calculation
29.624
315.959 Cu.m
LARSEN & TOUBRO LTD ECC DIVISION
ORCHID CROWN PROJECT - DADAR
Tower C - Measurement Sheet - R.C.C. Concrete for Slab & Slab Beams
Description No. L
1 R.C.C. Concrete for Slab & Slab Beams -
1 1672.090Area of slab with 250 mm thickness 1 216.700Deduction of Cutouts -1 -1 31.8302 -1 2.4503 -1 2.0004 & 5 -2 14.1406 -1 1.7607 -1 1.2808 -1 3.2209 -1 6.61010 -1 6.61011 -1 6.62012 -1 2.25013 -1 1.28014 -1 1.76025 -1 3.21815 -1 6.61516 -1 6.61517 -1 6.61518 -1 2.45019 -1 3.94020 -1 1.07021 -1 10.180
SL. No.
1 st basement floor slab Area of 1st basement floor slab
22 -1 10.18023 -1 3.94024 -1 1.070Deduction of Column & Shear walls -C1, C2, C4, C5, C17 -1 =124.843-85.747C3 -1 1.599C6, C10 -2 3.760C7, C8 -2 4.908SW1, SW2, SW3 -1 29.771Retaining wall - 3 Nos. -3 0.809SW4, SW5 -1 8.751
-2 0.341-1 2.8-1 6.439
Retaining walls - near C3 -1 0.862-1 0.992
Retaining walls - near C13 -1 0.856-1 0.584
C11, C12, C14, C15, C18 -1 =124.843-85.747C13 -1 1.599SW9, SW10 -1 8.747
-1 2.800-2 0.341-1 6.439
SW6, SW7, SW8 -1 29.771-3 0.810
Retaining walls -1 10.053-1 3.212-1 1.825
Podium column -8 3.141/4x0.6x0.6x0.20Slab Beams :LB2 1 3.650LB3 1 2.650
LB5 1 2.650LB7 1 2.100LB8 1 2.100LB10 1 1.300LB11 1 1.300LB12 1 2.000LB13 1 2.500LB14 1 2.500LB15 1 2.500LB16 1 1.200LB17 1 2.0001 1 3.0502 1 3.0507 1 1.8709 1 1.00010 1 0.60011 1 2.15014 1 1.00015 1 0.60016 1 2.15017 1 1.8701X 1 0.5252X 1 0.5251A 1 2.0751B 1 1.5002A 1 2.0752B 1 1.50012 1 3.00013 1 3.0003 1 2.2754 1 2.2755 1 2.2756 1 2.275
9A 1 2.7009B 1 2.70010A 1 2.70014A 1 2.70014B 1 2.70015A 1 2.7009AX 1 0.3009BX 1 0.30014AX 1 0.30014Bx 1 0.30011X 1 1.900
1 1.4701 1.6001 1.470
18 1 7.7361 7.913
18A 1 8.1791 7.776
18B 1 3.6231 3.324
18C 1 10.20219 1 10.71722 1 10.72019A 1 5.17722A 1 5.18620 1 7.60221 1 7.83623 1 5.71324 1 6.61227 1 3.650
TOTAL QUANTITY
Deduct Quantity from last billNET PAYABLE QUANTITY FOR RAB 22
1679.333
Corbel
LARSEN & TOUBRO LTD ECC DIVISION BA-22
ORCHID CROWN PROJECT - DADAR
Tower C - Measurement Sheet - R.C.C. Concrete for Slab & Slab Beams
B H Qty. Unit
1672.090 0.200 334.418216.700 0.050 10.835 345.253
31.830 0.200 -6.3662.450 0.200 -0.4902.000 0.200 -0.400
14.140 0.200 -5.6561.760 0.200 -0.3521.280 0.200 -0.2563.220 0.200 -0.6446.610 0.200 -1.3226.610 0.200 -1.3226.620 0.200 -1.3242.250 0.200 -0.4501.280 0.200 -0.2561.760 0.200 -0.3523.218 0.200 -0.6446.615 0.200 -1.3236.615 0.200 -1.3236.615 0.200 -1.3232.450 0.200 -0.4903.940 0.200 -0.7881.070 0.200 -0.214
10.180 0.200 -2.036
Total Quantity
10.180 0.200 -2.0363.940 0.200 -0.7881.070 0.200 -0.214 -30.369
=124.843-85.747 0.200 -7.8191.599 0.200 -0.3203.760 0.200 -1.5044.908 0.200 -1.963
29.771 0.200 -5.9540.809 0.200 -0.4858.751 0.200 -1.7500.341 0.200 -0.136
2.8 0.200 -0.5606.439 0.200 -1.2880.862 0.200 -0.1720.992 0.200 -0.1980.856 0.200 -0.1710.584 0.200 -0.117
=124.843-85.747 0.200 -7.8191.599 0.200 -0.3208.747 0.200 -1.7492.800 0.200 -0.5600.341 0.200 -0.1366.439 0.200 -1.288
29.771 0.200 -5.9540.810 0.200 -0.486
10.053 0.200 -2.0113.212 0.200 -0.6421.825 0.200 -0.365
3.141/4x0.6x0.6x0.20 -0.452 -44.222
0.550 0.900 1.8070.800 0.600 1.272
0.800 0.600 1.2720.550 1.750 2.0210.550 1.750 2.0210.500 0.600 0.3900.500 0.600 0.3900.750 0.850 1.2750.700 0.850 1.4880.700 0.850 1.4880.700 0.850 1.4880.750 0.850 0.7650.750 0.850 1.2750.300 0.450 0.4120.300 0.450 0.4120.300 0.450 0.2520.300 0.450 0.1350.300 0.450 0.0810.300 0.450 0.2900.300 0.450 0.1350.300 0.450 0.0810.300 0.450 0.2900.300 0.450 0.2520.300 0.450 0.0710.300 0.450 0.0710.230 0.450 0.2150.230 0.450 0.1550.230 0.450 0.2150.230 0.450 0.1550.230 0.450 0.3110.230 0.450 0.3110.150 0.550 0.1880.150 0.550 0.1880.230 0.550 0.2880.230 0.550 0.288
0.230 0.450 0.2790.230 0.450 0.2790.230 0.450 0.2790.230 0.450 0.2790.230 0.450 0.2790.230 0.450 0.2790.250 0.450 0.0340.250 0.450 0.0340.250 0.450 0.0340.250 0.450 0.0340.230 0.450 0.1970.230 0.450 0.1520.230 0.450 0.1660.230 0.450 0.1520.450 0.450 1.5670.450 0.450 1.6020.450 0.450 1.6560.450 0.450 1.5750.450 0.450 0.7340.450 0.450 0.6730.450 0.450 2.0660.450 0.450 2.1700.450 0.450 2.1710.450 0.450 1.0480.450 0.450 1.0500.450 0.450 1.5390.450 0.450 1.5870.300 0.600 1.0280.300 0.600 1.1900.550 0.450 0.903 46.784
= 317.45 Cu.m
= 150.00 Cu.m= 167.45 Cu.m
697.9695700
1.002909153
0.05
0.000 46.784
LARSEN & TOUBRO LTD ECC DIVISION
ORCHID CROWN PROJECT - DADAR
Description No. L B H Qty.
1 R.C.C. Concrete for Colunms & Shear Walls
- From 2nd basment lvl. to 1st basement lvl.
C1, C2, C3, C4, C5, C17 2 1.714 0.750 3.100 7.970
C11, C12, C13, C14, C15, C18 2 1.294 0.750 3.100 6.017
2 10.837 0.750 3.100 50.392
2 1.399 0.750 3.100 6.505
2 1.675 0.750 3.100 7.789
2 7.661 0.700 3.100 33.249
2 2.325 0.800 3.100 11.532
2 1.625 1.000 3.100 10.075
2 2.644 0.700 3.100 11.475
2 7.450 0.700 3.100 32.333
2 2.644 0.700 3.100 11.475
2 3.400 0.700 3.100 14.756
2 2.000 1.150 3.100 14.260
2 5.601 0.700 3.100 24.308
2 2.000 0.800 3.100 9.920
-1 3.191 3.100 -9.891
Deduct Cutouts -
Cutout No. 01 -1 1.200 0.750 2.100 -1.890
Cutout No. 02 -1 1.300 0.700 0.650 -0.591
Cutout No. 03 -1 2.500 0.700 2.100 -3.675
Cutout No. 04 -1 2.500 0.700 2.100 -3.675
Cutout No. 05 -1 0.350 0.700 0.350 -0.086
Cutout No. 06 -1 0.350 0.700 0.350 -0.086
Cutout No. 07 -1 2.500 0.700 2.100 -3.675
Deduct Cutouts -
Cutout No. 31 -1 0.600 0.700 0.300 -0.126
Cutout No. 32 -1 2.000 0.750 2.100 -3.150
TOWER 'C' - Measurement Sheet - R.C.C. Concrete for Colunms & Shear Walls
SL. No.
Cutout No. 30 -1 2.000 0.750 0.300 -0.450
Cutout No. 29 -1 =3.141/4*0.3*0.3 0.750 -0.053
Cutout No. 28 -1 1.000 0.700 0.400 -0.280
Cutout No. 37 -1 1.950 0.700 0.550 -0.751
C6, C10 2 4.700 0.800 2.900 21.808
SW4, SW5 2 1.725 0.800 3.100 8.556
SW9,SW10 2 6.600 0.550 3.100 22.506
2 7.475 0.500 3.100 23.173
2 3.000 0.250 3.100 4.650
2 3.000 0.300 3.100 5.580
2 4.600 0.250 3.100 7.130
2 2.275 0.150 3.100 2.116
2 1.600 0.550 3.100 5.456
2 6.975 0.550 3.100 23.785
2 3.450 0.500 3.100 10.695
Deduct Cutouts -
Cutout No. 10 -1 0.600 0.550 0.300 -0.099
Cutout No. 11 -1 1.000 0.500 0.600 -0.300
Deduct Cutouts -
Cutout No. 26 -1 1.000 0.550 0.300 -0.165
Cutout No. 27 -1 1.000 0.500 0.600 -0.300
C7, C8 - Circular column - 2500 mm dia. 2 =3.141/4x2.5x2.5x3.10 30.428
8 =3.141/4x0.60x0.60x3.10 7.011
Column Capitals - RC12, RC16 2 2.500 2.500 0.100 1.640
Retaining walls 1 6.612 0.150 3.100 3.075
1 5.713 0.150 3.100 2.657
1 2.857 0.300 3.100 2.657
1 1.949 0.300 3.100 1.813
2 8.600 0.300 3.100 15.996
1 10.189 0.500 3.100 15.793
Podium Columns - RC14, 13, 11, 12, 18, 17, 15, 16 - 600 mm dia.
1 9.928 0.500 3.100 15.388
1 6.425 0.500 3.100 9.959
1 3.650 0.500 3.100 5.658
SW1, SW2, SW3 2 1.699 1.007 3.100 10.604
SW7,SW8,SW9 2 4.610 1.000 3.100 28.582
2 7.575 0.700 3.100 32.876
2 6.725 0.550 3.100 22.932
2 7.425 0.500 3.100 23.018
2 1.000 0.500 3.100 3.100
2 11.600 0.450 3.100 32.364
4 2.600 0.300 3.100 9.672
4 2.450 0.250 3.100 7.595
2 2.600 0.800 3.100 12.896
Deduct Cutouts -
Cutout No. 08,24 -2 1.000 0.700 0.400 -0.560
Cutout No. 09,25 -2 1.000 0.700 0.400 -0.560
Cutout No. 35,36 -2 0.800 0.500 0.400 -0.320
Cutout No. 12,20 -2 1.000 0.500 0.400 -0.400
Cutout No. 13,19 -2 1.000 0.500 0.400 -0.400
Cutout No. 40,42 -2 0.250 0.250 1.800 -0.225
Cutout No. 41,43 -2 0.250 0.250 1.800 -0.225
Cutout No. 44,46 -2 0.250 0.250 1.800 -0.225
Cutout No. 45,47 -2 0.250 0.250 1.800 -0.225
TOTAL QUANTITY = =
Deduct Last month bill quantity =Net Payable Quantity FTM Dec-11 =
Ba-22
Unit
2.571
1.941
16.2555
2.0985
2.5125
10.7254
3.72
3.25
3.7016
10.43
3.7016
4.76
4.6
7.8414
3.2
242.166 81.3085 78.118
-13.678
Total Quantity
-4.810
21.808
113.646
-0.399
-0.465
30.428 30.41875
7.00848
8.650
72.994
3.420779
9.22
10.605
7.3975
7.425
1
10.44
3.12
2.45
183.639 4.16
59.23828 58.478
-3.140
650.840 Cu.m
504.41146.430 Cu.m
LARSEN & TOUBRO LTD ECC DIVISION
ORCHID CROWN PROJECT - DADAR
Description No. L B H Qty.
1 R.C.C. Concrete for Columns & Shear Walls
-
C1, C2, C3, C4, C5,C6,C7,C8,C9,C10,C11 1 5.097 0.700 3.100 11.060
1 6.700 0.700 3.100 14.539
1 0.854 0.175 3.100 0.462
1 2.150 0.800 3.100 5.332
1 14.165 0.700 3.100 30.738
1 2.228 0.700 3.100 4.835
1 3.240 0.900 3.100 9.040
1 1.150 0.700 3.100 2.496
1 2.210 0.900 3.100 6.166
1 9.446 0.700 3.100 20.498
1 3.200 0.900 3.100 8.928
1 5.450 0.700 3.100 11.827
1 1.850 0.700 3.100 4.015
1 3.675 0.900 3.100 10.253
1 2.950 0.700 3.100 6.402
1 3.675 0.700 3.100 7.975
1 1.550 1.500 3.100 7.208
1 2.625 0.850 3.100 6.917
1 7.770 0.700 3.100 16.861
Deduct Cutouts -
Cutout no. 31 -1 1.000 0.700 0.400 -0.280
Cutout no. 32 -1 0.300 0.700 0.300 -0.063
Cutout no. 33 -1 0.600 0.700 0.300 -0.126
Cutout no. 28 -1 2.000 0.700 2.100 -2.940
TOWER 'A' - Measurement Sheet - R.C.C. Concrete for Columns & Shear Walls
SL. No.
From 3rd basement to 2nd basement floor level
Cutout no. 30 -1 1.000 0.900 0.350 -0.315
Cutout no. 29 -1 1.000 0.700 0.350 -0.245
Cutout no. 27 -1 0.300 0.700 0.300 -0.063
Retaining wall - near C8 & C11 1 3.000 0.500 3.100 4.650
1 3.027 0.500 3.100 4.692
Retaining wall - near C3 1 1.750 0.300 3.100 1.628
1 3.650 0.300 3.100 3.395
C17, C21 2 =3.141/4x2.70x2.70x3.10 35.492
C20, C24 2 6.550 1.000 3.100 40.610
Lift 1 8.500 0.450 3.100 11.858
2 2.600 0.450 3.100 7.254
2 2.450 0.350 3.100 5.317
1 3.675 0.900 3.100 10.253
1 1.850 0.700 3.100 4.015
1 9.446 0.700 3.100 20.498
1 3.200 0.900 3.100 8.928
1 5.450 0.700 3.100 11.827
1 2.950 0.700 3.100 6.402
1 1.643 0.900 3.100 4.584
1 2.480 0.900 3.100 6.919
1 14.165 0.700 3.100 30.738
1 2.228 0.700 3.100 4.835
1 6.700 0.700 3.100 14.539
1 0.854 0.175 3.100 0.462
1 5.097 0.700 3.100 11.060
1 7.737 0.700 3.100 16.789
1 2.625 0.850 3.100 6.917
1 1.550 1.500 3.100 7.208
1 3.675 0.700 3.100 7.975
1 2.950 0.700 3.100 6.402
C38 1 2.150 0.800 3.100 5.332
Deduct Cutouts -
Cutout no. 9 -1 1.000 0.900 0.350 -0.315
C31, C32, C33, C34, C35, C36, C37, C38, C39, C40, C41
Cutout no. 8 -1 2.000 0.700 2.100 -2.940
Cutout no. 10 -1 1.000 0.700 0.350 -0.245
Cutout no. 11 -1 1.300 0.900 0.640 -0.749
Cutout no. 1 -1 2.300 0.700 2.100 -3.381
Cutout no. 2 -1 2.300 0.700 2.100 -3.381
Cutout no. 3 -1 2.500 0.700 2.100 -3.675
Cutout no. 5 -1 2.500 0.700 2.100 -3.675
Cutout no. 6 -1 2.500 0.700 2.100 -3.675
Cutout no. 7 -1 2.500 0.700 2.100 -3.675
Retaining wall - near C31 1 2.275 0.150 3.100 1.058
5 1 3.788 0.150 3.100 1.761
6 1 7.440 0.150 3.100 3.460
6 1 7.964 0.150 3.100 3.703
SW13A, SW12, SW13, SW14, SW15, SW16 2 10.601 1.200 3.100 78.871
SW25,SW26,SW27,SW28,SW29,SW30 2 2.476 0.900 3.100 13.816
2 17.875 0.900 3.100 99.743
2 1.633 0.903 3.100 9.143
2 1.656 0.978 3.100 10.036
2 2.185 1.054 3.100 14.279
2 9.320 1.200 3.100 69.341
2 1.588 0.541 3.100 5.325
Deduct Cutouts -
Cutout no. 24,12 -2 1.000 0.900 0.400 -0.720
Cutout no. 25,13 -2 1.200 0.900 0.350 -0.756
Cutout no. 26,14 -2 1.000 0.900 0.250 -0.450
SW18,SW22 2 7.300 0.900 3.100 40.734
2 1.035 0.600 3.100 3.850
2 5.250 0.600 3.100 19.530
2 6.200 0.450 3.100 17.298
2 2.450 0.300 3.100 4.557
2 2.450 0.500 3.100 7.595
2 1.202 0.476 3.100 3.546
2 6.202 0.385 3.100 14.804
Deduct Cutout no. 22 ,15 -2 1.000 0.600 0.500 -0.600
SW19 1 5.922 0.807 3.100 14.807
1 0.300 0.300 3.100 0.279
1 0.950 0.300 3.100 0.884
1 2.450 0.600 3.100 4.557
1 2.450 0.300 3.100 2.279
1 2.450 0.500 3.100 3.798
1 6.202 0.443 3.100 8.508
1 7.700 0.450 3.100 10.742
1 3.000 0.900 3.100 8.370
1 7.700 0.900 3.100 21.483
1 1.800 0.600 3.100 3.348
Retaining wall 1 3.000 0.150 3.100 1.395
SW23 1 5.922 0.807 3.100 14.807
1 6.102 0.441 3.100 8.342
1 2.450 0.600 3.100 4.557
1 2.450 0.300 3.100 2.279
1 2.450 0.500 3.100 3.798
1 6.800 0.450 3.100 9.486
1 1.800 0.600 3.100 3.348
1 3.000 0.900 3.100 8.370
1 6.800 0.900 3.100 18.972
Retaining wall 1 3.000 0.150 3.100 1.395
Podium Columns - PC2, PC18, PC18A 3 =3.141/4x0.60x0.60x3.10 2.629
TOTAL QUANTITY = =
BOQ Code:
RA Bill - 22
Unit
Total Quantity
181.517
14.364
35.492
40.610
24.428
3.3075
1.295
6.6122
2.88
3.815
2.065
1.4787
2.232
9.9155
1.5596
4.69
0.149023
3.5679
5.4159
2.23125
2.325
2.5725
2.065
1.72
159.970
9.982
298.627
111.314
80.448
75.353
2.629
1034.734 Cu.m
LARSEN & TOUBRO LTD ECC DIVISION
ORCHID CROWN PROJECT - DADAR
Description No.
1 R.C.C. Concrete for Slab & Slab Beams
- Ground floor slab
1
1
-11-1
For 500 mm thk. Slab 1Deduction of Cutouts -1 -12 -13 -14 -15 -16 -17 -1
Tower B - Measurement Sheet - R.C.C. Concrete for Slab & Slab Beams
Sr. No
.
For (+) 3.55 m - 350 mm thk. & (+) 4.60 m level - 250 mm thk.
For +3.55 m level slab - slab thk is 0.35 m - so add for 100 mm thk.
8 -19 -110 -111 -112 -113 -114 -115 -116 -117 -118 -119 -120 -121 -122 -127 -123, 24, 25 -326 -1Deduction of Column & Shear walls -
(a) C1, C2, C3, C4, C4A, C5A, C5B, C7A, C7B
=
(b) RW =© =(d) =(e) C15, C19 =(f) SW16, SW19 =(g) SW13, SW8, SW9, SW10, SW11, SW12
C26B, C26A, C30A, C31, C32, C30, C28A, C28B, C29
Circular Columns - C14, C18Podium Columns - 10 Nos.
SW22, SW23, SW24, SW25, SW26, SW27 =
(h) SW17, SW20 =Convert in Sqm =
-1Slab Beams :LB3 1LB9 1
11
LB12 111
LB11 1LB32 2
2LB7 1LB8 1LB7A 1LB8A 11 12 13 1
1112211
4 - (+) 3.55 m level slab
5 - (+) 3.55 m level slab6 - (+) 3.55 m level slab7 - (+) 3.55 m level slab8 - (+) 3.55 m level slab
1111111
16 211
27 223 124 126 125 122 231 132 133 134 135 136 137 138 139 140 141 142 143 1
18 - (+) 3.55 m level slab19 - (+) 3.55 m level slab13 - (+) 3.55 m level slab14 - (+) 3.55 m level slab22C - (+) 3.55 m level slab22A - (+) 3.55 m level slab22B - (+) 3.55 m level slab
17 - (+) 3.55 m level slab21 - (+) 3.55 m level slab
44 145 138X 141X 142X 145X 139X 140X 143X 144X 146, 47, 48 346X, 47X 220 249 149A 150 1LB13 1LB16 1LB17 1LB18 1LB22 1LB23 1
TOTAL QUANTITY Deduct last bill quantity Net Payble Quantity
LARSEN & TOUBRO LTD ECC DIVISION RAB 21
ORCHID CROWN PROJECT - DADAR
L B H Qty.
2095.597 0.250 523.899
539.238 0.100 53.924
179.861 0.100 -17.986514.884 0.100 51.488179.843 0.100 -17.984116.704 0.250 29.176 622.517
44.591 0.250 -11.1484.215 0.250 -1.0544.034 0.250 -1.009
12.514 0.250 -3.1294.860 0.250 -1.2154.860 0.250 -1.2150.643 0.250 -0.161
- Measurement Sheet - R.C.C. Concrete for Slab & Slab Beams
Total Quantity
0.670 0.250 -0.1686.201 0.250 -1.5504.860 0.250 -1.2154.860 0.250 -1.2154.034 0.250 -1.0091.470 0.250 -0.3684.860 0.250 -1.2154.860 0.250 -1.2157.840 0.250 -1.9602.250 0.250 -0.5630.411 0.250 -0.1034.860 0.250 -1.2154.860 0.250 -1.2152.850 0.250 -0.713
10.335 0.250 -2.5841.207 0.250 -0.3024.050 0.250 -3.0373.984 0.250 -0.996 -39.570
423.540
8.51651.52012.72158.950
141.300
395.139
395.139
196.020 1287.7061287.706 / 4.500 286.157 286.157286.157 x 0.250 -71.539 -71.539
2.050 0.900 0.350 0.6463.475 0.900 0.650 2.0333.875 0.900 0.650 2.2671.088 0.900 0.650 0.6364.375 0.900 0.650 2.5593.875 0.900 0.650 2.2671.088 0.900 0.650 0.6362.050 0.900 0.500 0.9231.378 0.900 1.700 4.2151.634 0.900 1.700 5.0001.203 0.831 0.600 0.5991.203 0.790 0.600 0.5705.922 1.346 0.200 1.5945.922 1.346 0.200 1.5944.500 0.300 0.350 0.4724.500 0.300 0.350 0.4723.547 0.666 0.350 0.8263.553 0.666 0.350 0.8282.412 0.450 0.300 0.3265.131 0.450 0.300 0.6934.950 0.450 0.100 0.4466.703 0.450 0.100 0.6039.010 0.450 0.400 1.6229.095 0.450 0.400 1.637
10.398 0.450 0.400 1.8729.245 0.450 0.400 1.6647.992 0.450 0.400 1.4397.636 0.450 0.400 1.3745.993 0.450 0.400 1.0795.474 0.450 0.400 0.9855.212 0.450 0.400 0.9382.450 0.450 0.200 0.4414.799 0.450 0.400 0.8643.536 0.450 0.400 0.6368.175 0.400 0.490 3.2053.398 0.230 0.350 0.2743.359 0.230 0.350 0.2701.996 0.230 0.350 0.1611.652 0.450 0.350 0.2602.450 1.000 0.350 1.7153.816 0.450 0.200 0.3435.099 0.450 0.200 0.4593.776 0.230 0.350 0.3041.200 0.600 0.350 0.2521.200 0.600 0.350 0.2521.200 0.600 0.350 0.2521.200 0.600 0.350 0.2521.500 0.480 0.350 0.2521.500 0.368 0.350 0.1931.500 0.368 0.350 0.1931.500 0.480 0.350 0.2521.500 0.480 0.350 0.2521.500 0.368 0.350 0.193
1.500 0.368 0.350 0.1931.500 0.480 0.350 0.2520.413 0.300 0.350 0.0430.413 0.300 0.350 0.0430.413 0.300 0.350 0.0430.413 0.300 0.350 0.0430.336 0.300 0.350 0.0350.336 0.300 0.350 0.0350.336 0.300 0.350 0.0350.336 0.300 0.350 0.0351.500 0.150 0.300 0.2030.150 0.350 0.300 0.0321.500 0.150 0.300 0.1352.235 0.230 0.350 0.1802.235 0.230 0.350 0.1803.000 0.230 0.350 0.2422.900 0.700 0.250 0.5082.600 0.700 0.250 0.4551.200 0.700 0.250 0.2102.800 0.700 0.250 0.4902.000 0.700 0.250 0.3501.500 0.700 0.250 0.262 58.096
= 569.504= 550.587= 18.917
697.9695
1679.333 7001.0029091529
RAB 21
Unit
CumSqmCum
0.6000.9000.9000.9000.9000.9000.9000.7501.9501.9500.8500.8500.4500.4500.6000.6000.6000.6000.6500.6500.4500.4500.7500.750
0.7500.7500.7500.7500.7500.7500.7500.4500.7500.7500.7400.6000.6000.6000.6000.6000.4500.4500.6000.6000.6000.6000.6000.6000.6000.6000.6000.6000.600
0.6000.6000.6000.6000.6000.6000.6000.6000.6000.6000.5500.5500.5500.6000.6000.6002.2502.2502.2502.2502.2500.600
Cu.mCu.mCu.m
LARSEN & TOUBRO LTD ECC DIVISION
ORCHID CROWN PROJECT - DADAR
Description No. L B H Qty.
1 Formwork for Columns & Shear Walls
-
C1, C2, C3, C4, C5,C6,C7,C8,C9,C10,C11 1 7.737 2.850 22.050
1 7.800 2.850 22.230
1 1.925 2.850 5.486
1 1.125 2.850 3.206
1 1.550 2.850 4.418
1 2.175 2.850 6.199
1 0.700 2.850 1.995
1 2.975 2.850 8.479
1 1.850 2.850 5.273
1 2.275 2.850 6.484
1 2.950 2.850 8.408
1 6.800 2.850 19.380
1 3.675 2.850 10.474
1 2.050 2.850 5.842
2 9.446 2.850 53.842
2 3.900 2.850 22.230
2 4.550 2.850 25.935
1 0.200 2.850 0.570
1 2.050 2.850 5.842
1 3.300 2.850 9.405
1 2.200 2.850 6.270
1 1.150 2.850 3.278
1 1.800 2.850 5.130
1 1.185 2.850 3.377
1 1.643 2.850 4.683
TOWER 'A' - Measurement Sheet - Formwork for Columns & Shear Walls
Sr. No.
From 3rd basement to 2nd basement floor level
1 15.535 2.850 44.275
1 7.317 2.850 20.853
1 2.252 2.850 6.418
1 0.700 2.850 1.995
1 2.158 2.850 6.150
1 4.072 2.850 11.605
1 12.452 2.850 35.488
1 11.142 2.850 31.755
1 0.173 2.850 0.493
1 0.174 2.850 0.496
C3 2 2.150 3.100 13.330
2 0.800 3.100 4.960
Add cutout formwork
Cutout no. 31 2 1.000 0.700 1.400
2 0.700 0.400 0.560
Cutout no. 32 2 0.300 0.700 0.420
2 0.700 0.300 0.420
Cutout no. 33 2 0.600 0.700 0.840
2 0.700 0.300 0.420
Cutout no. 28 2 2.000 0.700 2.800
2 0.700 2.100 2.940
-2 2.000 2.100 -8.400
Cutout no. 30 2 1.000 0.900 1.800
2 0.900 0.350 0.630
Cutout no. 29 2 1.000 0.700 1.400
2 0.700 0.350 0.490
Cutout no. 27 2 0.300 0.700 0.420
2 0.700 0.300 0.420
Retaining wall - near C8 & C11 2 3.000 3.100 18.600
2 3.027 3.100 18.767
Retaining wall - near C3 2 1.750 3.100 10.850
2 3.650 3.100 22.630
C17, C21 2 =3.141x2.70x2.85 48.340
C20, C24 4 6.550 2.850 74.670
4 1.000 2.850 11.400
Lift 2 8.500 2.850 48.450
2 2.600 2.850 14.820
2 3.050 2.850 17.385
4 2.450 2.850 27.930
1 15.835 2.850 45.130
1 4.072 2.850 11.605
1 0.700 2.850 1.995
1 2.252 2.850 6.418
1 7.317 2.850 20.853
1 1.161 2.850 3.309
1 1.643 2.850 4.683
1 1.150 2.850 3.278
1 1.800 2.850 5.130
1 2.220 2.850 6.327
1 0.200 2.850 0.570
1 2.050 2.850 5.842
1 3.000 2.850 8.550
2 4.550 2.850 25.935
2 3.900 2.850 22.230
1 10.146 2.850 28.916
1 9.446 2.850 26.921
1 2.050 2.850 5.842
1 1.850 2.850 5.273
1 2.275 2.850 6.484
1 3.675 2.850 10.474
1 2.950 2.850 8.408
1 2.975 2.850 8.479
1 0.700 2.850 1.995
C31, C32, C33, C34, C35, C36, C37, C38, C39, C40, C41
1 2.175 2.850 6.199
1 1.550 2.850 4.418
1 1.122 2.850 3.198
1 7.800 2.850 22.230
1 6.800 2.850 19.380
1 1.925 2.850 5.486
1 7.737 2.850 22.050
1 12.452 2.850 35.488
1 11.142 2.850 31.755
1 0.176 2.850 0.502
1 0.173 2.850 0.493
C38 2 2.150 3.100 13.330
2 0.800 3.100 4.960
Add cutout formwork
Cutout no. 9 2 1.000 0.900
2 0.900 0.350 0.630
Cutout no. 8 2 2.000 0.700 2.800
2 0.700 2.100 2.940
-2 2.000 2.100 -8.400
Cutout no. 10 2 1.000 0.700 1.400
2 0.700 0.350 0.490
Cutout no. 11 2 1.300 0.900 2.340
2 0.900 0.640 1.152
-2 1.300 6.400 -16.640
Cutout no. 1 2 2.300 0.700 3.220
2 0.700 2.100 2.940
-2 2.300 2.100 -9.660
Cutout no. 2 2 2.300 0.700 3.220
2 0.700 2.100 2.940
-2 2.300 2.100 -9.660
Cutout no. 3 2 2.500 0.700 3.500
2 0.700 2.100 2.940
-2 2.500 2.100 -10.500
Cutout no. 5 2 2.500 0.700 3.500
2 0.700 2.100 2.940
-2 2.500 2.100 -10.500
Cutout no. 6 2 2.500 0.700 3.500
2 0.700 2.100 2.940
-2 2.500 2.100 -10.500
Cutout no. 7 2 2.500 0.700 3.500
2 0.700 2.100 2.940
-2 2.500 2.100 -10.500
Retaining wall - near C31 &C38 2 2.275 3.100 14.105
5 2 3.788 3.100 23.486
6 2 7.440 3.100 46.128
6 2 7.964 3.100 49.377
SW19 1 6.004 2.850 17.111
1 4.341 2.850 12.372
3 0.300 2.850 2.565
1 0.600 2.850 1.710
2 0.950 2.850 5.415
1 0.300 2.850 0.855
1 0.600 2.850 1.710
5 2.450 2.850 34.913
2 2.700 2.850 15.390
1 3.233 2.850 9.214
1 6.200 2.850 17.670
1 6.204 2.850 17.681
1 3.350 2.850 9.548
1 3.450 2.850 9.833
4 3.000 2.850 34.200
1 3.350 2.850 9.548
1 2.850 2.850 8.123
1 1.800 2.850 5.130
1 2.700 2.850 7.695
1 0.600 2.850 1.710
1 7.700 2.850 21.945
1 0.900 2.850 2.565
SW23 1 6.004 2.850 17.111
1 5.241 2.850 14.937
1 6.204 2.850 17.681
1 6.200 2.850 17.670
1 2.900 2.850 8.265
5 2.450 2.850 34.913
1 3.223 2.850 9.186
2 2.700 2.850 15.390
1 1.550 2.850 4.418
1 4.350 2.850 12.397
2 3.000 2.850 17.100
1 2.700 2.850 7.695
1 1.800 2.850 5.130
1 0.950 2.850 2.708
1 4.350 2.850 12.397
1 6.800 2.850 19.380
SW18, SW22 2 1.935 2.850 11.030
2 1.035 2.850 5.900
2 7.300 2.850 41.610
2 6.700 2.850 38.190
2 0.900 2.850 5.130
4 5.250 2.850 59.850
2 6.200 2.850 35.340
4 2.700 2.850 30.780
8 2.450 2.850 55.860
2 6.200 2.850 35.340
2 6.204 2.850 35.363
2 0.333 2.850 1.898
2 0.600 2.850 3.420
2 0.515 2.850 2.936
2 1.203 2.850 6.857
Add Cutout formwork no. 22 & 15 4 1.000 0.600 2.400
4 0.600 0.500 1.200
-4 1.000 0.500 -2.000
2 1.207 2.850 6.880
2 10.664 2.850 60.785
2 10.538 2.850 60.067
2 1.200 2.850 6.840
2 2.537 2.850 14.461
2 1.513 2.850 8.624
2 18.778 2.850 107.035
2 2.505 2.850 14.279
4 2.450 2.850 27.930
2 3.375 2.850 19.238
1 3.221 2.850 9.180
1 3.204 2.850 9.131
1 1.741 2.850 4.962
1 1.632 2.850 4.651
2 6.550 2.850 37.335
2 6.860 2.850 39.102
2 2.468 2.850 14.068
2 1.572 2.850 8.960
2 0.816 2.850 4.651
2 1.694 2.850 9.656
2 9.049 2.850 51.579
2 1.513 2.850 8.624
-2 2.468 0.150 -0.740
Add cutout formwork
Cutout no. 24 & 12 4 1.000 0.900 3.600
4 0.900 0.400 1.440
SW13A, SW12, SW13, SW14, SW15, SW16 & SW25, SW26, SW27, SW28, SW29, SW30
Cutout no. 25 & 13 4 1.200 0.900 4.320
4 0.900 0.350 1.260
Cutout no. 26 & 14 4 1.000 0.900 3.600
4 0.900 0.250 0.900
Podium Columns - PC2, PC18, PC18A 3 =3.141x0.60x2.85 16.113
TOTAL QUANTITY =
R.A.BILL 21
Unit
7.737
7.8
1.925
1.125
1.55
2.175
0.7 152.05
2.975
1.85
2.275
2.95
6.8
3.675
2.05
18.892
7.8
9.1
0.2
2.05
3.3
2.2
1.15
1.8
1.185
1.643
Total Quantity
15.535
7.317
2.252
0.7
2.158
4.072
12.452
11.142
0.173
0.174
4.024
4.3
1.6 29.761
15.835
4.072
0.7
2.252
7.317
1.161
1.643
1.15
1.8
2.22
0.2
2.05
3
9.1
7.8
10.146
9.446
2.05
1.85
2.275
3.675
2.95
2.975
0.7
2.175
1.55
1.122
7.8
6.8
1.925
7.737
12.452
11.142
0.176
0.173
4.3
1.6
6.004
4.341
0.9
0.6
1.9
0.3
0.6
12.25
5.4
3.233
6.2
6.204
3.35
3.45
12
3.35
2.85
1.8
2.7
0.6
7.7
0.9
6.004 71.354
5.241
6.204
6.2
2.9
12.25
3.223
5.4
1.55
4.35
6
2.7
1.8
0.95
4.35
6.8
3.87
2.07
14.6
13.4
1.8
21
12.4
10.8
19.6
12.4
12.408
0.666
1.2
1.03
2.406 55.724
129.65
2.414
21.328
21.076
2.4
5.074
3.026
37.556
5.01
9.8
6.75
3.221
3.204
1.741
1.632
13.1
13.72
4.936
3.144
1.632
3.388
18.098
3.026
2702.319 Sq.m
LARSEN & TOUBRO LTD ECC DIVISION
ORCHID CROWN PROJECT - DADAR
Description No. L B H Qty.
1 Formwork for Slab & Slab Beams
1 1722.790 1722.790
0 81.886 0.000
Deduction of Cutouts -
1 -1 65.082 -65.082
2 -1 69.382 -69.382
3 -1 12.514 -12.514
4 -1 6.614 -6.614
5 -1 6.614 -6.614
6 -1 0.712 -0.712
7 -1 0.670 -0.670
8 -1 6.201 -6.201
9 -1 6.614 -6.614
10 -1 6.614 -6.614
11 -1 1.470 -1.470
12 -1 6.614 -6.614
13 -1 6.615 -6.615
14 -1 9.600 -9.600
15 -1 2.250 -2.250
-1 0.630 -0.630
16 -1 6.615 -6.615
17 -1 6.614 -6.614
18 -1 1.168 -1.168
19 -1 2.850 -2.850
20 -1 12.600 -12.600
21 -1 5.635 -5.635
22 -1 5.635 -5.635
Tower A - Measurement Sheet - Formwork for Slab & Slab Beams
Sr. No.
area of 2nd basement floor slab
add offset of 400 mm thk. Slab - Perimeter x thk. of slab
23 -1 5.635 -5.635
24 -1 25.565 -25.565
25 -1 28.715 -28.715
Add formwork around cutouts Perimeter slab thk.
1 1 44.845 0.250 11.211
2 1 51.531 0.250 12.883
3 1 15.700 0.250 3.925
4 1 10.300 0.250 2.575
5 1 10.300 0.250 2.575
6 1 5.350 0.250 1.338
7 1 5.069 0.250 1.267
8 1 10.019 0.250 2.505
9 1 10.300 0.250 2.575
10 1 10.300 0.250 2.575
11 1 6.100 0.250 1.525
12 1 10.300 0.250 2.575
13 1 10.300 0.250 2.575
14 1 12.400 0.250 3.100
15 1 7.500 0.250 1.875
1 4.800 0.250 1.200
16 1 10.300 0.250 2.575
17 1 10.300 0.250 2.575
18 1 5.665 0.250 1.416
19 1 7.900 0.250 1.975
20 1 14.400 0.250 3.600
21 1 9.500 0.250 2.375
22 1 9.500 0.250 2.375
23 1 9.500 0.250 2.375
24 1 29.250 0.250 7.313
25 1 23.342 0.250 5.836
Deduction of Columns & Shear walls-
C1, C2, C3, C4, C5, C6, C7, C8, C9, C10, C11 -1 =197.610-137.946 -59.664
add 1 1.979 1.979
Retaining walls -1 0.528 -0.528
-1 1.094 -1.094
-1 1.522 -1.522
-1 1.500 -1.500
-1 1.513 -1.513
C3 -1 1.720 -1.720
-1 69.408 -69.408
RW -1 2.953 -2.953
RW -1 0.450 -0.450
C20, C24 -2 6.550 -13.100
C17, C21 -2 5.725 -11.450
Lift -1 7.880 -7.880
SW25, SW26, SW27, SW28, SW29, SW30, SW23 -1 67.924 -67.924
RW -1 2.589 -2.589
RW -1 0.450 -0.450
SW18, SW22 -2 15.662 -31.324
Curve walls -2 2.601 -5.202
-1 2.593 -2.593
-1 2.589 -2.589
-1 =201.377-137.946 -63.431
Add 1 1.979 1.979
C38 -1 1.720 -1.720
Podium columns -3 3.141/4x0.6x0.6 -0.848
Slab Beams -
LB3 2 2.050 0.350 1.435
LB9 2 3.875 0.650 5.038
2 1.088 0.650 1.414
1 3.553 0.650 2.309
1 3.475 0.650 2.259
LB12 2 3.875 0.650 5.038
2 1.088 0.650 1.414
1 4.453 0.650 2.894
SW13A, SW12, SW13, SW14, SW15,SW16, SW19
C31, C32, C33, C34, C35, C36, C37, C38, C39, C40, C41
1 4.375 0.650 2.844
LB11 2 2.050 0.500 2.050
LB19 0 1.205 0.600 0.000
0 1.200 0.600 0.000
LB20 1 1.205 0.600 0.723
1 1.200 0.600 0.720
LB21 0 2.000 0.600 0.000
LB22 0 2.300 0.600 0.000
LB23 0 2.300 0.600 0.000
LB24 0 2.500 0.600 0.000
LB25 0 2.500 0.600 0.000
LB26 0 2.500 0.600 0.000
LB27 0 2.500 0.600 0.000
LB28 0 2.000 0.600 0.000
LB13 1 1.770 0.600 1.062
1 1.676 0.600 1.006
1 8 1.200 0.150 1.440
1A 2 2.235 0.350 1.564
2 3.000 0.350 2.100
1B 2 2.235 0.350 1.564
3 2 3.547 0.350 2.483
2 3.559 0.350 2.491
5 2 5.075 0.350 3.552
6 2 7.604 0.350 5.323
2 7.950 0.350 5.565
4 2 6.162 0.200 2.465
2 6.222 0.200 2.489
8 4 7.187 0.200 5.750
9 1 6.045 0.200 1.209
1 4.720 0.200 0.944
13 1 6.045 0.200 1.209
1 4.720 0.200 0.944
10, 11, 12 6 2.300 0.300 4.140
10X 4 0.15 0.300 0.180
14 2 4.65 0.200 1.860
17 2 4.775 0.200 1.910
15 2 6.778 0.200 2.711
16 2 6.778 0.200 2.711
18 4 4.500 0.350 6.300
26, 27 4 2.450 0.350 3.430
28 4 2.450 0.200 1.960
1 205.053 0.250 51.263
TOTAL QUANTITY =
Add pheriphery of slab thk. - Pheriphery of outer side of slab x thk. of slab
Unit
1722.790
Total Quantity
-309.228
88.693
-347.494
0.6
0.9
0.9
0.9
0.9
0.9
0.9
0.9
0.9
0.75
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.85
0.4
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.6
0.45
0.45
0.45
0.45
0.45
0.45
0.45
0.55
0.55
0.45
0.45
0.45
0.45
0.6
0.6
96.501 0.45
51.263
1302.525 Sqm
LARSEN & TOUBRO LTD ECC DIVISION
ORCHID CROWN PROJECT - DADAR
Sr. No. Description No.
1 Formwork for Slab & Slab Beams - area of Ground Floor Slab 1
0
000
For 500 mm thk. Slab 0Deduction of Cutouts -1 -12 -13 -14 -15 -16 -17 -18 -19 -110 -1
Tower B - Measurement Sheet - Formwork for Slab & Slab Beams
offset of slab due to slab thk. (various)
For +3.55 m level slab - slab thk is 0.35 m - so add for 100 mm thk.
11 -112 -113 -114 -115 -116 -117 -118 -119 -120 -121 -122 -127 -123, 24, 25 -326 -1
(a)
=
(b) RW =© =(d) =(e) C15, C19 =(f) SW16, SW19 =(g)
=
(h) SW17, SW20 =
Deduction of Column & Shear walls -C1, C2, C3, C4, C4A, C5A, C5B, C7A, C7B
C26B, C26A, C30A, C31, C32, C30, C28A, C28B, C29
Circular Columns - C14, C18Podium Columns - 10 Nos.
SW13, SW8, SW9, SW10, SW11, SW12SW22, SW23, SW24, SW25, SW26, SW27
Convert in Sqm -1Add Cutout formwork 1 12 13 14 15 16 17 18 19 110 111 112 113 114 115 116 117 118 119 120 121 122 127 123, 24, 25 326 1Slab Beams :LB3 2
LB9 222
LB12 2` 2
2LB11 2LB32 2
222
LB7 11
LB8 11
LB7A 22
LB8A 22
1 22 23 2
2222211
4 - (+) 3.55 m level slab
5 - (+) 3.55 m level slab6 - (+) 3.55 m level slab7 - (+) 3.55 m level slab
111111211111111
16 41111
27 423 224 226 225 222 431 232 233 2
8 - (+) 3.55 m level slab
18 - (+) 3.55 m level slab
19 - (+) 3.55 m level slab
13 - (+) 3.55 m level slab14 - (+) 3.55 m level slab
22C - (+) 3.55 m level slab
22A - (+) 3.55 m level slab
22B - (+) 3.55 m level slab
17 - (+) 3.55 m level slab
21 - (+) 3.55 m level slab
34 235 236 237 238 239 240 241 242 243 244 245 238X 241X 242X 245X 239X 240X 243X 244X 246, 47, 48 646X, 47X 420 449 249A 250 2LB13 0LB16 0LB17 2
LB18 0LB22 2LB23 0
1
TOTAL QUANTITY
Add pheriphery of slab thk. - Pheriphery of outer side of slab x thk. of slab
LARSEN & TOUBRO LTD ECC DIVISION RAB 21
ORCHID CROWN PROJECT - DADAR
L B H Qty.
2095.597 2095.597
Perimeter slab thk.
101.721 0.100 0.000
55.075 0.100 0.000102.279 0.100 0.00055.075 0.100 0.00082.500 0.250 0.000 2095.597Area
44.591 -44.5914.215 -4.2154.034 -4.034
12.514 -12.5144.860 -4.8604.860 -4.8606.435 -6.4356.704 -6.7046.201 -6.2014.860 -4.860
- Measurement Sheet - Formwork for Slab & Slab Beams
Total Quantity
4.860 -4.8604.034 -4.0341.470 -1.4704.860 -4.8604.860 -4.8607.840 -7.8402.250 -2.2500.411 -0.4114.860 -4.8604.860 -4.8602.850 -2.850
10.335 -10.3351.207 -1.2074.050 -12.1503.984 -3.984 -170.105
463.590
8.51651.52012.72158.950
166.287
395.139
230.480 1387.203
1387.203 / 4.500 -308.267 -308.267
36.125 0.250 9.0318.424 0.250 2.1068.855 0.250 2.214
15.669 0.250 3.9178.850 0.250 2.2138.850 0.250 2.2134.890 0.250 1.2235.069 0.250 1.267
10.019 0.250 2.5058.850 0.250 2.2138.850 0.250 2.2138.885 0.250 2.2216.100 0.250 1.5258.850 0.250 2.2138.850 0.250 2.213
11.200 0.250 2.8007.500 0.250 1.8753.340 0.250 0.8358.850 0.250 2.2138.850 0.250 2.2137.900 0.250 1.975
12.995 0.250 3.2495.908 0.250 1.4778.050 0.250 6.0387.984 0.250 1.996 63.953
2.050 0.350 1.435
3.475 0.650 4.5183.875 0.650 5.0381.088 0.650 1.4144.375 0.650 5.6883.875 0.650 5.0381.088 0.650 1.4142.050 0.500 2.0501.408 1.700 4.7871.347 1.700 4.5801.605 1.700 5.4571.664 1.700 5.6581.205 0.600 0.7231.200 0.600 0.7201.205 0.600 0.7231.205 0.600 0.7236.004 0.200 2.4025.841 0.200 2.3366.004 0.200 2.4025.841 0.200 2.3364.500 0.350 3.1504.500 0.350 3.1503.547 0.350 2.4833.553 0.350 2.4872.412 0.300 1.4475.131 0.300 3.0794.950 0.100 0.9906.703 0.100 1.3419.233 0.400 3.6938.990 0.400 3.596
9.402 0.400 3.7618.977 0.400 3.591
10.368 0.400 4.14710.428 0.400 4.1719.058 0.400 3.6239.432 0.400 3.7737.992 0.400 6.3947.566 0.400 3.0267.706 0.400 3.0825.921 0.400 2.3686.065 0.400 2.4265.325 0.400 2.1305.623 0.400 2.2495.551 0.400 2.2204.872 0.400 1.9492.450 0.200 1.9604.792 0.400 1.9174.805 0.400 1.9223.532 0.400 1.4133.539 0.400 1.4168.175 0.490 16.0233.398 0.350 2.3793.359 0.350 2.3511.996 0.350 1.3971.652 0.350 1.1562.450 0.350 3.4303.816 0.200 1.5265.099 0.200 2.0403.776 0.350 2.643
1.200 0.350 0.8401.200 0.350 0.8401.200 0.350 0.8401.200 0.350 0.8401.500 0.350 1.0501.500 0.350 1.0501.500 0.350 1.0501.500 0.350 1.0501.500 0.350 1.0501.500 0.350 1.0501.500 0.350 1.0501.500 0.350 1.0500.413 0.350 0.2890.413 0.350 0.2890.413 0.350 0.2890.413 0.350 0.2890.336 0.350 0.2350.336 0.350 0.2350.336 0.350 0.2350.336 0.350 0.2351.500 0.300 2.7000.150 0.300 0.1801.500 0.300 1.8002.235 0.350 1.5642.235 0.350 1.5643.000 0.350 2.1002.900 2.000 0.0002.600 2.000 0.0001.200 2.000 4.800
2.800 2.000 0.0002.000 2.000 8.0001.500 0.350 0.000 211.905
178.977 0.250 44.744 44.744
= 3325.030
RAB 21
Unit
Cum
Sqm
0.600
0.9000.9000.9000.9000.9000.9000.7501.950
1.950
0.850
0.8500.8500.450
0.450
0.6000.6000.6000.6000.6500.6500.4500.4500.750
0.750
0.750
0.750
0.7500.750
0.750
0.750
0.750
0.4500.750
0.750
0.7400.6000.6000.6000.6000.6000.4500.4500.600
0.6000.6000.6000.6000.6000.6000.6000.6000.6000.6000.6000.6000.6000.6000.6000.6000.6000.6000.6000.6000.5500.5500.5500.6000.6000.6002.2502.2502.250
2.2502.2500.600
Sq.m
LARSEN & TOUBRO LTD ECC DIVISION
ORCHID CROWN PROJECT - DADAR
Description No. L B H Qty.
1 Formwork for Columns & Shear Walls
- From 2nd basment to 1st basment lvl.
C1, C2,C3, C4, C5, C17 1 1.714 2.900 4.971
1 1.764 2.900 5.116
2 0.649 2.900 3.764
2 10.837 2.900 62.855
2 0.649 2.900 3.764
1 1.725 2.900 5.003
1 1.675 2.900 4.858
1 8.351 2.900 24.218
1 6.601 2.900 19.143
2 2.325 2.900 13.485
1 3.065 2.900 8.888
1 1.625 2.900 4.712
1 1.644 2.900 4.768
1 1.944 2.900 5.638
1 7.450 2.900 21.605
1 8.850 2.900 25.665
2 1.944 2.900 11.275
1 5.250 2.900 15.225
1 3.400 2.900 9.860
1 1.300 2.900 3.770
1 2.000 2.900 5.800
1 0.450 2.900 1.305
1 5.601 2.900 16.243
1 6.351 2.900 18.418
2 2.000 2.900 11.600
2 0.800 2.900 4.640
Add Cutout No. 01 2 1.200 0.750 1.800
2 0.750 2.100 3.150
TOWER 'C' - Measurement Sheet - Formwork for Columns & Shear Walls
Sr. No.
-2 1.200 2.100 -5.040
Cutout No. 02 2 1.300 0.700 1.820
2 0.700 0.650 0.910
-2 1.200 0.650 -1.560
Cutout No. 03 2 2.500 0.700 3.500
2 0.700 2.100 2.940
-2 2.500 2.100 -10.500
Cutout No. 04 2 2.500 0.700 3.500
2 0.700 2.100 2.940
-2 2.500 2.100 -10.500
Cutout No. 05 2 0.350 0.700 0.490
2 0.700 0.350 0.490
Cutout No. 06 2 0.350 0.700 0.490
2 0.700 0.350 0.490
Cutout No. 07 2 2.500 0.700 3.500
2 0.700 2.100 2.940
-2 2.500 2.100 -10.500
4 4.700 2.900 54.520
4 0.800 2.900 9.280
SW4, SW5 2 1.725 2.900 10.005
2 6.600 2.900 38.280
2 7.475 2.900 43.355
4 3.000 2.900 34.800
2 4.350 2.900 25.230
4 2.275 2.900 26.390
1 3.450 2.900 10.005
1 2.900 2.900 8.410
2 8.075 2.900 46.835
1 1.600 2.900 4.640
1 1.050 2.900 3.045
Add Cutout No. 10 2 0.600 0.550 0.660
2 0.550 0.300 0.330
Cutout No. 11 2 1.000 0.500 1.000
2 0.500 0.600 0.600
C6, C10 - 2 Nos.
SW9, SW10 2 1.725 2.900 10.005
2 6.600 2.900 38.280
2 7.475 2.900 43.355
4 3.000 2.900 34.800
2 4.350 2.900 25.230
4 2.275 2.900 26.390
1 1.600 2.900 4.640
1 1.050 2.900 3.045
1 2.900 2.900 8.410
1 3.450 2.900 10.005
2 8.025 2.900 46.545
Add Cutout No. 26 2 1.000 0.550 1.100
2 0.550 0.300 0.330
Cutout No. 27 2 1.000 0.500 1.000
2 0.500 0.600 0.600
2 =3.141x2.5x3.1 48.686
8 =3.141x0.60x3.1 46.738
Column Capitals - RC12, RC16 8 2.500 0.100 2.000
Retaining walls - 2 6.612 2.900 38.350
2 5.713 2.900 33.135
2 2.857 2.900 16.571
2 1.949 2.900 11.304
2 Nos. of walls 4 8.600 2.900 99.760
1 10.189 2.900 29.548
1 9.688 2.900 28.095
1 9.928 2.900 28.791
1 10.417 2.900 30.209
2 6.425 2.900 37.265
2 3.650 2.900 21.170
C7, C8 - Circular column - 2500 mm dia. - Perimeter x height of column
Podium Columns - RC14, 13, 11, 12, 18, 17, 15, 16 - 600 mm dia. - Perimeter x height of column
C11, C12, C13, C14, C15, C18 1 8.350 2.900 24.215
1 6.501 2.900 18.853
2 2.325 2.900 13.485
1 3.025 2.900 8.772
1 2.325 2.900 6.743
1 1.644 2.900 4.768
1 1.944 2.900 5.638
1 7.450 2.900 21.605
1 8.850 2.900 25.665
2 1.944 2.900 11.275
1 5.250 2.900 15.225
1 3.400 2.900 9.860
1 1.300 2.900 3.770
1 0.450 2.900 1.305
1 8.351 2.900 24.218
1 5.601 2.900 16.243
1 1.714 2.900 4.971
1 0.649 2.900 1.882
1 1.764 2.900 5.116
1 0.649 2.900 1.882
1 0.750 2.900 2.175
2 10.837 2.900 62.855
2 0.649 2.900 3.764
1 1.725 2.900 5.003
1 1.675 2.900 4.858
2 2.000 2.900 11.600
2 0.800 2.900 4.640
Add Cutout No. 31 2 0.600 0.700 0.840
2 0.700 0.300 0.420
Cutout No. 32 2 2.000 0.750 3.000
2 0.750 2.100 3.150
-2 2.000 2.100 -8.400
Cutout No. 30 2 2.000 0.750 3.000
2 0.750 0.300 0.450
2 2.000 0.300 1.200
Cutout No. 29 1 =3.141*0.3 0.750 0.053
Cutout No. 28 2 1.000 0.700 1.400
2 0.700 0.400 0.560
Cutout No. 37 2 1.950 0.700 2.730
2 0.700 0.550 0.770
2 1.950 0.550 2.145
SW1, SW2, SW3 1 1.587 2.900 4.602
1 1.007 2.900 2.920
1 1.810 2.900 5.249
2 4.610 2.900 26.738
1 0.300 2.900 0.870
2 7.575 2.900 43.935
2 6.725 2.900 39.005
2 7.425 2.900 43.065
2 0.500 2.900 2.900
2 1.000 2.900 5.800
2 11.600 2.900 67.280
6 2.600 2.900 45.240
4 2.300 2.900 26.680
6 2.700 2.900 46.980
Add Cutout No. 08 2 1.000 0.700 1.400
2 0.700 0.400 0.560
Cutout No. 09 2 1.000 0.700 1.400
2 0.700 0.400 0.560
Cutout No. 35 2 0.800 0.500 0.800
2 0.500 0.400 0.400
Cutout No. 12 2 1.000 0.500 1.000
2 0.500 0.400 0.400
Cutout No. 13 2 1.000 0.500 1.000
2 0.500 0.400 0.400
Cutout No. 40 2 0.250 0.250 0.125
2 0.250 1.800 0.900
-2 0.250 1.800 -0.900
Cutout No. 41 2 0.250 0.250 0.125
2 0.250 1.800 0.900
-2 0.250 1.800 -0.900
Cutout No. 44 2 0.250 0.250 0.125
2 0.250 1.800 0.900
Cutout No. 45 2 0.250 0.250 0.125
2 0.250 1.800 0.900
SW7, SW8, SW9 1 1.810 2.900 5.249
1 1.007 2.900 2.920
1 1.587 2.900 4.602
2 4.610 2.900 26.738
1 0.300 2.900 0.870
2 7.575 2.900 43.935
2 6.725 2.900 39.005
2 7.425 2.900 43.065
2 0.500 2.900 2.900
2 1.000 2.900 5.800
2 11.600 2.900 67.280
6 2.600 2.900 45.240
4 2.300 2.900 26.680
6 2.700 2.900 46.980
Add Cutout No. 24 2 1.000 0.700 1.400
2 0.700 0.400 0.560
Cutout No. 25 2 1.000 0.700 1.400
2 0.700 0.400 0.560
Cutout No. 36 2 0.800 0.500 0.800
2 0.500 0.400 0.400
Cutout No. 20 2 1.000 0.500 1.000
2 0.500 0.400 0.400
Cutout No. 19 2 1.000 0.500 1.000
2 0.500 0.400 0.400
Cutout No. 42 2 0.250 0.250 0.125
2 0.250 1.800 0.900
Cutout No. 43 2 0.250 0.250 0.125
2 0.250 1.800 0.900
-2 0.250 1.800 -0.900
Cutout No. 46 2 0.250 0.250 0.125
2 0.250 1.800 0.900
-2 0.250 1.800 -0.900
Cutout No. 47 2 0.250 0.250 0.125
2 0.250 1.800 0.900
TOTAL QUANTITY =Deduct last month bill Quantity =Net Payble Quantity =
UnitTotal Quantity
317.947
63.800
253.585
253.735
48.686
48.738
374.199
8.35
6.501
4.65
3.025
2.325
1.644
1.944
7.45
8.85
3.888
5.25
3.4
1.3
0.45
8.351
5.601
1.714
0.649
1.764
0.649
0.75
21.674
1.298
1.725
1.675
4
1.6
331.701
371.485
371.485
2435.360 Sq.m1537.792 Sq.m
897.568 Sq.m
LARSEN & TOUBRO LTD ECC DIVISION
Waterproofing - RaftSr.No. Description Units Nos L B
Tower APCC Belowe raft Sq.m 1 2,378.86Vertical Side Sq.m 1 234.40 1.70Slope Sq.m 1 32.10 2.21Slope Sq.m 1 11.15 1.80
Tower BPCC Belowe raft Sq.m 1 2,541.58Vertical Side Sq.m 1 192.29 1.70Slope Sq.m 1 32.10 2.21Slope Sq.m 1 11.15 1.80
Tower CPCC Belowe raft Sq.m 1 2,061.83Vertical Side Sq.m 1 171.48 1.60Slope Sq.m 2 26.45 2.19
ORCHID CROWN PROJECT - DADAR
LARSEN & TOUBRO LTD ECC DIVISION BOQ Code: Annex. A5
Bill. No.:- R.A.14
D QTY Remark
2,378.86398.4870.9420.07
2,868.35
5952,541.58 2,273.35326.8970.9420.07
2,959.48
2,061.83274.37115.85
2,452.05
LARSEN & TOUBRO LTD ECC DIVISION
Sr.No. Description Units Nos L B DTower AMain Raft Cum 1 2,378.86 3.50Lift pit Cum 1 10.50 9.55 1.80slope Cum 1 30.90 0.59Deduct - Lift Area Cum -3 2.30 2.45 1.80
Tower BMain Raft Cum 1 2,541.58 3.50Lift pit Cum 1 10.50 9.55 1.80Slope Cum 1 30.90 0.59Deduct - Lift Area Cum -3 2.30 2.45 1.80
Tower CMain Raft Cum 1 2,061.83 3.00Lift pit Cum 2 5.75 5.075 1.80Slope Cum 2 22.85 0.54Deduct - Lift Area Cum -2 2.40 2.28 1.80
MLCP & Non TowerPCC Belowe raft Cum 1 8,031.53
Certified Qty upto RA -13Certified Qty for RA -14
Total Quantity Certified upto RA-14
RAB 14 Certification
ORCHID CROWN PROJECT - DADAR
Measurement Sheet - Raft -Concrete (M60)
BOQ Code: Annex. A5
Bill. No.:- R.A.14
QTY Remark
8,326.01180.5018.08-30.43 1.15
8,494.15
8,895.53180.5018.08-30.43
9,063.67
6,185.49105.05 104.53524.68 104.535-19.66
6,295.56
2.245328,031.532,505.26
59.762,565.02
29.33
LARSEN & TOUBRO LTD ECC DIVISION
Sr.No. Description Units Nos L BTower APCC Below Raft Cum 1 2,378.86
1 234.40 0.15Vertical PCC around Lift Pit Cum 1 32.20 2.21
Tower B
PCC Below Raft Cum 1 2,541.581 192.29 0.15
Vertical PCC around Lift Pit Cum 1 32.20 2.21
Tower CPCC Below Raft Cum 1 2,061.83
1 171.48 0.15Vertical PCC around Lift Pit Cum 2 26.45 2.19
RAB 14 Certification
ORCHID CROWN PROJECT - DADAR
Measurement Sheet - Raft -Concrete (M60)
LARSEN & TOUBRO LTD ECC DIVISION BOQ Code: Annex. A5
Bill. No.:- R.A.14
D QTY Remark
0.15 356.830.15 5.270.15 10.69
4.8 2.19
372.80
0.15 381.240.15 4.330.15 10.69
396.26
0.15 309.270.15 3.860.15 17.38
330.51
RAB 14 Certification 1,099.56
LARSEN & TOUBRO LTD ECC DIVISION
FormworkSr.No. Description Units Nos L B
Tower AVertical Side Sq.m 1 234.40 3.50liftwall Sq.m 3 9.50 1.80liftwall Sq.m 1 11.15 1.80
Tower BVertical Side Sq.m 1 192.29 3.50At Pit Area Sq.m 3 9.50 1.80Slope Sq.m 1 11.15 1.80
Tower CVertical Side Sq.m 1 171.48 3.00At Pit Area Sq.m 2 9.95 1.50
ORCHID CROWN PROJECT - DADAR
LARSEN & TOUBRO LTD ECC DIVISION BOQ Code: Annex. A5
Bill. No.:- R.A.14
D QTY Remark
820.4151.3020.07
891.78
673.0051.3020.07
744.37
514.4529.85
544.30
ORCHID CROWN PROJECTTOWER 'A' - RAFTSUMMARY:-
28-May-12
SR. NO. PERTICULARS UNIT DIFFERENCE UNIT RATE RATE RAB NO REMARK
1 RAFT - PCC ( M-15)
1.a) Tower -"A" Cu.m 467.78 372.797 94.98 4900 465418.341 15 Considered Vertical P.C.C
1.b) Tower -"B" Cu.m 525.44 396.257 129.18 4900 632996.320 15 Considered Vertical P.C.C
1.c) Tower -"C" Cu.m 364.54 330.510 34.03 4900 166744.795 15 Considered Vertical P.C.C
258.20 1265159.457
2 RAFT - Formwork
2.a) Tower -"A" Sq.m 1187.36 891.777 295.58 519 153407.577
2.b) Tower -"B" Sq.m 778.07 744.375 33.70 519 17487.965
2.c) Tower -"C" Sq.m 619.53 544.296 75.23 519 39046.446
404.51 209941.9873 RAFT - Rebar
3.a) Tower -"A" MT 2954.263 2487.468 466.80 51171 23886366.945 15
3.b) Tower -"B" MT 3028.782 2597.181 431.60 51171 22085454.771 9
3.c) Tower -"C" MT 2115.272 1851.526 263.75 51171 13496146.566
1162.14 59467968.2824 Tower - A
4.a 2'nd Basement floor Slab & Beam (R.C.C ) Cu.m 320.52 312.704 7.82 8397 65632.702
4.b 3'rd Basement Column & Shear Wall (Formwork) Sq.m 3007.02 2733.411 273.61 519 142003.242
4.c 2'nd Basement Column & Shear Wall (Formwork) Sq.m 2852.09 2511.279 340.81 519 176880.805
4.d 2'nd Basement floor Slab & Beam (Formwork ) Sq.m 1565.21 1302.525 262.69 519 136333.603
4.e 1'st Basement floor Slab & Beam (Formwork ) Sq.m 1532.8 1478.853 53.95 519 27998.592
548848.944
5 Tower - B
5.a Ground Floor Slab & Slab Beam (R.C.C) Cu.m 578.17 569.504 8.67 8397 72768.375
5.b Ground Floor Slab & Slab Beam (Formwork) Sq.m 3388.77 3336.630 52.14 519 27060.578
99828.9536 Tower - C
6.a 1'st Basement floor Slab & Beam (R.C.C ) Cu.m 317.45 310.943 6.51 8397 54636.237
6.b 2'nd Basement Column & Shear Wall (Formwork) Sq.m 2630.18 2421.719 208.46 519 108191.319
6.c 1'st Basement Column & Shear Wall (Formwork) Sq.m 3576.42 3286.844 289.58 519 150289.770
6.d Ground Floor Slab & Slab Beam (Formwork) Sq.m 1518.84 1628.386 70 % only Billed
313117.327
7 Retaining Wall Lot
8 Non Tower Area Lot
SUB-TOTAL 61904864.950
CERTIFIED AS PER RAB
QUANTITY AS PER
DRAWING
At RAB # 24 - Summary
At RAB # 24 - Summary
At RAB # 24 - Summary
Calculation Error (To be Checked with L & T for final Quantity)
Calculation Error (To be Checked with L & T for final Quantity)
Calculation Error (To be Checked with L & T for final Quantity)
At RAB # 24 - Summary
At RAB # 24 - Summary
At RAB # 24 - Summary
At RAB # 24 - Summary
At RAB # 24 - Summary
At RAB # 24 - Summary
At RAB # 24 - Summary
At RAB # 24 - Summary
At RAB # 24 - Summary
At RAB # 24 - Summary
At RAB # 24 - Summary
Partial only Completed, Billed as per pourcard
Partial only Completed, Billed as per pourcard