    ID NO.:

    FIELD QUALITY PLAN

    FOR

    FUEL HANDLING SYSTEM

    FOR

    SHREE MEGA POWER(2x150MW)

    CETHAR VESSELS LIMITEDTIRUCHIRAPPALLI

    FIELD QUALITY ASSURANCE DEPARTMENT

    DOC. No: QPE-FHS-001REV. No : R00 / Oct-2010

    FRT-FQP-001-REV 00

  • 7/30/2019 Copy of FQP -Fuel Handling System

    2/21

    FIELD QUALITY PLAN

    FOR

    BOILER STRUCTURES

    FOR

    SHREE MEGA POWER

    PREPARED BY(P.Vijayaragavan, Engineer / QA)

    REVIEWED BY(N.Narayanasamy,VP /UB& UPP )

    APPROVED BY(V. Kandhsamy, Chief / FQA)

    DOCUMENT No. QPE-FHS-002

    R00 / OCT-2010

    ID No. DATE OF ISSUE

    COPY No:CONTROLLED /INFORMATION

    COPY

    NO. OFPAGES:

    30

    ISSUED BY

    ISSUED TO:

    CETHAR VESSELS LIMITEDTIRUCHIRAPPALLI

    FIELD QUALITY ASSURANCE DEPARTMENT

    FRT-FQA-002-REV 00

  • 7/30/2019 Copy of FQP -Fuel Handling System

    3/21

    CONTENTS

    DOC. NO. : QPE-FHS-001

    REV. NO. : R00

    SHEET: 1 / 1

    Sl. No DESCRIPTION NO. OF SHEETS

    1 STATUS OF AMENDMENTS 1

    2.AUTHORISATION FOR DIFFERENT CATEGORIES OFCHECKS

    1

    3. STATEMENT OF CHECKS 9

    4. DOCUMENTS REFERRED IN QUALITY PLAN 1

    5. LOGSHEETS : L-00 TO L-04 5

    6 FEEDBACK ON FIELD QUALITY PLAN 1

    FRT-FQP-003-REV 00

  • 7/30/2019 Copy of FQP -Fuel Handling System

    4/21

    STATUS OF AMENDMENTS

    DOC. NO. : QPE-FHS-001

    REV. NO. : RO0

    SHEET : 1 / 1

    SL.NO.

    REFERENCEOF SHEETSAMENDED

    AMENDMENT NO.& DATE

    REMARKS

    NIL

    FRT-FQP-004-REV 00

  • 7/30/2019 Copy of FQP -Fuel Handling System

    5/21

    AUTHORISATION FOR DIFFERENTCATEGORIES OF CHECKS

    DOC. NO. : QPE-FHS-001

    REV. NO. : RO0

    SHEET : 1 / 1

    CLASSIFICATION OFCHECKS

    CHECKING / WITNESSING AUTHORITYACCEPTINGAUTHORITY

    A CRITICAL

    CVL QAE HEAD/FQA

    SCL CONSTRUCTION SCL

    B MAJOR

    CVL ERECTION QAE

    SCL CONSTRUCTION SCL

    C MINOR

    CVL ERECTION HOS

    SCL --- SCL

    LEGNDS: QAE -QUALITY ASSURANCE ENGINEER

    HOS-HEAD OF SECTION

    NOTE

    1.QAE shall witness 'A' category checks. He is also authorised to carry outsurveillance in any of B and C category of checks at his discretion.

    2. In case of non-conformity, accepting authority shall ensure disposition beforeaccepting and the dis-positioning shall be reflected on log sheets / protocols.

    3. QAE shall ensure that only calibrated instruments are used for all measurements.

    FRT-FQP-005-REV 00

  • 7/30/2019 Copy of FQP -Fuel Handling System

    6/21

    STATEMENT OF CHECKS

    DOC. NO. : QPE-FHS-001

    REV. NO. : RO0

    SHEET: 01 / 09

    Capacity / Type: : 2 X 150MW

    System: : BOILER

    Sub-system: : FUEL HANDLING SYSTEM

    Area: : ERECTION

    NOTES:

    1. For checks where log sheets are not called for, suitable records should be maintained in theform of log book / protocols.

    2. As an evidence of having carried out the work satisfactorily, a general purpose log sheet,L-00 shall be maintained for all the checks.

    3. The above sub-system covers Foundation and erection of structures, truck tippler,gantry,lconveyors, transfer tower,vibrating feeder,vibrating screen & Crushers with house,metaldetectors, magnetic separators and belt weigher

    FRT-FQP-006-REV 00

  • 7/30/2019 Copy of FQP -Fuel Handling System

    7/21

    SUPPLIERS NAME& ADDRESS

    Cethar Vessels Limited4,Dindigul Road,

    Tiruchirappalli-620 001

    FIELD QUALITY PLAN CUSTOMER: M/S.SHREE CEMENT LTD.PROJECT: SHREE MEGA POWER

    2X150MW

    PACKAGE: EPC

    CONTRACT No.: EBJ 072 & 087

    SYSTEM: BOILER

    Sub system: Fuel handling system

    FQP No. : QPE-FHS-001REV. No. : R00PAGE No.: 02 / 09

    SL.NO

    CHARACTERISTICS/ITEMTYPE

    OFCHECK

    INSTRUMENT CLASS

    REFERENCEDOCUMENT/

    ACCEPTANCESTANDARD

    QUANTUM/FREQUENCY

    OF CHECK

    FORMATOF

    RECORD

    REMARKS/HOLD POINTS (H)

    1.0 FOUNDATION

    1.1 Availability of identified & protected permanent benchmark V B 100%

    1.2 Elevation of top of foundation pedestals with referenceto permanent bench mark

    MDumpy level /Water level /

    TapeB

    Drawing /erectionmanual

    100% L - 01

    1.3 Disposition of foundation pedestals with reference tolongitudinal axis of boiler and reference axis M

    Tape A -do- 100% L - 01

    1.4 Spacing between the foundation pedestals M Tape B -do- 100% L - 01

    1.5 Diagonals of the main column foundation pedestals M Tape B -do- 100% L - 011.6 Pitch distance of foundation pedestal bolts on both the

    axes and its diagonalsM Tape C -do- 100% L - 01

    2.0 STRUCTURES

    2.1 Material Receipt Verification &Identification CheckV Nil B

    Transport/packing Doc.

    100%

    2.2 Check for cleanliness of structures before erection.V Nil B Nil 100%

    2.3Pre-assembly of columns before erection , whereverapplicable. V/M

    Tape /Piano wire /Water level

    B

    Drawing 100%

    LEGEND: CLASS : A - CRITICAL, B - MAJOR, C - MINOR;A SHALL BE WITNESSED BY QA E OF CVL & CUSTOMER,B SHALL BE WITNESSED BY ERECTION OF CVL & CUSTOMER ANDC SHALL BE WITNESSED BY ERECTION OF CVL.TYPE : V- VISUAL, R- RECORD VERIFICATION, M- MEASUREMENT, P- PHYSICAL & T- TEST.

    FOR CUSTOMER USE

    MAIN SUPPLIER :CVL

    SIGNATURE REVIEWED BY APPROVED BY APPROVAL SEAL

    FRT-FQP-007-REV 00

  • 7/30/2019 Copy of FQP -Fuel Handling System

    8/21

    SUPPLIERS NAME& ADDRESS

    Cethar Vessels Limited4,Dindigul Road,

    Tiruchirappalli-620 001

    FIELD QUALITY PLAN CUSTOMER: M/S.SHREE CEMENT LTD.PROJECT: SHREE MEGA POWER

    2X150MW

    PACKAGE: EPC

    CONTRACT No.: EBJ 072 & 073

    SYSTEM: BOILER

    Sub system: Fuel handling system

    FQP No. : QPE-FHS-001REV. No. : R00PAGE No.: 03 / 09

    SL.NO

    CHARACTERISTICSTYPE

    OFCHECK

    INSTRUMENT CLASS

    REFERENCEDOCUMENT/

    ACCEPTANCESTANDARD

    QUANTUM/FREQUENCY

    OF CHECK

    FORMATOF

    RECORD

    REMARKS/HOLD POINTS (H)

    2.4 Individual column piece camber and sweep(Tolerance :1mm/M : 10 mm max.).

    M-do- B

    Drawing /erectionmanual

    100%

    2.5 Camber and sweep for assembled columns(Tolerance :1mm/M ; 18 mm max.).

    M -do- B -do- 100%

    2.6 Total length of column before erection(Tolerance : 15 mm max.).

    M Tape B -do- 100%

    2.7 Orientation of columns. Check for match mark,elevationmark, Column No.,splice size etc.

    V B -do- 100%

    2.8 Ensure matching of center line of base plate with pedestalaxes.

    V B -do- 100%

    2.9 Elevation of column at 1 meter level with reference tobenchmark (Tolerance : 5 mm).

    MWater level /

    TapeB

    Drawing /erectionmanual

    100%

    2.10 Alignment of first piece of column with horizontal beamsand vertical bracings (Tolerance :Position w.r.t. referenceaxis : 5mm; elevation: 5 mm).

    MTheodolite /

    Tape /Plumb bob

    B -do- 100%

    LEGEND: CLASS : A - CRITICAL, B - MAJOR, C - MINOR;A SHALL BE WITNESSED BY QAE OF CVL & CUSTOMER,B SHALL BE WITNESSED BY ERECTION OF CVL & CUSTOMER ANDC SHALL BE WITNESSED BY ERECTION OF CVL.TYPE : V- VISUAL, R- RECORD VERIFICATION, M- MEASUREMENT, P- PHYSICAL & T- TEST.

    FOR CUSTOMER USE

    MAIN SUPPLIER :CVL

    SIGNATUREREVIEWED BY APPROVED BY APPROVAL SEAL

    FRT-FQP-007-REV 00

  • 7/30/2019 Copy of FQP -Fuel Handling System

    9/21

    SUPPLIERS NAME& ADDRESS

    Cethar Vessels Limited4,Dindigul Road,

    Tiruchirappalli-620 001

    FIELD QUALITY PLAN CUSTOMER: M/S.SHREE CEMENT LTD.PROJECT: SHREE MEGA POWER

    2X150MW

    PACKAGE: EPC

    CONTRACT No.: EBJ 072 & 073

    SYSTEM: BOILER

    Sub system: Fuel handling system

    FQP No. : QPE-FHS-001REV. No. : R00PAGE No.: 04 / 09

    SL.NO

    CHARACTERISTICSTYPE

    OFCHECK

    INSTRUMENT CLASS

    REFERENCEDOCUMENT/

    ACCEPTANCESTANDARD

    QUANTUM/FREQUENCY

    OF CHECK

    FORMATOF

    RECORD

    REMARKS/HOLD POINTS (H)

    2.11 Completion of boxes with main brace level members ( MBL). V B -do- 100%

    2.12 Grouting gap below the column base(Min. 20mm ; max. 70 mm). M Tape B Drawing 100%

    2.13 Verification of test certificates and batch certificates of groutmaterial.

    V AProcedure for

    grouting100%

    2.14 Grouting of column bases. V/R ADrawing / Groutmanufactures

    Recommendation100% L - 04

    2.16 Alignment of columns at every stage of erection. MTheodolite /

    Tape /Plumb bob

    ADrawing / erection

    manual100% L - 05

    LEGEND: CLASS : A - CRITICAL, B - MAJOR, C - MINOR;A SHALL BE WITNESSED BY QAE OF CVL & CUSTOMER,B SHALL BE WITNESSED BY ERECTIONOF CVL & CUSTOMER ANDC SHALL BE WITNESSED BY ERECTION OF CVL.TYPE : V- VISUAL, R- RECORD VERIFICATION, M- MEASUREMENT, P- PHYSICAL & T- TEST.

    FOR CUSTOMER USE

    MAIN SUPPLIER :CVL

    SIGNATUREREVIEWED BY APPROVED BY APPROVAL SEAL

    FRT-FQP-007-REV 00

  • 7/30/2019 Copy of FQP -Fuel Handling System

    10/21

    SUPPLIERS NAME& ADDRESS

    Cethar Vessels Limited4,Dindigul Road,

    Tiruchirappalli-620 001

    FIELD QUALITY PLAN CUSTOMER: M/S.SHREE CEMENT LTD.PROJECT: SHREE MEGA POWER

    2X150MW

    PACKAGE: EPC

    CONTRACT No.: EBJ 072 & 073

    SYSTEM: BOILER

    Sub system: Fuel handling system

    FQP No. : QPE-FHS-001REV. No. : R00PAGE No.: 05/ 09

    SL.NO

    CHARACTERISTICSTYPE

    OFCHECK

    INSTRUMENT CLASSREFERENCE DOCUMENT/ACCEPTANCE STANDARD

    QUANTUM/FREQUENCY

    OF CHECK

    FORMATOF

    RECORD

    REMARKS/HOLD POINTS (H)

    4 WELDING

    4.1 Qualification of welders V / R AProcedure for structural

    welder / welding operatorqualification at site

    100%

    4.2Availability of approved WPS , Heat TreatmentSchedule,Erection Manual, Calibration testcertificates of instruments used.

    R A 100%

    4.3 Adoption of correct procedure , approvedelectrodes and methods.

    V/R A

    Drawings / Procedure forreceipt inspection and

    control of weldingconsumable at site / Heat

    Treatment Parameters

    100%

    4.4 Pre heating and interpass temperature. V/R

    Timetemperatur

    eRecorder /ThermalChalk

    A

    Drawing / Guidelines for

    Erection / Heat TreatmentParameters

    As per

    ReferenceDocument

    LEGEND: CLASS : A - CRITICAL, B - MAJOR, C - MINOR;A SHALL BE WITNESSED BY QAE OF CVL & CUSTOMER,B SHALL BE WITNESSED BY ERECTIONOF CVL & CUSTOMER ANDC SHALL BE WITNESSED BY ERECTION OF CVL.TYPE : V- VISUAL, R- RECORD VERIFICATION, M- MEASUREMENT, P- PHYSICAL & T- TEST.

    FOR CUSTOMER USE

    MAIN SUPPLIER :CVL

    SIGNATUREREVIEWED BY APPROVED BY APPROVAL SEAL

    FRT-FQP-007-REV 00

  • 7/30/2019 Copy of FQP -Fuel Handling System

    11/21

    SUPPLIERS NAME& ADDRESS

    Cethar Vessels Limited4,Dindigul Road,

    Tiruchirappalli-620 001

    FIELD QUALITY PLAN CUSTOMER: M/S.SHREE CEMENT LTD.PROJECT: SHREE MEGA POWER

    2X150MW

    PACKAGE: EPC

    CONTRACT No.: EBJ 072 & 073

    SYSTEM: BOILER

    Sub system: Fuel handling system

    FQP No. : QPE-FHS-001REV. No. : R00PAGE No.: 06 / 09

    SL.NO

    CHARACTERISTICSTYPE

    OFCHECK

    INSTRUMENT CLASS

    REFERENCEDOCUMENT/

    ACCEPTANCESTANDARD

    QUANTUM/FREQUENCY

    OF CHECK

    FORMATOF

    RECORD

    REMARKS/HOLD POINTS

    (H)

    5.0 NDE

    a) Edge preparationi .MPI for new edges prepared at site after flame cutting /trimming of respective member where t 38mm.

    V ACVL/PR/014 Rev.04CVL/PR/006 Rev.03

    100%

    ii . MPI/LPI for all gas cut edges for t 20mm and below38mm.

    -do- 10%

    iii . MPI/LPI for all bevel edges for t 20mm prior towelding

    -do- 100%

    b) Butt weldsi. MPI/ LPI on all back gouged / ground grooves

    prior to welding from second side.V B

    CVL/PR/014 Rev.04CVL/PR/006 Rev.03

    100%

    ii. RT for t 32mm. V A CVL/PR/095 Rev.00 100%

    Iii. MPI/LPI on finished welds for t > 25mm to t < 32 mm. V BCVL/PR/014 Rev.04CVL/PR/006 Rev.03

    100%

    Iv. MPI/LPI on finished welds up to 25 mm thick. V B -do- 10.00%LEGEND: CLASS : A - CRITICAL, B - MAJOR, C - MINOR;A SHALL BE WITNESSED BY QAE OF CVL & CUSTOMER,

    B SHALL BE WITNESSED BY ERECTION OF CVL & CUSTOMER ANDC SHALL BE WITNESSED BY ERECTION OF CVL.

    TYPE : V- VISUAL, R- RECORD VERIFICATION, M- MEASUREMENT, P-PHYSICAL & T- TEST.

    For Customer UseMain Supplier: CVL

    Signature Reviewed By Approved By Approval Seal

  • 7/30/2019 Copy of FQP -Fuel Handling System

    12/21

    SUPPLIERS NAME& ADDRESS

    Cethar Vessels Limited4,Dindigul Road,

    Tiruchirappalli-620 001

    FIELD QUALITY PLAN CUSTOMER: M/S.SHREE CEMENT LTD.PROJECT: SHREE MEGA POWER

    2X150MW

    PACKAGE: EPC

    CONTRACT No.: EBJ 072 & 073

    SYSTEM: BOILER

    Sub system: Fuel handling system

    FQP No. : QPE-FHS-001REV. No. : R00PAGE No.: 07 / 09

    SL.NO

    CHARACTERISTICSTYPE

    OFCHECK

    INSTRUMENT CLASSREFERENCE DOCUMENT/ACCEPTANCE STANDARD

    QUANTUM/FREQUENCY

    OF CHECK

    FORMATOF

    RECORD

    REMARKS/HOLD POINTS (H)

    d) Fillet welds

    I.)LPI/MPI For welds between flange and web andbearing stiffeners.

    V BCVL/PR/006 Rev.03CVL/PR/014 Rev.04

    100%

    ii.) LPI/MPI For other welds joining plate members inwhich both plate members are over 25 mm thick.

    V B -do- 100%

    iii.) LPI for All other welds V B CVL/PR/006 Rev.0310% of

    weld length

    6.0 Gantry construction

    i) Provision of Stool Support V

    ii) Provision of Deck sheet at fuel point Viii) Idlers location & alignment M Tape A Drawing 100%iv) Provision of mounting bracketv) Provision of floor grills

    V B Do--

    vi) Individual piece Dimension, holes location, bend &twist

    Vii) Gantry assembly dimension, holes location , bend &Twist .

    M Tape A Do--

    7 Head End & Tail End with pulleys Stringer arrangement M Do--

    i) Alignment

    ii) Centre to Centre Distance8 Drive Arrangement

    i) Alignment ( Axial & radial) MDialMicrometer

    A Drawing 100.00%

    LEGEND: CLASS : A - CRITICAL, B - MAJOR, C - MINOR;A SHALL BE WITNESSED BY QAE OF CVL & CUSTOMER,B SHALL BE WITNESSED BY ERECTION OF CVL & CUSTOMER ANDC SHALL BE WITNESSED BY ERECTION OF CVL.TYPE : V- VISUAL, R- RECORD VERIFICATION, M- MEASUREMENT, P- PHYSICAL & T- TEST.

    FOR CUSTOMER USE

    MAIN SUPPLIER :CVL

    SIGNATUREREVIEWED BY APPROVED BY APPROVAL SEAL

    FRT-FQP-007-REV 00

  • 7/30/2019 Copy of FQP -Fuel Handling System

    13/21

    SUPPLIERS NAME& ADDRESS

    Cethar Vessels Limited4,Dindigul Road,

    Tiruchirappalli-620 001

    FIELD QUALITY PLAN CUSTOMER: M/S.SHREE CEMENT LTD.PROJECT: SHREE MEGA POWER

    2X150MW

    PACKAGE: EPC

    CONTRACT No.: EBJ 072 & 073

    SYSTEM: BOILER

    Sub system: Fuel handling system

    FQP No. : QPE-FHS-001REV. No. : R00PAGE No.: 08 / 09

    SL.NO

    CHARACTERISTICSTYPE

    OFCHECK

    INSTRUMENT CLASSREFERENCE DOCUMENT/ACCEPTANCE STANDARD

    QUANTUM/FREQUENCY

    OF CHECK

    FORMATOF

    RECORD

    REMARKS/HOLD POINTS (H)

    9 Skirt Board arragement at Fuel feeding point V B Drawing 100.00%

    10 Grizzly hopper with Vibrating feederI) Hopper orientation , dimensions & Alignment M Tape A Drawing 100.00%ii) Vibratory feeder location & Alignment M -Do- A Drawing 100.00%

    11 Crusher , Screen & Vibrating feeder

    I) Orientation

    ii) Location M Tape A Drawing 100%

    iii)Alignment

    12 Inter connecting Chute

    I) Dimension , M Tape A Drawing 100%

    ii) Welding Soundness Visual B

    iii) location M Tape A

    Drawing 100.00%

    13 Laying of Belt V

    I) Splicing V B Drawing 100%

    14 ii) Hardness at the joint M Hardnesstester

    A 70 5 DegShore A

    100%

    15 Provision of Scrapper V A Drawing 100.00%

    LEGEND: CLASS : A - CRITICAL, B - MAJOR, C - MINOR;A SHALL BE WITNESSED BY QAE OF CVL & CUSTOMER,B SHALL BE WITNESSED BY ERECTION OF CVL & CUSTOMER ANDC SHALL BE WITNESSED BY ERECTION OF CVL.TYPE : V- VISUAL, R- RECORD VERIFICATION, M- MEASUREMENT, P- PHYSICAL & T- TEST.

    FOR CUSTOMER USE

    MAIN SUPPLIER :CVL REVIEWED BY APPROVED BY APPROVAL SEAL

  • 7/30/2019 Copy of FQP -Fuel Handling System

    14/21

    SUPPLIERS NAME& ADDRESS

    Cethar Vessels Limited4,Dindigul Road,

    Tiruchirappalli-620 001

    FIELD QUALITY PLAN CUSTOMER: M/S.SHREE CEMENT LTD.PROJECT: SHREE MEGA POWER

    2X150MW

    PACKAGE: EPC

    CONTRACT No.: EBJ 072 & 073

    SYSTEM: BOILER

    Sub system: Fuel handling system

    FQP No. : QPE-FHS-001REV. No. : R00PAGE No.: 09/ 09

    SL.NO

    CHARACTERISTICSTYPE

    OFCHECK

    INSTRUMENT CLASSREFERENCE DOCUMENT/ACCEPTANCE STANDARD

    QUANTUM/FREQUENCY

    OF CHECK

    FORMATOF

    RECORD

    REMARKS/HOLD POINTS (H)

    16 Trial run with all Safety accessories

    i) Provision of pull chord Switches V ADrawing /Equipment

    manual100%

    ii) Smooth operation

    iii) Vibration & Noise level of Drives

    17 Provision of Guard

    18 Provision of Fire fighting system V A Drawing 100%

    19 Assembly of Conveyor hood V A Drawing 100%

    20Erection of Dust extraction system , Dust suppressionsystem & Ducting

    V A Drawing 100%

    21 Cladding V B Drawing 100%

    LEGEND: CLASS : A - CRITICAL, B - MAJOR, C - MINOR;A SHALL BE WITNESSED BY QAE OF CVL & CUSTOMER,B SHALL BE WITNESSED BY ERECTION OF CVL & CUSTOMER ANDC SHALL BE WITNESSED BY ERECTION OF CVL.TYPE : V- VISUAL, R- RECORD VERIFICATION, M- MEASUREMENT, P- PHYSICAL & T- TEST.

    FOR CUSTOMER USE

    REVIEWED BY APPROVED BYAPPROVAL

    SEALMAIN SUPPLIER :CVL

  • 7/30/2019 Copy of FQP -Fuel Handling System

    15/21

    DOCUMENTS REFERRED INQUALITY PLAN

    DOC. NO. : QPE--002

    REV. NO.: RO0

    SHEET : 1 / 1

    SL.NO Reference Document

    Document /Procedure No Issuing Authority

    1Erection Manual-Boiler supportingstructures

    SMP/Erec/002 Construction

    2 Quality Plan - Structural BI079/012 Q A & C

    3 Procedure for Liquid PenetrentExamination

    CVL/PR/006 Q A & C

    4 Procedure for Radiographic Examination CVL/PR/095 Q A & C

    5Procedure for Magnetic ParticlesExamination

    CVL/PR/014 Q A & C

    6 Procedure for Post Weld Heat treatment CVL/PR/002A Q A & C

    7 Procedure for grouting CVL/FQA/PR/003 FQA

    8 Procedure for visual inspection CVL/PR/029 Q A & C

    9Procedure for Structural welder / weldingoperator qualification at site

    CVL/FQA/PR/002 FQA

    10 Welding Consumable Selection Chart BGS-2-24 to BSG-2-027 Engineering

    11 List of Approved Welding Consumables CVL/AWCL/001 Q A & C

    Notes:

    QA&C Quality Assurance & control

    FQA Field Quality Assurance

    FRT-FQP-009-REV 00

  • 7/30/2019 Copy of FQP -Fuel Handling System

    16/21

    RECORD OF QUALITY CHECKS

    SHEETNO. OF. FQP

    CHECKNO.

    RESULTSACHIEVED OK /

    NOT OK

    DRAWING /DOCUMENTREFERENCE

    FORMAT OFRECORD

    INSPECTED BYSIGN. & DATE

    CLEAREDBY SIGN.& DATE

    REMARKS

    Note: Any protocol made is to be numbered & mentioned in Format of Record column.

    PROJECT SYSTEM SUB - SYSTEM AREA DOC. NO. : QPE-FHS-001

    UNIT NO. REV. NO. : RO0

    RATINGLOG SHEET NO. : L - 00

    SHEET : 1/1

    FRT-FQP-010-REV 0

  • 7/30/2019 Copy of FQP -Fuel Handling System

    17/21

    INSTRUMENT REGN.NO

    DATE OF INSPECTION

    DRAWING/DOCUMENT REF.

    PITCH AND DIAGONAL DISTANCE OF FOUNDATION BOLTS

    AS PER DRAWING

    PEDESTAL DESIGNATION A B a1 a2 a3 a4 b1 b2 b3 b4 D1 D2

    L

    R

    L

    R

    L

    R

    L

    R

    L

    R

    Tolerances: 1. Pitch Distances : 3mm 2. Diagonal Difference : 5mm max All dimension are in mm

    NAMESIGN.&DATE

    DOC. NO. : QPE-FHS-001

    PROJECT INSPECTED BY REV. NO. : RO0

    UNIT NO. CLEARED BY LOG SHEET NO. : L - 01

    RATING CUSTOMER SHEET : 1 / 1

    FRT-FQP-011-REV 00

  • 7/30/2019 Copy of FQP -Fuel Handling System

    18/21

    INSTRUMENT REGN.NO

    DATE OF INSPECTION

    DRAWING/DOCUMENT REF.

    GROUTING OF COLUMN BASES

    1. Column number ( identification) :

    2. Grout material Specification :

    3. Ratio of proportion of grout mix :

    4. Whether any additives added : Yes / No

    If yes ,details :

    5. Date of grouting :

    6. Whether test cubes have been taken : Yes / No

    If yes ,details :

    7. Remarks :

    The following column bases _____________________________ are cleared for further erectionafter _______days of curing.

    NAMESIGN.&DATE

    DOC. NO. : QPE-FHS-001

    PROJECT INSPECTED BY REV. NO. : RO0

    UNIT NO. CLEARED BY LOG SHEET NO. : L - 02

    RATING CUSTOMER SHEET: 1 / 1

    FRT-FQP-011-REV 00

  • 7/30/2019 Copy of FQP -Fuel Handling System

    19/21

    INSTRUMENT REGN.NO

    DATE OF INSPECTION

    DRAWING/DOCUMENT REF.

    VERTICALITY OF COLUMNS

    ColumnNumber

    Elevation inmetres

    Inclined towards (mm)

    East West North South

    Tolerance : 1mm / M, 25 mm Max.

    NAMESIGN.&DATE

    DOC. NO. : QPE-FHS-001

    PROJECT INSPECTED BY REV. NO. : RO0

    UNIT NO. CLEARED BY LOG SHEET NO. : L - 03

    RATING CUSTOMER SHEET 1 / 1

    FRT-FQP-011-REV 00

  • 7/30/2019 Copy of FQP -Fuel Handling System

    20/21

    INSTRUMENT REGN.NO

    DATE OF INSPECTION

    DRAWING/DOCUMENT REF.

    JOINT INSPECTION PROTOCOL FOR COMPLETION OFSTRUCTURE AND EQUIPMENT

    SI. NO ACTIVITY OBSERVATION

    1

    2

    3

    4

    5

    6

    7

    8

    NAMESIGN.

    &DATE

    DOC. NO. : QPE-FHS-001

    PROJECT INSPECTED BY REV. NO. : RO0

    UNIT NO. CLEARED BY LOG SHEET NO. : L - 04

    RATING CUSTOMER SHEET : 1 / 3

    FRT-FQP-011-REV 00

  • 7/30/2019 Copy of FQP -Fuel Handling System

    21/21

    FEEDBACK ON FIELD QUALITY PLAN

    In the Field Quality Plan (FQP), for following Checks / Log sheets may be added / rewritten / deleted(cannot be carried out / not required) due to reasons as mentioned below:

    Sheet No.Of FQP

    Check No. /Log Sheet No.

    Proposed Change / Reasons / Remarks

    From To

    Head/FQA,CVL,Tiruchirappalli.

    PROJECT DOC. NO. : QPE-FHS-001

    UNIT NO. REV. NO. : RO0

    RATING SHEET : 1 / 1

    FRT-FQP-013-REV 00