    STANDARD COST CODES

    Jeddah, Kingdom of Saudi Arabia

  • 7/29/2019 Cost Codes

    2/37

  • 7/29/2019 Cost Codes

    3/37

    COST CODE LEVEL/STRUCTURE DETERMINATION

    Jeddah, Kingdom of Saudi Arabia

  • 7/29/2019 Cost Codes

    4/37

  • 7/29/2019 Cost Codes

    5/37

    COST CODE DETERMINATIONS:

    DIVISION:

    Division

    SUB DIVISION:

    Sub Division

    4 - COST ALLOCATIONS:

    Labor

    Material

    Equipment

    Subcon

    SAMPLE COST CODES:

    02 Site Works

    05 Subsurface Investigations & Demolition

    1 Labor

    TO BE READ AS:

    02.05.1 (Site Works/Subsurface Investigation & Demolition/Labor)

    COST CODE LEVEL/STRUCTURE

    1

    2

    3

    4

    RPS/CP Dept. Page 1

  • 7/29/2019 Cost Codes

    6/37

    DETAIL COST CODE ELEMENTS

    Jeddah, Kingdom of Saudi Arabia

  • 7/29/2019 Cost Codes

    7/37

  • 7/29/2019 Cost Codes

    8/37

    Division Sub Division Description

    01 General Requirements

    Basic Salary & Overtime for Indirect Personnel:

    01 Basic Salary & Overtime for Indirect Personnel

    Expenses for Indirect Personnel:

    02 Food Allowance for Indirect Personnel

    03 Housing allowance for Indirect Personnel

    04 Transportation allowance for Indirect Personnel

    05 Living Allowance for Indirect Personnel

    06 Air Ticket Allowance for Indirect Personnel

    07 Other Allowance for Indirect Personnel-(Social Insurance)

    08 Severance/End Service Pay09 Medical Insurance for Indirect Personnel

    10 Other Incentive/Bonuses for Indirect Personnel

    11 Other Indirect Expenses

    Administrative Personnel Expenses:

    12 Social Insurance

    13 Leave Pay

    14 Leave Passage

    15 Severance Pay

    16 Medical Expenses

    17 Insurance Expenses

    18 Visa Expenses

    19 Catering & Accomodation

    20 Transportation Vehicle for Staff

    21 Joining/Leaving Travel Expenses

    22 Training Expenses

    23 Miscellaneous Expenses

    RPS/CP Dept. Page 8 of 32

  • 7/29/2019 Cost Codes

    9/37

    Division Sub Division Description

    01 Site Office Running Expenses:

    24 Consumables incl. Medicine

    25 Water

    26 Electricity

    27 Stationary

    28 Telephone, Mail & Telefaxes

    29 Performance Bonds

    30 Insurance

    31 Business Travel & Accommodation

    32 Consultant and Professional Fees

    33 Entertainment34 Misc. Office Requirement

    35 Office Furniture & Equipment

    36 Blue Printing Materials

    37 Food & Beverage

    38 Computer, Printers, Network

    Client Running Expenses:

    39 Telephone Client Expense

    40 Copy Machine and Stationary Client Expense

    41 Food & Beverage Client Expenses

    42 Others Client Expense

    Geotechnical Studies:

    43 Testing Services

    Temporary Facilities & Utilities (Mobilization):

    44 Temporary Facilities & Utilities

    Overheads

    45 Jeddah Area Office

    Financial Expenses:

    46 Contingencies & Escalations

    47 Other Financial Expenses

    Design & Engineering:

    48 Design & Engineering icl. As-built drawing

    RPS/CP Dept. Page 9 of 32

  • 7/29/2019 Cost Codes

    10/37

    Division Sub Division Description

    01 Construction Equipments, Spareparts, Petrol, Oil & Lubricants:

    Misc. Equipment:

    49 Internal Rental

    50 External/Outside Rental

    Equipment, Tools & Spareparts:

    51 Equipment, Tools & Spareparts

    Petrol, Oil & Lubricants:

    52 Petrol, Oil & Lubricants

    Transportation cost of Material:

    53 Transportation cost of Material

    Scaffolding Rental:54 Scaffolding Rental -Internal

    55 Scaffolding Rental -External

    56 Shuttering

    Direct Construction Expenses:

    57 Submittals (Drawings, Reports, Etc.)

    58 Quality Control

    59 Utilities Connection

    60 Sanitation Services

    61 Cosumable Material, Tools, Equipment & Safety

    62 Contract Closeout

    02 Site Works

    05 Subsurface Investigations & Demolition

    10 Site Preparation

    15 Earthworks

    20 Tunneling, Piles & Caissons

    25 Railroad & Marine Works

    30 Paving & Surfacing

    35 Pipe Utilities

    40 Sewerage & Drainage

    45 Site Improvements

    50 Landscaping

    RPS/CP Dept. Page 10 of 32

  • 7/29/2019 Cost Codes

    11/37

    Division Sub Division Description

    03 Concrete Works

    05 Concrete Formworks

    10 Concrete Reinforcement

    15 Cast-In-Place Concrete

    20 Precast Concrete

    25 Cementitious Decks

    04 Masonry Works

    05 Mortar & Masonry Accessories

    10 Unit Masonry

    15 Stone

    20 Masonry Restoration & Cleaning/Refractories05 Metal Works

    05 Finishes & Fastening

    10 Structural Metal Framing

    15 Metal Joist

    20 Metal Decking

    25 Metal Fabrications

    30 Expansion Joints

    06 Wood & Plastic

    05 Fastener & Adhesive

    10 Rough Carpentry

    15 Finish Carpentry

    20 Wood Treatment

    25 Architectural Woodwork

    07 Thermal & Moisture Protection

    05 Waterproofing & Damproofing

    10 Insulation

    15 Shingles & Roofing Tiles

    20 Preformed Roofing & Sidings

    25 Membrane Roofing

    30 Flashing & Sheet Metal

    35 Roof Specialties & Accessories

    40 SkylightsRPS/CP Dept. Page 11 of 32

  • 7/29/2019 Cost Codes

    12/37

    Division Sub Division Description

    45 Joint Sealers

    RPS/CP Dept. Page 12 of 32

  • 7/29/2019 Cost Codes

    13/37

    Division Sub Division Description

    08 Doors & Windows

    05 Metal Doors & Frames

    10 Wood & Plastic Doors

    15 Special Doors

    20 Entrances & Storefronts

    25 Metal Windows

    30 Wood & Plastic Windows

    35 Hardware

    40 Glazing

    45 Glazed Curtain Wall

    09 Finishes05 Metal Support Systems

    10 Lath, Plaster & Gypsum Board

    15 Tile

    20 Terrazzo

    25 Acoustical Treatment & Wood Flooring

    30 Flooring & Carpet

    35 Special Flooring & Floor Treatment

    40 Special Coatings

    45 Painting & Wall Coverings

    10 Specialties

    05 Chalkboards, Compartments & Cubicles

    10 Louvers, Corner Protection & Access Flooring

    15 Fireplaces, Ext. Specialties & Flagpoles

    20 Identifying & Pedestrian Control Devices

    25 Lockers,Protective Covers & Postal Specialties

    30 Partitions & Storage Shelving

    35 Telephone specialties

    40 Toilet & Bath Accessories & Scales

    45 Wardrobe & Closet Specialties

    50 Equipment

    RPS/CP Dept. Page 13 of 32

  • 7/29/2019 Cost Codes

    14/37

    Division Sub Division Description

    11 Equipment

    05 Mercantile, Commercial & Detention Equipment

    10 Food Services, Residential, Darkroom, Athletic Equipment

    15 Industrial & Process Equipment

    20 Laboratory, Planetarium, Observatory Equipment

    25 Medical Equipment

    12 Furnishings

    05 Manufactured Casework

    10 Window Treatment

    15 Furniture & Accessories

    20 Multiple Seating25 Interior Plants & Planters

    13 Special Construction

    05 Special Construction

    10 Pre- Eng. Structures, Pools & Ice Rinks

    15 Tanks, Tank Covers, Filtration Equipment

    20 Utility Control Systems

    25 Recording & Transportation Control Instrumentation

    14 Conveying Systems

    05 Dumbwaiters

    10 Elevators

    15 Moving stairs & Walks

    20 Lifts

    25 Material Handling Systems

    30 Hoist & Cranes

    15 Mechanical Works

    05 Pipe & Fittings

    10 Plumbing Fixtures & Bathroom Accessories

    15 Plumbing Appliances

    20 Fire Extinguishing Systems

    25 Heating

    30 HVAC Piping Specialties

    35 Air Conditioning/Ventilating SystemRPS/CP Dept. Page 14 of 32

  • 7/29/2019 Cost Codes

    15/37

    Division Sub Division Description

    16 Electrical Works

    05 Raceways

    10 Conductors & Grounding

    15 Boxes & Wiring Devices

    20 Starters, Boards & switches

    25 Transformers & Bus Ducts

    30 Power Systems & Capacitors

    35 Lighting

    40 Electric Utilities

    45 Special Systems

    RPS/CP Dept. Page 15 of 32

  • 7/29/2019 Cost Codes

    16/37

    SUB-DETAIL COST CODE ELEMENTS DESCRIPTION

    Jeddah, Kingdom of Saudi Arabia

  • 7/29/2019 Cost Codes

    17/37

  • 7/29/2019 Cost Codes

    18/37

    Division

    01 General Requirements

    Basic Salary & Overtime for Indirect Personnel:

    01 Basic Salary & Overtime for Indirect Personnel

    Expenses for Indirect Personnel:

    02 Food Allowance for Indirect Personnel

    03 Housing allowance for Indirect Personnel

    04 Transportation allowance for Indirect Personnel

    05 Living Allowance for Indirect Personnel

    06 Air Ticket Allowance for Indirect Personnel

    07 Other Allowance for Indirect Personnel-(Social Insurance)

    08 Severance/End Service Pay

    09 Medical Insurance for Indirect Personnel

    10 Other Incentive/Bonuses for Indirect Personnel

    11 Other Indirect Expenses

    Administrative Personnel Expenses:

    12 Social Insurance

    13 Leave Pay

    14 Leave Passage

    15 Severance Pay

    16 Medical Expenses

    17 Insurance Expenses

    18 Visa Expenses

    19 Catering & Accomodation

    20 Transportation Vehicle for Staff

    21 Joining/Leaving Travel Expenses22 Training Expenses

    23 Miscellaneous Expenses

    Sub Division Description Sub-sub Division Description

    RPS/CP Dept. Page 18 of 37

  • 7/29/2019 Cost Codes

    19/37

    Division Sub Division Description Sub-sub Division Description

    01 Site Office Running Expenses:

    24 Consumables incl. Medicine

    25 Water

    26 Electricity

    27 Stationary

    28 Telephone, Mail & Telefaxes

    29 Performance Bonds

    30 Insurance

    31 Business Travel & Accommodation

    32 Consultant and Professional Fees

    33 Entertainment

    34 Misc. Office Requirement

    35 Office Furniture & Equipment

    36 Blue Printing Materials

    37 Food & Beverage

    38 Computer, Printers, Network

    Client Running Expenses:

    39 Telephone Client Expense

    40 Copy Machine and Stationary Client Expense

    41 Food & Beverage Client Expenses

    42 Others Client Expense

    Geotechnical Studies:

    43 Testing Services

    Temporary Facilities & Utilities (Mobilization):

    44 Temporary Facilities & UtilitiesOverheads

    45 Jeddah Area Office

    Financial Expenses:

    46 Contingencies & Escalations

    47 Other Financial Expenses

    Design & Engineering:

    48 Design & Engineering icl. As-built drawingRPS/CP Dept. Page 19 of 37

  • 7/29/2019 Cost Codes

    20/37

    Division Sub Division Description Sub-sub Division Description

    01 Construction Equipments, Spareparts, Petrol, Oil & Lubricants:

    Misc. Equipment:

    49 Internal Rental

    50 External/Outside Rental

    Equipment, Tools & Spareparts:

    51 Equipment, Tools & Spareparts

    Petrol, Oil & Lubricants:

    52 Petrol, Oil & Lubricants

    Transportation cost of Material:

    53 Transportation cost of Material

    Scaffolding Rental:

    54 Scaffolding Rental -Internal

    55 Scaffolding Rental -External

    56 Shuttering

    Direct Construction Expenses:

    57 Submittals (Drawings, Reports, Etc.)

    58 Quality Control

    59 Utilities Connection

    60 Sanitation Services

    61 Cosumable Material, Tools, Equipment & Safety

    62 Contract Closeout

    02 Site Works

    05 Subsurface Investigations & Demolition

    Std. Penetration Test

    Site DemolitionBuilding Demolition

    Selective Demolition

    Concrete Removal

    Asbestos removal

    RPS/CP Dept. Page 20 of 37

  • 7/29/2019 Cost Codes

    21/37

    Division Sub Division Description Sub-sub Division Description

    10 Site Preparation

    Site Clearing

    Selective Clearing

    Structure Moving

    Dewatering

    Well Points

    Relief Wells

    Shores

    Underpinning

    Sheet Piling

    Cribbing & Walers

    Slurry Wall

    15 Earthworks

    Grading

    Excavation, Backfill & Compaction

    Pavement Base

    Soil Stabilization

    Vibrofloatation

    Slope/Erosion Control

    Soil Treatment

    20 Tunneling, Piles & Caissons

    Tunnel Support Systems

    Pile Driving

    Driven Piles

    Boared/Augered PilesCaissons

    25 Railroad & Marine Works

    Railroad Trackwork

    Dredging

    Dock & Facilities

    RPS/CP Dept. Page 21 of 37

  • 7/29/2019 Cost Codes

    22/37

    Division Sub Division Description Sub-sub Division Description

    30 Paving & Surfacing

    Walk/Road/Parking Paving

    Unit pavers

    Curbs

    Athletic Pave/Surfacing

    Synthetic Surfacing

    Surfacing

    Bridges

    Pavement Markings

    35 Pipe Utilities

    Piped Utilities

    Manhole & Cleanouts

    Water Systems

    Water Wells

    Gas Distribution System

    40 Sewerage & Drainage

    Subdrainage Systems

    Sewage Systems

    Wastewater Systems

    Syptic Systems

    Relining Existing Pipelines

    45 Site Improvements

    Irrigation Systems

    Fountains

    Fences & GatesWalk/Road/Parking Appurtenances

    Playfield Equipment

    Site/Street Furnishings

    50 Landscaping

    Shrub/Tree Transplanting

    Soil Preparation

    Lawn & GrassesRPS/CP Dept. Page 22 of 37

  • 7/29/2019 Cost Codes

    23/37

    Division Sub Division Description Sub-sub Division Description

    Trees/Plants/Ground Cover

    RPS/CP Dept. Page 23 of 37

  • 7/29/2019 Cost Codes

    24/37

    Division Sub Division Description Sub-sub Division Description

    03 Concrete Works

    05 Concrete Formworks

    Structure C.I.P. Formworks

    10 Concrete Reinforcement

    Reinforcing Steel

    Welded Wire Fabric

    Stressing Tendons

    15 Cast-In-Place Concrete

    Structural Concrete

    Concrete Finishing

    20 Precast Concrete

    Structural Precast

    Architectural Precast

    Tilt-up Precast

    Precast Specialties

    25 Cementitious Decks

    Lightweight Concrete

    Wood Fiber Systems

    04 Masonry Works

    05 Mortar & Masonry Accessories

    Mortar

    Masonry Accessories

    10 Unit Masonry

    Chimneys

    Brick MasonryConcrete Unit Masonry

    Reinforced Unit Masonry

    Masonry Panels

    Structural Facing Tile

    Ceramic Veneer

    Masonry Veneer

    Glass Unit MasonryRPS/CP Dept. Page 24 of 37

  • 7/29/2019 Cost Codes

    25/37

    Division Sub Division Description Sub-sub Division Description

    Adobe Masonry

    RPS/CP Dept. Page 25 of 37

  • 7/29/2019 Cost Codes

    26/37

    Division Sub Division Description Sub-sub Division Description

    15 Stone

    Stone

    Rough Stone

    Cut Stone

    Simulated Stone

    Stone Veneer

    Marble

    Limestone

    Granite

    Sandstone

    Slate

    20 Masonry Restoration & Cleaning/Refractories

    Masonry Cleaning

    Masonry Restoration

    Flue Liners

    Fire Brick

    05 Metal Works

    05 Finishes & Fastening

    Metal Fastening

    10 Structural Metal Framing

    Bracing

    Structural Steel

    Structural Aluminum

    Steel Wire Rope

    15 Metal JoistSteel Joist

    20 Metal Decking

    Steel Deck

    25 Metal Fabrications

    Metal Stairs

    Ladders

    Handrails & RailingRPS/CP Dept. Page 26 of 37

  • 7/29/2019 Cost Codes

    27/37

    Division Sub Division Description Sub-sub Division Description

    Gratings & Floor Plates

    RPS/CP Dept. Page 27 of 37

  • 7/29/2019 Cost Codes

    28/37

    Division Sub Division Description Sub-sub Division Description

    Casting

    Metal Specialties

    30 Expansion Joints

    Expansion Cover Assemblies

    06 Wood & Plastic

    05 Fastener & Adhesive

    Fasteners & Adhesives

    10 Rough Carpentry

    Wood Framing

    Sheathing

    Subfloor

    Structural Panels

    Wood Decking

    Mineral Fbr. Cem. Panel

    Heavy Timber Costruction

    Wood Metal Systems

    Glued-Laminated Construction

    Wood Trusses

    15 Finish Carpentry

    Millwork Moldings

    Shelving

    Plastic Laminate

    Prefinish Wood Paneling

    Prefinish Hardboard Panel

    Board PanelingMisc. Finish Carpentry

    20 Wood Treatment

    Preservative Treatment

    25 Architectural Woodwork

    Custom Casework

    Stairwork & Handrails

    Misc. Ornamental ItemsRPS/CP Dept. Page 28 of 37

  • 7/29/2019 Cost Codes

    29/37

    Division Sub Division Description Sub-sub Division Description

    07 Thermal & Moisture Protection

    05 Waterproofing & Damproofing

    Sheet Waterproofing

    Bentonite Waterproofing

    Cementitious Waterproofing

    Bitumin Dampproofing

    Water Repellent Coat

    Cementitious Dampproofing

    Vapor Retarders

    10 Insulation

    Building Insulation

    Roof & Deck Insulation

    Exterior Insulation

    Fireproofing

    15 Shingles & Roofing Tiles

    Shingles

    Roofing Tile

    20 Preformed Roofing & Sidings

    Preformed Panels

    Composite Panels

    Cladding/Siding

    25 Membrane Roofing

    Built-up Roofing

    Cold Applied Roofing

    Prepared Roll RoofingElastomeric Roofing

    Modified Bit. Roofing

    Roof Maint. & Repairs

    30 Flashing & Sheet Metal

    Sheet Metal Roofing

    Sheet Metal Flash & Trim

    RPS/CP Dept. Page 29 of 37

  • 7/29/2019 Cost Codes

    30/37

    Division Sub Division Description Sub-sub Division Description

    35 Roof Specialties & Accessories

    Prefab Roof Specialties

    Roof Accessories

    40 Skylights

    Plastic Skylights

    Metal Framed Skylights

    Glass Block Skylights

    45 Joint Sealers

    Sealants & Caulking

    08 Doors & Windows

    05 Metal Doors & Frames

    Steel Doors & Frames

    Alum Doors & Frames

    10 Wood & Plastic Doors

    Wood & Plastic Doors

    15 Special Doors

    Access Doors

    Sliding Doors

    Security Doors

    Metal-Clad Doors

    Cold Storage Doors

    Coiling Doors

    Coiling Grilles

    Flexible Doors

    Sectional Overhead DoorsMultileaf Vertical Lift Doors

    Hangar Doors

    Special Purpose Doors

    Swing Doors

    Sound Retardant Doors

    Screen & Storm Doors

    RPS/CP Dept. Page 30 of 37

  • 7/29/2019 Cost Codes

    31/37

    Division Sub Division Description Sub-sub Division Description

    20 Entrances & Storefronts

    Aluminum

    Stainless Steel

    Automatic Doors

    Revolving Doors

    25 Metal Windows

    Steel Windows

    Aluminum Windows

    Metal Jalousie Windows

    Metal Storm Windows

    Screen

    30 Wood & Plastic Windows

    Wood Windows

    35 Hardware

    Finish Hardware

    Operators

    Weatherstripping/Seals

    Door/Window Accessories

    40 Glazing

    Glass

    Plastic Glazing

    45 Glazed Curtain Wall

    Glazed Curtain Walls

    09 Finishes

    05 Metal Support SystemsSuspension System

    10 Lath, Plaster & Gypsum Board

    Furring & Lathing

    Gypsum Plaster

    Veneer Plaster

    Aggregate Coatings

    Gypsum Board SystemsRPS/CP Dept. Page 31 of 37

  • 7/29/2019 Cost Codes

    32/37

    Division Sub Division Description Sub-sub Division Description

    Drywall Accessories

    RPS/CP Dept. Page 32 of 37

  • 7/29/2019 Cost Codes

    33/37

    Division Sub Division Description Sub-sub Division Description

    15 Tile

    Ceramic Tile

    Quarry Tile

    Glass Mosaics

    Metal Tile

    20 Terrazzo

    Portland Cement Terrazzo

    Precast Terrazzo

    25 Acoustical Treatment & Wood Flooring

    Acoustical Ceilings

    Acoustical Space Units

    Acoustical Insulation

    Wood Strip Flooring

    Wood Block Flooring

    Wood Composite Flooring

    30 Flooring & Carpet

    Marble Flooring

    Slate Flooring

    Brick Flooring

    Resilient Tile Flooring

    Resilient Accessories

    Sheet Carpet

    Carpet Tile

    35 Special Flooring & Floor Treatment

    Epoxy-Marble Flooring40 Special Coatings

    Glazed Coatings

    45 Painting & Wall Coverings

    Exterior Painting

    Interior Painting

    Wall Paper

    Surface PreparationRPS/CP Dept. Page 33 of 37

  • 7/29/2019 Cost Codes

    34/37

    Division Sub Division Description Sub-sub Division Description

    10 Specialties

    05 Chalkboards, Compartments & Cubicles

    Chalkboards

    Toilet Compartments

    Shower Compartments

    10 Louvers, Corner Protection & Access Flooring

    Metal Wall Louvers

    Wall & Corner Guards

    Access Flooring

    15 Fireplaces, Ext. Specialties & Flagpoles

    Prefabricated Fireplaces

    Fireplace Accessories

    Stoves

    Cupolas

    Ground Set Flagpoles

    Wall Mounted Flagpoles

    20 Identifying & Pedestrian Control Devices

    Directories

    Bulletin Boards

    Signs

    Turnstile

    25 Lockers,Protective Covers & Postal Specialties

    Metal Lockers

    Canopies

    Mail ChutesMail Boxes

    30 Partitions & Storage Shelving

    Wire Mesh Partitions

    Folding Gates

    Demountable Partitions

    Portable Partitions

    Panel PartitionsRPS/CP Dept. Page 34 of 37

  • 7/29/2019 Cost Codes

    35/37

    Division Sub Division Description Sub-sub Division Description

    Accordion Partitions

    RPS/CP Dept. Page 35 of 37

  • 7/29/2019 Cost Codes

    36/37

    Division Sub Division Description Sub-sub Division Description

    Storage & Shelving

    35 Telephone specialties

    Telephone Enclosures

    40 Toilet & Bath Accessories & Scales

    Bath Accessories

    Scales

    45 Wardrobe & Closet Specialties

    Coat Racks/Wardrobes

    50 Equipment

    Contractor Equipment

    Maintenance Equipment

    Security/Vault Equipment

    Teller and Service Equipment

    Ecclesiastical Equipment

    Library Equipment

    Theater/Stage Equipment

    11 Equipment

    05 Mercantile, Commercial & Detention Equipment

    Barber Shop Equipment

    Cash Register/Checking

    Display Cases

    Laundry/Dry Cleaning

    Projection Screens

    Service Station Equipment

    Parking Control EquipmentLoading Dock Equipment

    Waste Handling Equipment

    Detention Equipment

    10 Food Services, Residential, Darkroom, Athletic Equipment

    Food Service Equipment

    Disappearing Stairs

    Darkroom ProcessingRPS/CP Dept. Page 36 of 37

  • 7/29/2019 Cost Codes

    37/37

    Division Sub Division Description Sub-sub Division Description

    Revolving Darkroom Doors